AIA G702 Application and Certificate for Payment: Every Line, a Worked Example and the A201 Pay Cycle

Steel-framed commercial building under construction at dusk beside a lit site office trailer

The AIA G702 is the contractor’s monthly Application and Certificate for Payment: nine numbered lines turn G703 continuation sheet totals into the current payment due, and the architect certifies that amount to the owner.

Key takeaways

  • The G702-1992 has 9 numbered lines. Line 8, current payment due, is Line 6 minus Line 7, and Line 9, balance to finish, is Line 3 minus Line 6. Line 7 is Line 6 from the prior certificate, the certified figure, not the amount applied for (AIA G702-1992 sample; AIA G702 instructions).
  • Under AIA A201-2017 §9.3.1 the contractor submits at least 10 days before the payment date, and under §9.4.1 the architect has 7 days to certify, cut or withhold.
  • The worked example below gives a full G703 continuation sheet and the matching G702, with totals that reconcile to the dollar: $1,340,000 completed and stored, $134,000 retained and $279,000 due.
  • In the same $2,448,500 example, cutting retainage from 10% to 5% at 54.7% complete raises Line 8 from $279,000 to $346,000, a $67,000 release modelled on Illinois 30 ILCS 550/1.
  • Federal jobs run on different rules: FAR 52.232-27 makes a progress payment due 14 days after a proper request, and FAR 52.232-5(e) allows up to 10% retainage only when progress is unsatisfactory.

How do you fill out an AIA G702? A worked example you can copy

Fill in the G703 continuation sheet first, then carry its column totals to the nine G702 lines. The example is pay application 5 on a $2,400,000 contract with $48,500 of net change orders and 10% retainage: the G703 totals $1,340,000 completed and stored, and the G702 shows $279,000 due. All figures are invented CB&C arithmetic, so copy the layout and formulas, not the numbers.

  1. Fill in the G703 for the period: one row per schedule of values line, plus one row per change order, as AIA’s key-steps guide lists them. Column D is last month’s D + E, Column E is work done this period and Column F is material stored but not installed ($41,600 of storefront glass here).
  2. Total each column. Column G, $1,012,000 + $286,400 + $41,600 = $1,340,000, becomes Line 4.
  3. Enter Line 1, the original $2,400,000, and the change order summary: previous months $36,000 added and $6,000 deducted, this month $18,500 added, for a Line 2 of $48,500.
  4. Apply the retainage rate: 10% x $1,298,400 (Columns D + E) on Line 5a and 10% x $41,600 (Column F) on Line 5b.
  5. Copy Line 6 from the last certified G702 (application 4, certified at $927,000) into Line 7.
  6. Do the arithmetic for Lines 6, 8 and 9, then sign before a notary if the contract requires one and leave the architect’s certificate blank.

Step 1: the G703 continuation sheet

Brackets show a credit. Change order 2 deleted $6,000 of site lighting and was credited in full on an earlier application, so its scheduled value and Column D are both negative. Column I, line-by-line retainage, stays blank because one 10% rate applies to every line.

A ItemB Description of workC Scheduled value ($)D From previous application ($)E This period ($)F Materials presently stored ($)G Completed and stored to date, D + E + F ($)G / CH Balance to finish, C minus G ($)
1General conditions and mobilization300,000165,00030,0000195,00065.0%105,000
2Sitework and concrete360,000324,00018,0000342,00095.0%18,000
3Structural steel and metals420,000378,00042,0000420,000100.0%0
4Envelope: roofing, wall panels, storefront (storefront glass stored on site)480,00096,000120,00041,600257,60053.7%222,400
5Mechanical, plumbing and electrical600,00030,00065,400095,40015.9%504,600
6Finishes240,00000000.0%240,000
CO 1Change order 1, added entry canopy (approved in a previous month)36,00025,00011,000036,000100.0%0
CO 2Change order 2, deleted site lighting (approved in a previous month)(6,000)(6,000)00(6,000)100.0%0
CO 3Change order 3, added roof hatch and ladder (approved this month)18,50000000.0%18,500
Grand total2,448,5001,012,000286,40041,6001,340,00054.7%1,108,500

Step 2: the G702 lines

LineCalculationAmount
1 Original contract sumFrom the agreement$2,400,000
2 Net change by change orders$36,000 minus $6,000 + $18,500$48,500
3 Contract sum to date$2,400,000 + $48,500$2,448,500
4 Total completed and stored$1,012,000 + $286,400 + $41,600$1,340,000
5a Retainage, completed work10% x $1,298,400$129,840
5b Retainage, stored material10% x $41,600$4,160
5 Total retainage$129,840 + $4,160$134,000
6 Total earned less retainage$1,340,000 minus $134,000$1,206,000
7 Previous certificatesLine 6 of certificate 4$927,000
8 Current payment due$1,206,000 minus $927,000$279,000
9 Balance to finish$2,448,500 minus $1,206,000$1,242,500

A quick cross-check confirms Line 8. Application 4 carried $18,000 of stored material that has since been installed and moved into Column E, so this period’s gross is $286,400 of work plus a $23,600 net increase in stored material ($41,600 minus $18,000), or $310,000. Ten percent retainage leaves $279,000, the same figure as Line 8.

Run three checks before you sign, because an architect will run them too:

  • G703 Column C grand total equals Line 3: $2,448,500.
  • G703 Column G grand total equals Line 4: $1,340,000.
  • G703 Column H grand total plus Line 5 equals Line 9: $1,108,500 + $134,000 = $1,242,500.

Is there a free G702 template?

Not from AIA: the store listed the G702 at $59.99 for one-time use on October 26, 2026, with the G703 sold as a separate document (AIA store). The two tables above, with the formulas in the line table below, are enough to build a spreadsheet that checks your numbers each month. A spreadsheet that copies AIA’s printed form text is not a licensed AIA document, so when the contract names the G702 and G703, submit on the licensed forms.

What goes on Line 7 if the architect cut the last application?

Line 7 takes the prior certificate’s Line 6, not the prior application’s. If the architect had certified application 4 at $907,000 instead of $927,000, Line 7 becomes $907,000 and Line 8 becomes $299,000, because Line 6 is cumulative. Once the reason for the $20,000 cut is removed, A201-2017 §9.5.3 says the withheld amount is certified, and this arithmetic carries it into the current application.

What is the AIA G702 and when is it used?

The AIA G702, Application and Certificate for Payment, is a one-page form with two jobs: the contractor applies for a progress payment in the left half, and the architect certifies the amount due in the right half. AIA Contract Documents designed G702-1992 for projects where the contractor has a direct agreement with the owner, with procedures set by A201, the general conditions that most AIA owner-contractor agreements adopt (AIA G702 summary).

The form never travels alone. AIA’s instructions say to complete the G703 continuation sheet first, transfer its totals to the G702, sign and notarize the G702, and submit both to the architect, who forwards the certified pair to the owner. The owner then pays the contractor named on the form directly, and the architect’s certificate is not negotiable (G702-1992 instructions and form).

The numbers that matter most on every G702, with the rule each comes from:

ItemValueSource
Numbered lines on G702-19929 (Line 5 split into 5a and 5b)AIA sample, 2026
Current editionG702-1992, paired with G703-1992AIA Help Center
Price for one use$59.99 (October 26, 2026)AIA Contract Documents store
Submission lead timeAt least 10 days before the payment dateA201-2017 §9.3.1
Architect review window7 days after receiptA201-2017 §9.4.1
Contractor pays subcontractorsWithin 7 days after the owner paysA201-2017 §9.6.2
Stop-work notice after nonpayment7 additional daysA201-2017 §9.7
Federal progress payment due14 days after a proper requestFAR 52.232-27(a)(1)(i)(A)
Federal retainage cap10%, only if progress is unsatisfactoryFAR 52.232-5(e)
DocumentUsed forPairs withSource
G702-1992Owner to contractor progress billing, architect certifiesG703-1992, A201-2017AIA Help Center
G703-1992Continuation sheet: line items, stored materials, retainage by lineG702-1992 or G732AIA sample
G702S-2017Contractor to subcontractor billingSubcontract termsAIA instructions page
G702GMP-2021Cost of the work projects with a guaranteed maximum priceCost-plus agreementsAIA instructions page
G732Construction Manager as Adviser edition of the applicationG703-1992Named on the G703-1992 sample header

The G702 assumes an architect certifies for the owner. If your delivery method has no independent architect, the agreement names who signs the certificate, which is one of the practical differences covered in design-build vs design-bid-build contracts.

What does each line on the G702 calculate?

Each G702 line is either a contract figure, a G703 total or simple arithmetic on the lines above it. Lines 1 to 3 set the contract sum to date, Line 4 is the G703 Column G grand total, Line 5 is retainage, and Lines 6 to 9 work out what is earned, what was already certified, what is due now and what is left (G702-1992 sample, viewed October 19, 2026).

LineName on the formMathWhere the number comes from
1Original contract sumFixed contract priceSigned owner-contractor agreement
2Net change by change ordersAdditions minus deductionsChange order summary, signed change orders only
3Contract sum to dateLine 1 plus or minus Line 2Arithmetic
4Total completed and stored to dateG703 Column G grand totalG703, Columns D + E + F
5aRetainage on completed workRate x (Columns D + E)Contract retainage rate
5bRetainage on stored materialRate x Column FContract retainage rate
5 totalTotal retainage5a + 5b, or G703 Column I totalFixed rate uses 5a and 5b; variable rate uses Column I
6Total earned less retainageLine 4 minus Line 5 totalArithmetic
7Less previous certificates for paymentLine 6 from the prior certificateLast certified G702, zero on application 1
8Current payment dueLine 6 minus Line 7Arithmetic
9Balance to finish, including retainageLine 3 minus Line 6Arithmetic
How G703 continuation sheet columns feed G702 Lines 1 to 9 G703 continuation sheet G702 application lines Change order summary Additions minus deductions Column G grand total G = D + E + F Columns D + E Work completed to date Column F Materials presently stored Column I (variable rate) Retainage by line item Prior certificate Line 6 as certified last month Line 1 Original contract sum Line 2 Net change by change orders Line 3 Contract sum to date = Line 1 + Line 2 Line 4 Total completed and stored to date Line 5a Retainage % x completed work Line 5b Retainage % x stored material Line 5 total 5a + 5b, or Column I total Line 6 Total earned less retainage = 4 minus 5 Line 7 Less previous certificates for payment Line 8 Current payment due = 6 minus 7 Line 9 Balance to finish = 3 minus 6 Line labels follow AIA Document G702-1992 (AIA sample, viewed 2026-10-19). Arrows show where each number comes from. Line 7 uses the prior certificate’s Line 6, so an amount the architect cut last month carries forward.
Where each G702 number comes from: Column G becomes Line 4, Columns D + E and F set Lines 5a and 5b, and Line 8 is Line 6 minus Line 7. Line labels per AIA G702-1992 sample, viewed October 19, 2026.

How does the change order summary feed Line 2?

The G702 change order summary has two rows, changes approved in previous months by the owner and changes approved this month, each split into additions and deductions. The net of the four cells is Line 2. Work directed by a Construction Change Directive can be billed under A201-2017 §9.3.1.1 before a change order is signed, but it belongs on a G703 line, not in this summary, until the change order exists.

How does the G702 tie to the G703 continuation sheet?

The G703 holds the detail and the G702 holds the totals, so every G702 dollar except the contract figures traces to a G703 column. Column G, total completed and stored to date, becomes Line 4; Columns D and E are the base for Line 5a; Column F is the base for Line 5b; and Column I replaces 5a and 5b when retainage varies by line (G703-1992 sample).

G703 columnWhat it holdsWhere it lands on the G702
C, scheduled valueValue of each line item, change order lines includedGrand total should equal Line 3
D, from previous applicationWork billed before this period (prior D + E)Part of the Line 5a base
E, this periodWork completed this periodPart of the Line 5a base
F, materials presently storedStored materials not yet in D or ELine 5b base
G, total completed and storedD + E + FLine 4
H, balance to finishC minus GGrand total equals Line 3 minus Line 4
I, retainage (variable rate)Retainage by line itemLine 5 total when rates differ by line

Because AIA’s key-steps guide lists each change order as its own G703 line, the Column C grand total should match Line 3 and the Column G grand total must match Line 4 to the cent (AIA key steps for the G702). The line items come from the schedule of values, which A201-2017 §9.2 requires before the first application.

How does retainage reduction change Lines 5 and 8?

A reduction changes only the rate on Lines 5a and 5b, but because Line 5 is cumulative, the cut releases money already held. Illinois local public contracts follow this pattern: up to 10% before 50% completion, then reduced so no more than 5% is held (30 ILCS 550/1). Applied to the worked example at 54.7% complete, Line 8 rises by $67,000.

G702 line10% heldReduced to 5% at 50% completeDifference
5a Completed work$129,840$64,920$64,920 released
5b Stored material$4,160$2,080$2,080 released
5 Total retainage$134,000$67,000$67,000 released
6 Earned less retainage$1,206,000$1,273,000+$67,000
8 Current payment due$279,000$346,000+$67,000
9 Balance to finish$1,242,500$1,175,500minus $67,000
Retainage held on a $2,448,500 contract, by pay applicationLine chart: retainage climbs to $233,000 at 10%; with a cut to 5% at app 5 it drops to $67,000 and ends at $116,500.050,000100,000150,000200,000250,000$ heldApp 1App 2App 3App 4App 5App 6App 7App 810% held throughout5% after 50% complete
Cutting retainage from 10% to 5% at 54.7% complete releases $67,000 on pay app 5 of this illustration. Rule modelled on 30 ILCS 550/1; CB&C arithmetic, October 2026.
Pay appPercent completeLine 4Retainage at 10%Retainage, 5% after 50%
17.4%$180,000$18,000$18,000
217.2%$420,000$42,000$42,000
328.2%$690,000$69,000$69,000
442.1%$1,030,000$103,000$103,000
554.7%$1,340,000$134,000$67,000
669.0%$1,690,000$169,000$84,500
783.7%$2,050,000$205,000$102,500
895.2%$2,330,000$233,000$116,500

Where does the retainage rate on Line 5 come from?

The G702 has blanks for the percentages; the rate comes from the agreement and, on many jobs, a statute. A201-2017 §9.3.1 says the application reflects retainage if provided for in the Contract Documents, so the agreement controls on private work unless a state cap applies. Across 46 jurisdictions with a percentage cap on public work, 30 set it at 5%, per the public construction retainage caps by state.

Contract typeRetainage ruleReduction or release ruleSource
Federal fixed-price constructionUp to 10%, only if progress is unsatisfactoryRelease remaining funds at substantial completion, keeping an adequate amountFAR 52.232-5(e), FAR 32.103
Florida public, over $200,000Up to 5% of each progress paymentLower rate or a contract schedule of reductions allowedFla. Stat. 255.078
Texas public works10% under $5 million; 5% at $5 million or morePartial release allowed; rest at completionTex. Gov’t Code 2252.032
Illinois local public worksUp to 10% before 50% completeAt 50%, reduce so no more than 5% is held30 ILCS 550/1
California private, signed from Jan. 1, 20265% of each payment and of the contract priceCap applies down the subcontract chainCal. Civ. Code 8811
AIA private agreementRate written in the agreementAs the agreement statesA201-2017 §9.3.1
FAR 52.232-5 paragraph (e) on Acquisition.gov with the 10 percent retainage sentence boxed
FAR 52.232-5(e), Payments under Fixed-Price Construction Contracts: federal retainage of up to 10 percent only when progress is unsatisfactory. Acquisition.gov, accessed October 19, 2026.

Private work has fewer caps: 13 jurisdictions limit private retainage by statute, 10 of them at 5%, per the mechanics lien and private retainage laws by state.

What does the architect’s certificate mean, and does the G702 need a notary?

By signing the certificate, the architect represents to the owner, under A201-2017 §9.4.2, that the work has progressed to the point indicated, its quality matches the Contract Documents and the contractor is entitled to the amount certified. The certificate does not represent exhaustive inspections, a review of means and methods, or a check of how earlier payments were spent.

A certificate is also not acceptance. A201-2017 §9.6.6 says a Certificate for Payment, a progress payment or owner occupancy does not accept work that fails the Contract Documents, so an owner who pays application 5 can still reject defective work found at substantial completion. If the architect certifies a different amount, AIA’s instructions call for initials on every changed figure on both the G702 and G703 plus a written explanation.

Does the G702 have to be notarized?

Only if the contract requires it. AIA’s G702-1992 instructions tell the contractor to sign and have the form notarized, and the form carries a notary block (state, county, subscribed and sworn, commission expiry), but A201-2017 §9.3.1 says the application shall be notarized, if required. Read the agreement, the supplementary conditions and any lender draw requirements, and follow the strictest one.

The contractor’s signature also certifies that the work is done per the Contract Documents and that earlier payments were passed on to the people owed. Federal jobs use their own wording: FAR 52.232-5(c) requires a signed certification with each request, and payment is not made without it. Unless the contractor provides a payment bond in the full penal sum, A201-2017 §9.6.7 says money paid for subcontracted work is held for those subcontractors, one reason owners look at surety bond coverage on commercial projects.

How long does each step of the G702 pay cycle take under A201?

A201-2017 sets three fixed clocks around the G702: the contractor submits at least 10 days before the payment date (§9.3.1), the architect acts within 7 days of receipt (§9.4.1), and the contractor pays subcontractors within 7 days of being paid (§9.6.2). The payment date itself comes from the owner-contractor agreement, such as the day-of-month blanks in A101-2017 §5.1.3.

StepDeadlineA201-2017 sectionExample date (illustration)
Contractor submits G702 and G703At least 10 days before the payment date§9.3.1Oct 25
Architect certifies, cuts or withholdsWithin 7 days after receipt§9.4.1Nov 1
Owner pays the certified amountDate set in the agreement§9.6.1Nov 15
Contractor pays subcontractorsWithin 7 days after receipt of payment§9.6.2Nov 22
Owner still unpaid, contractor may give notice7 days after the payment date§9.7Nov 22
Earliest stop-work date7 additional days after notice§9.7Nov 29
A201-2017 pay application cycle with example dates One pay application cycle under A201-2017 (illustration dates) Oct 25 Nov 1 Nov 15 Nov 22 Nov 29 G702 + G703 to architect At least 10 days before pay date (9.3.1) Architect acts Within 7 days: certify, cut or withhold (9.4.1) Owner pays Date set in the agreement, e.g. A101 5.1.3 (9.6.1) Subs paid 7 days after contractor is paid (9.6.2) Stop work If unpaid 7 days late, then 7 days notice Example: payment date Nov 15, application received Oct 25 (21 days ahead, above the 10-day minimum). Owner unpaid by Nov 22 lets the contractor send notice; work may stop Nov 29 (A201-2017 9.7). Section numbers: AIA A201-2017 General Conditions, as posted by the University of Maine System (accessed 2026-10-19). Your agreement can change every one of these periods; the dates here are an illustration, not contract terms.
One A201-2017 pay cycle with illustration dates: submit 10 or more days ahead (§9.3.1), architect acts in 7 days (§9.4.1), subs paid 7 days after payment (§9.6.2), stop work after 7 more days’ notice (§9.7).

Public owners often run on a statute instead. Federal agencies owe a progress payment 14 days after a proper request and must return an improper invoice within 7 days (FAR 52.232-27), while the median state deadline for a public owner to pay a prime contractor is 30 days across 49 jurisdictions, per the CB&C prompt payment registry checked October 8, 2026. Every monthly cycle sits inside Phase 6 of the commercial construction process from contract to closeout.

Why do G702 pay applications get rejected?

Most rejections trace to a number that does not reconcile or a document that is missing. A201-2017 §9.5.1 lists seven grounds to withhold, from defective work to unpaid subcontractors, and §9.3 sets the paperwork each application needs, so the table below pairs each common problem with the clause a reviewer can point to.

ProblemWhat the reviewer seesRule behind itFix before submitting
Line 4 does not equal G703 Column GTotals disagree by any amountG702 instructions: transfer G703 totalsRe-foot Column G and copy the grand total
Line 7 copied from the last applicationLine 7 above the last certified Line 6Form label: Line 6 from prior certificateUse the certified figure
Unsigned change order in Line 2Summary total above approved changesChange order summary lists approved changesBill directive work on a G703 line under §9.3.1.1
Stored materials without proofColumn F with no invoices, title or insuranceA201-2017 §9.3.2Attach bills of sale, insurance and location; get owner approval for off-site storage
Missing lien waiversNo releases from subs paid last monthA201-2017 §9.3.1Collect waivers in the form the owner requires
Percent complete ahead of the siteColumn E above what the architect observedA201-2017 §9.4.2Bill observed progress; walk the job with the architect
Billing for work you will not pay a sub forSub dispute plus full billingA201-2017 §9.3.1.2Leave disputed sub amounts out
Subs not paid from the last paymentOwner evidence request unanswered after 7 daysA201-2017 §9.5.1.3, §9.6.4Send proof of payment with the application
Wrong retainage rateLine 5 rate differs from the agreement or statuteA201-2017 §9.3.1; state capsCheck the rate and any 50% reduction trigger
No notary where requiredBlank notary blockAgreement terms; A201-2017 §9.3.1Sign before a notary and state your capacity

What several guides say vs what the form says

Several widely read G702 guides, checked on October 19, 2026, contain claims that change the math or the paperwork. The table sets each claim against the AIA G702-1992 sample, the G702 instructions, A201-2017 or the FAR, so a reviewer can check the primary source before copying a formula into a billing spreadsheet.

Claim seen in online G702 guides (October 2026)What the primary source saysSource
Line 9 is Line 6 minus Line 3Line 9 is Line 3 minus Line 6, a positive balance including retainageG702-1992 sample
Line 7 is Line 6 of the previous applicationLine 7 is Line 6 from the prior certificate, the certified figureG702-1992 sample
The form always requires a notary, or no rule requires oneAIA instructions say notarize; A201-2017 §9.3.1 says notarized, if requiredG702 instructions, A201-2017
The G702 costs $43.99$59.99 for one-time use on October 19, 2026AIA store
Retainage is typically 10%30 of 46 capped jurisdictions set public retainage at 5%; federal is 10% only for unsatisfactory progressFAR 52.232-5(e)

What should you do in each pay application situation?

The right move depends on who certifies, what changed since the last certificate and which rule sets retainage. The decision table below covers the eight situations that most often change a G702, each with the clause or statute behind it; the flowchart after it shows the architect’s three options under A201-2017 §9.4.1.

IfThenRule
The architect certified less than you applied forCarry the certified Line 6 into Line 7 and resolve the reasonsG702 instructions; A201-2017 §9.5.3
You disagree with the cutSubmit a Claim under Article 15A201-2017 §9.5.2
The project passes 50% complete on a reducing contractChange the 5a and 5b rates on that applicationAgreement; e.g. 30 ILCS 550/1
Materials are stored off siteGet the owner’s written approval first, plus title and insurance proofA201-2017 §9.3.2
Work was directed but no change order is signedBill it on a G703 line, not the change order summaryA201-2017 §9.3.1.1
No certificate 7 days after the architect received itGive 7 days’ notice before stopping workA201-2017 §9.7
The job is federalAdd the FAR certification; expect payment 14 days after a proper requestFAR 52.232-5(c), 52.232-27
A construction loan funds the jobMatch the G702 to the loan’s draw conditions before submittingLoan agreement

A201-2017 §9.5.1 lets the architect withhold a certificate, in whole or in part, on seven grounds:

  1. Defective work not remedied.
  2. Third-party claims filed or reasonably likely, unless the contractor posts acceptable security.
  3. Subcontractors or suppliers not paid properly.
  4. Reasonable evidence the unpaid balance cannot finish the work.
  5. Damage to the owner or a separate contractor.
  6. Reasonable evidence of a late finish where the unpaid balance cannot cover the delay damages.
  7. Repeated failure to carry out the work per the Contract Documents.
Architect certification decision under A201-2017 sections 9.4 and 9.5 G702 and G703 received by architect Can the architect make the 9.4.2 representations for the full amount? Yes: certify in full within 7 days, copy to contractor (9.4.1 option 1) No. Is part of the amount supportable? Yes: certify reduced amount, initial changed figures, attach reasons (9.4.1 option 2) No: withhold the whole certificate and give written reasons (9.4.1 option 3) Reasons removed: withheld amounts are certified (9.5.3). Disputed: either party may file a Claim under Article 15 (9.5.2). Grounds to withhold (9.5.1): .1 defective work not remedied .2 third-party claims .3 subs or suppliers not paid .4 balance cannot finish the work .5 damage to owner or others .6 late finish, balance too small .7 repeated failure to perform
The architect certifies in full, certifies a reduced amount with initialled changes, or withholds the whole certificate, on the seven grounds in A201-2017 §9.5.1.

A construction loan can add a second reviewer: the lender may set its own draw conditions, such as an inspection or title update, on top of the certified application, so match the G702 to the loan agreement before submitting. Owners vetting builders can ask how each one reconciles its G702 and G703 each month, alongside the steps in how to choose a commercial contractor, and keep each certified application with the lien waivers listed in the commercial project document checklist.

A month-by-month example of how retainage builds up and is released, with state caps and the federal rule, is in our guide to retainage in construction.

When a lender funds the job, each G702 becomes one line of the construction draw schedule the lender inspects and funds.

How we compiled this

We read 13 primary documents in October 2026: the AIA G702-1992 and G703-1992 sample previews, the G702 instructions, summary and key-steps guide from AIA Contract Documents, A201-2017 as posted by the University of Maine System, FAR 52.232-5, 52.232-27 and 32.103 on Acquisition.gov, and four state retainage statutes. The worked example uses invented figures and CB&C arithmetic. We did not reproduce AIA form text, which is copyrighted, and this page is not legal or financial advice. On October 26, 2026 we re-checked A201-2017 sections 9.3.1, 9.4.1, 9.6.2 and 9.7 against the posted text and the G702 price on the AIA store.

Frequently asked questions

Does an AIA G702 need to be notarized?

Only when the contract requires it. AIA’s G702-1992 instructions tell the contractor to sign and notarize the form, and the form includes a notary block, but A201-2017 §9.3.1 says the application is notarized, if required. Check the agreement, the supplementary conditions and any lender draw rules, and follow whichever is strictest.

What is the difference between the G702 and the G703?

The G703 continuation sheet lists every line item with its scheduled value, work this period, stored materials and retainage. The G702 is the one-page summary: it takes the G703 Column G total as Line 4, applies retainage on Lines 5a and 5b, subtracts prior certificates on Line 7 and shows the current payment due on Line 8.

What goes on Line 7 of a G702?

Line 7 is Line 6 from the prior certificate, the amount the architect certified last time, not the amount you applied for. It is zero on application 1. If the architect cut the last application by $20,000, Line 7 drops by $20,000 and the cumulative Line 6 brings that amount back once the reason is resolved.

How is retainage calculated on a G702?

Line 5a is the retainage rate times G703 Columns D plus E, the work completed to date. Line 5b is the rate times Column F, stored materials. The total is 5a plus 5b, or the Column I total when rates vary by line. At 10%, $1,298,400 of completed work gives $129,840 on Line 5a.

How long does the architect have to certify a G702?

Under A201-2017 §9.4.1, the architect has 7 days after receiving the application to certify the full amount, certify a reduced amount with reasons, or withhold the whole certificate with reasons. If no certificate issues within 7 days through no fault of the contractor, §9.7 lets the contractor stop work after 7 more days’ notice.

How much does an AIA G702 cost?

AIA Contract Documents listed the G702 at $59.99 for one-time use on October 26, 2026, and sells the G703 continuation sheet separately at the same price. AIA’s instructions license up to ten copies of a completed G702 for one project. The form text is copyrighted, so free downloads that copy it are not licensed AIA documents.

Is a G702 a lien waiver?

No. The G702 requests and certifies payment; it does not release lien rights. A201-2017 §9.3.1 lets the owner require releases and waivers of liens from subcontractors and suppliers with each application, and AIA sells separate waiver forms, such as the G901 conditional waiver on progress payment, listed with the G702 on its store page in October 2026.