
Mechanics lien laws by state: lien deadlines, preliminary notice and prompt pay rules for commercial subcontractors
- Primary data
- State mechanic's lien and private prompt payment statutes, 50 states and DC
- Data period
- Statutes in force on 2026-10-06
- Latest release used
- 2026-10-06
- Next release
- Quarterly re-check (next check January 2027)
- Geography
- United States: 50 states and the District of Columbia
- Sources
- 159 (156 Tier 1)
Mechanics lien laws by state give a subcontractor on private commercial work from 45 days (Hawaii) to 8 months (New York) to file a lien; the median across 51 jurisdictions is 90 days. 15 jurisdictions require preliminary notice, and 35 have a private prompt payment law.
Mechanic's lien and prompt payment rules by state
Checked quarterly. Last checked 2026-10-06. Entries are neutral records of public data; each links to its source record.
| State | Notice, lien deadline, enforcement and prompt pay | Date | Evidence | Source |
|---|---|---|---|---|
| Alabama | Notice: No. No early-job notice; a subcontractor must give the owner written notice of the lien claim before filing (35-11-218). Lien: 4 months after last work or materials (subcontractors; original contractors 6 months). Enforce: 6 months after maturity of the entire debt. Private prompt pay: owner 30 days; subs 7 days after prime is paid; 1% per month. (Ala. Code 35-11-215, 35-11-218, 35-11-221, 8-29-3) | 2026-10-06 | statute | Record |
| Alaska | Notice: No. Notice of right to lien is optional ('may'); it shifts the burden of proof. Lien: 120 days after completing the contract or ceasing work (15 days after a recorded notice of completion for claimants without a notice of right to lien). Enforce: 6 months after recording (or 6 months after a timely recorded extension notice). Private prompt pay: none located. (AS 34.35.064, 34.35.068, 34.35.080) | 2026-10-06 | statute | Record |
| Arizona | Notice: Required. Preliminary 20-day notice within 20 days after first furnishing. Lien: 120 days after completion (60 days after a recorded notice of completion). Enforce: 6 months after recording. Private prompt pay: owner 7 days; subs 7 days after prime is paid; 1.5% per month. (A.R.S. 33-992.01, 33-993, 33-998, 32-1182, 32-1183) | 2026-10-06 | statute | Record |
| Arkansas | Notice: Required. Commercial: notice of nonpayment to owner and contractor within 75 days after labor or materials supplied. Lien: 120 days after last furnishing. Enforce: 15 months after filing. Private prompt pay: none located. (Ark. Code 18-44-115(b), 18-44-117, 18-44-119) | 2026-10-06 | statute (unofficial FindLaw copy; official code is on a LexisNexis portal that scripts cannot open) | Record |
| California | Notice: Required. Preliminary notice within 20 days after first furnishing (late notice covers only work in the prior 20 days). Lien: Earlier of 90 days after completion or 30 days after a recorded notice of completion or cessation. Enforce: 90 days after recording. Private prompt pay: owner 30 days; subs 7 days after prime is paid; 2% per month. (Cal. Civ. Code 8204, 8414, 8460, 8800, 8811; Bus. and Prof. Code 7108.5) | 2026-01-01 | statute | Record |
| Colorado | Notice: No. No early-job notice; notice of intent at least 10 days before filing. Lien: 4 months after last labor or materials (laborers by the day: 2 months after completion). Enforce: 6 months after last work or completion. Private prompt pay: none located. (C.R.S. 38-22-109, 38-22-110) | 2026-10-06 | statute (official CRS 2024 printout) | Record |
| Connecticut | Notice: No. No early-job notice; subcontractors without an assented written subcontract give notice of intent within 90 days after ceasing work. Lien: 90 days after ceasing work (copy served on owner within 30 days after lodging). Enforce: 1 year after the lien is recorded. Private prompt pay: owner 30 days; subs 25 days after prime is paid; 1% per month. (Conn. Gen. Stat. 49-34, 49-35, 49-39, 42-158i, 42-158j, 42-158k) | 2026-10-06 | statute | Record |
| Delaware | Notice: No. No early-job notice. Lien: 120 days after completing labor or last delivery of materials (contractors 180 days). Enforce: The statement of claim is itself filed in Superior Court as the enforcement action. Private prompt pay: owner 30 days; subs 15 days after prime is paid; legal rate. (25 Del. C. 2711; 6 Del. C. 3506, 3507) | 2026-10-06 | statute | Record |
| District of Columbia | Notice: No. No early-job notice. Lien: Notice of intent during construction or within 90 days after completion or termination. Enforce: 180 days after recording the notice of intent. Private prompt pay: owner 15 days; subs 7 days after prime is paid; 1.5% per month. (D.C. Code 40-301.02, 40-303.13, 27A-102, 27A-103, 27A-104) | 2026-10-06 | statute | Record |
| Florida | Notice: Required. Notice to owner before or within 45 days after starting work. Lien: 90 days after final furnishing. Enforce: 1 year after recording. Private prompt pay: no fixed day count; s. 55.03 rate plus 12% per year. (Fla. Stat. 713.06, 713.08, 713.22, 715.12) | 2026-10-06 | statute | Record |
| Georgia | Notice: Conditional. Notice to contractor within 30 days of notice of commencement or first delivery, if a notice of commencement is filed. Lien: 90 days after completing the work. Enforce: 365 days after filing, plus notice of suit within 30 days. Private prompt pay: owner 15 days; subs 10 days after prime is paid; 1% per month. (O.C.G.A. 44-14-361.1, 44-14-361.5, 13-11-4, 13-11-7) | 2026-10-06 | statute (unofficial FindLaw copy; official code is on a LexisNexis portal that scripts cannot open) | Record |
| Hawaii | Notice: No. No early-job notice. Lien: Application and notice filed within 45 days after the date of completion. Enforce: 3 months after the order directing the lien to attach. Private prompt pay: subs 10 days after prime is paid; 1.5% per month. (HRS 507-43, 444-25) | 2026-10-06 | statute | Record |
| Idaho | Notice: No. No early-job notice for commercial work. Lien: 90 days after completing labor or materials. Enforce: 6 months after filing. Private prompt pay: none located. (Idaho Code 45-507, 45-510) | 2026-10-06 | statute | Record |
| Illinois | Notice: No. No early-job notice; subcontractor notice to owner within 90 days after completion. Lien: 4 months after completion to bind third parties (2 years as to the owner). Enforce: 2 years after completion. Private prompt pay: owner 15 days; subs 15 calendar days after prime is paid; 10% per year. (770 ILCS 60/7, 60/9, 60/24, 60/28; 815 ILCS 603/10, 603/20) | 2026-10-06 | statute | Record |
| Indiana | Notice: No. No early-job notice for commercial work. Lien: 90 days after last labor or materials (60 days for residential). Enforce: 1 year after recording. Private prompt pay: none located. (Ind. Code 32-28-3-3, 32-28-3-6) | 2026-10-06 | statute (unofficial FindLaw copy; official code is on an interactive IGA site that scripts cannot open) | Record |
| Iowa | Notice: No. No notice for first-tier subcontractors; lower tiers notify the general contractor within 30 days (572.33). Lien: 90 days for full rights; later posting (up to 2 years and 90 days) limited to unpaid contract balance. Enforce: 2 years after the 90-day period expires. Private prompt pay: none located. (Iowa Code 572.9, 572.10, 572.27, 572.33) | 2026-10-06 | statute | Record |
| Kansas | Notice: No. No early-job notice for commercial work. Lien: 3 months after last furnishing (5 months on non-residential work with a notice of extension). Enforce: 1 year after filing. Private prompt pay: owner 30 days; subs 7 business days after prime is paid; 18% per year. (K.S.A. 60-1103, 60-1105, 16-1803, 16-1804) | 2026-10-06 | statute | Record |
| Kentucky | Notice: No. No early-job notice; subcontractors notify owner of intent within 120 days after last furnishing (75 days for claims under $1,000). Lien: 6 months after ceasing work. Enforce: 12 months after filing. Private prompt pay: owner 30 days; subs 15 business days after prime is paid; 12% per year. (KRS 376.010, 376.080, 376.090, 371.405) | 2025-06-27 | statute | Record |
| Louisiana | Notice: No. No early-job notice for subcontractors. Lien: 60 days after notice of termination or substantial completion (30 days or 6 months when a notice of contract is filed). Enforce: 1 year after filing the statement. Private prompt pay: owner 35 days; subs 7 days after prime is paid; 1.5% per month penalty. (La. R.S. 9:4822, 9:4823, 9:2784) | 2026-10-06 | statute | Record |
| Maine | Notice: No. No early-job notice. Lien: 90 days after last labor or materials. Enforce: Suit within 120 days after last labor or materials. Private prompt pay: owner 20 days; subs 7 days after prime is paid; statutory rate plus 1% per month penalty. (10 M.R.S. 3253, 3255, 1113, 1114, 1118) | 2026-10-06 | statute | Record |
| Maryland | Notice: No. No early-job notice; notice of intention to the owner within 120 days after doing the work. Lien: Petition to establish the lien within 180 days after work finished (notice to owner within 120 days). Enforce: 1 year after the petition is filed. Private prompt pay: owner 30 days; subs 7 days after prime is paid; court-awarded interest. (Md. Real Prop. 9-104, 9-105, 9-109, 9-302) | 2026-10-06 | statute | Record |
| Massachusetts | Notice: No. No early-job notice. Lien: Notice of contract within 90 days after last work (60 days after a notice of substantial completion); statement of account within 120 days. Enforce: 90 days after filing the statement of account. Private prompt pay: no fixed day count. (M.G.L. c. 254 ss. 4, 8, 11; c. 149 ss. 29E, 29F) | 2026-10-06 | statute | Record |
| Michigan | Notice: Required. Notice of furnishing within 20 days after first furnishing (late notice reduces, does not defeat, the lien). Lien: 90 days after last furnishing. Enforce: 1 year after recording. Private prompt pay: none located. (MCL 570.1109, 570.1111, 570.1117) | 2026-10-06 | statute | Record |
| Minnesota | Notice: No. Prelien notice not required on non-residential projects over 5,000 square feet. Lien: 120 days after last work or materials. Enforce: 1 year after the last item of the claim. Private prompt pay: subs 10 days after prime is paid; 1.5% per month. (Minn. Stat. 514.011, 514.08, 514.12, 337.10) | 2026-10-06 | statute | Record |
| Mississippi | Notice: No. No notice for first-tier subcontractors; claimants without privity with the contractor notify it within 30 days. Lien: 90 days after last work or materials. Enforce: Payment action within 180 days after filing. Private prompt pay: subs 15 days after prime is paid; 0.5% per day penalty, capped at 15%. (Miss. Code 85-7-405, 85-7-407, 87-7-3, 87-7-5, 87-9-3) | 2026-10-06 | statute (unofficial FindLaw copy; official code is on a LexisNexis portal that scripts cannot open) | Record |
| Missouri | Notice: No. No early-job notice; 10 days' notice to the owner before filing. Lien: 6 months after the debt accrued. Enforce: 6 months after filing. Private prompt pay: no fixed day count; up to 1.5% per month. (RSMo 429.080, 429.100, 429.170, 431.180, 436.303) | 2026-10-06 | statute | Record |
| Montana | Notice: No. Commercial improvements are exempt from the notice of right to claim a lien. Lien: 90 days after final furnishing or a notice of completion. Enforce: 2 years after filing. Private prompt pay: owner 7 days; subs 7 days after prime is paid; 1.5% per month. (MCA 71-3-531, 71-3-535, 71-3-562, 28-2-2103, 28-2-2104) | 2026-10-06 | statute | Record |
| Nebraska | Notice: No. No early-job notice for commercial work. Lien: 120 days after final furnishing. Enforce: 2 years after recording. Private prompt pay: owner 30 days; subs 10 days after prime is paid; 1% per month. (Neb. Rev. Stat. 52-137, 52-140, 45-1203, 45-1204, 45-1205) | 2026-10-06 | statute | Record |
| Nevada | Notice: Required. Notice of right to lien; it covers work done in the 31 days before it is given. Lien: 90 days after completion or last work (40 days after a notice of completion). Enforce: 6 months after recording. Private prompt pay: owner 21 days; subs 10 days after prime is paid. (NRS 108.226, 108.233, 108.245, 624.609, 624.624) | 2026-10-06 | statute | Record |
| New Hampshire | Notice: Required. Notice to owner before performing the work (later notice allowed with limits). Lien: Lien lasts 120 days after work; secured by court attachment within that time. Enforce: Attachment within 120 days. Private prompt pay: none located. (RSA 447:5, 447:9, 447:10) | 2026-10-06 | statute | Record |
| New Jersey | Notice: No. No early-job notice for commercial work. Lien: 90 days after last work. Enforce: 1 year after last work. Private prompt pay: owner 30 days; subs 10 calendar days after prime is paid; prime rate plus 1%. (N.J.S.A. 2A:44A-6, 2A:44A-14, 2A:30A-2) | 2026-10-06 | statute (unofficial FindLaw copy; official code is on a LexisNexis portal that scripts cannot open) | Record |
| New Mexico | Notice: No. No notice for first-tier subcontractors; lower tiers give notice within 60 days on claims over $5,000. Lien: 90 days after completion. Enforce: 2 years after filing. Private prompt pay: owner 21 days; subs 7 days after prime is paid; 1.5% per month. (NMSA 48-2-6, 48-2-2.1, 48-2-10, 57-28-5) | 2026-10-06 | statute (unofficial FindLaw copy; official code is on a LexisNexis portal that scripts cannot open) | Record |
| New York | Notice: No. No early-job notice. Lien: 8 months after completion or final furnishing (4 months for a single-family dwelling). Enforce: 1 year after filing. Private prompt pay: owner 30 days; subs 7 days after prime is paid; 1% per month (late retainage). (N.Y. Lien Law 10, 17; Gen. Bus. Law 756, 756-a, 756-c) | 2026-10-06 | statute | Record |
| North Carolina | Notice: Conditional. Notice to lien agent within 15 days after first furnishing where a lien agent is designated. Lien: 120 days after last furnishing. Enforce: 180 days after last furnishing. Private prompt pay: subs 7 days after prime is paid; 1% per month. (N.C. Gen. Stat. 44A-11.2, 44A-12, 44A-13, 22C-2) | 2026-10-06 | statute | Record |
| North Dakota | Notice: No. No early-job notice; 10 days' notice before recording. Lien: 90 days after last contribution (later filing allowed with limits, up to 3 years). Enforce: 3 years after recording (30 days after an owner demand). Private prompt pay: none located. (N.D.C.C. 35-27-02, 35-27-13, 35-27-14, 35-27-25) | 2026-10-06 | statute | Record |
| Ohio | Notice: Conditional. Notice of furnishing within 21 days after first work, if a notice of commencement is recorded. Lien: 75 days after last work (60 days for 1 to 2 family dwellings). Enforce: Lien lasts 6 years; 60 days after an owner's notice to commence suit. Private prompt pay: subs 10 calendar days after prime is paid; 18% per year. (Ohio Rev. Code 1311.05, 1311.06, 1311.11, 1311.13, 4113.61) | 2026-10-06 | statute | Record |
| Oklahoma | Notice: No. No early-job notice; pre-lien notice within 75 days after last furnishing (claims of $10,000 or more). Lien: 90 days after last furnishing (original contractors 4 months). Enforce: 1 year after filing. Private prompt pay: owner 28 days; subs 10 calendar days after prime is paid. (42 O.S. 142.6, 143, 172; 15 O.S. 820) | 2026-10-06 | statute + agency page (Construction Industries Board copy, March 2024) | Record |
| Oregon | Notice: No. Notice of right to lien not needed for labor or labor and materials on a commercial improvement. Lien: 75 days after ceasing work or completion, whichever is earlier. Enforce: 120 days after filing. Private prompt pay: subs 7 days after prime is paid; 1.5% per month (owner). (ORS 87.021, 87.035, 87.055, 701.625, 701.630) | 2026-10-06 | statute | Record |
| Pennsylvania | Notice: Conditional. Notice of furnishing within 45 days on projects of $1,500,000 or more with a posted notice of commencement. Lien: 6 months after completing the work (30 days' notice of intent before filing). Enforce: 2 years after filing. Private prompt pay: owner 20 days; subs 14 days after prime is paid; 1% per month. (49 P.S. 1501, 1501.3, 1502, 1701; 73 P.S. 505, 507) | 2026-10-06 | statute | Record |
| Rhode Island | Notice: No. No early-job notice. Lien: Notice of intention within 200 days after the work. Enforce: Complaint and lis pendens within 40 days after recording the notice of intention. Private prompt pay: none located. (R.I. Gen. Laws 34-28-4, 34-28-10) | 2026-10-06 | statute | Record |
| South Carolina | Notice: No. No early-job notice for first-tier subcontractors. Lien: 90 days after last labor or materials. Enforce: 6 months after last labor or materials. Private prompt pay: owner 21 days; subs 7 days after prime is paid; 1% per month. (S.C. Code 29-5-90, 29-5-120, 29-6-30, 29-6-50) | 2026-10-06 | statute | Record |
| South Dakota | Notice: No. No notice for first-tier subcontractors (44-9-53 applies to lower tiers when a notice of project commencement is filed). Lien: 120 days after last work or materials. Enforce: 6 years after the last item (30 days after an owner demand). Private prompt pay: none located. (SDCL 44-9-15, 44-9-24, 44-9-26, 44-9-53) | 2026-10-06 | statute | Record |
| Tennessee | Notice: Required. Notice of nonpayment within 90 days after the end of each month with unpaid work (non-residential). Lien: 90 days after completion or abandonment of the improvement. Enforce: 90 days after service of the notice of lien. Private prompt pay: no fixed day count; 1.5% per month. (Tenn. Code 66-11-112, 66-11-115, 66-11-145, 66-34-103, 66-34-601) | 2026-10-06 | statute (unofficial FindLaw copy; official code is on a LexisNexis portal that scripts cannot open) | Record |
| Texas | Notice: Required. Notice of claim by the 15th day of the 3rd month after each month of unpaid work. Lien: 15th day of the 4th month after the month of last work (shortest interval about 105 days). Enforce: 1 year after the last day to file the lien affidavit. Private prompt pay: owner 35 days; subs 7 days after prime is paid; 1.5% per month. (Tex. Prop. Code 53.052, 53.056, 53.158, 28.002, 28.004) | 2022-01-01 | statute | Record |
| Utah | Notice: Required. Preliminary notice filed with the state registry within 20 days after starting work. Lien: 180 days after final completion (90 days after a notice of completion). Enforce: 180 days after filing the lien. Private prompt pay: none located. (Utah Code 38-1a-501, 38-1a-502, 38-1a-701, 13-8-5) | 2023-02-27 | statute | Record |
| Vermont | Notice: No. No timed notice; a subcontractor's lien reaches only the contract balance unpaid when the owner receives its notice. Lien: 180 days after payment became due for the last work. Enforce: 180 days after filing the memorandum. Private prompt pay: owner 20 days; subs 7 days after prime is paid; statutory rate plus 1% per month penalty. (9 V.S.A. 1921, 1924, 4002, 4003, 4007) | 2026-10-06 | statute | Record |
| Virginia | Notice: No. No early-job notice for commercial work. Lien: 90 days after the last day of the month of last work (and within 90 days of completion). Enforce: Later of 6 months after recording or 60 days after completion. Private prompt pay: owner 60 days; subs 7 days after prime is paid; per Va. Code 2.2-4355. (Va. Code 43-4, 43-7, 43-17, 11-4.6) | 2026-10-06 | statute | Record |
| Washington | Notice: No. Not required of subcontractors hired directly by the prime contractor. Lien: 90 days after ceasing work. Enforce: 8 calendar months after recording. Private prompt pay: none located. (RCW 60.04.031, 60.04.091, 60.04.141) | 2026-10-06 | statute | Record |
| West Virginia | Notice: No. No early-job notice. Lien: 100 days after completing the subcontract. Enforce: 6 months after filing. Private prompt pay: none located. (W. Va. Code 38-2-7, 38-2-9, 38-2-34) | 2026-10-06 | statute | Record |
| Wisconsin | Notice: No. 60-day notice not required where the improvement is partly or wholly non-residential. Lien: 6 months after last work or materials. Enforce: 2 years after filing the claim. Private prompt pay: none located. (Wis. Stat. 779.02, 779.06) | 2026-10-06 | statute | Record |
| Wyoming | Notice: Required. Preliminary notice within 30 days after first providing work or materials. Lien: 120 days after last work or substantial completion (contractors 150 days). Enforce: 180 days after filing. Private prompt pay: none located. (Wyo. Stat. 29-2-106, 29-2-109, 29-2-112) | 2026-10-06 | statute | Record |
Mechanics lien laws by state: how long subcontractors have to file
Most states give a subcontractor about three months. 26 of 51 jurisdictions fall between 60 and 90 days, and the median is 90 days. The long tail (Kentucky, Maryland, Missouri, Pennsylvania, Utah, Vermont, Wisconsin, Rhode Island and New York) runs from 6 months to 8 months.
We read the lien statute of each state and DC on 2026-10-06 and recorded the deadline for a first-tier subcontractor (hired by the prime contractor) on a private, non-residential project. Deadlines written in months were converted at 30 days a month so they can be compared. The shortest is 45 days (Hawaii), the median is 90 days, the mean is 113.5 days and the longest is 240 days (New York's 8 months).
Private commercial work; months converted at 30 days; checked 2026-10-06
Source: CB&C reading of each state's lien statute on official legislature or code sites (FindLaw copies for AR, GA, IN, MS, NJ, NM, TN), checked 2026-10-06
23 jurisdictions use exactly 90 days. The 91 to 120 day group (15 jurisdictions) includes states written as 4 months (Alabama, Colorado, Illinois) and Texas, whose 2022 rule sets the 15th day of the 4th month after the month of last work, which is about 105 days at its shortest.
50 states and DC, first-tier subcontractor, private commercial work
Source: CB&C analysis of state lien statutes, checked 2026-10-06
| Deadline bucket | Jurisdictions | Share | Which |
|---|---|---|---|
| Under 60 days | 1 | 2.0% | Hawaii |
| 60 to 90 days | 26 | 51.0% | Louisiana, Ohio, Oregon, California, Connecticut, District of Columbia, Florida, Georgia, Idaho, Indiana, Iowa, Kansas, Maine, Massachusetts, Michigan, Mississippi, Montana, Nevada, New Jersey, New Mexico, North Dakota, Oklahoma, South Carolina, Tennessee, Virginia, Washington |
| 91 to 120 days | 15 | 29.4% | West Virginia, Texas, Alabama, Alaska, Arizona, Arkansas, Colorado, Delaware, Illinois, Minnesota, Nebraska, New Hampshire, North Carolina, South Dakota, Wyoming |
| Over 120 days | 9 | 17.6% | Kentucky, Maryland, Missouri, Pennsylvania, Utah, Vermont, Wisconsin, Rhode Island, New York |
| All jurisdictions | 51 | 100% | Minimum 45 days, median 90 days, mean 113.5 days, maximum 240 days |
Day-equivalents: months x 30; Texas uses the shortest interval of its '15th day of the 4th month' rule. Private commercial work, first-tier subcontractor.
Source: [38][109][31][139] Hawaii State Legislature; New York State Senate, Open Legislation; The Florida Legislature, Online Sunshine; Texas Legislature, Texas Constitution and Statutes
Mechanic's lien: A claim recorded against real property by someone who improved it and was not paid. If it is enforced in court in time, the property can be sold to pay the debt.
Day-equivalent: Our conversion of each statutory deadline into days (months x 30) so states can be compared. The statute wording, not the day count, controls.

For licensing rules that sit alongside these lien rights, see our commercial contractor licensing registry, which records the state licence rules that apply before any of these lien rights matter.
Shortest and longest lien deadlines
Hawaii, Louisiana, Ohio and Oregon give subcontractors the least time. New York, Rhode Island and seven states at 6 months give the most, but a long filing window can come with a short window to sue.
Hawaii requires the application and notice within 45 days after the date of completion of the improvement, and the lien expires 3 months after the court's order directing it to attach unless suit is filed. Louisiana's private works rule is 60 days after a notice of termination or substantial completion. Ohio allows 75 days after last work on commercial projects, and Oregon 75 days after the claimant stops work or the project is completed, whichever is earlier.
At the long end, New York allows 8 months after completion on commercial work (4 months for a single-family dwelling). Rhode Island allows 200 days for a notice of intention but then requires a complaint and lis pendens within 40 days of recording it. Utah allows 180 days after final completion unless the owner files a notice of completion, which cuts it to 90 days.
Show all 51 rows
| Rank | Jurisdiction | Day-equivalent | Statute wording (summarised) | Statute |
|---|---|---|---|---|
| 1 | Hawaii | 45 | Application and notice filed within 45 days after the date of completion | HRS 507-43, 444-25 |
| 2 | Louisiana | 60 | 60 days after notice of termination or substantial completion (30 days or 6 months when a notice of contract is filed) | La. R.S. 9:4822, 9:4823, 9:2784 |
| 3 | Ohio | 75 | 75 days after last work (60 days for 1 to 2 family dwellings) | Ohio Rev. Code 1311.05, 1311.06, 1311.11, 1311.13, 4113.61 |
| 4 | Oregon | 75 | 75 days after ceasing work or completion, whichever is earlier | ORS 87.021, 87.035, 87.055, 701.625, 701.630 |
| 5 | California | 90 | Earlier of 90 days after completion or 30 days after a recorded notice of completion or cessation | Cal. Civ. Code 8204, 8414, 8460, 8800, 8811 |
| 6 | Connecticut | 90 | 90 days after ceasing work (copy served on owner within 30 days after lodging) | Conn. Gen. Stat. 49-34, 49-35, 49-39, 42-158i, 42-158j, 42-158k |
| 7 | District of Columbia | 90 | Notice of intent during construction or within 90 days after completion or termination | D.C. Code 40-301.02, 40-303.13, 27A-102, 27A-103, 27A-104 |
| 8 | Florida | 90 | 90 days after final furnishing | Fla. Stat. 713.06, 713.08, 713.22, 715.12 |
| 9 | Georgia | 90 | 90 days after completing the work | O.C.G.A. 44-14-361.1, 44-14-361.5, 13-11-4, 13-11-7 |
| 10 | Idaho | 90 | 90 days after completing labor or materials | Idaho Code 45-507, 45-510 |
| 11 | Indiana | 90 | 90 days after last labor or materials (60 days for residential) | Ind. Code 32-28-3-3, 32-28-3-6 |
| 12 | Iowa | 90 | 90 days for full rights; later posting (up to 2 years and 90 days) limited to unpaid contract balance | Iowa Code 572.9, 572.10, 572.27, 572.33 |
| 13 | Kansas | 90 | 3 months after last furnishing (5 months on non-residential work with a notice of extension) | K.S.A. 60-1103, 60-1105, 16-1803, 16-1804 |
| 14 | Maine | 90 | 90 days after last labor or materials | 10 M.R.S. 3253, 3255, 1113, 1114, 1118 |
| 15 | Massachusetts | 90 | Notice of contract within 90 days after last work (60 days after a notice of substantial completion); statement of account within 120 days | M.G.L. c. 254 ss. 4, 8, 11 |
| 16 | Michigan | 90 | 90 days after last furnishing | MCL 570.1109, 570.1111, 570.1117 |
| 17 | Mississippi | 90 | 90 days after last work or materials | Miss. Code 85-7-405, 85-7-407, 87-7-3, 87-7-5, 87-9-3 |
| 18 | Montana | 90 | 90 days after final furnishing or a notice of completion | MCA 71-3-531, 71-3-535, 71-3-562, 28-2-2103, 28-2-2104 |
| 19 | Nevada | 90 | 90 days after completion or last work (40 days after a notice of completion) | NRS 108.226, 108.233, 108.245, 624.609, 624.624 |
| 20 | New Jersey | 90 | 90 days after last work | N.J.S.A. 2A:44A-6, 2A:44A-14, 2A:30A-2 |
| 21 | New Mexico | 90 | 90 days after completion | NMSA 48-2-6, 48-2-2.1, 48-2-10, 57-28-5 |
| 22 | North Dakota | 90 | 90 days after last contribution (later filing allowed with limits, up to 3 years) | N.D.C.C. 35-27-02, 35-27-13, 35-27-14, 35-27-25 |
| 23 | Oklahoma | 90 | 90 days after last furnishing (original contractors 4 months) | 42 O.S. 142.6, 143, 172 |
| 24 | South Carolina | 90 | 90 days after last labor or materials | S.C. Code 29-5-90, 29-5-120, 29-6-30, 29-6-50 |
| 25 | Tennessee | 90 | 90 days after completion or abandonment of the improvement | Tenn. Code 66-11-112, 66-11-115, 66-11-145, 66-34-103, 66-34-601 |
| 26 | Virginia | 90 | 90 days after the last day of the month of last work (and within 90 days of completion) | Va. Code 43-4, 43-7, 43-17, 11-4.6 |
| 27 | Washington | 90 | 90 days after ceasing work | RCW 60.04.031, 60.04.091, 60.04.141 |
| 28 | West Virginia | 100 | 100 days after completing the subcontract | W. Va. Code 38-2-7, 38-2-9, 38-2-34 |
| 29 | Texas | 105 | 15th day of the 4th month after the month of last work (shortest interval about 105 days) | Tex. Prop. Code 53.052, 53.056, 53.158, 28.002, 28.004 |
| 30 | Alabama | 120 | 4 months after last work or materials (subcontractors; original contractors 6 months) | Ala. Code 35-11-215, 35-11-218, 35-11-221, 8-29-3 |
| 31 | Alaska | 120 | 120 days after completing the contract or ceasing work (15 days after a recorded notice of completion for claimants without a notice of right to lien) | AS 34.35.064, 34.35.068, 34.35.080 |
| 32 | Arizona | 120 | 120 days after completion (60 days after a recorded notice of completion) | A.R.S. 33-992.01, 33-993, 33-998, 32-1182, 32-1183 |
| 33 | Arkansas | 120 | 120 days after last furnishing | Ark. Code 18-44-115(b), 18-44-117, 18-44-119 |
| 34 | Colorado | 120 | 4 months after last labor or materials (laborers by the day: 2 months after completion) | C.R.S. 38-22-109, 38-22-110 |
| 35 | Delaware | 120 | 120 days after completing labor or last delivery of materials (contractors 180 days) | 25 Del. C. 2711 |
| 36 | Illinois | 120 | 4 months after completion to bind third parties (2 years as to the owner) | 770 ILCS 60/7, 60/9, 60/24, 60/28 |
| 37 | Minnesota | 120 | 120 days after last work or materials | Minn. Stat. 514.011, 514.08, 514.12, 337.10 |
| 38 | Nebraska | 120 | 120 days after final furnishing | Neb. Rev. Stat. 52-137, 52-140, 45-1203, 45-1204, 45-1205 |
| 39 | New Hampshire | 120 | Lien lasts 120 days after work; secured by court attachment within that time | RSA 447:5, 447:9, 447:10 |
| 40 | North Carolina | 120 | 120 days after last furnishing | N.C. Gen. Stat. 44A-11.2, 44A-12, 44A-13, 22C-2 |
| 41 | South Dakota | 120 | 120 days after last work or materials | SDCL 44-9-15, 44-9-24, 44-9-26, 44-9-53 |
| 42 | Wyoming | 120 | 120 days after last work or substantial completion (contractors 150 days) | Wyo. Stat. 29-2-106, 29-2-109, 29-2-112 |
| 43 | Kentucky | 180 | 6 months after ceasing work | KRS 376.010, 376.080, 376.090, 371.405 |
| 44 | Maryland | 180 | Petition to establish the lien within 180 days after work finished (notice to owner within 120 days) | Md. Real Prop. 9-104, 9-105, 9-109, 9-302 |
| 45 | Missouri | 180 | 6 months after the debt accrued | RSMo 429.080, 429.100, 429.170, 431.180, 436.303 |
| 46 | Pennsylvania | 180 | 6 months after completing the work (30 days' notice of intent before filing) | 49 P.S. 1501, 1501.3, 1502, 1701 |
| 47 | Utah | 180 | 180 days after final completion (90 days after a notice of completion) | Utah Code 38-1a-501, 38-1a-502, 38-1a-701, 13-8-5 |
| 48 | Vermont | 180 | 180 days after payment became due for the last work | 9 V.S.A. 1921, 1924, 4002, 4003, 4007 |
| 49 | Wisconsin | 180 | 6 months after last work or materials | Wis. Stat. 779.02, 779.06 |
| 50 | Rhode Island | 200 | Notice of intention within 200 days after the work | R.I. Gen. Laws 34-28-4, 34-28-10 |
| 51 | New York | 240 | 8 months after completion or final furnishing (4 months for a single-family dwelling) | N.Y. Lien Law 10, 17 |
Triggers differ: last work, completion of the project, or a recorded notice of completion. Read the statute before relying on a day count.
Source: [38][55][117][124][109][128] Hawaii State Legislature; Louisiana State Legislature; Ohio Legislative Service Commission; Oregon State Legislature; New York State Senate, Open Legislation; State of Rhode Island General Assembly
States that require preliminary notice
15 of 51 jurisdictions require early notice from a first-tier subcontractor: 11 on every private commercial job and 4 only when a notice of commencement or lien agent exists. Missing the notice usually limits or defeats the lien.
1 = required (always or when a notice of commencement or lien agent exists), 0 = not required
Source: CB&C reading of state lien statutes, checked 2026-10-06
The 11 always-required jurisdictions are Arizona, Arkansas, California, Florida, Michigan, Nevada, New Hampshire, Tennessee, Texas, Utah, Wyoming. The windows are short: 20 days after first furnishing in Arizona, California, Michigan and Utah, 30 days in Wyoming, 45 days in Florida, and monthly notices in Texas and Tennessee. Arkansas requires a notice of nonpayment within 75 days after work is supplied on commercial projects.
Georgia (30 days), Ohio (21 days) and Pennsylvania (45 days, projects of $1,500,000 or more) tie notice to a recorded notice of commencement, and North Carolina to a designated lien agent (15 days). Several states that exempt first-tier subcontractors still require notice from sub-subcontractors and suppliers, including Iowa, Mississippi, New Mexico and South Dakota.
| Jurisdiction | Status | Rule | Statute |
|---|---|---|---|
| Arizona | Required on every private commercial job | Preliminary 20-day notice within 20 days after first furnishing | A.R.S. 33-992.01, 33-993, 33-998, 32-1182, 32-1183 |
| Arkansas | Required on every private commercial job | Commercial: notice of nonpayment to owner and contractor within 75 days after labor or materials supplied | Ark. Code 18-44-115(b), 18-44-117, 18-44-119 |
| California | Required on every private commercial job | Preliminary notice within 20 days after first furnishing (late notice covers only work in the prior 20 days) | Cal. Civ. Code 8204, 8414, 8460, 8800, 8811; Bus. and Prof. Code 7108.5 |
| Florida | Required on every private commercial job | Notice to owner before or within 45 days after starting work | Fla. Stat. 713.06, 713.08, 713.22, 715.12 |
| Michigan | Required on every private commercial job | Notice of furnishing within 20 days after first furnishing (late notice reduces, does not defeat, the lien) | MCL 570.1109, 570.1111, 570.1117 |
| Nevada | Required on every private commercial job | Notice of right to lien; it covers work done in the 31 days before it is given | NRS 108.226, 108.233, 108.245, 624.609, 624.624 |
| New Hampshire | Required on every private commercial job | Notice to owner before performing the work (later notice allowed with limits) | RSA 447:5, 447:9, 447:10 |
| Tennessee | Required on every private commercial job | Notice of nonpayment within 90 days after the end of each month with unpaid work (non-residential) | Tenn. Code 66-11-112, 66-11-115, 66-11-145, 66-34-103, 66-34-601 |
| Texas | Required on every private commercial job | Notice of claim by the 15th day of the 3rd month after each month of unpaid work | Tex. Prop. Code 53.052, 53.056, 53.158, 28.002, 28.004 |
| Utah | Required on every private commercial job | Preliminary notice filed with the state registry within 20 days after starting work | Utah Code 38-1a-501, 38-1a-502, 38-1a-701, 13-8-5 |
| Wyoming | Required on every private commercial job | Preliminary notice within 30 days after first providing work or materials | Wyo. Stat. 29-2-106, 29-2-109, 29-2-112 |
| Georgia | Required when a notice of commencement or lien agent exists | Notice to contractor within 30 days of notice of commencement or first delivery, if a notice of commencement is filed | O.C.G.A. 44-14-361.1, 44-14-361.5, 13-11-4, 13-11-7 |
| North Carolina | Required when a notice of commencement or lien agent exists | Notice to lien agent within 15 days after first furnishing where a lien agent is designated | N.C. Gen. Stat. 44A-11.2, 44A-12, 44A-13, 22C-2 |
| Ohio | Required when a notice of commencement or lien agent exists | Notice of furnishing within 21 days after first work, if a notice of commencement is recorded | Ohio Rev. Code 1311.05, 1311.06, 1311.11, 1311.13, 4113.61 |
| Pennsylvania | Required when a notice of commencement or lien agent exists | Notice of furnishing within 45 days on projects of $1,500,000 or more with a posted notice of commencement | 49 P.S. 1501, 1501.3, 1502, 1701; 73 P.S. 505, 507 |
Notices due only shortly before or after a lien filing (notice of intent) are not counted. Lower-tier rules can be stricter.
Source: [6][14][30][139][141][156][35][118][114][126] Arizona State Legislature; California Legislative Information; The Florida Legislature, Online Sunshine; Texas Legislature, Texas Constitution and Statutes; Utah State Legislature; Wyoming Legislature; FindLaw (Thomson Reuters) copy of the Official Code of Georgia; Ohio Legislative Service Commission; North Carolina General Assembly; Pennsylvania General Assembly
Preliminary notice: A notice sent early in a job (or monthly) telling the owner and prime contractor that the sender may claim a lien if unpaid. It is different from a notice of intent sent shortly before filing.
Private prompt payment acts, deadlines and interest rates
35 jurisdictions set payment timing for private construction. Seven days after the prime contractor is paid is the most common flow-down rule, and interest on late payment is usually 1% to 1.5% per month.
35 jurisdictions with a private prompt payment statute
Source: CB&C reading of state prompt payment statutes, checked 2026-10-06
17 jurisdictions require the prime contractor to pay subcontractors within 7 days of receiving payment, 8 within 10 days, 5 within 14 or 15 days (Kentucky counts business days), and Connecticut within 25 days. Florida, Massachusetts, Missouri and Tennessee regulate payment without a single flow-down day count.
25 jurisdictions also set an owner-to-prime deadline, with a median of 30 days. Triggers differ: Texas and Louisiana count 35 days from the owner's receipt of a payment request, Virginia 60 days from an invoice, and Arizona and Montana 7 days after a request is certified or approved.
Show all 35 rows
| Jurisdiction | Owner to prime contractor (days) | Prime to subcontractor after receipt | Interest or penalty | Statute |
|---|---|---|---|---|
| Alabama | 30 | 7 days | 1% per month | Ala. Code 35-11-215, 35-11-218, 35-11-221, 8-29-3 |
| Arizona | 7 | 7 days | 1.5% per month | A.R.S. 33-992.01, 33-993, 33-998, 32-1182, 32-1183 |
| California | 30 | 7 days | 2% per month | Cal. Civ. Code 8204, 8414, 8460, 8800, 8811; Bus. and Prof. Code 7108.5 |
| Connecticut | 30 | 25 days | 1% per month | Conn. Gen. Stat. 49-34, 49-35, 49-39, 42-158i, 42-158j, 42-158k |
| Delaware | 30 | 15 days | legal rate | 25 Del. C. 2711; 6 Del. C. 3506, 3507 |
| District of Columbia | 15 | 7 days | 1.5% per month | D.C. Code 40-301.02, 40-303.13, 27A-102, 27A-103, 27A-104 |
| Florida | Not fixed by statute | Not fixed by statute | s. 55.03 rate plus 12% per year | Fla. Stat. 713.06, 713.08, 713.22, 715.12 |
| Georgia | 15 | 10 days | 1% per month | O.C.G.A. 44-14-361.1, 44-14-361.5, 13-11-4, 13-11-7 |
| Hawaii | Not fixed by statute | 10 days | 1.5% per month | HRS 507-43, 444-25 |
| Illinois | 15 | 15 calendar days | 10% per year | 770 ILCS 60/7, 60/9, 60/24, 60/28; 815 ILCS 603/10, 603/20 |
| Kansas | 30 | 7 business days | 18% per year | K.S.A. 60-1103, 60-1105, 16-1803, 16-1804 |
| Kentucky | 30 | 15 business days | 12% per year | KRS 376.010, 376.080, 376.090, 371.405 |
| Louisiana | 35 | 7 days | 1.5% per month penalty | La. R.S. 9:4822, 9:4823, 9:2784 |
| Maine | 20 | 7 days | statutory rate plus 1% per month penalty | 10 M.R.S. 3253, 3255, 1113, 1114, 1118 |
| Maryland | 30 | 7 days | court-awarded interest | Md. Real Prop. 9-104, 9-105, 9-109, 9-302 |
| Massachusetts | Not fixed by statute | Not fixed by statute | Not stated in sections reviewed | M.G.L. c. 254 ss. 4, 8, 11; c. 149 ss. 29E, 29F |
| Minnesota | Not fixed by statute | 10 days | 1.5% per month | Minn. Stat. 514.011, 514.08, 514.12, 337.10 |
| Mississippi | Not fixed by statute | 15 days | 0.5% per day penalty, capped at 15% | Miss. Code 85-7-405, 85-7-407, 87-7-3, 87-7-5, 87-9-3 |
| Missouri | Not fixed by statute | Not fixed by statute | up to 1.5% per month | RSMo 429.080, 429.100, 429.170, 431.180, 436.303 |
| Montana | 7 | 7 days | 1.5% per month | MCA 71-3-531, 71-3-535, 71-3-562, 28-2-2103, 28-2-2104 |
| Nebraska | 30 | 10 days | 1% per month | Neb. Rev. Stat. 52-137, 52-140, 45-1203, 45-1204, 45-1205 |
| Nevada | 21 | 10 days | Not stated in sections reviewed | NRS 108.226, 108.233, 108.245, 624.609, 624.624 |
| New Jersey | 30 | 10 calendar days | prime rate plus 1% | N.J.S.A. 2A:44A-6, 2A:44A-14, 2A:30A-2 |
| New Mexico | 21 | 7 days | 1.5% per month | NMSA 48-2-6, 48-2-2.1, 48-2-10, 57-28-5 |
| New York | 30 | 7 days | 1% per month (late retainage) | N.Y. Lien Law 10, 17; Gen. Bus. Law 756, 756-a, 756-c |
| North Carolina | Not fixed by statute | 7 days | 1% per month | N.C. Gen. Stat. 44A-11.2, 44A-12, 44A-13, 22C-2 |
| Ohio | Not fixed by statute | 10 calendar days | 18% per year | Ohio Rev. Code 1311.05, 1311.06, 1311.11, 1311.13, 4113.61 |
| Oklahoma | 28 | 10 calendar days | Not stated in sections reviewed | 42 O.S. 142.6, 143, 172; 15 O.S. 820 |
| Oregon | Not fixed by statute | 7 days | 1.5% per month (owner) | ORS 87.021, 87.035, 87.055, 701.625, 701.630 |
| Pennsylvania | 20 | 14 days | 1% per month | 49 P.S. 1501, 1501.3, 1502, 1701; 73 P.S. 505, 507 |
| South Carolina | 21 | 7 days | 1% per month | S.C. Code 29-5-90, 29-5-120, 29-6-30, 29-6-50 |
| Tennessee | Not fixed by statute | Not fixed by statute | 1.5% per month | Tenn. Code 66-11-112, 66-11-115, 66-11-145, 66-34-103, 66-34-601 |
| Texas | 35 | 7 days | 1.5% per month | Tex. Prop. Code 53.052, 53.056, 53.158, 28.002, 28.004 |
| Vermont | 20 | 7 days | statutory rate plus 1% per month penalty | 9 V.S.A. 1921, 1924, 4002, 4003, 4007 |
| Virginia | 60 | 7 days | per Va. Code 2.2-4355 | Va. Code 43-4, 43-7, 43-17, 11-4.6 |
Owner deadlines run from different triggers (receipt, approval, certification, billing date). Many statutes apply only when the contract is silent.
Source: [140][17][18][36][49][57][104][150] Texas Legislature, Texas Constitution and Statutes; California Legislative Information; California Legislative Information; FindLaw (Thomson Reuters) copy of the Official Code of Georgia; Kansas Office of Revisor of Statutes; Louisiana State Legislature; FindLaw (Thomson Reuters) copy of the New Jersey Statutes; Virginia General Assembly, Legislative Information System

Payment terms are one reason to read bid documents closely; our guide on how to compare construction bids covers payment and retainage clauses, and slow payment is one of the pressures discussed in our analysis of the construction business failure rate.
| Deadline after the prime is paid | Jurisdictions | Which |
|---|---|---|
| 7 days | 17 | Alabama, Arizona, California, District of Columbia, Kansas, Louisiana, Maine, Maryland, Montana, New Mexico, New York, North Carolina, Oregon, South Carolina, Texas, Vermont, Virginia |
| 10 days | 8 | Georgia, Hawaii, Minnesota, Nebraska, Nevada, New Jersey, Ohio, Oklahoma |
| 14 or 15 days | 5 | Delaware, Illinois, Kentucky, Mississippi, Pennsylvania |
| 25 days | 1 | Connecticut |
| No fixed day count | 4 | Florida, Massachusetts, Missouri, Tennessee |
Kansas counts 7 business days and Kentucky 15 business days. 'No fixed day count' covers Florida, Massachusetts, Missouri and Tennessee.
Source: [18][140][115][121][54] California Legislative Information; Texas Legislature, Texas Constitution and Statutes; North Carolina General Assembly; Ohio Legislative Service Commission; Kentucky General Assembly
Retainage caps on private work
13 jurisdictions cap retainage on private projects by statute. 10 set 5% and 3 allow 10%, two of them stepping down to 5% once the work is half done.
California's cap is the newest: Civil Code 8811 limits retention to 5% of each payment and of the contract price for private works contracts entered on or after 2026-01-01, unless payment and performance bonds are required. Massachusetts applies its 5% cap to projects of $3,000,000 or more and New York to projects of $150,000 or more.
| Jurisdiction | Cap | Rule | Statute |
|---|---|---|---|
| California | 5% | 5% of each payment and of the contract price (contracts on or after 2026-01-01, unless bonds are required) | Cal. Civ. Code 8204, 8414, 8460, 8800, 8811; Bus. and Prof. Code 7108.5 |
| Connecticut | 5% | 5% of each progress payment (contracts over $25,000) | Conn. Gen. Stat. 49-34, 49-35, 49-39, 42-158i, 42-158j, 42-158k |
| Kansas | 5% | 5% (up to 10% if needed to ensure performance) | K.S.A. 60-1103, 60-1105, 16-1803, 16-1804 |
| Massachusetts | 5% | 5% of progress payments (projects of $3,000,000 or more) | M.G.L. c. 254 ss. 4, 8, 11; c. 149 ss. 29E, 29F |
| Minnesota | 5% | 5% | Minn. Stat. 514.011, 514.08, 514.12, 337.10 |
| Mississippi | 5% | 5% | Miss. Code 85-7-405, 85-7-407, 87-7-3, 87-7-5, 87-9-3 |
| Nevada | 5% | 5% of each payment (owner to prime contractor) | NRS 108.226, 108.233, 108.245, 624.609, 624.624 |
| New York | 5% | 5% (projects of $150,000 or more) | N.Y. Lien Law 10, 17; Gen. Bus. Law 756, 756-a, 756-c |
| Tennessee | 5% | 5% of the contract amount | Tenn. Code 66-11-112, 66-11-115, 66-11-145, 66-34-103, 66-34-601 |
| Utah | 5% | 5% of each payment and of the total price | Utah Code 38-1a-501, 38-1a-502, 38-1a-701, 13-8-5 |
| Illinois | 10% | 10% until 50% complete, then 5% | 770 ILCS 60/7, 60/9, 60/24, 60/28; 815 ILCS 603/10, 603/20 |
| Missouri | 10% | 10% of each payment | RSMo 429.080, 429.100, 429.170, 431.180, 436.303 |
| Nebraska | 10% | 10%, then 5% of later payments once 50% complete | Neb. Rev. Stat. 52-137, 52-140, 45-1203, 45-1204, 45-1205 |
Massachusetts applies to projects of $3,000,000 or more; New York to projects of $150,000 or more; California to contracts entered on or after 2026-01-01.
Source: [19][22][50][71][78][83][100][112][137][144][43][88][97] California Legislative Information; Connecticut General Assembly; Kansas Office of Revisor of Statutes; The 194th General Court of Massachusetts; Minnesota Office of the Revisor of Statutes; FindLaw (Thomson Reuters) copy of the Mississippi Code; Nevada Legislature; New York State Senate, Open Legislation; FindLaw (Thomson Reuters) copy of the Tennessee Code; Utah State Legislature; Illinois General Assembly; Missouri Revisor of Statutes; Nebraska Legislature
Retainage: A share of each progress payment held back until the work is complete, used as security for performance.
Counts and distributions
Distribution of subcontractor lien deadlines
Formulamin, median, mean, max of lien day-equivalents; counts by bucket (under 60, 60 to 90, 91 to 120, over 120)
Inputs: lien rows for all 51 jurisdictions (e.g. 69, 110, 200, 243); derived d1 to d10 (fact sheet rows)
Result: Minimum 45, median 90, mean 113.5, maximum 240 days. Buckets: 1, 26, 15, 9 jurisdictions.
51.0% of jurisdictions give 60 to 90 days, so a subcontractor who tracks a 60-day internal deadline is inside the window almost everywhere except Hawaii.
Limitations: Months are converted at 30 days; deadlines run from different triggers (last work, completion, notice of completion), so day counts are approximate and not interchangeable.
Preliminary notice requirement count
Formulacount of jurisdictions coded 2 (required) or 1 (conditional) for a first-tier subcontractor
Inputs: notice rows for all 51 jurisdictions; derived d11 to d14 (fact sheet rows)
Result: 11 required, 4 conditional, 15 total (29.4% of 51).
About 3 in 10 jurisdictions make early notice a condition of full lien rights for a subcontractor hired by the prime contractor.
Limitations: Lower-tier subcontractors and suppliers face notice rules in more states; notices due shortly before filing are excluded by definition.
Private prompt payment statutes and flow-down deadlines
Formulacount of jurisdictions with a private prompt payment statute; distribution of prime-to-subcontractor deadlines; median owner deadline
Inputs: pp, sub and owner rows; derived d15 to d22 (fact sheet rows)
Result: 35 jurisdictions (68.6%). Flow-down: 17 at 7 days, 8 at 10, 5 at 14 or 15, 1 at 25, 4 with no fixed count. Median owner deadline 30 days (25 jurisdictions).
Where a statute exists, the subcontractor's clock is usually a week after the prime is paid, but the prime's own clock runs from different events, so total time to payment varies widely.
Limitations: 'None located' means no private payment-timing statute was found in the sections reviewed; most statutes yield to contract terms when the contract sets them.
Statutory retainage caps on private work
Formulacount of jurisdictions whose statute caps private retainage; count by cap level
Inputs: retainage rows; derived d23 to d25 (fact sheet rows)
Result: 13 jurisdictions: 10 at 5%, 3 at 10%.
A 5% cap is now the most common statutory limit on private retainage among states that set one.
Limitations: Thresholds (Massachusetts $3,000,000, New York $150,000, Connecticut over $25,000) and bond exceptions mean a cap may not apply to a given job.
Sensitivity check: excluding unofficial statute copies
Formularecompute median lien deadline, notice count and prompt pay count without AR, GA, IN, MS, NJ, NM, TN
Inputs: derived d26 to d29 (fact sheet rows)
Result: Median 102.5 days; 12 notice jurisdictions; 30 prompt pay jurisdictions (of 44).
The median is sensitive to these seven entries because six of them sit at 90 days; with 44 jurisdictions the median falls between two values and rises, so the 90-day median should be read with the unofficial-copy flag in mind.
Limitations: Those seven entries could lag an amendment that the copy has not yet picked up.
Key findings
- Across 50 states and DC, the median subcontractor lien deadline on private commercial work is 90 days and the mean is 113.5 days (statutes checked 2026-10-06).[31][109][38]
- 26 jurisdictions (51.0%) set a deadline of 60 to 90 days, 15 set 91 to 120 days, 9 set more than 120 days, and 1 (Hawaii) sets under 60 days.[38][55][109]
- Hawaii requires the application for a lien within 45 days after the date of completion of the improvement (HRS 507-43).[38]
- New York allows a notice of lien within 8 months after completion on commercial work, versus 4 months for a single-family dwelling (Lien Law 10).[109]
- Rhode Island gives 200 days for a notice of intention, but the claimant must then file suit within 40 days of recording it (R.I. Gen. Laws 34-28-4, 34-28-10).[128][129]
- Utah allows 180 days after final completion if no notice of completion is filed, and 90 days after one is filed (Utah Code 38-1a-502).[142]
- 11 jurisdictions require early preliminary notice on every private commercial job: Arizona, Arkansas, California, Florida, Michigan, Nevada, New Hampshire, Tennessee, Texas, Utah, Wyoming.[6][14][30][72][139][141][156]
- 4 jurisdictions require notice only in set circumstances: Georgia and Ohio when a notice of commencement is filed, North Carolina when a lien agent is designated, and Pennsylvania on projects of $1,500,000 or more with a posted notice of commencement.[35][118][114][126]
- Montana, Minnesota (over 5,000 square feet), Oregon, Washington and Wisconsin expressly exempt commercial work or first-tier subcontractors from their notice rules.[89][75][124][151][154]
- 35 of 51 jurisdictions (68.6%) have a private prompt payment statute; 17 of them require payment to subcontractors within 7 days of the prime contractor's receipt.[140][18][115][10]
- Where a statute sets an owner-to-prime payment deadline (25 jurisdictions), the median is 30 days; Virginia's 60 days is the longest and Arizona and Montana (7 days after approval or certification) the shortest.[150][9][92]
- Late-payment interest is usually 1% per month (Georgia, North Carolina, Pennsylvania, South Carolina) or 1.5% per month (Arizona, Texas, Tennessee and others); California sets 2% per month, and Kansas and Ohio 18% per year.[37][115][127][17][49][121]
- 13 jurisdictions cap private retainage by statute: California, Connecticut, Kansas, Massachusetts, Minnesota, Mississippi, Nevada, New York, Tennessee, Utah at 5%, and Illinois, Missouri, Nebraska at 10%.[19][22][78][112][88][97][43]
- Excluding the 7 jurisdictions read from unofficial statute copies, the median lien deadline moves from 90 to 102.5 days, because six of those seven use 90 days; the count of jurisdictions at 60 to 90 days stays the largest group.[11][34][134]
Executive summary
- The median deadline for a first-tier subcontractor to file a mechanic's lien on private commercial work is 90 days across the 50 states and DC (statutes checked 2026-10-06).
- 23 jurisdictions use exactly 90 days, and 26 of 51 (51.0%) fall between 60 and 90 days.
- Hawaii is shortest at 45 days after completion; Louisiana allows 60 days, and Ohio and Oregon 75 days.
- New York is longest at 8 months after completion (a 240-day equivalent), followed by Rhode Island at 200 days.
- 11 jurisdictions require preliminary notice from a first-tier subcontractor on every private commercial job, and 4 more require it when the owner records a notice of commencement or names a lien agent.
- 35 jurisdictions have a private prompt payment statute; the most common flow-down deadline is 7 days after the prime contractor is paid (17 jurisdictions).
- 13 jurisdictions cap retainage on private work by statute: 10 at 5% and 3 at 10%.
- California's 5% cap on private retention took effect for contracts entered on or after 2026-01-01 (Civ. Code 8811).
Questions people ask
How long do you have to file a mechanic's lien?
For a subcontractor on private commercial work, between 45 days (Hawaii) and 8 months (New York); the median across the 50 states and DC is 90 days and 23 jurisdictions use exactly 90 days (statutes checked 2026-10-06). The clock usually starts at your last work or at project completion, and a recorded notice of completion can shorten it.
Which states require a preliminary notice?
15 jurisdictions require early notice from a first-tier subcontractor on private commercial work. 11 always do: Arizona, Arkansas, California, Florida, Michigan, Nevada, New Hampshire, Tennessee, Texas, Utah, Wyoming. Georgia, North Carolina, Ohio and Pennsylvania require it when a notice of commencement or lien agent is in place.
What is a mechanic's lien?
A mechanic's lien is a claim recorded against land and buildings by a contractor, subcontractor or supplier who improved the property and was not paid. If the claimant files on time and sues within the enforcement period, a court can order the property sold to pay the debt.
What is the prompt payment act for private construction?
It is a state statute that sets how fast owners must pay prime contractors and how fast primes must pay subcontractors on private jobs, usually with interest for late payment. 35 jurisdictions have one; the most common subcontractor deadline is 7 days after the prime is paid.
Can a subcontractor file a lien on a commercial property?
Yes. Every state and DC gives subcontractors lien rights on private commercial property, subject to notice and filing deadlines.
Frequently asked questions
Which state has the shortest mechanic's lien deadline?
Hawaii: the application for a lien must be filed within 45 days after the date of completion of the improvement (HRS 507-43, checked 2026-10-06). Louisiana's 60 days is next.
Which state has the longest mechanic's lien deadline?
New York allows a notice of lien within 8 months after completion on commercial work (Lien Law 10). Rhode Island allows 200 days for a notice of intention.
What is the most common lien deadline for subcontractors?
90 days. 23 of 51 jurisdictions use exactly 90 days for a subcontractor on private commercial work.
How long do I have to sue to enforce a lien?
It varies widely: 90 days after recording in California, 6 months in Arizona and Nevada, 1 year in Florida, Michigan and New York, 2 years in Montana, Pennsylvania and Wisconsin. Rhode Island requires suit within 40 days of recording the notice of intention.
Does Texas still require monthly notices?
Yes. Since the HB 2237 changes effective 2022-01-01, a subcontractor must send a notice of claim for unpaid work by the 15th day of the 3rd month after each month of unpaid work on commercial projects (Tex. Prop. Code 53.056).
What happens if I miss California's 20-day preliminary notice?
You can still send it, but your lien, stop payment notice and bond claim cover only work provided within 20 days before the notice and after it (Civ. Code 8204).
How fast must a prime contractor pay a subcontractor?
In 17 of the 35 prompt pay jurisdictions, within 7 days after the prime is paid. Georgia, Hawaii, Minnesota, Nebraska, Nevada, New Jersey, Ohio and Oklahoma use 10 days.
What interest applies to late private construction payments?
It depends on the state: 1% per month in Georgia, North Carolina, Pennsylvania and South Carolina; 1.5% per month in Arizona, Texas, Tennessee, Minnesota and others; 2% per month in California; 18% per year in Kansas and Ohio.
Which states cap retainage on private projects?
13 by statute: California, Connecticut, Kansas, Massachusetts, Minnesota, Mississippi, Nevada, New York, Tennessee and Utah at 5%, and Illinois, Missouri and Nebraska at 10%.
How often is this registry updated?
Quarterly. It was last checked on 2026-10-06, and the next check is due in January 2027, when Utah's new retention statute version takes effect.
Download the data
Every table in this report is available as a CSV under CC BY 4.0. The fact sheet lists each value with its source URL and access date.
- derived_metrics.csv (CSV)
- fact_sheet.csv (CSV)
- Mechanic's lien and prompt payment rules by state (CSV)
- Distribution of subcontractor lien filing deadlines, 50 states and DC (checked 2026-10-06) (CSV)
- Subcontractor lien filing deadline by jurisdiction, shortest to longest (CSV)
- Jurisdictions that require preliminary notice from a first-tier subcontractor on private commercial work (CSV)
- Private prompt payment statutes: owner and subcontractor payment deadlines and interest (CSV)
- Statutory caps on retainage in private construction (CSV)
- Prime-to-subcontractor payment deadline in the 35 private prompt pay jurisdictions (CSV)
For journalists and researchers
If you cite only a few, cite these
- Median subcontractor lien deadline: 90 days (range 45 to 240 days), 50 states and DC, private commercial work, checked 2026-10-06.[38][109][31]
- Preliminary notice required in 15 of 51 jurisdictions for first-tier subcontractors on private commercial work.[6][14][30]
- Private prompt payment statutes in 35 of 51 jurisdictions; statutory private retainage caps in 13.[140][19]
Most quotable statistics
- The median deadline for a subcontractor to file a mechanic's lien on private commercial work in the US is 90 days (50 states and DC, statutes checked 2026-10-06).[31][34][151]
- Hawaii has the shortest subcontractor lien deadline at 45 days after completion; New York has the longest at 8 months.[38][109]
- 15 of 51 jurisdictions require a first-tier subcontractor to send preliminary notice on private commercial work, 11 of them on every job.[6][14][139]
- 35 of 51 jurisdictions have a private construction prompt payment statute, and the most common rule is payment to subcontractors within 7 days of the prime contractor being paid.[140][18][115]
- 13 jurisdictions cap retainage on private construction; 10 set the cap at 5%.[19][22][78]
- California capped private-project retention at 5% for contracts entered on or after January 1, 2026.[19]
Press summary
A new registry from Commercial Builders & Contractors checks the mechanic's lien and prompt payment statutes of all 50 states and the District of Columbia as of October 6, 2026, and links each entry to the statute text. For a subcontractor on a private commercial project, the deadline to file a lien runs from 45 days in Hawaii to 8 months in New York, with a median of 90 days; 23 jurisdictions use exactly 90 days. 15 jurisdictions require a first-tier subcontractor to send preliminary notice, 11 of them on every job. 35 jurisdictions have a private prompt payment statute, most often requiring payment to subcontractors within 7 days after the prime contractor is paid, and 13 cap retainage on private work, 10 of them at 5%. California's 5% retention cap took effect for contracts signed on or after January 1, 2026. The registry is not legal advice; deadlines have exceptions, and the statute and a local lawyer should be checked before relying on any date. Data and tables are free to reuse under CC BY 4.0.
Suggested headlines
- Subcontractors get a median 90 days to file a mechanic's lien on commercial jobs, a 50-state check finds
- From 45 days in Hawaii to 8 months in New York: the spread in US mechanic's lien deadlines
- 15 jurisdictions make subcontractors send notice early or lose lien rights
- 35 jurisdictions set prompt pay rules for private construction; 7 days is the most common flow-down deadline
- California joins states capping private retainage at 5%
How to cite this report
Commercial Builders & Contractors. (2026). Mechanics lien laws by state: lien deadlines, preliminary notice and prompt pay rules for commercial subcontractors. Retrieved from https://commercialbuildersandcontractors.com/mechanics-lien-laws-by-state/
Reuse license
Data and tables are licensed CC BY 4.0. Attribution: “Source: Commercial Builders & Contractors, Mechanics lien laws by state: lien deadlines, preliminary notice and prompt pay rules for commercial subcontractors” with a link to this page.
Methodology
Selection: we read the mechanic's lien statute of each of the 50 states and DC, plus the state's private construction prompt payment statute where one exists, on 2026-10-06. Official government sites were used for 44 jurisdictions. For Arkansas, Georgia, Indiana, Mississippi, New Jersey, New Mexico and Tennessee the official code sits on an interactive portal that scripts cannot open, so we read the statute text from FindLaw's copy and marked those entries 'unofficial copy'. Oklahoma lien sections come from the state Construction Industries Board's March 2024 copy and its payment section from the Senate's 2019 compilation. Colorado comes from the official CRS 2024 printout.
Scope and definitions: every entry describes a first-tier subcontractor (hired by the prime contractor) on a private, non-residential project. 'Preliminary notice' counts only a notice due early in the job or monthly as a condition of full lien rights; notices of intent due shortly before filing are not counted. Deadlines written in months are converted at 30 days a month; Texas's '15th day of the 4th month' rule is entered at its shortest interval (about 105 days). Where a statute gives different deadlines for residential work, we note it but use the commercial rule.
Verification: a copy of every statute page was saved in raw/, and scripts/check_quotes.py asserts that 235 verbatim phrases supporting the values appear in those copies. Tier 2 and Tier 3 guides (Husch Blackwell, Fullerton & Knowles, Levelset) were used only to compare coverage, never as a source of a deadline.
Conflicts and limits: where a statute sets a default that applies only if the contract is silent (Alabama, Delaware, Oklahoma and others), we report the default. 'None located' for prompt payment means no private payment-timing statute was found in the sections reviewed, not proof that none exists. Courts interpret these deadlines, and case law can change how a deadline is counted.
Derived metrics (counts, medians, shares) are calculated in scripts/build_report.py from the fact sheet and stored in derived_metrics.csv. The registry is checked quarterly; last checked 2026-10-06.
This registry summarises statute text as posted on 2026-10-06. It is not legal advice. Lien and payment deadlines have exceptions (notices of completion, owner demands, residential rules, bonded projects) and courts read them strictly. Check the statute linked for your state and speak with a construction lawyer licensed there before relying on any deadline.
This report presents published data with its limitations. It is not legal, financial or investment advice.
Sources, ranked by quality
Tier 1: primary and official sources (156)
- [1] Alabama Legislature (ALISON). Code of Alabama 35-11-215 (verified statement, time for filing). Current code as posted. Accessed 2026-10-06.
- [2] Alabama Legislature (ALISON). Code of Alabama 35-11-221 (limitation of actions). Current code as posted. Accessed 2026-10-06.
- [3] Alabama Legislature (ALISON). Code of Alabama 35-11-218 (notice by persons other than original contractor). Current code as posted. Accessed 2026-10-06.
- [4] Alabama Legislature (ALISON). Code of Alabama 8-29-3 (timely payments to contractors and subcontractors). Current code as posted. Accessed 2026-10-06.
- [5] Alaska State Legislature. Alaska Statutes 34.35.050 to 34.35.125 (mechanics' liens). Current statutes as posted. Accessed 2026-10-06.
- [6] Arizona State Legislature. A.R.S. 33-992.01 (preliminary twenty day notice). Current statutes as posted. Accessed 2026-10-06.
- [7] Arizona State Legislature. A.R.S. 33-993 (procedure to perfect lien). Current statutes as posted. Accessed 2026-10-06.
- [8] Arizona State Legislature. A.R.S. 33-998 (limitation of action to foreclose lien). Current statutes as posted. Accessed 2026-10-06.
- [9] Arizona State Legislature. A.R.S. 32-1182 (progress payments by owner). Current statutes as posted. Accessed 2026-10-06.
- [10] Arizona State Legislature. A.R.S. 32-1183 (payment by contractor and subcontractor). Current statutes as posted. Accessed 2026-10-06.
- [11] FindLaw (Thomson Reuters) copy of the Arkansas Code. Ark. Code 18-44-117 (filing of lien), FindLaw copy. Copy current as of 2024-03-28. Accessed 2026-10-06.
- [12] FindLaw (Thomson Reuters) copy of the Arkansas Code. Ark. Code 18-44-115 (notice requirements), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [13] FindLaw (Thomson Reuters) copy of the Arkansas Code. Ark. Code 18-44-119 (limitation of actions), FindLaw copy. Copy current as of 2024-03-28. Accessed 2026-10-06.
- [14] California Legislative Information. Cal. Civil Code 8204 (preliminary notice timing). Current code as posted. Accessed 2026-10-06.
- [15] California Legislative Information. Cal. Civil Code 8414 (claimant other than direct contractor: time to record). Current code as posted. Accessed 2026-10-06.
- [16] California Legislative Information. Cal. Civil Code 8460 (action to enforce lien). Current code as posted. Accessed 2026-10-06.
- [17] California Legislative Information. Cal. Civil Code 8800 (progress payments by owner). Current code as posted. Accessed 2026-10-06.
- [18] California Legislative Information. Cal. Business and Professions Code 7108.5 (payment to subcontractors). Current code as posted. Accessed 2026-10-06.
- [19] California Legislative Information. Cal. Civil Code 8811 (retention on private works, SB 61). Added by Stats. 2025, Ch. 49; effective 2026-01-01. Accessed 2026-10-06.
- [20] Colorado General Assembly, Office of Legislative Legal Services. Colorado Revised Statutes 2024, Title 38 (38-22-109 and 38-22-110). CRS 2024 printout (latest edition at this path; 2025 path returned 404). Accessed 2026-10-06.
- [21] Connecticut General Assembly. Conn. Gen. Stat. chapter 847 (49-34, 49-35, 49-39). Current statutes as posted. Accessed 2026-10-06.
- [22] Connecticut General Assembly. Conn. Gen. Stat. chapter 742b (42-158i to 42-158o, construction contracts). Current statutes as posted. Accessed 2026-10-06.
- [23] Delaware Code Online. 25 Del. C. chapter 27, subchapter II (2711, time for filing). Current code as posted. Accessed 2026-10-06.
- [24] Delaware Code Online. 6 Del. C. chapter 35 (Building Construction Payments). Current code as posted. Accessed 2026-10-06.
- [25] Council of the District of Columbia, D.C. Law Library. D.C. Code 40-301.02 (notice of intent). Current code as posted. Accessed 2026-10-06.
- [26] Council of the District of Columbia, D.C. Law Library. D.C. Code 40-303.13 (when suit to be commenced). Current code as posted. Accessed 2026-10-06.
- [27] Council of the District of Columbia, D.C. Law Library. D.C. Code 27A-102 (prompt payments to contractors). Current code as posted. Accessed 2026-10-06.
- [28] Council of the District of Columbia, D.C. Law Library. D.C. Code 27A-104 (prompt payments to subcontractors). Current code as posted. Accessed 2026-10-06.
- [29] Council of the District of Columbia, D.C. Law Library. D.C. Code 27A-103 (failure to make prompt payments). Current code as posted. Accessed 2026-10-06.
- [30] The Florida Legislature, Online Sunshine. Fla. Stat. 713.06 (notice to owner). 2026 Florida Statutes. Accessed 2026-10-06.
- [31] The Florida Legislature, Online Sunshine. Fla. Stat. 713.08 (claim of lien). 2026 Florida Statutes. Accessed 2026-10-06.
- [32] The Florida Legislature, Online Sunshine. Fla. Stat. 713.22 (duration of lien). 2026 Florida Statutes. Accessed 2026-10-06.
- [33] The Florida Legislature, Online Sunshine. Fla. Stat. 715.12 (Construction Contract Prompt Payment Law). 2026 Florida Statutes. Accessed 2026-10-06.
- [34] FindLaw (Thomson Reuters) copy of the Official Code of Georgia. O.C.G.A. 44-14-361.1 (creation and declaration of liens), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [35] FindLaw (Thomson Reuters) copy of the Official Code of Georgia. O.C.G.A. 44-14-361.5 (notice to contractor), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [36] FindLaw (Thomson Reuters) copy of the Official Code of Georgia. O.C.G.A. 13-11-4 (time limits for payments), FindLaw copy. Copy current as of 2024-03-28. Accessed 2026-10-06.
- [37] FindLaw (Thomson Reuters) copy of the Official Code of Georgia. O.C.G.A. 13-11-7 (interest), FindLaw copy. Copy current as of 2024-03-28. Accessed 2026-10-06.
- [38] Hawaii State Legislature. HRS 507-43 (notice of lien; time for filing; duration). Current HRS as posted. Accessed 2026-10-06.
- [39] Hawaii State Legislature. HRS 444-25 (payment for goods and services). Current HRS as posted. Accessed 2026-10-06.
- [40] Idaho Legislature. Idaho Code 45-507 (claim of lien). Current statutes as posted. Accessed 2026-10-06.
- [41] Idaho Legislature. Idaho Code 45-510 (duration of lien). Current statutes as posted. Accessed 2026-10-06.
- [42] Illinois General Assembly. 770 ILCS 60 (Mechanics Lien Act), printer version. Current ILCS as posted. Accessed 2026-10-06.
- [43] Illinois General Assembly. 815 ILCS 603 (Contractor Prompt Payment Act), printer version. Current ILCS as posted. Accessed 2026-10-06.
- [44] FindLaw (Thomson Reuters) copy of the Indiana Code. Indiana Code 32-28-3-3 (notice of intention to hold lien), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [45] FindLaw (Thomson Reuters) copy of the Indiana Code. Indiana Code 32-28-3-6 (enforcement), FindLaw copy. Copy current as of 2026-01-01. Accessed 2026-10-06.
- [46] Iowa Legislature. Iowa Code 2026, chapter 572 (mechanic's lien). Iowa Code 2026. Accessed 2026-10-06.
- [47] Kansas Office of Revisor of Statutes. K.S.A. 60-1103 (subcontractors and suppliers lien). Current statutes as posted. Accessed 2026-10-06.
- [48] Kansas Office of Revisor of Statutes. K.S.A. 60-1105 (limitations). Current statutes as posted. Accessed 2026-10-06.
- [49] Kansas Office of Revisor of Statutes. K.S.A. 16-1803 (private construction contracts; payment). Current statutes as posted. Accessed 2026-10-06.
- [50] Kansas Office of Revisor of Statutes. K.S.A. 16-1804 (retainage). Current statutes as posted. Accessed 2026-10-06.
- [51] Kentucky General Assembly. KRS 376.010 (mechanics' and materialman's liens). Effective 2023-06-29. Accessed 2026-10-06.
- [52] Kentucky General Assembly. KRS 376.080 (statement filed within six months). Effective 1990-07-13. Accessed 2026-10-06.
- [53] Kentucky General Assembly. KRS 376.090 (limitation on action to enforce lien). Current statutes as posted. Accessed 2026-10-06.
- [54] Kentucky General Assembly. KRS 371.405 (Fairness in Construction Act payment terms). Effective 2025-06-27. Accessed 2026-10-06.
- [55] Louisiana State Legislature. La. R.S. 9:4822 (preservation of claims and privileges). Current statutes as posted. Accessed 2026-10-06.
- [56] Louisiana State Legislature. La. R.S. 9:4823 (extinguishment of claims and privileges). Current statutes as posted. Accessed 2026-10-06.
- [57] Louisiana State Legislature. La. R.S. 9:2784 (prompt payment by owners and to subcontractors). Current statutes as posted. Accessed 2026-10-06.
- [58] Maine Legislature, Revisor's Office. 10 M.R.S. 3253 (dissolution unless claim filed). Current statutes as posted. Accessed 2026-10-06.
- [59] Maine Legislature, Revisor's Office. 10 M.R.S. 3255 (liens preserved and enforced by action). Current statutes as posted. Accessed 2026-10-06.
- [60] Maine Legislature, Revisor's Office. 10 M.R.S. 1113 (owner's payment obligations). Current statutes as posted. Accessed 2026-10-06.
- [61] Maine Legislature, Revisor's Office. 10 M.R.S. 1114 (contractor's and subcontractor's payment obligations). Current statutes as posted. Accessed 2026-10-06.
- [62] Maine Legislature, Revisor's Office. 10 M.R.S. 1118 (disputes; penalties). Current statutes as posted. Accessed 2026-10-06.
- [63] Maryland General Assembly. Md. Code, Real Property 9-104 (subcontractor notice). Current statutes as posted. Accessed 2026-10-06.
- [64] Maryland General Assembly. Md. Code, Real Property 9-105 (petition to establish lien). Current statutes as posted. Accessed 2026-10-06.
- [65] Maryland General Assembly. Md. Code, Real Property 9-109 (right to enforce expires). Current statutes as posted. Accessed 2026-10-06.
- [66] Maryland General Assembly. Md. Code, Real Property 9-302 (prompt payment). Current statutes as posted. Accessed 2026-10-06.
- [67] The 194th General Court of Massachusetts. M.G.L. c. 254, s. 4 (notice of subcontract). Current General Laws as posted. Accessed 2026-10-06.
- [68] The 194th General Court of Massachusetts. M.G.L. c. 254, s. 8 (statement of account). Current General Laws as posted. Accessed 2026-10-06.
- [69] The 194th General Court of Massachusetts. M.G.L. c. 254, s. 11 (action to enforce lien). Current General Laws as posted. Accessed 2026-10-06.
- [70] The 194th General Court of Massachusetts. M.G.L. c. 149, s. 29E (private construction prompt pay, $3,000,000 or more). Current General Laws as posted. Accessed 2026-10-06.
- [71] The 194th General Court of Massachusetts. M.G.L. c. 149, s. 29F (retainage in private construction). Current General Laws as posted. Accessed 2026-10-06.
- [72] Michigan Legislature. MCL 570.1109 (notice of furnishing). Current MCL as posted. Accessed 2026-10-06.
- [73] Michigan Legislature. MCL 570.1111 (claim of lien, 90 days). Current MCL as posted. Accessed 2026-10-06.
- [74] Michigan Legislature. MCL 570.1117 (enforcement, 1 year). Current MCL as posted. Accessed 2026-10-06.
- [75] Minnesota Office of the Revisor of Statutes. Minn. Stat. 514.011 (prelien notice and exceptions). Current statutes as posted. Accessed 2026-10-06.
- [76] Minnesota Office of the Revisor of Statutes. Minn. Stat. 514.08 (lien statement, 120 days). Current statutes as posted. Accessed 2026-10-06.
- [77] Minnesota Office of the Revisor of Statutes. Minn. Stat. 514.12 (one-year limitation). Current statutes as posted. Accessed 2026-10-06.
- [78] Minnesota Office of the Revisor of Statutes. Minn. Stat. 337.10 (prompt payment; retainage). Current statutes as posted. Accessed 2026-10-06.
- [79] FindLaw (Thomson Reuters) copy of the Mississippi Code. Miss. Code 85-7-405 (construction lien), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [80] FindLaw (Thomson Reuters) copy of the Mississippi Code. Miss. Code 85-7-407 (notice by persons without privity), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [81] FindLaw (Thomson Reuters) copy of the Mississippi Code. Miss. Code 87-7-5 (payment of subcontractors), FindLaw copy. Copy current as of 2025-01-01. Accessed 2026-10-06.
- [82] FindLaw (Thomson Reuters) copy of the Mississippi Code. Miss. Code 87-7-3 (payments to contractors; interest), FindLaw copy. Copy current as of 2025-01-01. Accessed 2026-10-06.
- [83] FindLaw (Thomson Reuters) copy of the Mississippi Code. Miss. Code 87-9-3 (retainage maximum), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [84] Missouri Revisor of Statutes. RSMo 429.080 (lien filed within six months). Current RSMo as posted. Accessed 2026-10-06.
- [85] Missouri Revisor of Statutes. RSMo 429.100 (ten days' notice before filing). Current RSMo as posted. Accessed 2026-10-06.
- [86] Missouri Revisor of Statutes. RSMo 429.170 (actions commenced in six months). Current RSMo as posted. Accessed 2026-10-06.
- [87] Missouri Revisor of Statutes. RSMo 431.180 (private design or construction work; interest). Effective 1999-08-28. Accessed 2026-10-06.
- [88] Missouri Revisor of Statutes. RSMo 436.303 (private construction retainage). Effective 2002-08-28. Accessed 2026-10-06.
- [89] Montana Legislature. MCA 71-3-531 (notice of right to claim lien; exceptions). MCA 2025. Accessed 2026-10-06.
- [90] Montana Legislature. MCA 71-3-535 (attachment of lien; filing). MCA 2025. Accessed 2026-10-06.
- [91] Montana Legislature. MCA 71-3-562 (limitation on actions). MCA 2025. Accessed 2026-10-06.
- [92] Montana Legislature. MCA 28-2-2103 (payment by owner and contractor). MCA 2025. Accessed 2026-10-06.
- [93] Montana Legislature. MCA 28-2-2104 (interest on delayed payments). MCA 2025. Accessed 2026-10-06.
- [94] Nebraska Legislature. Neb. Rev. Stat. 52-137 (attachment and enforcement of lien). Current statutes as posted. Accessed 2026-10-06.
- [95] Nebraska Legislature. Neb. Rev. Stat. 52-140 (duration of lien). Current statutes as posted. Accessed 2026-10-06.
- [96] Nebraska Legislature. Neb. Rev. Stat. 45-1203 (Construction Prompt Pay Act payment). Current statutes as posted. Accessed 2026-10-06.
- [97] Nebraska Legislature. Neb. Rev. Stat. 45-1204 (withholdings; retainage). Current statutes as posted. Accessed 2026-10-06.
- [98] Nebraska Legislature. Neb. Rev. Stat. 45-1205 (interest on delayed payment). Current statutes as posted. Accessed 2026-10-06.
- [99] Nevada Legislature. NRS chapter 108 (108.226, 108.233, 108.245). Current NRS as posted. Accessed 2026-10-06.
- [100] Nevada Legislature. NRS chapter 624 (624.609, 624.624). Current NRS as posted. Accessed 2026-10-06.
- [101] New Hampshire General Court. RSA chapter 447 (liens for labor and materials). Current RSA as posted. Accessed 2026-10-06.
- [102] FindLaw (Thomson Reuters) copy of the New Jersey Statutes. N.J.S.A. 2A:44A-6 (lien claim lodged within 90 days), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [103] FindLaw (Thomson Reuters) copy of the New Jersey Statutes. N.J.S.A. 2A:44A-14 (action to enforce within one year), FindLaw copy. Copy current as of 2024-01-01. Accessed 2026-10-06.
- [104] FindLaw (Thomson Reuters) copy of the New Jersey Statutes. N.J.S.A. 2A:30A-2 (Prompt Payment Act), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [105] FindLaw (Thomson Reuters) copy of the New Mexico Statutes. NMSA 48-2-6 (time for filing lien claim), FindLaw copy. Copy current as of 2024-01-01. Accessed 2026-10-06.
- [106] FindLaw (Thomson Reuters) copy of the New Mexico Statutes. NMSA 48-2-2.1 (notice for claims over $5,000), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [107] FindLaw (Thomson Reuters) copy of the New Mexico Statutes. NMSA 48-2-10 (duration of lien), FindLaw copy. Copy current as of 2024-01-01. Accessed 2026-10-06.
- [108] FindLaw (Thomson Reuters) copy of the New Mexico Statutes. NMSA 57-28-5 (Retainage Act payments), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [109] New York State Senate, Open Legislation. N.Y. Lien Law 10 (filing of notice of lien). Page published 2026-10-02. Accessed 2026-10-06.
- [110] New York State Senate, Open Legislation. N.Y. Lien Law 17 (duration of lien). Page published 2026-10-02. Accessed 2026-10-06.
- [111] New York State Senate, Open Legislation. N.Y. General Business Law 756-a (prompt payment obligations). Current law as posted. Accessed 2026-10-06.
- [112] New York State Senate, Open Legislation. N.Y. General Business Law 756-c (retention). Current law as posted. Accessed 2026-10-06.
- [113] New York State Senate, Open Legislation. N.Y. General Business Law 756 (definitions; $150,000 threshold). Current law as posted. Accessed 2026-10-06.
- [114] North Carolina General Assembly. N.C. Gen. Stat. chapter 44A, article 2 (44A-11.2, 44A-12, 44A-13). Current statutes as posted. Accessed 2026-10-06.
- [115] North Carolina General Assembly. N.C. Gen. Stat. chapter 22C (payment to subcontractors). Current statutes as posted. Accessed 2026-10-06.
- [116] North Dakota Legislative Branch. N.D.C.C. chapter 35-27 (construction liens). Current century code as posted. Accessed 2026-10-06.
- [117] Ohio Legislative Service Commission. Ohio Rev. Code 1311.06 (affidavit filing periods). Current code as posted. Accessed 2026-10-06.
- [118] Ohio Legislative Service Commission. Ohio Rev. Code 1311.05 (notice of furnishing). Current code as posted. Accessed 2026-10-06.
- [119] Ohio Legislative Service Commission. Ohio Rev. Code 1311.13 (duration of liens). Effective 2007-03-30. Accessed 2026-10-06.
- [120] Ohio Legislative Service Commission. Ohio Rev. Code 1311.11 (notice to commence suit). Current code as posted. Accessed 2026-10-06.
- [121] Ohio Legislative Service Commission. Ohio Rev. Code 4113.61 (payment of subcontractors). Current code as posted. Accessed 2026-10-06.
- [122] Oklahoma Construction Industries Board (state agency copy). Oklahoma Statutes Title 42 (sections of interest, incl. 142.6, 143, 172). Agency copy dated March 2024. Accessed 2026-10-06.
- [123] Oklahoma State Senate. Oklahoma Statutes Title 15 (15-820, payments on private bid projects). Senate compilation dated December 2019. Accessed 2026-10-06.
- [124] Oregon State Legislature. ORS chapter 87 (87.021, 87.035, 87.055). Current ORS as posted. Accessed 2026-10-06.
- [125] Oregon State Legislature. ORS 701.620 to 701.640 (prompt payment, private construction). Current ORS as posted. Accessed 2026-10-06.
- [126] Pennsylvania General Assembly. Mechanics' Lien Law of 1963 (Act 497 of 1963), consolidated PDF. Unconsolidated statute as posted. Accessed 2026-10-06.
- [127] Pennsylvania General Assembly. Contractor and Subcontractor Payment Act (Act 7 of 1994), PDF. As amended through Act 27 of 2018. Accessed 2026-10-06.
- [128] State of Rhode Island General Assembly. R.I. Gen. Laws 34-28-4 (notice of intention). Current laws as posted. Accessed 2026-10-06.
- [129] State of Rhode Island General Assembly. R.I. Gen. Laws 34-28-10 (complaint and lis pendens within 40 days). Current laws as posted. Accessed 2026-10-06.
- [130] South Carolina Legislature. S.C. Code Title 29, chapter 5 (mechanics' liens). Current code as posted. Accessed 2026-10-06.
- [131] South Carolina Legislature. S.C. Code Title 29, chapter 6 (payments to contractors). Current code as posted. Accessed 2026-10-06.
- [132] South Dakota Legislature. SDCL 44-9-15 (lien statement within 120 days). Current codified law as posted. Accessed 2026-10-06.
- [133] South Dakota Legislature. SDCL Title 44 (44-9-24, 44-9-53). Current codified law as posted. Accessed 2026-10-06.
- [134] FindLaw (Thomson Reuters) copy of the Tennessee Code. Tenn. Code 66-11-112 (recording of lien), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [135] FindLaw (Thomson Reuters) copy of the Tennessee Code. Tenn. Code 66-11-145 (remote contractor notice of nonpayment), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [136] FindLaw (Thomson Reuters) copy of the Tennessee Code. Tenn. Code 66-11-115 (liens by remote contractors), FindLaw copy. Copy current as of 2024-01-02. Accessed 2026-10-06.
- [137] FindLaw (Thomson Reuters) copy of the Tennessee Code. Tenn. Code 66-34-103 (retainage), FindLaw copy. Copy as posted. Accessed 2026-10-06.
- [138] FindLaw (Thomson Reuters) copy of the Tennessee Code. Tenn. Code 66-34-601 (interest), FindLaw copy. Copy current as of 2024-01-02. Accessed 2026-10-06.
- [139] Texas Legislature, Texas Constitution and Statutes. Tex. Prop. Code chapter 53 (mechanic's liens). HB 2237 (2021) changes effective 2022-01-01. Accessed 2026-10-06.
- [140] Texas Legislature, Texas Constitution and Statutes. Tex. Prop. Code chapter 28 (prompt pay). Current statutes as posted. Accessed 2026-10-06.
- [141] Utah State Legislature. Utah Code 38-1a-501 (preliminary notice). Effective 2014-05-13. Accessed 2026-10-06.
- [142] Utah State Legislature. Utah Code 38-1a-502 (notice of construction lien). Current code as posted. Accessed 2026-10-06.
- [143] Utah State Legislature. Utah Code 38-1a-701 (action to enforce lien). Current code as posted. Accessed 2026-10-06.
- [144] Utah State Legislature. Utah Code 13-8-5 (limitation on retention proceeds). Effective 2023-02-27; superseded 2027-01-01. Accessed 2026-10-06.
- [145] Vermont General Assembly. 9 V.S.A. chapter 51 (mechanics' liens). Current statutes as posted. Accessed 2026-10-06.
- [146] Vermont General Assembly. 9 V.S.A. chapter 102 (prompt payment). Current statutes as posted. Accessed 2026-10-06.
- [147] Virginia General Assembly, Legislative Information System. Va. Code 43-4 (memorandum of lien). Current code as posted. Accessed 2026-10-06.
- [148] Virginia General Assembly, Legislative Information System. Va. Code 43-7 (perfection of lien by subcontractor). Current code as posted. Accessed 2026-10-06.
- [149] Virginia General Assembly, Legislative Information System. Va. Code 43-17 (limitation on suit). Current code as posted. Accessed 2026-10-06.
- [150] Virginia General Assembly, Legislative Information System. Va. Code 11-4.6 (payment clauses in construction contracts). Current code as posted. Accessed 2026-10-06.
- [151] Washington State Legislature. RCW chapter 60.04 (mechanics' and materialmen's liens). Current RCW as posted. Accessed 2026-10-06.
- [152] West Virginia Legislature. W. Va. Code 38-2-9 (notice and recordation of subcontractor's lien). Current code as posted. Accessed 2026-10-06.
- [153] West Virginia Legislature. W. Va. Code 38-2-34 (time to bring suit). Current code as posted. Accessed 2026-10-06.
- [154] Wisconsin State Legislature. Wis. Stat. 779.02 (notice requirements and exceptions). Current statutes as posted. Accessed 2026-10-06.
- [155] Wisconsin State Legislature. Wis. Stat. 779.06 (claim for lien; action within 2 years). Current statutes as posted. Accessed 2026-10-06.
- [156] Wyoming Legislature. Wyo. Stat. Title 29, chapter 2 (29-2-106, 29-2-109, 29-2-112). Current title PDF as posted. Accessed 2026-10-06.
Tier 2: trade bodies, market research, company data (1)
- [159] Levelset (a Procore company). Mechanics Lien Guide and FAQs. Last updated 2025-11-12. Accessed 2026-10-06.
Tier 3: journalism and expert commentary (2)
- [157] Fullerton & Knowles, P.C.. 50 State Summary of Mechanic's Lien Law (reprint of NACM Manual of Credit and Commercial Laws, 2019 edition). States 'current through July 1, 2019'. Accessed 2026-10-06.
- [158] Husch Blackwell LLP. 50-State Construction Law Map. Undated landing page. Accessed 2026-10-06.