AIA contract documents are the American Institute of Architects’ standard construction forms: 300+ agreements and forms in seven series, A to G, licensed at $179.99 per agreement and $59.99 per form for one-time use (aiacontracts.com, October 2026).
Key takeaways
- A typical fixed-price job needs a set, not one form: B101-2017 with the architect, A101-2017 plus the A201-2017 general conditions with the builder, G702 and G703 every pay period, and G704, G706, G706A and G707 at closeout. A201 is incorporated by reference into A101, A102, A103, A401, B101 and B103 (AIA A201-2017 summary).
- Design-build runs on A141-2024, which replaced A141-2014; check the edition year, because AIA’s own series list still showed the 2014 edition when last modified on July 23, 2026 (AIA A141-2024 summary).
- An old year does not mean an old form: G702-1992 and G703-1992 are still the current pay application forms, and G706, G706A and G707 (1994) are still the current closeout forms (AIA list of current documents).
- A one-time document “may be finalized only once”, and AIA does not publish the price of its unlimited subscription with 1, 3 or 5 seats (AIA How it works).
- ConsensusDocs, founded in 2007, sells 116 contracts in a $1,400 a year Full Package, and its ConsensusDocs 200 combines the agreement and general conditions that AIA splits into A101 and A201 (ConsensusDocs comparison matrix).
| Key number | What it means | Source |
|---|---|---|
| 300+ | Agreements and forms in the AIA library | AIA How it works, Oct 2026 |
| 7 | Series: A, B, C, D, E, F and G | AIA list, modified Jul 23, 2026 |
| $179.99 | One-time license for an agreement such as A101-2017 or A201-2017 | aiacontracts.com A101 page, Oct 2026 |
| $59.99 | One-time license for a form such as G702-1992 or G704-2017 | aiacontracts.com G702 page, Oct 2026 |
| 10 days | Pay application due before each progress payment date | A201-2017 Section 9.3.1 |
| 10 years | Outer limit for claims after substantial completion | A201-2017 Section 15.1.2 |
| $1,400 a year | ConsensusDocs Full Package, 116 contracts | ConsensusDocs pricing, Oct 2026 |
What are AIA contract documents?
AIA contract documents are copyrighted standard forms that AIA Contract Documents (ACD Operations, LLC) publishes for the American Institute of Architects. The publisher says the forms have been an industry standard since 1888, are used on more than 200,000 projects a year and are drafted by a Documents Committee of more than 35 industry members (AIA Contract Documents explainer).
The forms are national, not state specific. AIA says they “are not drafted to reflect the laws of any particular state”, so a state lien, licensing or prompt payment statute can override a clause in the A201-2017 general conditions. Public works payment deadlines and retainage caps in all 50 states and DC are compared in our prompt payment and retainage tracker by state.
This page describes the forms and how they are licensed; it is not legal advice. Before you sign, ask a construction attorney two things: which A201-2017 clauses your state’s statutes override, and what your supplementary conditions should change, using AIA’s A503 guide as the starting list.
How are the AIA document series organized?
AIA sorts its documents by letter, and the letter names the relationship. A covers owner and contractor agreements, B owner and architect, C other agreements, D miscellaneous, E exhibits, F facility management and G contract administration forms. The year after the number is the edition, so A201-2017 is the 2017 general conditions (AIA list of current documents).
| Series | What it covers | Current examples | Source |
|---|---|---|---|
| A | Owner-contractor agreements, general conditions, bonds, bidding | A101-2017, A133-2019, A141-2024, A201-2017, A312-2010 | AIA list |
| B | Owner-architect agreements and architect scopes | B101-2017, B133-2019, B141-2024 | AIA list |
| C | Other agreements: consultants, CM as adviser, joint ventures | C101-2018, C132-2019, C401-2017 | AIA list |
| D | Miscellaneous: area methods, checklists, guides | D101-1995, D200-1995, D503-2020 | AIA list |
| E | Exhibits for BIM and sustainable projects | E201-2022, E204-2017 | AIA list |
| F | Facility management: maintenance agreements, work orders | F101-2023, F201-2023 | AIA list |
| G | Contract administration and project forms | G701-2017, G702-1992, G704-2017, G706-1994 | AIA list |
The digits after the letter mark the family, which tells you what fits together. Documents ending in 01 belong to the conventional design-bid-build set (A101, B101, A201, A401), 33 to construction manager as constructor (A133, B133), 32 to construction manager as adviser (A132, B132, C132) and 41 to design-build (A141, B141, C141, A441).
Which AIA contract documents matter on a commercial project?
Thirteen documents cover most commercial work an owner or general contractor will sign: four owner-builder agreements (A101, A102, A133, A141), the A201 general conditions, the B101 owner-architect agreement and seven G-series forms for changes, payment and closeout. The table gives each one’s current edition, what it governs, what AIA’s store sells it with and its one-time price.
| Document | Current edition | What it governs | AIA sells it with | One-time price | Source |
|---|---|---|---|---|---|
| A101 | 2017 | Owner-contractor, stipulated (fixed) sum; insurance and bonds in Exhibit A | A201, G702, G703 | $179.99 | AIA summary, store |
| A102 | 2017 | Owner-contractor, cost of the work plus a fee with a guaranteed maximum price (GMP) | A201 | $179.99 | AIA store |
| A133 | 2019 | Owner and construction manager as constructor; GMP set by the Exhibit A amendment | A201, B133 | $179.99 | AIA summary, store |
| A141 | 2024 | Owner and design-builder; Design-Build Amendment is Exhibit B | B141 | $179.99 | AIA summary, store |
| A201 | 2017 | General conditions: roles, payment, changes, claims, completion; 15 articles; not a contract on its own | A101, A401, B101 | $179.99 | AIA summary, store |
| B101 | 2017 | Owner-architect; five phases of basic services | A201, C401 | $179.99 | AIA summary, store |
| G701 | 2017 | Change order agreed by owner, contractor and architect | A201, G714 | $59.99 | AIA store |
| G702 | 1992 | Application and certificate for payment: work completed and stored, retainage, prior payments, change orders | G703, G901, G902 | $59.99 | AIA store |
| G703 | 1992 | Continuation sheet listing each line of the schedule of values | G702 | $59.99 | AIA store |
| G704 | 2017 | Certificate of substantial completion; warranties start on that date unless stated | A201, G706, G707 | $59.99 | AIA summary, store |
| G706 | 1994 | Contractor’s affidavit that debts and claims are paid, exceptions listed | G706A, G707 | $59.99 | AIA summary, store |
| G706A | 1994 | Contractor’s affidavit that lien releases or waivers were received | G706, G901, G904 | $59.99 | AIA store |
| G707 | 1994 | Consent of surety to final payment on bonded work | G706, A312 | $59.99 | AIA summary, store |
An old year in the title does not mean a form is stale. AIA’s retired list, dated July 31, 2024, withdraws G702 editions up to 1983 and G704 editions up to 2000, which leaves G702-1992 and G704-2017 as the current forms (AIA retired documents list). AIA’s G704 summary also notes that AIA does not publish a standard schedule of values form, so G703 lines follow the contractor’s own schedule of values (AIA G704-2017 summary).
Which documents go together for each delivery method?
Choose the delivery method first and the AIA family follows. Design-bid-build uses A101 or A102 with A201 and B101; construction management at risk uses A133 with A201 and B133; design-build uses A141 with B141. A133-2019 is coordinated with A201-2017 and B133-2019 specifically, so mixing families can break the cross-references (AIA A133-2019 summary).
| Piece | Design-bid-build, fixed price | Design-bid-build, cost plus GMP | Construction management at risk | Design-build |
|---|---|---|---|---|
| Owner-builder agreement | A101-2017 | A102-2017 | A133-2019 (GMP: Exhibit A) | A141-2024 (progressive: A141PDB-2024) |
| General conditions | A201-2017 | A201-2017 | A201-2017 | No A201 (A141 set) |
| Owner-architect | B101-2017 | B101-2017 | B133-2019 | B141-2024, signed by design-builder |
| Pay application | G702-1992 + G703-1992 | G702GMP-2021 + G703CW-2021 | G702GMP-2021 + G703CW-2021 | G742-2024 + G743-2024 |
| Substantial completion | G704-2017 | G704-2017 | G704-2017 | G744-2024 |
| ConsensusDocs equivalent | CD 200 | No matrix row | CD 500 + 500.1 | CD 410 or 415 |
The design-build column is the 2024 family: AIA lists G741 through G745 and G841 as the matching change, payment, completion and directive forms (AIA 2024 design-build update). A201 is not among the documents the A201 summary lists as incorporating it, which is why the design-build column carries no A201. The trade-offs between these methods are set out in our design-build vs design-bid-build comparison.
If a construction manager will price the job during design, the A133 path applies, and the GMP mechanics behind its Exhibit A are explained in our guide to construction management at risk and the GMP. For a single design-and-build contract under A141-2024, the selection checks are in our guide to hiring design-build contractors.
How do the forms run from contract to closeout?
On a design-bid-build job the AIA forms arrive in a fixed order: B101 at design, A101 or A102 with A201 at builder selection, G702 and G703 every pay period, G701 for each agreed change, G704 at substantial completion, then G706, G706A and G707 before final payment. A201-2017 sets the timing rule behind each step (A201-2017 text).
- Design: the owner signs B101-2017; the architect’s five phases of basic services run from schematic design to construction.
- Builder selection: owner and contractor sign A101-2017 or A102-2017 + A201-2017, with Exhibit A setting insurance and bonds; AIA’s payment and performance bond form is A312-2010.
- Each pay period: the contractor submits G702-1992 + G703-1992 at least 10 days before the payment date (a line-by-line walk-through is in our AIA G702 guide), itemized by the schedule of values and backed by lien releases if required (A201 9.3.1).
- Each change: G701-2017 when owner, contractor and architect agree on price and time; G714-2017, a construction change directive, when they do not.
- Substantial completion: the architect prepares G704-2017 (A201 9.8.4), and warranties start on that date unless the form says otherwise.
- Final payment: G706-1994, G706A-1994, G707-1994 and the other items in A201 9.10.2 come in before final payment and the last retainage are due.
- Claims window: A201-2017 Section 15.1.2 cuts off claims not started within 10 years after substantial completion, and Section 15.3.1 makes mediation a condition before arbitration or litigation.
Section 9.10.2 of A201-2017 lists six items that hold up final payment and the remaining retained percentage. Three of them map to AIA G-series forms that AIA sells at $59.99 each (AIA G706 summary).
| A201-2017 Section 9.10.2 item | AIA form | Signed by | When it applies |
|---|---|---|---|
| (1) Affidavit that payrolls and bills are paid | G706-1994 | Contractor, listing exceptions | Any project on A201 |
| (6) Other payment or lien release data the owner requires | G706A-1994 | Contractor | When the owner asks for releases |
| (4) Consent of surety, if any | G707-1994 | Surety | Bonded projects |
| (2) and (3) Insurance certificate and renewal statement | ACORD 25 with G715-2017 supplement | Contractor and broker | Insurance that runs past final payment |
| (5) Special warranties | No AIA form; maker and subcontractor warranties | Contractor | Where specifications require them |
G707 matters because the surety agrees that final payment does not release its bond obligations, which preserves the owner’s rights under the bond (G707-1994 summary). Bond thresholds under the Miller Act and state laws are in our construction surety bond statistics. Which lien waiver form to collect at each payment, and the lien deadlines and preliminary notice rules that decide whether a G706A release is enough, differ by state and are tracked in our mechanics lien laws by state table.
Which editions of AIA contract documents are current in October 2026?
As of October 2026 the conventional set is the 2017 edition (A101, A102, A201, B101), construction manager as constructor is 2019 (A133, B133), design-build is 2024 (A141, B141) and the payment and closeout forms date from 1992 and 1994. Several public pages, including one AIA page, still show an older edition or a different count (AIA A141-2024 summary).
| What some pages say | Where it appears | What the primary source says | Primary source |
|---|---|---|---|
| A141-2014 is the design-build agreement | AIA series list (modified Jul 23, 2026); ConsensusDocs matrix rows 410 and 415 | A141-2024 “replaces AIA Document A141-2014” and sells at $179.99 | AIA summary, store |
| G744-2014 is the design-build completion form | AIA series list | G744-2024 is in the 2024 design-build family | AIA 2024 update |
| Documents sit in “six series” | AIA series list header | The same list shows seven, including F for facility management (F101-2023) | AIA list |
| “Over 180” or “nearly 200” forms | AIA Rhode Island; AIA New York State | “300+ documents”; the subscription page heading reads 236 contracts and forms | AIA How it works, subscription page |
| G707 is the consent of surety to release of retainage | AIA G706 summary | G707-1994 is titled Consent of Surety to Final Payment | AIA G707 summary |
AIA publishes no fixed revision calendar; its explainer says documents are reviewed on an ongoing basis, and the families move as sets. The A201 summary lists A201-2007 as the prior edition, and AIA’s retired list shows A141-2004 withdrawn before the 2014 and 2024 design-build editions (AIA retired documents list).
How do you buy or license AIA contract documents?
AIA Contract Documents sells each document as a one-time use license, $179.99 for an agreement and $59.99 for a form, or as an unlimited annual subscription with 1, 3 or 5 seats and no published price. A one-time document “may be finalized only once”, and AIA Minnesota says members get 20% off digital purchases (AIA How it works; AIA Minnesota, October 2026).
Paper copies still exist: AIA Minnesota takes paper orders and ships them once a week. AIA New York State notes that the documents are copyrighted and licensed for one-time use, so an A201-2017 posted with a public bid is not a reusable template for your next project (AIA New York State).
The worked example below prices a 12-month design-bid-build job on one-time licenses, read from the October 2026 product pages. It assumes each monthly G702 and G703 is finalized as its own document, which is how we read “may be finalized only once”; confirm with AIA before budgeting.
| Line | Documents | Count | Unit price | Subtotal | Source |
|---|---|---|---|---|---|
| Agreements | B101, A101, A201 | 3 | $179.99 | $539.97 | AIA store |
| Monthly pay applications, 12 months | G702 + G703 | 24 | $59.99 | $1,439.76 | AIA store |
| Closeout | G704, G706, G706A, G707 | 4 | $59.99 | $239.96 | AIA store |
| AIA list total | 31 | $2,219.69 | CB&C arithmetic | ||
| AIA total with 20% member discount | 31 | $1,775.75 | AIA Minnesota discount | ||
| ConsensusDocs Full Package, 1 year | 116 contracts | $1,400.00 | ConsensusDocs pricing |
The break point is about 23 forms. Twenty-three one-time forms at $59.99 cost $1,379.77 and the 24th takes the total to $1,439.76, past a year of the ConsensusDocs Full Package at $1,400. A contractor running more than one AIA job a year has a reason to ask AIA for a subscription quote at that volume, since AIA does not print one.
How does ConsensusDocs compare with AIA contract documents?
ConsensusDocs is the main alternative family: launched in 2007 by 20 organizations, now backed by more than 40 coalition members and sold as annual packages from $645 to $1,400. Its own matrix maps each form to an AIA number, such as ConsensusDocs 200 to A101 plus A201 and ConsensusDocs 500 to A133 plus A201 (ConsensusDocs comparison matrix, October 2026).
| Point | AIA Contract Documents | ConsensusDocs | Source |
|---|---|---|---|
| Started | Industry standard “since 1888” (publisher claim) | 2007, 20 founding organizations | ACD, ConsensusDocs about |
| Drafted by | AIA Documents Committee, 35+ members | Coalition of 40+ industry organizations | ACD, ConsensusDocs about |
| Library | 300+ documents in 7 series | 110+ documents in 200 to 900 series; 116 in the Full Package | ACD, ConsensusDocs catalog |
| Lump-sum owner-builder contract | A101-2017 agreement + A201-2017 general conditions (2 documents) | ConsensusDocs 200: agreement and general conditions in 1 document | ConsensusDocs matrix |
| CM at risk | A133-2019 + A201-2017 | ConsensusDocs 500 + 500.1 GMP amendment | ConsensusDocs matrix |
| Design-build | A141-2024 | ConsensusDocs 410 (GMP) or 415 (lump sum) | ConsensusDocs matrix |
| Owner-architect | B101-2017 | ConsensusDocs 240 | ConsensusDocs matrix |
| Pay application | G702-1992 + G703-1992 | ConsensusDocs 291 or 292 + 293 schedule of values | ConsensusDocs matrix |
| Price | $179.99 or $59.99 per one-time document; subscription price not published | $645 to $1,400 a year by package; Owner package $1,290 for 63 contracts | ACD store, ConsensusDocs pricing |
| Free review | No free sample offer on the AIA pages we read | Up to 3 free contract samples on request | ConsensusDocs home |
The structural difference shows up first in a negotiation. If the other side sends ConsensusDocs 200, the matrix tells you its AIA counterpart is A101 with A201-2017, so your attorney can compare the two clause by clause instead of reading a new form cold.
Which contract family and form should you pick?
Match the agreement to how the price is set and who designs, then add forms for bonds and closeout. The decision table uses AIA’s own guidance: A101 for a fixed price, A102 for cost plus a GMP, A133 when the builder joins during design, A141 for design-build, and A104 or A105 for smaller jobs (AIA help centre, October 2026).
| If | Use | Threshold or reason | Source |
|---|---|---|---|
| Price is fixed by bid or negotiation before work starts | A101-2017 + A201-2017, B101-2017 | Cost set in advance | AIA A101 summary |
| Owner pays actual cost up to a ceiling after design | A102-2017 + A201-2017 | Cost plus fee with a GMP | AIA A102 page |
| Builder joins during design and later gives a GMP | A133-2019 + A201-2017, B133-2019 | GMP binds once Exhibit A is signed | AIA A133 summary |
| One firm designs and builds | A141-2024; A141PDB-2024 if price develops progressively | Contract sum fixed by Exhibit B amendment | AIA A141 summary |
| Job is of limited scope | A104-2017 | AIA’s alternative to A101 + A201 | AIA A201 summary |
| Residential or small commercial job | A105-2017 | Smaller, less complex work | AIA A201 summary |
| Contractor is bonded | A312-2010 bonds; G707-1994 at final payment | Surety consent keeps bond rights | AIA G707 summary |
| You will finalize more than 23 one-time forms in a year | Ask AIA for a subscription quote, or price ConsensusDocs | 23 x $59.99 = $1,379.77 vs $1,400 | CB&C arithmetic |
| The other side or your lender already uses ConsensusDocs | ConsensusDocs 200, 500, or 410 / 415 | Matrix gives the AIA counterpart | ConsensusDocs matrix |
The agreement is only part of the choice; the builder matters as much as the form. Our checklist for choosing a commercial contractor covers the A305 qualification statement, bonding letters and references to collect before you send an A101.
The seven phases where each of these forms gets signed, from feasibility to closeout, are laid out in our guide to the commercial construction process.
How we compiled this
We read 13 AIA Contract Documents product pages, 2 AIA licensing pages, 11 AIA help centre summaries, the AIA series list, the A201-2017 text posted with a City of Rochester, NH bid and 5 ConsensusDocs pages, all in October 2026. Prices are list prices shown to a logged-out visitor; we did not buy documents or use the software. Vendor blogs were read for question phrasing only, never as a source of fact, and no AIA contract text is reproduced beyond section references. On October 26, 2026 we re-checked the A201 and G702 prices and the A201-2017 sections cited here.
Frequently asked questions
Are AIA contract documents free?
No. AIA Contract Documents sells one-time licenses at $179.99 for an agreement such as A101-2017 and $59.99 for a form such as G702-1992, plus an unlimited annual subscription whose price is not published (aiacontracts.com, October 2026). The documents are copyrighted and licensed for one-time use. ConsensusDocs, the main alternative, offers up to three free samples before you buy.
Can you modify an AIA contract document?
Yes. AIA’s software lets users edit and finalize documents, and AIA publishes A503 as a guide for supplementary conditions that amend A201-2017. The A201 summary lists supplementary conditions as one of the contract documents, alongside the agreement, drawings and specifications (AIA help centre, October 2026). Ask your attorney for a redline that shows every change before anyone signs.
What is the difference between AIA A101 and A102?
A101-2017 is for a stipulated sum, a fixed price set by bid or negotiation before work starts. A102-2017 is for the cost of the work plus a fee with a guaranteed maximum price, so the owner pays actual costs up to a ceiling. Both adopt the A201-2017 general conditions and sell for $179.99 each as one-time documents (AIA, October 2026).
Is AIA A201 a contract on its own?
No. A201-2017 is the general conditions, and AIA calls it the keystone document because it is incorporated by reference into A101, A102, A103, A401, B101 and B103. It sets the rules for payment, changes, claims and completion across 15 articles, while price, time and the parties sit in the agreement it is attached to (AIA help centre, October 2026).
Are AIA contract documents valid in every state?
They can be used in any state, but AIA says the documents are not drafted to reflect the laws of any particular state. State statutes on liens, prompt payment, retainage and licensing can override a clause in A201-2017, which is why the A201 summary points users to A503, AIA’s guide for writing supplementary conditions (AIA, October 2026).
How often does the AIA update its contract documents?
AIA publishes no fixed schedule; its explainer says documents are reviewed on an ongoing basis. Families move together: the conventional set went from 2007 to 2017 editions, construction manager as constructor documents to 2019 and design-build to 2024. AIA’s retired list, dated July 31, 2024, shows which older editions have been withdrawn.
Which AIA forms are needed for final payment?
Under A201-2017 Section 9.10.2, final payment and remaining retainage wait for the contractor’s affidavit, proof of insurance, consent of surety if the job is bonded and any lien release data the owner requires. The AIA forms are G706-1994, G706A-1994 and G707-1994, each $59.99 as a one-time document, usually after G704-2017 records substantial completion.
Sources
All sources accessed October 19, 2026.
- A101-2017 product page (price, pairings), AIA Contract Documents (accessed 2026-10-19)
- A102-2017 product page, AIA Contract Documents (accessed 2026-10-19)
- A133-2019 product page, AIA Contract Documents (accessed 2026-10-19)
- A141-2024 product page, AIA Contract Documents (accessed 2026-10-19)
- A201-2017 product page, AIA Contract Documents (accessed 2026-10-19)
- B101-2017 product page, AIA Contract Documents (accessed 2026-10-19)
- G701-2017 product page, AIA Contract Documents (accessed 2026-10-19)
- G702-1992 product page, AIA Contract Documents (accessed 2026-10-19)
- G703-1992 product page, AIA Contract Documents (accessed 2026-10-19)
- G704-2017 product page, AIA Contract Documents (accessed 2026-10-19)
- G706-1994 product page, AIA Contract Documents (accessed 2026-10-19)
- G706A-1994 product page, AIA Contract Documents (accessed 2026-10-19)
- G707-1994 product page, AIA Contract Documents (accessed 2026-10-19)
- How it works (one-time use and subscription), AIA Contract Documents (accessed 2026-10-19)
- Unlimited Subscription, AIA Contract Documents (accessed 2026-10-19)
- What Are AIA Contract Documents?, AIA Contract Documents (accessed 2026-10-19)
- List of all current AIA Contract Documents by series, AIA Contract Documents (accessed 2026-10-19)
- Summary: A201-2017, General Conditions of the Contract for Construction, AIA Contract Documents help centre (accessed 2026-10-19)
- Summary: A101-2017, Owner and Contractor, Stipulated Sum, AIA Contract Documents help centre (accessed 2026-10-19)
- Summary: A133-2019, Owner and Construction Manager as Constructor, GMP, AIA Contract Documents help centre (accessed 2026-10-19)
- Summary: A141-2024, Owner and Design-Builder, AIA Contract Documents help centre (accessed 2026-10-19)
- Updates to 2024 Design-Build Documents and Progressive Design-Build release, AIA Contract Documents help centre (accessed 2026-10-19)
- Summary: B101-2017, Owner and Architect, AIA Contract Documents help centre (accessed 2026-10-19)
- Summary: G704-2017, Certificate of Substantial Completion, AIA Contract Documents help centre (accessed 2026-10-19)
- Summary: G706-1994, Contractor’s Affidavit of Payment of Debts and Claims, AIA Contract Documents help centre (accessed 2026-10-19)
- Summary: G707-1994, Consent of Surety to Final Payment, AIA Contract Documents help centre (accessed 2026-10-19)
- List: Retired Documents (as of July 31, 2024), AIA Contract Documents help centre (accessed 2026-10-19)
- AIA Document A201-2017 text (sample posted with a city bid), Sections 9.3.1, 9.8.4, 9.10.2, 15.1.2, 15.1.6.2, 15.3.1, City of Rochester, NH (accessed 2026-10-19)
- About ConsensusDocs, ConsensusDocs (accessed 2026-10-19)
- ConsensusDocs Pricing and Packages, ConsensusDocs (accessed 2026-10-19)
- ConsensusDocs Contract Catalog, ConsensusDocs (accessed 2026-10-19)
- AIA Comparison Chart, ConsensusDocs (accessed 2026-10-19)
- ConsensusDocs home (free samples), ConsensusDocs (accessed 2026-10-19)
- AIA Contract Documents (paper orders, member discount), AIA Minnesota (accessed 2026-10-19)
- AIA Contract Documents, AIA Rhode Island (accessed 2026-10-19)
- AIA Contract Documents (copyright and one-time use), AIA New York State (accessed 2026-10-19)