AIA Contract Documents: Which Forms Go Together and What They Cost

Site office table with rolled blueprints, a binder and a hard hat beside a window onto steel framing

AIA contract documents are the American Institute of Architects’ standard construction forms: 300+ agreements and forms in seven series, A to G, licensed at $179.99 per agreement and $59.99 per form for one-time use (aiacontracts.com, October 2026).

Key takeaways

  • A typical fixed-price job needs a set, not one form: B101-2017 with the architect, A101-2017 plus the A201-2017 general conditions with the builder, G702 and G703 every pay period, and G704, G706, G706A and G707 at closeout. A201 is incorporated by reference into A101, A102, A103, A401, B101 and B103 (AIA A201-2017 summary).
  • Design-build runs on A141-2024, which replaced A141-2014; check the edition year, because AIA’s own series list still showed the 2014 edition when last modified on July 23, 2026 (AIA A141-2024 summary).
  • An old year does not mean an old form: G702-1992 and G703-1992 are still the current pay application forms, and G706, G706A and G707 (1994) are still the current closeout forms (AIA list of current documents).
  • A one-time document “may be finalized only once”, and AIA does not publish the price of its unlimited subscription with 1, 3 or 5 seats (AIA How it works).
  • ConsensusDocs, founded in 2007, sells 116 contracts in a $1,400 a year Full Package, and its ConsensusDocs 200 combines the agreement and general conditions that AIA splits into A101 and A201 (ConsensusDocs comparison matrix).
Key numberWhat it meansSource
300+Agreements and forms in the AIA libraryAIA How it works, Oct 2026
7Series: A, B, C, D, E, F and GAIA list, modified Jul 23, 2026
$179.99One-time license for an agreement such as A101-2017 or A201-2017aiacontracts.com A101 page, Oct 2026
$59.99One-time license for a form such as G702-1992 or G704-2017aiacontracts.com G702 page, Oct 2026
10 daysPay application due before each progress payment dateA201-2017 Section 9.3.1
10 yearsOuter limit for claims after substantial completionA201-2017 Section 15.1.2
$1,400 a yearConsensusDocs Full Package, 116 contractsConsensusDocs pricing, Oct 2026

What are AIA contract documents?

AIA contract documents are copyrighted standard forms that AIA Contract Documents (ACD Operations, LLC) publishes for the American Institute of Architects. The publisher says the forms have been an industry standard since 1888, are used on more than 200,000 projects a year and are drafted by a Documents Committee of more than 35 industry members (AIA Contract Documents explainer).

The forms are national, not state specific. AIA says they “are not drafted to reflect the laws of any particular state”, so a state lien, licensing or prompt payment statute can override a clause in the A201-2017 general conditions. Public works payment deadlines and retainage caps in all 50 states and DC are compared in our prompt payment and retainage tracker by state.

This page describes the forms and how they are licensed; it is not legal advice. Before you sign, ask a construction attorney two things: which A201-2017 clauses your state’s statutes override, and what your supplementary conditions should change, using AIA’s A503 guide as the starting list.

How are the AIA document series organized?

AIA sorts its documents by letter, and the letter names the relationship. A covers owner and contractor agreements, B owner and architect, C other agreements, D miscellaneous, E exhibits, F facility management and G contract administration forms. The year after the number is the edition, so A201-2017 is the 2017 general conditions (AIA list of current documents).

SeriesWhat it coversCurrent examplesSource
AOwner-contractor agreements, general conditions, bonds, biddingA101-2017, A133-2019, A141-2024, A201-2017, A312-2010AIA list
BOwner-architect agreements and architect scopesB101-2017, B133-2019, B141-2024AIA list
COther agreements: consultants, CM as adviser, joint venturesC101-2018, C132-2019, C401-2017AIA list
DMiscellaneous: area methods, checklists, guidesD101-1995, D200-1995, D503-2020AIA list
EExhibits for BIM and sustainable projectsE201-2022, E204-2017AIA list
FFacility management: maintenance agreements, work ordersF101-2023, F201-2023AIA list
GContract administration and project formsG701-2017, G702-1992, G704-2017, G706-1994AIA list

The digits after the letter mark the family, which tells you what fits together. Documents ending in 01 belong to the conventional design-bid-build set (A101, B101, A201, A401), 33 to construction manager as constructor (A133, B133), 32 to construction manager as adviser (A132, B132, C132) and 41 to design-build (A141, B141, C141, A441).

Which AIA contract documents matter on a commercial project?

Thirteen documents cover most commercial work an owner or general contractor will sign: four owner-builder agreements (A101, A102, A133, A141), the A201 general conditions, the B101 owner-architect agreement and seven G-series forms for changes, payment and closeout. The table gives each one’s current edition, what it governs, what AIA’s store sells it with and its one-time price.

DocumentCurrent editionWhat it governsAIA sells it withOne-time priceSource
A1012017Owner-contractor, stipulated (fixed) sum; insurance and bonds in Exhibit AA201, G702, G703$179.99AIA summary, store
A1022017Owner-contractor, cost of the work plus a fee with a guaranteed maximum price (GMP)A201$179.99AIA store
A1332019Owner and construction manager as constructor; GMP set by the Exhibit A amendmentA201, B133$179.99AIA summary, store
A1412024Owner and design-builder; Design-Build Amendment is Exhibit BB141$179.99AIA summary, store
A2012017General conditions: roles, payment, changes, claims, completion; 15 articles; not a contract on its ownA101, A401, B101$179.99AIA summary, store
B1012017Owner-architect; five phases of basic servicesA201, C401$179.99AIA summary, store
G7012017Change order agreed by owner, contractor and architectA201, G714$59.99AIA store
G7021992Application and certificate for payment: work completed and stored, retainage, prior payments, change ordersG703, G901, G902$59.99AIA store
G7031992Continuation sheet listing each line of the schedule of valuesG702$59.99AIA store
G7042017Certificate of substantial completion; warranties start on that date unless statedA201, G706, G707$59.99AIA summary, store
G7061994Contractor’s affidavit that debts and claims are paid, exceptions listedG706A, G707$59.99AIA summary, store
G706A1994Contractor’s affidavit that lien releases or waivers were receivedG706, G901, G904$59.99AIA store
G7071994Consent of surety to final payment on bonded workG706, A312$59.99AIA summary, store
How old is each current AIA edition?Bar chart: G702 and G703 are 34 years old, G706, G706A and G707 32, the 2017 set 9, A133 7 and A141 2 years in 2026.yearsG702 (1992)34.0G703 (1992)34.0G706 (1994)32.0G706A (1994)32.0G707 (1994)32.0A101 (2017)9A102 (2017)9A201 (2017)9B101 (2017)9G701 (2017)9G704 (2017)9A133 (2019)7A141 (2024)2
Payment and closeout forms are the oldest current AIA editions: G702-1992 is 34 years old in 2026, while A141-2024 is 2 (AIA Contract Documents, accessed October 19, 2026).

An old year in the title does not mean a form is stale. AIA’s retired list, dated July 31, 2024, withdraws G702 editions up to 1983 and G704 editions up to 2000, which leaves G702-1992 and G704-2017 as the current forms (AIA retired documents list). AIA’s G704 summary also notes that AIA does not publish a standard schedule of values form, so G703 lines follow the contractor’s own schedule of values (AIA G704-2017 summary).

Which documents go together for each delivery method?

Choose the delivery method first and the AIA family follows. Design-bid-build uses A101 or A102 with A201 and B101; construction management at risk uses A133 with A201 and B133; design-build uses A141 with B141. A133-2019 is coordinated with A201-2017 and B133-2019 specifically, so mixing families can break the cross-references (AIA A133-2019 summary).

PieceDesign-bid-build, fixed priceDesign-bid-build, cost plus GMPConstruction management at riskDesign-build
Owner-builder agreementA101-2017A102-2017A133-2019 (GMP: Exhibit A)A141-2024 (progressive: A141PDB-2024)
General conditionsA201-2017A201-2017A201-2017No A201 (A141 set)
Owner-architectB101-2017B101-2017B133-2019B141-2024, signed by design-builder
Pay applicationG702-1992 + G703-1992G702GMP-2021 + G703CW-2021G702GMP-2021 + G703CW-2021G742-2024 + G743-2024
Substantial completionG704-2017G704-2017G704-2017G744-2024
ConsensusDocs equivalentCD 200No matrix rowCD 500 + 500.1CD 410 or 415
Grid of AIA agreements, general conditions, pay and completion forms and ConsensusDocs numbers for four delivery methods Which AIA documents pair up, by delivery method Current editions as of October 2026 Design-bid-build,fixed price Design-bid-build,cost plus GMP Constructionmanagement at risk Design-build Owner-builderagreement A101-2017 A102-2017 A133-2019GMP: Exhibit A A141-2024progressive:A141PDB-2024 Generalconditions A201-2017 A201-2017 A201-2017 No A201(A141 set) Owner-architect B101-2017 B101-2017 B133-2019 B141-2024signed by design-builder Pay application G702-1992 +G703-1992 G702GMP-2021 +G703CW-2021 G702GMP-2021 +G703CW-2021 G742-2024 +G743-2024 Substantialcompletion G704-2017 G704-2017 G704-2017 G744-2024 ConsensusDocsequivalent CD 200 No matrix row CD 500 + 500.1 CD 410 or 415 Sources: AIA Contract Documents product and help pages; ConsensusDocs comparison matrix (accessed 2026-10-19)
AIA pairs A101 and A102 with A201 and B101, A133 with A201 and B133, and A141 with B141; ConsensusDocs numbers from its comparison matrix (accessed October 19, 2026).

The design-build column is the 2024 family: AIA lists G741 through G745 and G841 as the matching change, payment, completion and directive forms (AIA 2024 design-build update). A201 is not among the documents the A201 summary lists as incorporating it, which is why the design-build column carries no A201. The trade-offs between these methods are set out in our design-build vs design-bid-build comparison.

If a construction manager will price the job during design, the A133 path applies, and the GMP mechanics behind its Exhibit A are explained in our guide to construction management at risk and the GMP. For a single design-and-build contract under A141-2024, the selection checks are in our guide to hiring design-build contractors.

How do the forms run from contract to closeout?

On a design-bid-build job the AIA forms arrive in a fixed order: B101 at design, A101 or A102 with A201 at builder selection, G702 and G703 every pay period, G701 for each agreed change, G704 at substantial completion, then G706, G706A and G707 before final payment. A201-2017 sets the timing rule behind each step (A201-2017 text).

  1. Design: the owner signs B101-2017; the architect’s five phases of basic services run from schematic design to construction.
  2. Builder selection: owner and contractor sign A101-2017 or A102-2017 + A201-2017, with Exhibit A setting insurance and bonds; AIA’s payment and performance bond form is A312-2010.
  3. Each pay period: the contractor submits G702-1992 + G703-1992 at least 10 days before the payment date (a line-by-line walk-through is in our AIA G702 guide), itemized by the schedule of values and backed by lien releases if required (A201 9.3.1).
  4. Each change: G701-2017 when owner, contractor and architect agree on price and time; G714-2017, a construction change directive, when they do not.
  5. Substantial completion: the architect prepares G704-2017 (A201 9.8.4), and warranties start on that date unless the form says otherwise.
  6. Final payment: G706-1994, G706A-1994, G707-1994 and the other items in A201 9.10.2 come in before final payment and the last retainage are due.
  7. Claims window: A201-2017 Section 15.1.2 cuts off claims not started within 10 years after substantial completion, and Section 15.3.1 makes mediation a condition before arbitration or litigation.
Seven-step timeline from B101 at design to G706, G706A and G707 at final payment and the 10-year claims limit The AIA document sequence on a design-bid-build project Timing rules from A201-2017; forms are current AIA editions, October 2026 1 Design B101-2017 Five phases of basic services 2 Builder selection A101-2017 or A102-2017 + A201-2017 Exhibit A sets insurance and bonds 3 Each pay period G702-1992 + G703-1992 Submit 10 days before the payment date (A201 9.3.1) 4 Each change G701-2017 or G714-2017 Agreed change order vs construction change directive 5 Substantial completion G704-2017 Architect certifies; warranties start (A201 9.8.4) 6 Final payment G706-1994, G706A-1994, G707-1994 Required before final payment (A201 9.10.2) 7 Claims window A201-2017 Section 15.1.2 Up to 10 years after substantial completion Sources: A201-2017 text (City of Rochester, NH sample); AIA help centre summaries (accessed 2026-10-19)
A201-2017 sets the timing: pay applications 10 days before the payment date (9.3.1), G704 at substantial completion (9.8.4), closeout forms before final payment (9.10.2), claims within 10 years (15.1.2).

Section 9.10.2 of A201-2017 lists six items that hold up final payment and the remaining retained percentage. Three of them map to AIA G-series forms that AIA sells at $59.99 each (AIA G706 summary).

A201-2017 Section 9.10.2 itemAIA formSigned byWhen it applies
(1) Affidavit that payrolls and bills are paidG706-1994Contractor, listing exceptionsAny project on A201
(6) Other payment or lien release data the owner requiresG706A-1994ContractorWhen the owner asks for releases
(4) Consent of surety, if anyG707-1994SuretyBonded projects
(2) and (3) Insurance certificate and renewal statementACORD 25 with G715-2017 supplementContractor and brokerInsurance that runs past final payment
(5) Special warrantiesNo AIA form; maker and subcontractor warrantiesContractorWhere specifications require them

G707 matters because the surety agrees that final payment does not release its bond obligations, which preserves the owner’s rights under the bond (G707-1994 summary). Bond thresholds under the Miller Act and state laws are in our construction surety bond statistics. Which lien waiver form to collect at each payment, and the lien deadlines and preliminary notice rules that decide whether a G706A release is enough, differ by state and are tracked in our mechanics lien laws by state table.

Which editions of AIA contract documents are current in October 2026?

As of October 2026 the conventional set is the 2017 edition (A101, A102, A201, B101), construction manager as constructor is 2019 (A133, B133), design-build is 2024 (A141, B141) and the payment and closeout forms date from 1992 and 1994. Several public pages, including one AIA page, still show an older edition or a different count (AIA A141-2024 summary).

What some pages sayWhere it appearsWhat the primary source saysPrimary source
A141-2014 is the design-build agreementAIA series list (modified Jul 23, 2026); ConsensusDocs matrix rows 410 and 415A141-2024 “replaces AIA Document A141-2014” and sells at $179.99AIA summary, store
G744-2014 is the design-build completion formAIA series listG744-2024 is in the 2024 design-build familyAIA 2024 update
Documents sit in “six series”AIA series list headerThe same list shows seven, including F for facility management (F101-2023)AIA list
“Over 180” or “nearly 200” formsAIA Rhode Island; AIA New York State“300+ documents”; the subscription page heading reads 236 contracts and formsAIA How it works, subscription page
G707 is the consent of surety to release of retainageAIA G706 summaryG707-1994 is titled Consent of Surety to Final PaymentAIA G707 summary

AIA publishes no fixed revision calendar; its explainer says documents are reviewed on an ongoing basis, and the families move as sets. The A201 summary lists A201-2007 as the prior edition, and AIA’s retired list shows A141-2004 withdrawn before the 2014 and 2024 design-build editions (AIA retired documents list).

How do you buy or license AIA contract documents?

AIA Contract Documents sells each document as a one-time use license, $179.99 for an agreement and $59.99 for a form, or as an unlimited annual subscription with 1, 3 or 5 seats and no published price. A one-time document “may be finalized only once”, and AIA Minnesota says members get 20% off digital purchases (AIA How it works; AIA Minnesota, October 2026).

Paper copies still exist: AIA Minnesota takes paper orders and ships them once a week. AIA New York State notes that the documents are copyrighted and licensed for one-time use, so an A201-2017 posted with a public bid is not a reusable template for your next project (AIA New York State).

The worked example below prices a 12-month design-bid-build job on one-time licenses, read from the October 2026 product pages. It assumes each monthly G702 and G703 is finalized as its own document, which is how we read “may be finalized only once”; confirm with AIA before budgeting.

LineDocumentsCountUnit priceSubtotalSource
AgreementsB101, A101, A2013$179.99$539.97AIA store
Monthly pay applications, 12 monthsG702 + G70324$59.99$1,439.76AIA store
CloseoutG704, G706, G706A, G7074$59.99$239.96AIA store
AIA list total31$2,219.69CB&C arithmetic
AIA total with 20% member discount31$1,775.75AIA Minnesota discount
ConsensusDocs Full Package, 1 year116 contracts$1,400.00ConsensusDocs pricing
One-time AIA licenses on a 12-month job vs a ConsensusDocs yearBar chart: AIA agreements $539.97, pay forms $1,439.76, closeout $239.96, AIA total $2,219.69 vs ConsensusDocs $1,400.$AIA agreements: B101, A101, A201540AIA pay forms: 12 G702 + 12 G7031,440AIA closeout: G704, G706, G706A, G707240AIA total, 31 one-time documents2,220ConsensusDocs Full Package, 1 year1,400
At list prices, 31 one-time AIA documents for a 12-month design-bid-build job total $2,219.69, against $1,400 for a year of the ConsensusDocs Full Package (aiacontracts.com, consensusdocs.org, October 2026).

The break point is about 23 forms. Twenty-three one-time forms at $59.99 cost $1,379.77 and the 24th takes the total to $1,439.76, past a year of the ConsensusDocs Full Package at $1,400. A contractor running more than one AIA job a year has a reason to ask AIA for a subscription quote at that volume, since AIA does not print one.

How does ConsensusDocs compare with AIA contract documents?

ConsensusDocs is the main alternative family: launched in 2007 by 20 organizations, now backed by more than 40 coalition members and sold as annual packages from $645 to $1,400. Its own matrix maps each form to an AIA number, such as ConsensusDocs 200 to A101 plus A201 and ConsensusDocs 500 to A133 plus A201 (ConsensusDocs comparison matrix, October 2026).

PointAIA Contract DocumentsConsensusDocsSource
StartedIndustry standard “since 1888” (publisher claim)2007, 20 founding organizationsACD, ConsensusDocs about
Drafted byAIA Documents Committee, 35+ membersCoalition of 40+ industry organizationsACD, ConsensusDocs about
Library300+ documents in 7 series110+ documents in 200 to 900 series; 116 in the Full PackageACD, ConsensusDocs catalog
Lump-sum owner-builder contractA101-2017 agreement + A201-2017 general conditions (2 documents)ConsensusDocs 200: agreement and general conditions in 1 documentConsensusDocs matrix
CM at riskA133-2019 + A201-2017ConsensusDocs 500 + 500.1 GMP amendmentConsensusDocs matrix
Design-buildA141-2024ConsensusDocs 410 (GMP) or 415 (lump sum)ConsensusDocs matrix
Owner-architectB101-2017ConsensusDocs 240ConsensusDocs matrix
Pay applicationG702-1992 + G703-1992ConsensusDocs 291 or 292 + 293 schedule of valuesConsensusDocs matrix
Price$179.99 or $59.99 per one-time document; subscription price not published$645 to $1,400 a year by package; Owner package $1,290 for 63 contractsACD store, ConsensusDocs pricing
Free reviewNo free sample offer on the AIA pages we readUp to 3 free contract samples on requestConsensusDocs home

The structural difference shows up first in a negotiation. If the other side sends ConsensusDocs 200, the matrix tells you its AIA counterpart is A101 with A201-2017, so your attorney can compare the two clause by clause instead of reading a new form cold.

Which contract family and form should you pick?

Match the agreement to how the price is set and who designs, then add forms for bonds and closeout. The decision table uses AIA’s own guidance: A101 for a fixed price, A102 for cost plus a GMP, A133 when the builder joins during design, A141 for design-build, and A104 or A105 for smaller jobs (AIA help centre, October 2026).

IfUseThreshold or reasonSource
Price is fixed by bid or negotiation before work startsA101-2017 + A201-2017, B101-2017Cost set in advanceAIA A101 summary
Owner pays actual cost up to a ceiling after designA102-2017 + A201-2017Cost plus fee with a GMPAIA A102 page
Builder joins during design and later gives a GMPA133-2019 + A201-2017, B133-2019GMP binds once Exhibit A is signedAIA A133 summary
One firm designs and buildsA141-2024; A141PDB-2024 if price develops progressivelyContract sum fixed by Exhibit B amendmentAIA A141 summary
Job is of limited scopeA104-2017AIA’s alternative to A101 + A201AIA A201 summary
Residential or small commercial jobA105-2017Smaller, less complex workAIA A201 summary
Contractor is bondedA312-2010 bonds; G707-1994 at final paymentSurety consent keeps bond rightsAIA G707 summary
You will finalize more than 23 one-time forms in a yearAsk AIA for a subscription quote, or price ConsensusDocs23 x $59.99 = $1,379.77 vs $1,400CB&C arithmetic
The other side or your lender already uses ConsensusDocsConsensusDocs 200, 500, or 410 / 415Matrix gives the AIA counterpartConsensusDocs matrix
Flowchart: one firm designs and builds leads to A141-2024; builder with GMP to A133; fixed price to A101; else A102 Which AIA owner-builder agreement fits? Will one firm design and build? Yes A141-2024progressive: A141PDB-2024 No: owner hires an architect Does the builder join during designand give a GMP? Yes A133-2019 + A201-2017architect: B133-2019 No Is the price fixed beforeconstruction starts? Yes A101-2017 + A201-2017architect: B101-2017 No: open book with a ceiling A102-2017 + A201-2017cost plus fee with a GMP Smaller jobs: A104-2017 (limited scope) or A105-2017 (residential or small commercial).Bonded job: add A312-2010 bonds and G707-1994 at final payment.
The same logic as the decision table: A141-2024 for design-build, A133-2019 for a GMP from a builder hired during design, A101-2017 for a fixed price, A102-2017 for open book with a ceiling (AIA help centre, October 2026).

The agreement is only part of the choice; the builder matters as much as the form. Our checklist for choosing a commercial contractor covers the A305 qualification statement, bonding letters and references to collect before you send an A101.

The seven phases where each of these forms gets signed, from feasibility to closeout, are laid out in our guide to the commercial construction process.

How we compiled this

We read 13 AIA Contract Documents product pages, 2 AIA licensing pages, 11 AIA help centre summaries, the AIA series list, the A201-2017 text posted with a City of Rochester, NH bid and 5 ConsensusDocs pages, all in October 2026. Prices are list prices shown to a logged-out visitor; we did not buy documents or use the software. Vendor blogs were read for question phrasing only, never as a source of fact, and no AIA contract text is reproduced beyond section references. On October 26, 2026 we re-checked the A201 and G702 prices and the A201-2017 sections cited here.

Frequently asked questions

Are AIA contract documents free?

No. AIA Contract Documents sells one-time licenses at $179.99 for an agreement such as A101-2017 and $59.99 for a form such as G702-1992, plus an unlimited annual subscription whose price is not published (aiacontracts.com, October 2026). The documents are copyrighted and licensed for one-time use. ConsensusDocs, the main alternative, offers up to three free samples before you buy.

Can you modify an AIA contract document?

Yes. AIA’s software lets users edit and finalize documents, and AIA publishes A503 as a guide for supplementary conditions that amend A201-2017. The A201 summary lists supplementary conditions as one of the contract documents, alongside the agreement, drawings and specifications (AIA help centre, October 2026). Ask your attorney for a redline that shows every change before anyone signs.

What is the difference between AIA A101 and A102?

A101-2017 is for a stipulated sum, a fixed price set by bid or negotiation before work starts. A102-2017 is for the cost of the work plus a fee with a guaranteed maximum price, so the owner pays actual costs up to a ceiling. Both adopt the A201-2017 general conditions and sell for $179.99 each as one-time documents (AIA, October 2026).

Is AIA A201 a contract on its own?

No. A201-2017 is the general conditions, and AIA calls it the keystone document because it is incorporated by reference into A101, A102, A103, A401, B101 and B103. It sets the rules for payment, changes, claims and completion across 15 articles, while price, time and the parties sit in the agreement it is attached to (AIA help centre, October 2026).

Are AIA contract documents valid in every state?

They can be used in any state, but AIA says the documents are not drafted to reflect the laws of any particular state. State statutes on liens, prompt payment, retainage and licensing can override a clause in A201-2017, which is why the A201 summary points users to A503, AIA’s guide for writing supplementary conditions (AIA, October 2026).

How often does the AIA update its contract documents?

AIA publishes no fixed schedule; its explainer says documents are reviewed on an ongoing basis. Families move together: the conventional set went from 2007 to 2017 editions, construction manager as constructor documents to 2019 and design-build to 2024. AIA’s retired list, dated July 31, 2024, shows which older editions have been withdrawn.

Which AIA forms are needed for final payment?

Under A201-2017 Section 9.10.2, final payment and remaining retainage wait for the contractor’s affidavit, proof of insurance, consent of surety if the job is bonded and any lien release data the owner requires. The AIA forms are G706-1994, G706A-1994 and G707-1994, each $59.99 as a one-time document, usually after G704-2017 records substantial completion.