Construction Management at Risk: How CMAR and the GMP Work
Construction management at risk (CMAR) is a delivery method where you hire an architect and, separately, a construction manager who gives cost and schedule advice during design, then commits to a guaranteed maximum price (GMP) and builds the project. Costs above the GMP, apart from owner changes, fall on the construction manager.
- Early builder inputEstimates and constructability reviews at each design stage.
- A price ceilingThe GMP caps the cost of the work, fee and contingency.
- Your own architectDesign stays under a separate contract with you.
What construction management at risk means
In construction management at risk the construction manager plays two roles in sequence. During design it works as your adviser, pricing the drawings as they develop, checking constructability and planning the schedule. Once design is far enough along it proposes a guaranteed maximum price, and when you accept it the manager becomes the builder, holding the trade subcontracts and carrying the risk of overruns within the agreed scope. The General Services Administration, which calls the method construction manager as constructor, describes it as engaging the contractor during design and setting a ceiling on the construction price before construction documents are prepared.
CM at risk vs CM agency: A CM agent advises the owner for a fee but holds no trade contracts and guarantees no price; the owner contracts with the trades or a general contractor. A CM at risk holds the contracts and commits to the GMP.
CMAR is one of the delivery options on our commercial construction services hub, alongside design-build and traditional design-bid-build.
Our guide to construction management companies compares agency, at-risk and general contractor firms and shows the fees public owners write into each contract.
The construction management at risk process, step by step
- Selection
Owners usually select on qualifications, preconstruction approach, team, fee percentage and general conditions, not on a full construction price.
- Preconstruction services
Estimates at schematic design, design development and construction documents; constructability reviews; schedule; value analysis.
- Early release packages
Site work, foundations, steel or long-lead equipment can be bought before the full GMP when the schedule needs it.
- GMP proposal
The manager prices the cost of the work, contingency, general conditions and fee, with written assumptions and clarifications.
- GMP amendment
Accepting the proposal makes the manager contractually bound to build at or below the GMP.
- Subcontractor buyout
Trade packages are bid to subcontractors; public owners often require open, documented procurement.
- Construction and reconciliation
Monthly cost reporting, contingency tracking, and a final reconciliation of actual cost against the GMP.
Our commercial construction process guide shows how these steps line up with design phases and permits.

How a guaranteed maximum price is built
A GMP is not a lump sum. You pay the actual cost of the work plus the agreed fee, up to the ceiling. If the project comes in under, the savings go back to you or are shared as the contract says; the AIA form leaves room for specific savings-sharing terms. If it comes in over for reasons inside the manager's scope, the manager absorbs it. The GMP is only as good as the documents and assumptions it was based on, so read the qualifications list as carefully as the number.
| Component | Inside the GMP? | What to check |
|---|---|---|
| Cost of the work (subcontracts, materials, self-performed labor) | Yes | How each trade package was bid and awarded |
| Construction manager's contingency | Yes | What it may be used for and whether unused amounts return to you |
| General conditions (site staff, trailer, temporary utilities) | Yes | Lump sum, capped or reimbursed at cost |
| Fee | Yes | Percentage of cost or fixed amount; how it applies to change orders |
| Insurance and bonds | Usually | Which policies and rates; Exhibit B requirements |
| Allowances | Yes | Whether each allowance is realistic for the unfinished design |
| Owner contingency and owner changes | No | Held by you for scope changes and unknowns |
| Design fees, permits and impact fees, furniture | Usually no | Who pays and when |
Typical arrangement under cost-plus-fee GMP agreements such as AIA A133-2019; contract terms decide.
Source: [1]
The same cost-plus-fee mechanics apply outside CMAR, and our guide to the cost-plus contract works through fixed, percentage and GMP fees side by side.
The owner's job during preconstruction
CMAR works best when the owner treats preconstruction as active work rather than a waiting period. At each design milestone you will receive an estimate from the manager and, often, a list of options to bring cost back to budget. Decisions made quickly keep the architect and manager aligned; decisions deferred tend to resurface as assumptions in the GMP. Set a budget with a clear owner contingency before design starts, and agree how estimate variances will be reconciled between the architect's cost consultant, if you have one, and the manager.
- Decision logRecord every scope and quality decision with its cost effect and date.
- Estimate reconciliationCompare the manager's estimate with any independent estimate line by line at each milestone.
- Early package approvalsApprove early releases only when the design behind them is stable.
- Subcontractor bid reviewAttend bid openings or review bid tabulations before the GMP is final.
Our guide to preconstruction services lists the estimates, reviews and fee terms to expect at each design stage.
The AIA A133 agreement and related documents
The most widely used private form is AIA Document A133-2019, the agreement between owner and construction manager as constructor where payment is the cost of the work plus a fee with a guaranteed maximum price. It splits services into a preconstruction phase and a construction phase, which may overlap on fast-tracked jobs. The GMP is set by an amendment, Exhibit A, and Exhibit B sets insurance and bond requirements. A133 is coordinated with the A201-2017 general conditions and the B133-2019 owner and architect agreement written for CMAR projects. Section 6.1.7 lets the parties add terms for the manager to share savings when the final cost is below the GMP.
Standard forms are routinely edited. Have a construction attorney review the agreement, particularly the definition of the cost of the work, contingency use and the treatment of savings. This is general information, not legal advice.
Because A133-2019 adopts the general conditions, its claim deadlines and insurance framework come from AIA A201-2017 and its 15 articles.
How A133-2019 pairs with A201-2017, B133-2019 and the GMP pay forms is shown in our AIA contract documents navigator.
Why the GMP matters when input costs outrun prices
A GMP moves price risk from you to the manager for the scope it covers, and that risk has been real. Federal producer price data shows what nonresidential contractors pay for materials, energy and services rising 8.9% in the year to August 2026, while the prices they charge for new nonresidential buildings rose 5.3%. Since January 2020 the gap is 52.8% against 46.3%. Managers price this risk into contingency and escalation allowances, which is one reason GMPs set very early carry larger contingencies.
Producer prices and hourly earnings, January 2020 = 100
Source: U.S. Bureau of Labor Statistics, Producer Price Indexes and Current Employment Statistics; CB&C rebasing
The squeeze differs by building type. Warehouses saw the smallest output price gain in the twelve months to August 2026, 4.3%, against the same 8.9% rise in inputs. Our commercial construction price index tracks the gap monthly, and the cost per square foot guide explains how to set an early budget before the manager's first estimate.
12-month change to August 2026
Source: U.S. Bureau of Labor Statistics, Producer Price Indexes (August 2026, preliminary)
CMAR on public projects: Florida's statute as an example
Public owners need statutory authority to use CMAR, and state laws set the rules. Florida's is section 255.103 of the Florida Statutes. Agencies select construction management entities through the qualifications-based process in section 287.055, the Consultants' Competitive Negotiation Act. The entity may be required to offer a guaranteed maximum price and a guaranteed completion date, or a lump-sum price, and when it does it must secure a surety bond under section 255.05 and hold the construction subcontracts. Agencies may also award continuing contracts for projects whose estimated construction cost does not exceed $7.5 million each; the statute directs the Department of Management Services to adjust that cap every July 1 starting in 2025, so confirm the current figure.
At the federal level, the General Services Administration adopted construction manager as constructor in a rule effective January 21, 2020, now codified at GSAR Subpart 536.71. Federal construction spending by state and buyer is in our federal construction contracts by state report.

Construction management at risk vs design-build vs design-bid-build
| Question | CM at risk | Design-build | Design-bid-build |
|---|---|---|---|
| Owner's contracts | Architect plus construction manager | One design-builder | Architect, then general contractor |
| Builder selected on | Mostly qualifications, fee and general conditions | Qualifications, proposal, or both | Lowest responsive bid, typically |
| Builder joins | During design | At the start | After drawings are complete |
| Price set | GMP amendment | Proposal or Design-Build Amendment | Bid award |
| Design control | Owner, through own architect | Design-builder, against owner criteria | Owner, through own architect |
| Main owner risk | Assumptions behind an early GMP | Vague criteria | Change orders from design gaps |
| Typical AIA form | A133-2019 | A141-2024 | A101 with A201 |
Typical arrangements. Public owners must follow their own procurement statutes.
The biggest practical difference between CMAR and design-build is who the architect works for. In CMAR the architect is yours, which keeps an independent design check, while the manager's early estimates keep the design on budget. In design-build both sit in one contract. Compared with design-bid-build, CMAR gives up a single hard-bid price on finished drawings in exchange for builder input during design and an earlier start. Our design-build vs design-bid-build guide covers the other pairing.
When CMAR fits
- Complex or phased projects: occupied renovations, hospitals and campuses where sequencing advice during design pays off.
- Tight schedules: early packages let site work and structure start before interiors are designed.
- Owners who want design control: the architect stays under your contract.
- Larger budgets: preconstruction fees and the reporting load make more sense on bigger jobs.
- Less suited: small, simple, fully designed buildings, where a hard bid is quicker and gives clean price competition.
Selecting a construction manager at risk
- Estimate accuracyAsk how their design-stage estimates compared with final GMPs and final costs on recent jobs.
- Preconstruction teamMeet the estimator, scheduler and project manager who will work during design.
- Fee and general conditionsCompare the fee percentage and how general conditions are priced: lump sum, cap or cost.
- Contingency rulesHow the manager's contingency is used, reported and returned if unspent.
- Subcontractor procurementOpen bidding, owner participation in bid openings, and whether the manager may self-perform work.
- Bonding and licensingBonding capacity for the GMP and the right license class for the state.
In South Florida, ask how the manager's preconstruction team handles High-Velocity Hurricane Zone product approvals and wind design reviews, since they affect long-lead envelope packages; our HVHZ construction primer explains why. Our guide to choosing a commercial contractor covers license and reference checks for any delivery method.
On hospital renovations, the CM's preconstruction work should include an ICRA class for every work area and a list of sprinkler and alarm outages, as explained in our healthcare construction guide.
Frequently asked questions
What is construction management at risk?
A delivery method in which the owner hires an architect and a construction manager separately. The manager advises during design, then commits to a guaranteed maximum price and builds the project, carrying the risk of overruns within its scope.
What is the difference between CM at risk and a general contractor?
A general contractor under design-bid-build usually joins after design and wins on bid price. A CM at risk joins during design, is chosen mainly on qualifications and fee, gives preconstruction advice, and then acts as the general contractor under a GMP.
What happens if the project costs more than the GMP?
For costs within the agreed scope, the construction manager pays the overrun. Owner-directed changes, and conditions the contract allocates to the owner, adjust the GMP through change orders.
What happens to savings under the GMP?
Unspent amounts generally stay with the owner unless the contract shares them. AIA A133-2019 includes a place to agree how the manager participates in savings when the final cost is below the GMP.
Is CMAR more expensive than design-bid-build?
Not necessarily. You pay preconstruction fees and the manager carries a contingency, but early cost advice can avoid redesign and the schedule can be shorter. Compare the full cost, including time, for your project.
Which contract is used for CM at risk?
In private work, AIA A133-2019 with A201-2017 general conditions and B133-2019 for the architect is common. Public agencies often use their own forms under their state statute. Have an attorney review whichever you use.
Can public agencies in Florida use CMAR?
Yes. Section 255.103 of the Florida Statutes authorizes construction management entities, selected through the section 287.055 process, and lets agencies require a guaranteed maximum price backed by a surety bond.
How early should the construction manager be hired?
Usually at or before schematic design, so its estimates and constructability reviews can still shape the design. Hiring late removes much of the benefit.
Sources
- [1] AIA Contract Documents. Instructions: A133-2019, Owner and Construction Manager as Constructor, Cost of the Work Plus a Fee with a GMP. Accessed 2026-10-07.
- [2] AIA Contract Documents. Summary: A141-2014, Agreement Between Owner and Design-Builder. Accessed 2026-10-07.
- [3] General Services Administration, Federal Register (via govinfo.gov). GSAR: Adoption of Construction Project Delivery Method Involving Early Industry Engagement, Construction Manager as Constructor (CMc), final rule, 84 FR 69648. Accessed 2026-10-07.
- [4] Federal Highway Administration. Alternative Project Delivery Defined: Design-Build. Accessed 2026-10-07.
- [5] The Florida Senate. Florida Statutes 255.103, Construction management or program management entities. Accessed 2026-10-07.
- [6] The Florida Senate. Florida Statutes 287.055, Acquisition of professional architectural, engineering, landscape architectural, or surveying and mapping services (CCNA). Accessed 2026-10-07.
- [7] U.S. Bureau of Labor Statistics. Producer Price Index industry data for construction (pc.data.75.Construction). Accessed 2026-10-07.
- [8] U.S. Bureau of Labor Statistics. PPI commodity data for construction, including WPU801 (wp.data.80.Construction). Accessed 2026-10-07.
- [9] U.S. Bureau of Labor Statistics. PPI inputs to construction industries (wp.data.80i.ConstructnInputs). Accessed 2026-10-07.
- [10] U.S. Bureau of Labor Statistics. Current Employment Statistics, construction hours and earnings (ce.data.20b). Accessed 2026-10-07.