Data Center Construction Projects in the US: 44 Announcements Worth $735.9 Billion, Checked Against Census Spending

A sourced registry of every $1 billion-plus US data center announcement we could verify from January 2024 to October 2026, with state totals, project sizes and the official spending series they feed into.
Primary data
CB&C registry of government and company announcements; U.S. Census Bureau Construction Spending (C30)
Data period
Announcements 2024-01-01 to 2026-10-05; Census monthly series January 2014 to August 2026
Latest release used
2026-10-01
Next release
2026-11-02 (Census, September 2026 data); registry checked monthly
Geography
United States, by state
Sources
76 (40 Tier 1)
Short answer

Our registry of data center construction projects lists 44 US announcements of $1 billion or more made from January 2024 to October 5, 2026, totaling $735.9 billion in announced, not spent, investment. New Mexico, Kentucky and Texas lead. Census data put actual data center construction spending at $49.7 billion in 2025.

$735.9Bannounced in 44 data center projects of $1 billion or more, January 2024 to October 2026 (announced, not spent)[15][24][21][9]
$49.7Bactual US private data center construction spending in 2025 (Census, construction put in place)[3]
$85.0Bdata center construction spending in August 2026 at a seasonally adjusted annual rate[2][1]
59.1%share of the 44 entries backed by a state, local or federal government record[11][14][9]

Registry of announced US data center projects of $1 billion or more

Checked monthly. Last checked 2026-10-05. Entries are neutral records of public data; each links to its source record.

Developer and projectAnnounced investment, capacity, location and statusDateEvidenceSource
Amazon Web Services: Madison County data center complexes$10 billion; Madison County, Mississippi; status: Announced2024-01-25government recordRecord
Google: Kansas City data center$1 billion; Kansas City, Missouri; status: Announced2024-03-20company statementRecord
Amazon Web Services: New Carlisle data center campus$11 billion; St. Joseph County (New Carlisle), Indiana; status: Announced2024-04-25corroboratedRecord
Google: Fort Wayne data center$2 billion; Fort Wayne, Indiana; status: Announced2024-04-26government recordRecord
Microsoft: Mount Pleasant datacenter campus, phase 1$3.3 billion through 2026; Mount Pleasant (Racine County), Wisconsin; status: First facility construction completed 2026-06-232024-05-08corroboratedRecord
Microsoft: La Porte data center$1 billion; La Porte, Indiana; status: Announced2024-06-03government recordRecord
Amazon Web Services: Greater Ohio data center expansion$10 billion; Greater Ohio (sites not named), Ohio; status: Announced2024-12-17corroboratedRecord
Amazon Web Services: Butts and Douglas county data centersat least $11 billion; Butts County and Douglas County, Georgia; status: Announced2025-01-07company statementRecord
Compass Datacenters: Meridian data center campus$10 billion at full fit-out; Lauderdale County (Meridian), Mississippi; status: Announced2025-01-09company statementRecord
Amazon Web Services: North Carolina AI campus$10 billion; Richmond County, North Carolina; status: Announced2025-06-04government recordRecord
Google: Iowa investment incl. Big Cedar data center$7 billion; Cedar Rapids (statewide figure), Iowa; status: Announced2025-06-04company statementRecord
Amazon Web Services: Salem Township and Falls Township campusesat least $20 billion; Luzerne County and Bucks County, Pennsylvania; status: Announced2025-06-09government recordRecord
Cielo Digital Infrastructure: Gaffney data center project$2.1 billion; Cherokee County (Gaffney), South Carolina; status: Announced2025-06-24government recordRecord
CoreWeave: Lancaster AI data centerup to $6 billion; Lancaster County, Pennsylvania; status: Announced2025-07-15company statementRecord
Google: Stillwater campus and Pryor expansion$9 billion over two years; Stillwater and Pryor, Oklahoma; status: Announced2025-08-13company statementRecord
Applied Digital: Polaris Forge 2$3 billion; capacity 280 MW; Harwood, North Dakota; status: Groundbreaking planned for September 20252025-08-18company statementRecord
AVAIO Digital: Brandon data center campus$6 billion; Rankin County (Brandon), Mississippi; status: Announced2025-08-19government recordRecord
Vantage Data Centers: Frontier campusover $25 billion; capacity 1.4 GW; Shackelford County, Texas; status: Announced2025-08-19company statementRecord
Google: Virginia expansion incl. Chesterfield County data center$9 billion through 2026; Chesterfield County, Virginia; status: Announced2025-08-27company statementRecord
Microsoft: Mount Pleasant datacenter campus, second phase$4 billion (total $7 billion); Mount Pleasant (Racine County), Wisconsin; status: Announced2025-09-18government recordRecord
STACK Infrastructure and BorderPlex Digital Assets (tenant: Oracle, OpenAI): Project Jupiterup to $165 billion over 30 years; minimum initial $50 billion; Doña Ana County (Santa Teresa), New Mexico; status: County incentive terms approved; construction start anticipated Q4 20252025-09-25corroboratedRecord
Google: West Memphis data center$4 billion through 2027; Crittenden County (West Memphis), Arkansas; status: Announced2025-10-02corroboratedRecord
Google: Berkeley County expansion and two Dorchester County sites$9 billion through 2027; Berkeley County and Dorchester County, South Carolina; status: Construction continuing at Dorchester sites2025-10-13company statementRecord
Vantage Data Centers (Oracle, OpenAI): Lighthouse campus (Stargate)$15 billion or more; capacity close to 1 GW; Port Washington, Wisconsin; status: Construction to begin soon; completion 20282025-10-22company statementRecord
Related Digital (Oracle, OpenAI): The Barn (Stargate)$16 billion; capacity more than 1 GW; Saline Township, Michigan; status: Under construction (2026-06-01)2025-10-30company statementRecord
Meta: Beaver Dam AI data center campusmore than $1 billion; Beaver Dam, Wisconsin; status: Announced2025-11-12government recordRecord
Fluidstack for Anthropic: Custom data centers in Texas and New York$50 billion; Sites not named, Texas and New York; status: Sites coming online through 20262025-11-12company statementRecord
Google: Armstrong and Haskell county campuses$40 billion through 2027; Armstrong County and Haskell County, Texas; status: Announced2025-11-14corroboratedRecord
Amazon Web Services: Vicksburg data center campusat least $3 billion; Warren County (Vicksburg), Mississippi; status: Construction expected to begin in 20262025-11-20corroboratedRecord
Amazon: Northern Indiana data center campuses$15 billion; capacity 2.4 GW; Northern Indiana (sites not named in release), Indiana; status: Announced2025-11-24company statementRecord
Hut 8 (tenant: Fluidstack): River Bend AI campus, phase 1up to $10 billion; capacity 330 MW utility, 245 MW IT; up to 1,000 MW; West Feliciana Parish, Louisiana; status: Announced2025-12-17company statementRecord
xAI: MACROHARDRR data centermore than $20 billion; Southaven (DeSoto County), Mississippi; status: Operations expected February 20262026-01-08government recordRecord
Meta: Lebanon data center campus (LEAP District)more than $10 billion; Lebanon, Indiana; status: Groundbreaking 2026-02-112026-02-11government recordRecord
Amazon: Northwest Louisiana data center campuses$12 billion; Caddo Parish and Bossier Parish, Louisiana; status: Construction expected to begin in weeks2026-02-23government recordRecord
Penzance Management: Bedington Campus$4 billion at full build-out; Berkeley County, West Virginia; status: Announced2026-02-26government recordRecord
Google: Lenoir data center expansion$1 billion over two years; Lenoir, North Carolina; status: Announced2026-03-13government recordRecord
Google: New Florence data center$15 billion; Montgomery County (New Florence), Missouri; status: Announced2026-05-21government recordRecord
Google: Jackson County campus expansion$1.5 billion for 2026 and 2027; Jackson County, Alabama; status: Announced2026-06-15company statementRecord
Meta: Richland Parish Data Center (Hyperion)more than $50 billion (cumulative); capacity 5 GW IT; Richland Parish (Holly Ridge), Louisiana; status: Expansion announced2026-07-13government recordRecord
Meta with BlackRock: El Paso data center ventureabout $14 billion total development cost; El Paso, Texas; status: Joint venture formed2026-07-28company statementRecord
Brookfield and NextEra Energy: Paducah Site data center campus$100 billion; capacity 1.8 GW utility, over 1.2 GW compute; Paducah, Kentucky; status: Subject to final agreements; full build by 20322026-07-29corroboratedRecord
Fluidstack: Cameron County AI campus, phase 1$4 billion first phase; capacity up to 1.5 GW; Cameron County, Texas; status: Construction began2026-09-21company statementRecord
Amazon Web Services: King George data center campus$6 billion; King George County, Virginia; status: County agreement reached2026-09-29government recordRecord
Amazon: Montgomery City data center campus$10 billion; Montgomery County (Montgomery City), Missouri; status: Announced2026-10-01government recordRecord

Where data center construction projects cluster by state

21 states have at least one announced project of $1 billion or more. Dollar rankings are dominated by single very large campuses; counts point to Mississippi, Indiana, Texas and Wisconsin.

Announced data center investment by state

Entries of $1 billion or more announced January 2024 to October 2026; the $50 billion Texas and New York program is not allocated

Announced data center investment by stateTile map of announced data center investment by state: New Mexico $165 billion, Kentucky $100 billion, Texas $83 billion, Louisiana $72 billion, Mississippi $49 billion and Indiana $39 billion lead; 21 states have at least one entry.AKMEVTNHWAIDMTND: 3ND3MNILWI: 23.3WI23.3MI: 16.0MI16.0NYRIMAORNVWYSDIA: 7IA7IN: 39.0IN39.0OH: 10.0OH10.0PA: 26.0PA26.0NJCTCAUTCONEMO: 26.0MO26.0KY: 100KY100WV: 4WV4VA: 15.0VA15.0MDDEAZNM: 165NM165KSAR: 4AR4TNNC: 11.0NC11.0SC: 11.1SC11.1DCOK: 9OK9LA: 72.0LA72.0MS: 49.0MS49.0AL: 1.5AL1.5GA: 11.0GA11.0HITX: 83.0TX83.0FLPR1.5 to 44 to 11.011.0 to 15.015.0 to 26.026.0 to 72.072.0 to 165$ billions announced

Source: CB&C registry of state, local and company announcements, checked 2026-10-05

Announced data center investment by state, January 2024 to October 2026 Download CSV
StateEntriesAnnounced ($ billions)Largest entry
New Mexico1165.0STACK Infrastructure and BorderPlex Digital Assets (tenant: Oracle, OpenAI), Project Jupiter
Kentucky1100.0Brookfield and NextEra Energy, Paducah Site data center campus
Texas483.0Google, Armstrong and Haskell county campuses
Louisiana372.0Meta, Richland Parish Data Center (Hyperion)
Mississippi549.0xAI, MACROHARDRR data center
Indiana539.0Amazon, Northern Indiana data center campuses
Missouri326.0Google, New Florence data center
Pennsylvania226.0Amazon Web Services, Salem Township and Falls Township campuses
Wisconsin423.3Vantage Data Centers (Oracle, OpenAI), Lighthouse campus (Stargate)
Michigan116.0Related Digital (Oracle, OpenAI), The Barn (Stargate)
Virginia215.0Google, Virginia expansion incl. Chesterfield County data center
South Carolina211.1Google, Berkeley County expansion and two Dorchester County sites
Georgia111.0Amazon Web Services, Butts and Douglas county data centers
North Carolina211.0Amazon Web Services, North Carolina AI campus
Ohio110.0Amazon Web Services, Greater Ohio data center expansion
Oklahoma19.0Google, Stillwater campus and Pryor expansion
Iowa17.0Google, Iowa investment incl. Big Cedar data center
Arkansas14.0Google, West Memphis data center
West Virginia14.0Penzance Management, Bedington Campus
North Dakota13.0Applied Digital, Polaris Forge 2
Alabama11.5Google, Jackson County campus expansion
Texas and New York (not allocated)150.0Fluidstack for Anthropic, custom data centers

Announced amounts as stated by governments or companies; not money spent; multi-year; may include IT equipment. One multi-state entry is listed separately.

Source: [10][24][21][9] Mississippi Development Authority; Office of the Texas Governor; Doña Ana County, New Mexico; U.S. Department of Energy

New Mexico ($165 billion) and Kentucky ($100 billion) rank first and second on one entry each. Project Jupiter's figure is a 30-year potential total stated by Doña Ana County, and the Paducah figure is a campus plus dedicated power generation to be built by 2032 (Doña Ana County; DOE).

Texas has 4 entries worth $83 billion, Louisiana 3 worth $72 billion, Mississippi 5 worth $49 billion and Indiana 5 worth $39 billion. Missouri and Pennsylvania each total $26 billion, and Wisconsin has 4 entries worth $23.3 billion.

The $50 billion Anthropic and Fluidstack program covers sites in Texas and New York without a stated split, so it is listed separately and left out of state totals (Fluidstack, 2025-11-12).

How large are announced data center construction projects?

Most announced dollars sit in a handful of campuses. The median entry is $10 billion, while the 4 entries of $50 billion or more hold $365 billion.

Announced data center projects by size

Number of registry entries in each announced-amount band

Announced data center projects by sizeBar chart of entries by size band: 14 entries from $1 billion to under $5 billion, 7 from $5 billion to under $10 billion, 15 from $10 billion to under $20 billion, 4 from $20 billion to under $50 billion and 4 at $50 billion or more.0510.015.020.0entries14.0$1B to under $5B7$5B to under $10B15.0$10B to under $20B4$20B to under $50B4$50B and above

Source: CB&C registry, 44 entries, checked 2026-10-05

Size distribution of announced data center projects Download CSV
Announced amountEntriesAnnounced ($ billions)Share of entries (%)
$1B to under $5B1434.931.8
$5B to under $10B752.015.9
$10B to under $20B15179.034.1
$20B to under $50B4105.09.1
$50B and above4365.09.1

44 entries of $1 billion or more announced 2024-01-01 to 2026-10-05.

Source: [15][63] Louisiana Economic Development; Amazon

14 entries fall between $1 billion and under $5 billion ($34.9 billion), 7 between $5 billion and under $10 billion ($52 billion), 15 between $10 billion and under $20 billion ($179 billion) and 4 between $20 billion and under $50 billion ($105 billion).

Largest announced data center projects

Announced investment, $ billions

Largest announced data center projectsHorizontal bars of the 15 largest announced projects, led by Project Jupiter in New Mexico at up to $165 billion and the Paducah, Kentucky campus at $100 billion, followed by Meta in Louisiana at $50 billion and the Anthropic program at $50 billion.$ billionsSTACK Infrastructure and BorderPlex Digita165Brookfield and NextEra Energy, KY100Fluidstack for Anthropic, TX/NY50.0Meta, LA50.0Google, TX40.0Vantage Data Centers, TX25.0Amazon Web Services, PA20.0xAI, MS20.0Related Digital, MI16.0Vantage Data Centers, WI15.0Amazon, IN15.0Google, MO15.0Meta with BlackRock, TX14.0Amazon, LA12.0Amazon Web Services, IN11.0

Source: CB&C registry; amounts as stated by governments and companies

Fifteen largest announced data center projects in the registry Download CSV
DeveloperProjectStateAnnounced ($ billions)Capacity statedDateEvidence
STACK Infrastructure and BorderPlex Digital Assets (tenant: Oracle, OpenAI)Project JupiterNew Mexico165.0Not stated2025-09-25corroborated
Brookfield and NextEra EnergyPaducah Site data center campusKentucky100.01.8 GW utility, over 1.2 GW compute2026-07-29corroborated
Fluidstack for AnthropicCustom data centers in Texas and New YorkTexas and New York50.0Not stated2025-11-12company statement
MetaRichland Parish Data Center (Hyperion)Louisiana50.05 GW IT2026-07-13government record
GoogleArmstrong and Haskell county campusesTexas40.0Not stated2025-11-14corroborated
Vantage Data CentersFrontier campusTexas25.01.4 GW2025-08-19company statement
Amazon Web ServicesSalem Township and Falls Township campusesPennsylvania20.0Not stated2025-06-09government record
xAIMACROHARDRR data centerMississippi20.0Not stated2026-01-08government record
Related Digital (Oracle, OpenAI)The Barn (Stargate)Michigan16.0more than 1 GW2025-10-30company statement
Vantage Data Centers (Oracle, OpenAI)Lighthouse campus (Stargate)Wisconsin15.0close to 1 GW2025-10-22company statement
AmazonNorthern Indiana data center campusesIndiana15.02.4 GW2025-11-24company statement
GoogleNew Florence data centerMissouri15.0Not stated2026-05-21government record
Meta with BlackRockEl Paso data center ventureTexas14.0Not stated2026-07-28company statement
AmazonNorthwest Louisiana data center campusesLouisiana12.0Not stated2026-02-23government record
Amazon Web ServicesNew Carlisle data center campusIndiana11.0Not stated2024-04-25corroborated

Ties at $10 billion are ordered by registry date. Capacity shown only where the source states it.

Source: [21][9][15][61][24] Doña Ana County, New Mexico; U.S. Department of Energy; Louisiana Economic Development; Fluidstack; Office of the Texas Governor

Stated capacity appears in a minority of announcements. Where it is stated, examples include Vantage's 1.4 GW Frontier campus in Texas ($25 billion), Applied Digital's 280 MW Polaris Forge 2 in North Dakota ($3 billion) and Amazon's 2.4 GW northern Indiana plan ($15 billion). These pairs come from different scopes and years, so we do not divide dollars by megawatts.

Developers with two or more registry entries Download CSV
Developer (parent)EntriesAnnounced ($ billions)
Amazon11118.0
Google1198.5
Meta475.0
Vantage Data Centers240.0
Microsoft38.3

Counts entries in this registry only; a developer's other projects below $1 billion or outside the date range are not included.

Source: [63][24][15][20] Amazon; Office of the Texas Governor; Louisiana Economic Development; Wisconsin Economic Development Corporation

Amazon (11 entries, $118 billion), Google (11 entries, $98.5 billion) and Meta (4 entries, $75 billion) account for the most registry entries. Microsoft has 3 entries worth $8.3 billion, all in Wisconsin and Indiana.

How much of the announced pipeline is on the public record

59.1% of entries and 70.7% of announced dollars are backed by a government record. The remainder rely on company statements.

Registry entries by evidence level Download CSV
Evidence levelEntriesShare of entries (%)Announced ($ billions)Share of announced dollars (%)
government record1840.9184.125.0
corroborated818.2336.345.7
company statement1840.9215.529.3

Government record: state or local government or federal agency publication. Corroborated: a government record and a company statement both confirm the project.

Source: [11][14] Indiana Economic Development Corporation; Office of the Governor of Ohio

A government record is a governor's release, a state economic development agency release, a county or city notice, or a federal agency release. 18 entries rest on a government record and 8 are corroborated by both a government record and a company statement. 18 entries (40.9%, $215.5 billion) rest on a company statement alone.

Government records are not proof that money has been spent. Several record incentives or county agreements whose terms depend on minimum investment thresholds, such as Indiana's 35-year sales tax credit for Microsoft's La Porte data center tied to a minimum $1 billion of eligible investment (IEDC, 2024-06-03).

How data center construction projects show up in Census spending data

Census measures what is built each month. It shows $49.7 billion of data center construction in 2025 and a $85.0 billion annual rate in August 2026, far below announced totals, because the measures differ.

US private data center construction spending

Monthly, seasonally adjusted annual rate, $ billions, January 2014 to August 2026

US private data center construction spendingLine chart of Census data center construction spending rising from $1.6 billion SAAR in January 2014 to $85.0 billion SAAR in August 2026, with the steepest climb after 2023.020.040.060.080.0100$ billions SAARJan 2014May 2015Sep 2016Jan 2018May 2019Sep 2020Jan 2022May 2023Sep 2024Aug 2026

Source: U.S. Census Bureau, Construction Spending (privsatime.xlsx), August 2026 release of 2026-10-01

The Census Bureau's Construction Spending survey reports private data center construction as a subcategory of office, starting January 2014. Census defines it as buildings that contain the hardware needed for storing, processing and transmitting digital information, and the series excludes land acquisition and production or special-purpose equipment (Census definitions). Some announced figures explicitly include IT equipment: Compass says its $10 billion Meridian figure includes future tenants' IT equipment.

The annual rate rose from $1.6 billion in January 2014 to $85.0 billion in August 2026, a multiple of 51.9. August 2026 was 73.2% above August 2025 ($49.1 billion). Data centers were 11.0% of private nonresidential construction in August 2026, against 0.5% in January 2014.

Data center construction spending by calendar year

Sum of monthly values, $ billions, not seasonally adjusted

Data center construction spending by calendar yearBar chart of annual Census data center construction spending from $1.8 billion in 2014 to $34.8 billion in 2024 and $49.7 billion in 2025.020.040.060.0$ billions1.820142.720154.120164.720176.920188.520199.220209.9202112.6202220.0202334.8202449.72025

Source: U.S. Census Bureau, Construction Spending (privtime.xlsx), August 2026 release

US private data center construction spending by year (Census C30) Download CSV
YearSpending ($ millions)Change from prior year (%)
20141,797
20152,74552.8
20164,12150.1
20174,66713.2
20186,93348.6
20198,48322.4
20209,2318.8
20219,9497.8
202212,58326.5
202319,99558.9
202434,79774.0
202549,73742.9
2026 (January to August)45,22641.7 (vs. Jan to Aug 2025)

Sum of monthly not seasonally adjusted values from privtime.xlsx, August 2026 release. Construction put in place; excludes land and production or special-purpose equipment.

Source: [3][1] U.S. Census Bureau; U.S. Census Bureau

Seasonally adjusted annual rate (SAAR): A monthly value adjusted for seasonal patterns and multiplied to an annual pace. It is not the amount spent in that month.

Announced totals and Census spending answer different questions. The registry total of $735.9 billion is 14.8 times 2025 Census spending and 8.7 times the August 2026 annual rate. Announcements dated 2025 alone ($450.1 billion) are 9.0 times 2025 spending. The gap reflects multi-year horizons (up to 30 years for Project Jupiter), IT equipment inside some announced figures (Compass says its $10 billion includes tenants' IT equipment), power plants inside others, and projects that may slow or stop.

The monthly series and its revisions are analysed on our commercial construction spending page; this report uses it only as the official yardstick for the announcements.

Power and grid constraints on data center construction

Power supply now shapes where and how fast projects proceed. Federal and grid-reliability sources tie most forecast demand growth to data centers, and several states paused incentives or permits in 2026.

Substation and transmission lines beside a data center construction site
Illustrative photograph. Generated image, not a specific project.
  • Data centers used 176 TWh, about 4.4% of US electricity, in 2023, up from 58 TWh in 2014; projections reach 325 to 580 TWh, or 6.7% to 12%, by 2028 (DOE, 2024-12-20).
  • NERC's 2025 Long-Term Reliability Assessment (January 2026) forecasts summer peak demand in its assessment areas to rise by over 224 GW over 10 years and winter peak by 245 GW, and says new data centers account for most of the increase (NERC).
  • EIA's September 2026 outlook forecasts US electricity sales of 4,135 billion kWh in 2026, almost 2% above 2025, citing data center development (EIA).

Several announcements bundle power with the campus. The Paducah plan includes up to 4.6 GW of dedicated generation; Hut 8's River Bend phase starts with 330 MW of utility capacity from Entergy; DTE Energy agreed to supply 1.4 GW to the Saline Township campus in Michigan (NextEra, Entergy, Michigan Advance).

State policy shifted in 2026. Ohio paused new data center tax exemption requests (2026-05-27); Illinois paused new Data Center Investment Program agreements starting July 1 (announced 2026-06-05); Texas's governor announced developer commitments to his data center standards (2026-08-18) and, according to CNBC, paused environmental permits for new data centers pending an audit (2026-09-21); Virginia issued Executive Order 22 (2026-09-18); California signed 7 bills (2026-09-21).

The White House said on 2026-07-23 that its Ratepayer Protection Pledge, under which large data center operators fund the generation and infrastructure their projects require, covers 80% of power delivered to US homes and businesses.

What the data center pipeline means for commercial contractors

The work is concentrated in very large, electrically intensive campuses that need thousands of trade workers at peak. Electricians are the trade most directly exposed.

Generators and electrical gear staged on a data center jobsite
Illustrative photograph. Generated image, not a specific project.
  • Meta's Richland Parish project is expected to support 7,500 construction jobs (Louisiana Economic Development, 2026-07-13).
  • Meta's Lebanon, Indiana campus is expected to support more than 4,000 construction jobs at peak (City of Lebanon, 2026-02-11).
  • Vantage's Port Washington, Wisconsin campus expects more than 4,000 skilled construction jobs, mostly union (Vantage, 2025-10-22).
  • Project Jupiter's county terms cite approximately 2,500 construction jobs from 2025 to 2028 (Doña Ana County).
  • Oracle says more than $5 billion invested in site construction at Saline Township will go to Michigan contractors and suppliers (Oracle, 2026-06-01).

Electricians held 821,000 jobs in 2025 with median pay of $63,190; BLS projects 9% employment growth from 2025 to 2035 and about 72,700 openings a year (BLS). Those figures cover all industries. Wider workforce data are on our construction labor shortage page, and material and bid price trends on our commercial construction price index page.

Counts and distributions

Announced investment by state

Formulasum and count of registry values by state; multi-state entries excluded

Inputs: fact sheet registry rows; derived d2, d28 to d31 (fact sheet rows)

Result: 21 states; New Mexico $165 billion (1), Kentucky $100 billion (1), Texas $83 billion (4); top three = 50.7% of $685.9 billion allocated.

Dollar rankings follow single megaprojects; counts are a better signal of breadth.

Limitations: Announced, not spent; overlap possible; amounts are stated by governments or companies with different scopes.

Size distribution

Formulacount and sum of entries in five announced-amount bands

Inputs: registry rows; derived d3, d32, d33 (fact sheet rows)

Result: 14 / 7 / 15 / 4 / 4 entries from the smallest band to the largest; median $10 billion; 52.3% at $10 billion or more.

The pipeline is top-heavy: the 4 largest entries hold about half of announced dollars.

Limitations: Only announcements of $1 billion or more are in scope.

Announced pipeline vs. Census spending

Formularegistry total / calendar-2025 Census data center spending

Inputs: derived d2, d13, d22 to d27 (fact sheet rows)

Result: 14.8 times 2025 spending; 8.7 times the August 2026 annual rate; 2025 announcements alone 9.0 times 2025 spending.

Announcements describe intentions over many years; Census describes construction put in place each month.

Limitations: Different scopes (equipment, power plants, land), horizons and certainty. Not a forecast of future spending.

Government-record share

Formulaentries with a government record / all entries

Inputs: derived d1, d4 to d11 (fact sheet rows)

Result: 26 of 44 entries (59.1%); 70.7% of announced dollars.

Most entries can be traced to a public agency; dollar share is lifted by Project Jupiter and Paducah.

Limitations: A government record confirms an announcement or incentive, not spending.

Download the calculations (CSV)

Key findings

  1. 44 US data center construction projects of $1 billion or more were announced from 2024-01-01 to 2026-10-05 and verified in a government or company record, totaling $735.9 billion announced.[10][15][33]
  2. Announcements dated 2025 account for 24 entries and $450.1 billion; 2026 to October 5 accounts for 13 entries and $247.5 billion; 2024 accounts for 7 entries and $38.3 billion.[11][24][33]
  3. Project Jupiter in Doña Ana County, New Mexico carries the largest stated figure: up to $165 billion over 30 years, with a minimum initial investment of $50 billion (Doña Ana County).[21]
  4. The Paducah Site campus in Kentucky was announced on 2026-07-29 at $100 billion, with up to 1.8 GW of utility capacity and up to 4.6 GW of dedicated generation by 2032.[9][67]
  5. Texas has 4 entries totaling $83 billion, led by Google's $40 billion statewide plan announced 2025-11-14 and Vantage's $25 billion Frontier campus in Shackelford County.[24][52]
  6. Louisiana has 3 entries totaling $72 billion, including Meta's Richland Parish commitment of more than $50 billion (2026-07-13) and Amazon's $12 billion Caddo and Bossier campuses (2026-02-23).[15][28]
  7. Mississippi has 5 entries totaling $49 billion, including xAI's Southaven project of more than $20 billion (2026-01-08).[26][10]
  8. Indiana has 5 entries totaling $39 billion, including Amazon's $15 billion northern Indiana plan for 2.4 GW (2025-11-24).[63][27]
  9. US private data center construction spending reached $49.7 billion in 2025, up 42.9% from 2024 (Census, sum of monthly values).[3]
  10. In August 2026 data center construction ran at $85.0 billion SAAR, 11.0% of private nonresidential construction, up from 0.5% in January 2014.[2]
  11. January to August 2026 data center spending was $45.2 billion, 41.7% above the same months of 2025 ($31.9 billion).[3]
  12. Data centers used 4.4% of US electricity in 2023 and are projected to use 6.7% to 12% by 2028 (DOE summary of the LBNL report).[5]
  13. NERC's 2025 assessment forecasts summer peak demand to rise by over 224 GW over 10 years, 69% more than the prior year's 132 GW projection, with data centers the main driver.[6]

Executive summary

  • The registry holds 44 US data center construction projects with a stated investment of $1 billion or more, announced from 2024-01-01 to 2026-10-05, totaling $735.9 billion in announced investment.
  • Two very large campuses carry $265.0 billion of that total: Project Jupiter in Doña Ana County, New Mexico (up to $165 billion over 30 years) and the Paducah, Kentucky campus ($100 billion). Without them the total is $470.9 billion.
  • By count, Mississippi and Indiana lead with 5 entries each; by announced dollars, New Mexico, Kentucky and Texas lead, with $348 billion or 50.7% of the amount allocated to single states.
  • The median announced project is $10 billion, and 23 of 44 entries (52.3%) are $10 billion or more.
  • Amazon and Google each account for 11 entries; Amazon's announcements total $118 billion and Google's $98.5 billion.
  • Census counts $49.7 billion of private data center construction put in place in 2025, up 42.9% from $34.8 billion in 2024 and 27.7 times the 2014 level.
  • The announced total is 14.8 times 2025 Census spending; the two figures measure different things (multi-year announcements that can include IT equipment and power plants vs. construction put in place in one year), so the ratio describes scale, not a forecast.
  • 26 of 44 entries (59.1%) are backed by a government record; 18 rest on a company statement alone.

Questions people ask

How many data centers are being built in the US?

No federal agency publishes a count of data centers under construction. This registry lists 44 projects of $1 billion or more announced from January 2024 to October 5, 2026. Census reports spending, not counts: $49.7 billion of data center construction in 2025. A Construction Dive analysis of Cleanview data reported that planned and operating projects nearly tripled between March and August 2026.

Which state has the most data center construction?

By announced dollars in this registry, New Mexico ($165 billion, one project), Kentucky ($100 billion) and Texas ($83 billion) lead. By number of $1 billion-plus announcements, Mississippi and Indiana lead with 5 each. Census does not publish data center spending by state, and Construction Dive's count of planned projects puts Virginia first.

How much does it cost to build a data center?

Only stated figures are reported here. Announced projects in the registry range from $1 billion to up to $165 billion, with a median of $10 billion. Stated pairs include $3 billion for 280 MW (Applied Digital, North Dakota), $25 billion for 1.4 GW (Vantage, Texas) and $15 billion for 2.4 GW (Amazon, Indiana). Scopes differ, and some include IT equipment.

Who is building the most data centers?

In this registry Amazon and Google each have 11 announcements of $1 billion or more, worth $118 billion and $98.5 billion. Meta has 4 worth $75 billion. The largest single figures belong to Project Jupiter (STACK Infrastructure and BorderPlex Digital Assets, with Oracle and OpenAI) and the Paducah campus (Brookfield and NextEra Energy).

How much is spent on data center construction each year?

Census counts $49.7 billion of private data center construction in 2025 and $34.8 billion in 2024, a rise of 42.9%. January to August 2026 reached $45.2 billion, and August 2026 ran at $85.0 billion SAAR. These figures measure construction put in place, not equipment purchases or land.

Frequently asked questions

What counts as a data center construction project in this registry?

A US data center campus or expansion with a publicly stated investment of $1 billion or more, announced from 2024-01-01 to 2026-10-05, for which we opened a government or company record.

What is the total announced investment?

$735.9 billion across 44 entries. It is announced, not spent, and some figures span decades or include equipment and power plants.

What is the largest announced data center project?

Project Jupiter in Doña Ana County, New Mexico, with up to $165 billion over 30 years and a minimum initial investment of $50 billion, according to Doña Ana County.

How much did the US spend on data center construction in 2025?

$49.7 billion, according to the Census Bureau's Construction Spending series (sum of monthly values), up 42.9% from 2024.

Why is announced investment so much larger than Census spending?

Announcements cover many years, can include IT equipment and power generation, and may not all proceed. Census measures construction put in place each month. The registry total is 14.8 times 2025 Census spending.

Which states have the most $1 billion-plus data center announcements?

Mississippi and Indiana with 5 each, followed by Texas and Wisconsin with 4 each.

How much electricity do data centers use?

About 4.4% of US electricity in 2023, or 176 TWh, with projections of 6.7% to 12% by 2028, according to DOE's summary of the LBNL report.

Are states slowing data center development?

Some are changing terms. In 2026 Ohio paused new data center tax exemption requests, Illinois paused new incentive agreements, Virginia issued an accountability executive order and California signed 7 data center bills, according to the governors' offices.

How many construction jobs do these projects create?

Stated estimates include 7,500 construction jobs for Meta in Richland Parish, more than 4,000 at peak for Meta in Lebanon, Indiana, and approximately 2,500 for Project Jupiter.

How often is the registry updated?

Monthly. It was last checked on 2026-10-05; new announcements, status changes and corrections are added at each check.

Download the data

Every table in this report is available as a CSV under CC BY 4.0. The fact sheet lists each value with its source URL and access date.

For journalists and researchers

If you cite only a few, cite these

  1. 44 projects, $735.9 billion announced, January 2024 to October 2026 (CB&C registry).[15][21]
  2. $49.7 billion of US data center construction in 2025 (Census).[3]
  3. Announced pipeline = 14.8 times 2025 Census spending.[3]

Most quotable statistics

  • 44 US data center construction projects of $1 billion or more were announced from January 2024 to October 5, 2026, totaling $735.9 billion in announced investment (CB&C registry).[15][21][9]
  • US private data center construction spending was $49.7 billion in 2025, up 42.9% from 2024 (U.S. Census Bureau).[3]
  • Data center construction ran at $85.0 billion SAAR in August 2026, 73.2% above August 2025 (U.S. Census Bureau).[2]
  • Data centers were 11.0% of US private nonresidential construction spending in August 2026, up from 0.5% in January 2014 (Census).[2]
  • Announced US data center investment since 2024 is 14.8 times actual 2025 data center construction spending, a gap explained by multi-year horizons, equipment and power plants inside announced figures.[3][47]
  • 59.1% of $1 billion-plus US data center announcements since 2024 are backed by a government record (CB&C registry).[11][14]

Press summary

Commercial Builders & Contractors has published a sourced registry of US data center construction projects. It lists 44 projects with a stated investment of $1 billion or more announced from January 2024 to October 5, 2026, totaling $735.9 billion in announced investment. Each entry links to a governor's release, state agency notice, county record or company statement, and 59.1% are backed by a government record. New Mexico, Kentucky and Texas lead by announced dollars, while Mississippi and Indiana lead by count. The median project is $10 billion. For comparison, Census data show $49.7 billion of private data center construction in 2025 and a $85.0 billion annual rate in August 2026. The announced total is 14.8 times 2025 spending because announcements cover many years and can include IT equipment and power plants. The registry is checked monthly; data are free to reuse under CC BY 4.0.

Suggested headlines

  • 44 data center construction projects worth $735.9 billion announced in the US since 2024
  • US data center construction spending hits $85.0 billion annual rate in August 2026
  • Two campuses in New Mexico and Kentucky account for $265.0 billion of announced data center investment
  • Mississippi and Indiana lead in $1 billion-plus data center announcements
  • Announced data center investment is 14.8 times what Census counted as built in 2025

How to cite this report

Commercial Builders & Contractors. (2026). Data Center Construction Projects in the US: 44 Announcements Worth $735.9 Billion, Checked Against Census Spending. Retrieved from https://commercialbuildersandcontractors.com/data-center-construction-projects/

Reuse license

Data and tables are licensed CC BY 4.0. Attribution: “Source: Commercial Builders & Contractors, Data Center Construction Projects in the US: 44 Announcements Worth $735.9 Billion, Checked Against Census Spending” with a link to this page.

Methodology

Selection: we searched governor, state economic development agency, county, city and federal agency releases, then company releases, for US data center projects with a stated investment of $1 billion or more announced from 2024-01-01 to 2026-10-05. An entry is included only if we opened a source that states the amount. News reports are used only for dates or corroboration.

Evidence levels: government record (state, local or federal publication), company statement (developer, tenant or utility release) and corroborated (both confirm the project). One row per announcement; expansions of a campus announced earlier are recorded at the latest stated cumulative figure (Meta, Richland Parish; Meta and BlackRock, El Paso) to avoid double counting.

Amounts: we use the figure as stated. For more than $X or up to $X we use X. Statewide company figures (for example Google in Texas, Oklahoma, Virginia and South Carolina) can include cloud infrastructure and community programs. Totals are announced, not spent, can span decades, can include IT equipment and power generation, and may overlap (the Fluidstack Cameron County phase may be part of the Anthropic program).

Exclusions: Blackstone's $25 billion Pennsylvania plan mixes data centers and gas generation; Stargate sites without a per-site figure; news-only figures such as an OpenAI project in Effingham County, Georgia; and announcements before 2024 or under $1 billion. See excluded.md.

Census context: private data center construction from the Census Bureau's Construction Spending (C30) August 2026 release of 2026-10-01; annual values are sums of not seasonally adjusted months. The next release, with September data, is due 2026-11-02. Derived metrics and formulas are in derived_metrics.csv.

Update schedule: the registry is checked monthly; last checked 2026-10-05.

This report presents published data with its limitations. It is not legal, financial or investment advice.

Sources, ranked by quality

Tier 1: primary and official sources (40)

Tier 2: trade bodies, market research, company data (29)

Tier 3: journalism and expert commentary (7)