Modular Construction: How It Works, Which Code Applies, and What Public Records Show It Costs

Crane setting a finished building module on a concrete foundation, with more modules waiting on trailers

Modular construction builds finished, three-dimensional modules in a factory, then trucks and sets them on a site-built foundation. The modules meet the same building code as site-built work, inspected in the plant under state programs in 39 states and D.C.

Key takeaways

  • The 2024 International Building Code (IBC) treats a relocatable modular building as new construction, requires an 11-item manufacturer’s data plate on each module and lets the building official accept in-plant inspection reports (IBC 2024 Section 3113).
  • As of November 2023, 39 states and Washington, D.C. ran their own off-site construction programs for plan review and factory inspection; in the other 11 states the local building department decides (International Code Council, Nov. 28, 2023).
  • Texas has required modules to meet the 2021 IBC and the 2020 National Electrical Code since July 1, 2024, according to the Texas Department of Licensing and Regulation (TDLR), and Florida exempts modular buildings that carry a state insignia from local code amendments (Fla. Stat. 553.37(4)).
  • Twelve Texas modular projects registered with the state from 2022 to 2026 show a median of $145 per sq ft and 4.0 months on site, from $100 for school classrooms to $571 for a lab (TDLR TABS, our compilation).
  • Washington State’s 2017 school study found permanent modular classrooms took 7 to 12 months from design to completion against 27 to 42 months for site-built ones, but cost $336 to $344 per sq ft against $316 (Washington Department of Commerce, Oct. 2017).
  • The Modular Building Institute (MBI) puts the 2025 U.S. permanent modular market at $20.5 billion, about 5.1% of construction activity in the segments it tracks (MBI, July 14, 2026).

What is modular construction?

Modular construction is a factory-first way to build: rooms or sections of a building are framed, wired, plumbed and finished as boxes in a plant, then shipped and joined on site. Florida’s statute defines a modular building as a closed structure made in manufacturing facilities for residential, commercial, institutional, storage and industrial use (Fla. Stat. 553.36(13)).

Two families matter for commercial owners. A permanent modular building sits on a permanent foundation and is regulated like any other building; the TDLR program covers modular buildings “installed on permanent foundations” (TDLR Industrialized Housing and Buildings). A relocatable building is, in the IBC’s words, “constructed and designed to be reused multiple times and transported to different building sites” (IBC 2024 Section 202).

TypeWhat ships from the plantCode pathTypical commercial useSource
Permanent modular (volumetric)Finished 3D modules with structure, mechanical, electrical and plumbing (MEP) systems and finishesState-adopted building code plus a state program where one existsSchools, offices, clinics, dormitories, multifamilyTDLR
Relocatable building3D modules built to be moved and reusedIBC 2024 Sec. 3113; International Existing Building Code (IEBC) Chapter 14 when moved or alteredClassrooms, swing space during renovation, site officesIBC 2024 Ch. 31
Panelized or component systemsFlat wall, floor or roof panelsICC/MBI 1200 covers them; Florida’s program only covers three-dimensional componentsHotels, apartments, framing packagesFla. Stat. 553.36(6)
HUD-code manufactured homeSections on a permanent chassis, 8 body ft or more wide or 40 body ft or more longFederal code, 24 CFR Part 3280; excluded from IBC 3113 when used as a dwellingHousing, not commercial buildings24 CFR 3280.2
Pre-engineered metal building (PEMB), for contrastSteel frame members, purlins, girts and panelsAISC 360 and AISI S100 steel design; erected on siteWarehouses, shops, gymsCB&C PEMB guide

A pre-engineered metal building is often lumped in with modular, but it ships as loose frames and panels designed to AISC 360 and AISI S100 that a crew bolts up on site, not as finished rooms. The frame types, loads and codes for that system are covered in our guide to the pre-engineered metal building.

How does modular construction work, step by step?

A commercial modular project runs in 8 steps, and its main schedule gain comes from running factory work and site work at the same time. The modules go through state or third-party plan review while the local building department permits the foundation and utilities. Each step below names the rule that governs it in the 2024 IBC, Texas Occupations Code Chapter 1202 or Florida Statutes Chapter 553.

Modular construction in 8 steps Eight steps from choosing permanent or relocatable to final inspection, each with its governing code section. Modular construction: 8 steps and the rule behind each 1 Choose permanent or relocatable IBC 2024 Sec. 202 and 3113 2 Design the modules ICC/MBI 1200-2021 3 Plan review: state or third party Tex. Occ. Code 1202.154; Fla. Stat. 553.37(1)(a) 4 Local permit: foundation and site Tex. Occ. Code 1202.252; Fla. Stat. 553.38 5 Factory build, in-plant inspection Fla. Stat. 553.37(1)(c); IBC 1704.2.5.1 6 Insignia or decal and data plate Fla. Stat. 553.37(3); IBC 3113.3 7 Ship and set modules 23 CFR 658.15: 102 in. legal width 8 Connect, final inspection, CO IBC 3113.4; Tex. Occ. Code 1202.252(b) Steps 3 and 4 run in parallel: state plan review for the modules, local permit for the site.
The 8 steps of a commercial modular project and the rule behind each, from IBC 2024, Tex. Occ. Code Ch. 1202, Fla. Stat. 553.37 and 553.38 and 23 CFR 658.15 (accessed November 1, 2026).
  1. Choose permanent or relocatable. A relocatable unit must comply with IBC 2024 Section 3113 and, each time it moves, with IEBC Chapter 14 (IBC 3113.1.1).
  2. Design the modules. ICC/MBI 1200-2021 sets out the roles of the architect, modular manufacturer and general contractor, the plant location relative to the site, material lead times and the line between structural and nonstructural modules.
  3. Plan review for the factory-built part. In Texas the modules need plans carrying the state council’s stamp of approval (Tex. Occ. Code 1202.155); in Florida the state approves the manufacturer’s drawings and quality control manual (Fla. Stat. 553.37(1)(a) and (b)).
  4. Local permit for the foundation and site. A Texas city may require all local permits before construction starts on the site and may inspect the foundation and erection (Tex. Occ. Code 1202.252).
  5. Factory build with in-plant inspection. Florida’s inspection agency watches the first building start to finish, then inspects every module at least once and at least 75% of each module’s subsystems (Fla. Stat. 553.37(1)(c)). Under IBC 1704.2.5.1, work in an approved fabricator’s plant needs no separate special inspection.
  6. Label each module. Florida requires the state insignia and a manufacturer’s data plate before installation (Fla. Stat. 553.37(3)); the IBC data plate lists 11 items, including occupancy group, design loads, the inspection agency and electrical service size (IBC 3113.3).
  7. Ship and set. Federal rules cap vehicle width at 102 inches on the National Network, and wider modules move under a state special use permit (23 CFR 658.15). A crane then sets each module on the foundation.
  8. Connect, inspect and occupy. Crews join modules and connect utilities; the building official may require a final inspection before occupancy (Tex. Occ. Code 1202.252(b)) and may accept the plant’s inspection reports for work hidden in the factory (IBC 3113.4). The steps to the occupancy certificate itself are in our guide to the certificate of occupancy.

Because the owner pays for modules before they reach the site, payment terms matter more than on a site-built job. Florida bars installing any module without the state insignia (Fla. Stat. 553.37(3)), so tie factory payments to inspected, labeled modules. Ask for a pay schedule that lists factory production, delivery and site work as separate lines, as described in our guide to the schedule of values.

Which building code applies to a modular building?

A modular building follows the same building code as a site-built building of the same occupancy; the factory location changes who inspects, not which rules apply. The 2024 IBC adds three modular-specific layers: Section 3113 for relocatable buildings, Section 1704.2.5 for fabricated items and the referenced IEBC Chapter 14 for moved buildings. ICC/MBI 1200 and 1205 are the two consensus standards written for off-site work.

RuleWhat it requiresApplies toSource
IBC 2024 Sec. 3113.1 and 3113.1.1New relocatable buildings meet new-construction rules; existing ones being altered, added to, changed in occupancy or relocated meet IEBC Chapter 14Relocatable buildings; not manufactured housing used as dwellingsIBC Ch. 31
IBC 2024 Sec. 3113.28 extra submittal items, including manufacturer, serial number, type of construction and design loadsRelocatable buildingsIBC Ch. 31
IBC 2024 Sec. 3113.3Data plate on or next to the electrical panel with 11 itemsEach relocatable moduleIBC Ch. 31
IBC 2024 Sec. 3113.4Building official may accept off-site inspection reports from approved agenciesRelocatable buildingsIBC Ch. 31
IBC 2024 Sec. 1704.2.5.1No special inspection in an approved fabricator’s plant; fabricator submits a certificate of complianceStructural members and assemblies made in a shopIBC Ch. 17
ICC/MBI 1200-2021Planning, design, fabrication and assembly requirements, first editionComponentized, panelized and modular elementsICC
ICC/MBI 1205-2021Inspection, approval and regulatory compliance of off-site components and their assembly on site, first editionResidential and commercial off-site workICC

Neither standard replaces the building code. ICC’s November 2023 Building Safety Journal article says the two standards cover the whole off-site process and asks federal agencies to support state and local adoption through grants and technical help (ICC, 2023). Ask your building official which edition of the IBC the jurisdiction enforces and whether it accepts third-party in-plant inspection reports under Section 3113.4 before you sign a factory contract.

Do state modular programs replace the local permit?

No. State programs approve the factory-built modules, and the local government keeps zoning, setbacks, the foundation, utilities and the final inspection. Texas and Florida both split the work this way in statute, and California adds a school-only layer through the Division of the State Architect (DSA). In the 11 states without a program, the local building department reviews the modules itself, according to ICC.

StateProgram and lawWhat the state approvesWhat stays localSource
TexasTDLR Industrialized Housing and Buildings, Tex. Occ. Code Ch. 1202Design review, council stamp, in-plant inspection, decal on each module; 2021 IBC and 2020 NEC since July 1, 2024Local permits, foundation and erection inspections, final inspection before occupancy (Sec. 1202.252)Tex. Occ. Code 1202
FloridaFlorida Department of Business and Professional Regulation (DBPR) manufactured buildings program, Fla. Stat. 553.35 to 553.42Drawings, quality control manual, in-plant inspection, insignia; insignia buildings exempt from local amendmentsZoning, setbacks, site development, on-site installation, aesthetics; fees only for inspections the local government performs (Sec. 553.38)Fla. Stat. 553.38
California (public schools)DSA, IR 16-1 under the 2025 California Building CodePre-check (PC) designs for relocatable and modular school buildings; new plans each time a relocatable is movedSite plan items: utilities, fire access, accessible routeDSA IR 16-1, rev. Apr. 1, 2026
11 states without a programLocal building code enforcementNone at state levelPlan review and inspection of modules and siteICC, 2023
Florida Statutes 553.37 with subsections (3) and (4) boxed: insignia required, exempt from local amendments
Fla. Stat. 553.37(3) and (4), boxed: no modular building may be installed without the state insignia and a data plate, and insignia buildings are exempt from local amendments. Source: Florida Legislature, accessed November 1, 2026.

Texas also draws a size line. A commercial structure counts as an industrialized building unless it sits on something other than a permanent foundation and is either closed to the public or under 1,500 sq ft and not used as a school or place of worship (Tex. Occ. Code 1202.003(d)). Relocatable classrooms bought or leased on or after January 1, 2010 must meet the same industrialized building rules (Sec. 1202.004).

The site half of a modular job is ordinary construction: Florida leaves on-site installation to local authorities (Fla. Stat. 553.38), and the contractor setting the foundation and connecting utilities still needs whatever license the state requires for commercial work. State-by-state thresholds are in our table of commercial contractor licensing by state.

How much does commercial modular construction cost?

Public records in Texas put commercial modular projects at a median of $145 per sq ft, with a 4.0-month median on-site schedule. The range runs from $100 per sq ft for plain school classrooms to $571 for a biosafety level 2 (BSL-2) lab. These are estimated costs registered from 2022 to 2026 in TDLR’s Texas Architectural Barriers Online System (TABS), an accessibility filing, not bid results; ISD means independent school district.

TABS recordOwner and buildingCountySq ftEstimated cost$/sq ftOn-site datesMonths
TABS2024026420Campbell ISD, 7,800 sq ft classroom building (access by others)Hunt7,800$780,000$100Aug 2024 to Jun 20259.0
TABS2023016234Wylie ISD, one modular classroomCollin1,536$157,797$103Jun 2023 to Aug 20231.9
TABS2026001704Austin ISD, three new portablesTravis4,500$480,000$107Sep 2025 to Dec 20253.5
TABS2024015832Fort Worth ISD, 20-portable village during a renovationTarrant21,520$2,800,000$130May 2024 to Jul 20242.1
TABS2024026564Houston Airport System, 25 modular buildings (temporary relocation)Harris18,207$2,500,000$137Aug 2024 to Dec 20244.0
TABS2023002600Klein ISD, Flex School North (classrooms, administration, cafeteria, library)Harris68,000$9,628,858$142Nov 2022 to Aug 20239.1
TABS2025027027Lago Vista ISD, two modular classroom buildingsTravis9,728$1,450,000$149May 2025 to Aug 20253.7
TABS2024010839Harris County, Channelview modular wellness complexHarris10,000$2,150,000$215Feb 2024 to Oct 20248.0
TABS2026003672Texas Parks and Wildlife Department, modular office plus site workBurnet1,568$428,000$273Oct 2025 to Feb 20263.9
TABS2025007313Private owner, Dallas bus terminal relocation, modular buildingDallas5,460$1,500,000$275Mar 2025 to Sep 20255.6
TABS2026013667University of Texas, Brownsville, new modular buildingCameron6,850$2,000,000$292Mar 2026 to Aug 20265.0
TABS2025015231University of Texas, Laredo BSL-2 lab buildingWebb1,750$1,000,000$571May 2025 to Jul 20252.5
Texas modular projects: estimated cost per square footBar chart of 12 Texas modular projects from $100 per sq ft for Campbell ISD classrooms to $571 for a UT Laredo lab; median $145.$ per sq ftCampbell ISD classrooms (2024)100Wylie ISD classroom (2023)103Austin ISD portables (2025)107Fort Worth ISD portable village (2024)130Houston Airport System, 25 modulars (2024)137Klein ISD Flex School North (2022)142Lago Vista ISD classrooms (2025)149Harris County wellness complex (2024)215Texas Parks and Wildlife office (2025)273Dallas bus terminal modular (2025)275UT Brownsville modular (2026)292UT Laredo BSL-2 lab (2025)571
Twelve Texas modular projects registered with TDLR from 2022 to 2026 range from $100 to $571 per sq ft, median $145. Source: TDLR TABS, accessed November 1, 2026.

For scale, Rider Levett Bucknall’s Q3 2026 report lists elementary school hard costs of $290 to $405 per sq ft in Austin and $290 to $415 in Dallas (RLB, Q3 2026). The modular school records above sit well below that, but they are mostly single-story classroom buildings without gyms, kitchens or the site work of a full campus, so the gap is not a like-for-like saving. City-by-city site-built benchmarks are on our commercial construction cost per square foot page.

Federal awards show where modular pricing climbs. Secure space, clinical space and leases cost far more per square foot than classrooms:

AwardAgency and scopePlaceObligatedStartSource
FA580824C0003Air Force: design, procure and build a 40 ft by 45 ft (1,800 sq ft) modular building for secure space, about $1,415 per sq ftNot listed$2,547,200Sept. 30, 2024USAspending
FA580824C0002Air Force: same 40 ft by 45 ft secure modular scope at Moton Field, about $1,404 per sq ftNot listed$2,527,200Sept. 30, 2024USAspending
75H71021C00001Indian Health Service: 16-bed emergency room modular building with set-up and installationAtmore, AL$16,367,888.52Sept. 16, 2021USAspending
36C10F23F0002Veterans Affairs: modular building for swing space during a Building 8 renovationSan Francisco, CA$2,629,109.87Nov. 16, 2022USAspending
W9127819F0037Army: provide and lease modular buildingsTyndall Air Force Base, FL$10,370,462.50Dec. 11, 2018USAspending

Four inputs move a modular price the most in these records. Use type is the largest: classrooms ran $100 to $149 per sq ft in the Texas filings, a lab $571 and federal secure space about $1,404 to $1,415. Size is next, since fixed delivery, crane and hookup costs spread over fewer feet: a 653 sq ft modular driver restroom at a Bell County distribution center was registered at $401,253, about $614 per sq ft (TABS2026011550). Site work and lease terms follow; the Fort Worth ISD portable village included removing a running track and new fencing, and the Army’s Tyndall contract is a lease, not a purchase.

Is modular faster and cheaper than site-built?

Faster, yes, in the one public study that compared both methods line by line; cheaper, not per square foot. Washington State’s 2017 assessment of K-3 classrooms found modular-permanent buildings took 7 to 12 months from design to completion against 27 to 42 months for site-built ones. Modular cost $336 to $344 per sq ft against $316, while the eight-classroom modular building came in 7.3% cheaper per classroom.

Option (Washington, 2017)Design, permit and build timeCost per classroomCost per sq ftLife cycleCost per sq ft per year
Traditional site-built (stick frame)27 to 42 months$291,160$31630 years$10.54
Portable classroomLess than 3 months$250,768$26810 years$26.88
Modular-permanent, cross-laminated timber (CLT), 4 classrooms7 to 12 months$302,300$33650 years$6.72
Modular-permanent eight-plex (stick frame)10 months$269,760$34430 years$11.47
Months from design to completion, upper end of each rangeBar chart: up to 42 months for site-built classrooms, 12 for CLT modular, 10 for the modular eight-plex and under 3 for portables.010.020.030.040.050.0months42.0Traditional site-built3Portable classroom12.0Modular-permanent CLT10.0Modular-permanenteight-plex
Washington’s site-built classrooms took up to 42 months from design to completion against 10 to 12 for modular-permanent options. Source: Washington Department of Commerce, Table 4, October 2017.

The eight-plex record is a real bid: North Thurston School District’s 6,275 sq ft building came to $2,158,078 including tax, and a district official said construction itself took three to four months (Washington Department of Commerce, Table 22 and p. 24). Note one inconsistency in the report: Table 22 lists the eight-plex life cycle as 10 years while Tables 1 and 4 list 30 years; we use Tables 1 and 4.

Several top-ranking guides repeat cost and speed claims that the primary records only partly support:

Common claimWhat the primary record showsSource
Modular is up to 20% cheaper than site-builtPer sq ft, Washington’s modular options cost 6.3% (CLT) and 8.9% (eight-plex) more than site-built; per classroom the eight-plex was 7.3% cheaper and the CLT building 3.8% dearerWashington Dept. of Commerce, 2017
Modular cuts schedules by 20% to 50%MBI’s 2026 report gives 20% to 50%; Washington’s eight-plex took 10 months against 27 to 42, a 63% to 76% shorter path because design and permitting also shrankMBI, 2026; Washington, 2017
Modular buildings skip the local permitTexas cities may require all local permits, foundation inspections and a final inspection (Sec. 1202.252); Florida keeps zoning and installation local (Sec. 553.38)Tex. Occ. Code; Fla. Stat.
Modular is about 6% of new constructionMBI measures 5.1% of U.S. construction activity in key segments for 2025, and 5.2% for North America; the denominator is select segments, not all constructionMBI, 2026; MBI

When does modular construction fit, and when does it not?

Modular fits repetitive rooms on a deadline, temporary space and remote or weather-limited sites; it fits poorly when the program needs wide clear spans or the site cannot take oversize trucks and a crane. The thresholds below include the 102-inch road width limit, Washington’s 7 to 12 month modular schedule and the Texas 1,500 sq ft line. Use them to decide which bids to request.

If your project…ThenThreshold or ruleSource
Needs space for less than about 10 years (swing space, enrollment peak)Lease or buy relocatable unitsWashington portables: 10-year life, under 3 months to deliver; IEBC Chapter 14 applies on each moveWashington, 2017; IBC 3113.1.1
Is a public school relocatable in CaliforniaBudget for DSA review at every moveNew plans to DSA each time a relocatable is movedDSA IR 16-1
Needs clear spans for a gym, warehouse or plantPrice a PEMB or tilt-up shellA road-legal module is 102 in. wide; wider loads need a state permit23 CFR 658.15
Has repetitive rooms and must open within 12 monthsGet permanent modular bidsWashington modular-permanent: 7 to 12 months vs 27 to 42 site-builtWashington, 2017
Is secure, lab or clinical spaceExpect high modular unit costs; compare with site-built$571 per sq ft (Texas BSL-2 lab); about $1,404 to $1,415 (federal secure space)TDLR TABS; USAspending
Is in Texas, under 1,500 sq ft, not on a permanent foundation and not a school or place of worshipCheck local rules instead of TDLROutside the industrialized building definitionTex. Occ. Code 1202.003(d)
Is in one of the 11 states without a programAsk the building official to accept plant inspection reports in writingIBC 2024 Section 3113.4ICC, 2023
Should this project be modular? Decision flowchart: temporary need leads to relocatable; wide clear spans lead to PEMB or tilt-up; repetitive rooms on a tight schedule lead to permanent modular. Should this commercial project be modular? Need the space for under 10 years? (swing space, enrollment peak) Yes Relocatable: lease or buy IEBC Ch. 14 applies on each move No Need clear spans wider than a module? (gym, warehouse, plant) Yes PEMB or tilt-up Road limit 102 in. wide without a permit No Repetitive rooms and occupancy in 12 months? (classrooms, offices, clinic rooms) Yes Permanent modular WA 2017: 7 to 12 months vs 27 to 42 No Trucks and a crane can reach the site? (oversize permit route, crane pad) Yes Price modular and site-built Compare both bids line by line No Build on site
Four questions that sort a commercial project into relocatable, PEMB or tilt-up, permanent modular or site-built, using thresholds from Washington’s 2017 study, 23 CFR 658.15 and IEBC Chapter 14.

If the decision lands on a steel shell instead, our guide to metal building kits covers what a kit includes and what it leaves out. For concrete wall buildings, our step-by-step guide to tilt-up construction lists the OSHA 29 CFR 1926.704 and ACI 551 rules. Modular manufacturers often work inside a single design-build contract, so the delivery method choice in our design-build vs design-bid-build comparison applies here too.

Modular units still sit on a site-built foundation, priced in our concrete slab cost per square foot guide.

How we compiled this

We read the 2024 IBC Chapters 2, 17 and 31, Texas Occupations Code Chapter 1202, Florida Statutes 553.36 to 553.38, California DSA IR 16-1, two federal regulations (23 CFR 658.15 and 24 CFR 3280.2), the Washington Department of Commerce 2017 study, MBI’s July 2026 market release, RLB’s Q3 2026 cost report and 5 USAspending award records, all accessed November 1, 2026. We pulled 246 TDLR TABS registrations whose names contain “modular” or “portable” and kept 12 where the scope names a building and the square footage is building area; we dropped site-work-only, renovation and site-area filings. CB&C is a matching service, not a code consultant; this page is not legal advice, so confirm the code path for your site with the building official.

Frequently asked questions

What is the difference between modular and manufactured buildings?

A manufactured home is built on a permanent chassis to the federal HUD code and is designed as a dwelling (24 CFR 3280.2). A modular building is built to the same state-adopted building code as site-built work and set on a foundation. IBC 2024 Section 3113 excludes manufactured housing used as dwellings, and Florida’s modular statute does not apply to mobile homes.

How wide can a module be on the road?

Federal rules set a 102-inch vehicle width limit on the National Network, with 108 inches allowed in Hawaii (23 CFR 658.15). A state may grant special use permits for wider loads, including manufactured housing. Wider modules mean fewer joints but need permits, route surveys and sometimes escorts, so confirm the route before the design fixes module sizes.

Can a modular building be moved later?

A relocatable building can, by definition: the IBC describes it as designed to be reused and moved to different sites. When it moves, IBC 2024 Section 3113.1.1 sends it to IEBC Chapter 14. In California, a public school must submit new plans to the Division of the State Architect every time a relocatable building is moved (DSA IR 16-1, 2026).

How long does a modular building last?

Washington’s 2017 school study assigned a 10-year life cycle to portable classrooms, 30 years to a stick-frame modular eight-plex and 50 years to a cross-laminated timber modular building (Washington Department of Commerce). Permanent modular buildings are designed to the same code as site-built ones, so their life depends on materials, envelope and maintenance rather than the factory method.

Do modular buildings need a building permit?

Yes, for the site part. A Texas city may require all applicable local permits before construction begins, plus foundation, erection and final inspections (Tex. Occ. Code 1202.252). Florida reserves zoning, setbacks, site development and installation review to local governments and limits their fees to inspections they actually perform (Fla. Stat. 553.38).

Is modular construction cheaper than building on site?

Not reliably per square foot. Washington’s 2017 study priced modular-permanent classrooms at $336 to $344 per sq ft against $316 for site-built, though one modular option was 7.3% cheaper per classroom. Twelve Texas modular filings from 2022 to 2026 show a $145 per sq ft median (TDLR TABS), mostly simple classroom and office buildings.

Is a shipping container building the same as modular construction?

The IBC treats it separately. Section 3114 of the 2024 IBC covers intermodal shipping containers repurposed as buildings, while Section 3113 covers relocatable modular buildings. A container previously approved as an existing relocatable building complying with IEBC Chapter 14 is an exception to Section 3114, so ask the building official which section your unit falls under.

Sources

Codes, standards and law

Cost, schedule and project records

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.