Notice to Proceed in Construction: What It Starts and What Goes in the Letter

Graded commercial building pad with an excavator and site trailer at the start of construction

A notice to proceed (NTP) is the owner’s written order telling the contractor to start work: under AIA A101-2017 §3.1 it can fix the date of commencement, and the Contract Time is counted from that date.

Key takeaways

  • AIA A101-2017 §3.1 offers 3 boxes for the date of commencement: the Agreement date, “a date set forth in a notice to proceed issued by the Owner,” or a custom rule; if none is checked, the Agreement date governs (A101-2017, Oakton Community College copy).
  • A201-2017 §8.1.1 measures the Contract Time to Substantial Completion, and §8.1.4 makes every “day” a calendar day unless the contract says otherwise (A201-2017 sample).
  • Federal fixed-price construction contracts use FAR 52.211-10 (Apr 1984): the contractor must start within a set number of calendar days after it receives the notice to proceed.
  • Federal bonds must reach the Contracting Officer “in any event, before starting work” under FAR 52.228-15(c), and the Miller Act requires them on construction contracts over $150,000 (FAR 28.102-1).
  • Public owners commonly allow 10 calendar days from the NTP to start work: New Mexico State University, the New Mexico Public School Facilities Authority and Wisconsin DOT all use 10 (NM PSFA form 00 5501, rev. Nov 2025).

What is a notice to proceed in construction?

A notice to proceed is a short letter from the owner, or the owner’s contracting officer, that authorizes the contractor to begin the work in a signed contract and names the day the schedule starts. Los Angeles’s Bureau of Engineering puts it plainly: “The NTP date is the first day of the contract period” (LA Project Delivery Manual §14.7, rev. May 2018).

The NTP is a separate step from the award. Cobb County School District awarded its $36,711,400 Eastvalley Elementary replacement on March 25, 2022 and issued the NTP 7 days later, on April 1, 2022, the same day the Owner/Contractor Agreement was fully signed (Cobb County NTP letter). Three similar-sounding notices do different jobs:

DocumentWho issues itWhat it doesSource
Notice of awardOwnerTells the low or best bidder it won; starts the window to sign the contract and deliver bonds (10 days after receipt of the forms on federal jobs)FAR 52.228-1(d)
Notice to proceedOwner or contracting officerAuthorizes work under a signed contract; can set the date of commencement that starts the Contract TimeA101-2017 §3.1; FAR 52.211-10
Limited notice to proceedOwnerAuthorizes only named early work, such as design, permits or long-lead orders, up to a dollar capDC DGS letter contract template
Notice of commencement (Florida)Owner, recorded with the countyA lien-law filing under Florida Statutes §713.13; it does not authorize work or start contract timeFla. Stat. §713.13

The Florida filing is a different instrument with its own deadlines, covered in our guide to the Florida notice of commencement.

How does a notice to proceed start contract time?

Under AIA documents the NTP starts the clock only if the agreement says so. A201-2017 §8.1.2 states that “the date of commencement of the Work is the date established in the Agreement,” and A101-2017 §3.2 measures the Contract Time from that date. The owner chooses the trigger by checking one of 3 boxes in A101 §3.1.

If the §3.1 box for “a date set forth in a notice to proceed” is not checked and no other rule is written in, the printed fallback makes the Agreement date the date of commencement (A101-2017 §3.1). That means days can run while permits or bonds are still pending. Our AIA A101 guide walks through every blank in Articles 3 to 7.

Federal contracts work the same way with different words. FAR 52.211-10 requires the contractor to “commence work under this contract within” a number of calendar days “after the date the Contractor receives the notice to proceed,” and to finish by a stated date or number of days. Under Alternate I, when the completion date is a fixed calendar date, it moves one day for each day the NTP arrives late, unless the delay came from the contractor’s failure to sign or deliver its performance and payment bonds (FAR 11.404(b)).

Screenshot of FAR 52.211-10 with the start-within-calendar-days-after-the-notice-to-proceed sentence boxed
FAR 52.211-10 (Apr 1984): the contractor must commence work within a set number of calendar days after it receives the notice to proceed. Source: Acquisition.gov, accessed 2026-11-09.

Worked example: what a late NTP does to the completion date

Take an A101 job with “Not later than 300 calendar days from the date of commencement” in §3.3.1 and a $3,000 daily liquidated damages rate, the rate Cobb County used. The arithmetic below counts calendar days per A201 §8.1.4, so weekends and holidays count.

ScenarioDate of commencementContract TimeSubstantial Completion dueEffect
A: §3.1 NTP box checked, NTP dated Monday, Feb 1, 2027Feb 1, 2027300 calendar daysNov 28, 2027Baseline
B: same box, permit slips and NTP is dated Feb 22, 2027Feb 22, 2027300 calendar daysDec 19, 2027Deadline moves 21 days with the NTP; no claim needed
C: no box checked, Agreement signed Monday, Jan 4, 2027, work starts Feb 1Jan 4, 2027 (printed fallback)300 calendar daysOct 31, 2027Contractor loses 28 days; finishing on the Scenario A date would expose it to 28 x $3,000 = $84,000 unless it wins a time extension

Scenario C is the case for checking the §3.1 NTP box on any job where the permit, bonds or financing are not in hand when the Agreement is signed. Every date in the table falls on the same weekday because 300 days is 42 weeks and 6 days. The construction schedule the contractor submits under A201 §3.10.1 must show the date of commencement as its first milestone.

What must be in place before an owner issues an NTP?

Most owners issue the NTP only after 5 things are confirmed: a fully signed agreement, delivered bonds, insurance certificates, the owner’s own property insurance and the permit. Wisconsin DOT’s manual says an NTP “should never be issued by the region before the execution of a contract” (WisDOT CMM 2-22 §222.1, Oct 2026), and Los Angeles issues it only after its Risk Manager approves bonds and insurance.

PrerequisiteRuleSource
Agreement signed by both partiesNo NTP before contract executionWisDOT CMM §222.1
Performance and payment bondsFederal: 100% of the original contract price each, delivered before starting work; required above $150,000FAR 52.228-15(b), (c); FAR 28.102-1(a)
Contractor insurance certificatesDelivered “prior to commencement of the Work”; contractor may not knowingly start before insurance is effectiveA101 Exhibit A §A.3.1.1; A201 §8.2.2
Owner’s builder’s risk policyOwner secures it and gives evidence before commencement, unless shifted to the contractorA101 Exhibit A §A.2.1, §A.2.3.1
Building permitContractor secures and pays for it unless the contract says otherwiseA201 §3.7.1
Owner financing evidenceOn written request, the contractor need not start until the owner shows it can pay; Contract Time extendsA201 §2.2.1
Purchase order and pre-work documentsNo work “on the site, off the site” before bonds, certificate of insurance and a purchase orderNM PSFA form 00 5501
Preconstruction conferenceFederal: attendance required if the contracting officer calls one; UC schedules it in the NTP letterFAR 52.236-26; UC NTP form

The bond side of this list is covered in our guides to the bid bond, which secures the promise to sign and bond, and the performance bond, which must be in the owner’s hands before the NTP and on federal jobs equals 100% of the original contract price. The builder’s risk start date matters too: the University of California’s builder’s risk program starts coverage “on the Notice to Proceed date for the construction phase” (UC builder’s risk FAQ), and our builder’s risk insurance guide covers who buys it.

Decision flow: full notice to proceed, limited notice to proceed, or wait Five checks in order: agreement signed, bonds delivered, insurance certificates and owner property insurance in place, building permit issued, site access and financing evidence. If all are yes, issue a full notice to proceed. If the agreement is not signed, do not issue one. If bonds, insurance, permit or site are missing but long-lead orders or design must start, issue a limited notice to proceed with a named scope and a dollar cap; otherwise wait. Before you issue a notice to proceed: five checks 1. Agreement signed by both parties? WisDOT CMM 222.1: never issue before execution 2. Performance and payment bonds delivered? FAR 52.228-15(c): before starting work 3. Insurance certificates and builder’s risk in place? A201 §8.2.2; A101 Exhibit A §A.2.1, §A.3.1.1 4. Building permit issued? A201 §3.7.1: contractor secures it unless shifted 5. Site access and financing evidence ready? A201 §2.2.1: contractor may refuse to start without it All yes: issue a full notice to proceed State the commencement date and the Contract Time No: do not issue any NTP Sign the agreement first No on 2 to 5: wait, or issue a limited NTP only for named early work: design, permits, long-lead orders, with a dollar cap DC DGS letter NTP: $950,000 cap PCC early work: $480,220 for long-lead materials YesYesYesYesYes NoNo
Five checks before an NTP: signed agreement, bonds, insurance, permit, site and financing; any gap points to waiting or a capped limited NTP. Sources: WisDOT CMM 222.1, FAR 52.228-15(c), AIA A201-2017, accessed 2026-11-09.

What is the difference between a limited NTP and a full NTP?

A limited notice to proceed (LNTP) authorizes only named early work, with a dollar cap, before the full price is settled. A full NTP authorizes all the contract work and usually starts the Contract Time. The DC Department of General Services template caps one at $950,000. Owners use limited notices on design-build and construction manager at risk jobs where design, permits or long-lead orders must start before the guaranteed maximum price (GMP) is signed.

PointLimited NTPFull NTPSource
ScopeNamed tasks only, such as design advance, permits, long-lead materialsAll work in the contract documentsDC DGS template ¶2
PriceNot-to-exceed cap; DC DGS template: $950,000Contract Sum or GMPDC DGS template ¶4
Real examplePortland Community College early work amendment: $480,220 for long-lead materials, board authorized $528,242 with 10% contingency (July 16, 2020)Followed once the GMP was approvedPCC Board resolution 21-007
End pointMerges into the final contract or ends on a stated dateRuns to Substantial CompletionDC DGS template ¶1, ¶6
Contract TimeStarts only if the contract says so: write it in A101 §3.1 “Established as follows”Starts on the stated date of commencementA101-2017 §3.1

The cap is the owner’s main protection. Paragraph 4 of the DC Department of General Services template says the design-builder is not “entitled to receive more than this amount” without advance written approval from a Contracting Officer, and the letter terminates when the definitized contract is signed. Our comparison of design-build vs design-bid-build explains why early packages are more common on design-build jobs.

Dollar limits on two public early-work authorizationsBar chart: DC DGS cap $950,000; PCC early work $480,220; PCC authorization $528,242$DC DGS letter contract NTP cap (template)950,000PCC early work amendment (proposal)480,220PCC board authorization incl. 10% continge528,242
Limited notices carry hard caps: $950,000 in the DC DGS template and $528,242 authorized for PCC’s 2020 early work. Sources: DC DGS Attachment N; PCC resolution 21-007, accessed 2026-11-09.

What goes in a notice to proceed letter?

A notice to proceed letter is usually 1 page with 10 elements: who, which project, which contract, the start date, the Contract Time, the completion date, the delay rate, the documents still owed, the meeting and a signature block. The public forms below were compared line by line, and the table lists each element with the form that uses it.

ElementExample wording or valueForm that uses it
Date of the notice“Date of Notice to Proceed”NMSU form, rev. Apr 2020
Contractor, project name, project and contract numbersProject title, RFP number, project numberCobb County NTP
Contract amount“Amount of Contract: $36,711,400.00”Cobb County NTP
Reference to the signed agreement“Pursuant to your Construction Contract dated …”City of Saint Paul form
Date of commencement or start window“commence work … within ten (10) calendar days of the above date”NM PSFA form 00 5501
Contract Time and completion date“Substantial Completion [#] calendar days thereafter, which shall be [Date]”NM PSFA form 00 5501
Liquidated damages$3,000 per consecutive calendar dayCobb County NTP
Documents still owedBonds, certificate of insurance, purchase order before any workNM PSFA form 00 5501
Preconstruction conferenceLocation, date and timeUC NTP form
Owner contact and contractor acknowledgment“Please acknowledge acceptance of this notice … and mail back one copy”City of Saint Paul form

Sample notice to proceed text

The sample below combines the elements above for a private A101 job where §3.1 ties commencement to the NTP. Replace every bracket; the 10-day start window and calendar-day count follow the public forms cited. Send it by a method the contract’s notice clause accepts, because FAR 52.211-10 counts from the day the contractor receives it.

[Owner letterhead] [Date of this notice]

To: [Contractor legal name, address]. Re: [Project name], [Project number], Agreement dated [date] (AIA A101-2017), Contract Sum $[amount].

This letter is the Notice to Proceed under §3.1 of the Agreement. The date of commencement of the Work is [date]. Under §3.3.1, Substantial Completion is due not later than [number] calendar days from that date, which is [date], subject to adjustments under the Contract Documents. Liquidated damages of $[amount] per calendar day apply under §4.5.

We have received your performance and payment bonds and the certificates of insurance required by Exhibit A §A.3.1.1. The building permit [number] was issued on [date]. A preconstruction meeting will be held at [location] on [date and time].

Owner’s representative: [name, phone, email]. Please sign below to acknowledge receipt and return one copy within [number] days.

[Owner signature, title] Received by Contractor: [signature, title, date]

How many days do public agencies allow after an NTP?

The window between the NTP and the required start is short. Across the public forms reviewed, 10 calendar days is the most common figure, Saint Paul uses 7 working days, and Los Angeles issues the NTP 5 to 15 days after its Risk Manager approves the insurance. Completion periods are set project by project, from 45 days for a roof to 395 days for a school.

Agency or formStart rule after the NTPCompletion ruleSource
New Mexico State UniversityCommence within 10 days of the NTP dateBlank number of consecutive calendar days from the NTP dateNMSU form, rev. Apr 2020
New Mexico PSFA (school districts)Within 10 calendar daysSubstantial Completion a stated number of calendar days laterForm 00 5501, Nov 2025
Wisconsin DOTContract starting date is the start of operations or the 10th calendar day after notice, whichever is earlierWorking day, calendar day or completion date contractsCMM §222.1
City of Saint Paul, MNBe prepared to begin within 7 working days of receiptCompletion date written into the noticeSaint Paul NTP form
City of Los Angeles, Bureau of EngineeringNTP usually issued 5 to 15 days after Risk Management approves insurance; NTP date is day 1Contract period set in the bid packageProject Delivery Manual §14.7
Washington County, MD roof replacement (2022)Not stated in the agenda reportSubstantially complete within 45 consecutive calendar days of the NTP; complete within 150 days; $250 per day liquidated damagesAgenda report PUR-1557
Cobb County School District, GA (2022)Commencement on the NTP date, April 1, 2022Substantial Completion: tennis courts January 3, 2023 (277 days), school May 1, 2023 (395 days); final July 3, 2023 (458 days); $3,000 per dayCobb County NTP letter
Federal fixed-price constructionContracting Officer fills in the number of calendar daysDays after NTP receipt or a calendar date; liquidated damages per calendar day under FAR 52.211-12FAR 52.211-10; FAR 52.211-12
Notice to proceed timeline: award to final completion Top: the generic sequence from contract award, bonds and insurance, notice to proceed and date of commencement, contract time, substantial completion and final completion. Bottom: Cobb County School District Eastvalley Elementary dates: award March 25, 2022; commencement April 1, 2022 (7 days later); substantial completion May 1, 2023 (395 days); final completion July 3, 2023 (63 days); liquidated damages 3,000 dollars per day. From award to notice to proceed to substantial completion (not to scale) 1. Award Owner accepts bid or signs agreement (A101 date) 2. Bonds and insurance FAR: bonds within 10 days of forms 3. Notice to proceed Sets the date of commencement 4. Contract Time runs in calendar days (A201 §8.1.1, §8.1.4) 5. Substantial completion Clock stops; LDs stop accruing Start window after the NTP: 10 calendar days (NMSU, NM PSFA, WisDOT), 7 working days (St. Paul), blank in FAR 52.211-10 Real example: Cobb County School District, Eastvalley Elementary replacement ($36,711,400) Mar 25, 2022 Contract awarded Apr 1, 2022 Agreement signed, NTP, date of commencement 7 days 395 calendar days May 1, 2023 Substantial completion 63 days Jul 3, 2023 Final completion Liquidated damages: $3,000 per consecutive calendar day after each stipulated date (substantial and final). Source: Cobb County School District notice to proceed dated April 1, 2022; FAR 52.228-1(d); A201-2017 Art. 8.
Cobb County’s Eastvalley Elementary NTP came 7 days after award and set 395 days to substantial completion, with $3,000 per day liquidated damages. Source: Cobb County School District NTP, April 1, 2022, accessed 2026-11-09.
Calendar days from the notice to proceed to each completion milestoneBar chart: 45 and 150 days for the Washington County roof; 277, 395 and 458 days for Cobb County milestonescalendar daysWashington County, MD roof: substantial co45.0Washington County, MD roof: completion150Cobb County tennis courts: substantial com277Cobb County school: substantial completion395Cobb County school: final completion458
Contract time counted from the NTP ran from 45 days (roof, substantial) to 458 days (school, final). Sources: Washington County PUR-1557 and Cobb County NTP, accessed 2026-11-09.

The Contract Time ends at Substantial Completion, not final completion, under A201 §8.1.1; the certification steps are in our guide to substantial completion.

What are the risks of starting work without a notice to proceed?

Work done before the NTP is usually at the contractor’s cost and risk. Los Angeles (Project Delivery Manual §14.7) states that “any work undertaken by the Contractor before issuance of the NTP is done so at the Contractor’s own risk,” and New Mexico PSFA bars any work or expense before bonds, insurance and a purchase order are in place. The owner carries risk too, mainly lost days and uninsured work.

  1. No payment: New Mexico PSFA will not accept an invoice dated before the purchase order or before the schedule of values is approved (form 00 5501).
  2. No insurance: A201 §8.2.2 bars the contractor from knowingly starting before the required insurance is effective, unless the owner instructs it in writing (A201-2017). Federal jobs on a government installation require written notice that insurance is in place before work starts (FAR 52.228-5(b)).
  3. No bond: on federal jobs, bonds are due “before starting work,” and work done without them can support default termination under FAR 52.228-1(d) if forms are not returned within 10 days.
  4. Lost days for the contractor: if A101 §3.1 is left unchecked, the clock runs from the Agreement date even while the site is closed (Scenario C above).
  5. No time relief for contractor-caused delay: FAR 52.211-10 Alternate I extends the completion date for a late NTP except when the delay came from the contractor’s failure to sign or deliver bonds.

This is general information about standard forms and public examples, not legal advice; ask a construction attorney licensed in the project’s state to review your agreement’s §3.1 choice and any early-work letter before work begins.

Should you issue a full NTP, a limited NTP, or wait?

Use the decision table when the agreement is signed but one item is still open. The thresholds come from the A201 and FAR clauses cited above; a limited NTP is the tool when early orders cannot wait, and the full NTP waits for bonds, insurance and the permit.

IfThenRule
Agreement not yet signed by both partiesIssue nothing; use a signed letter contract with a cap if work must startWisDOT §222.1; DC DGS template
Signed, bonds and insurance in, permit pending, long-lead equipment neededLimited NTP for submittals and orders, named scope, not-to-exceed amountPCC resolution 21-007
Signed, everything in hand except site accessWait, or issue the NTP with a later commencement date statedA101 §3.1
Federal contract over $150,000, bonds not deliveredNo NTP; bonds are due before workFAR 52.228-15(c)
Contractor requests financing evidence in writingProvide it before the commencement date or expect a time extensionA201 §2.2.1
All 5 checks clearFull NTP with the date of commencement, Contract Time and completion dateNM PSFA form

Once work starts, money moves through the lender process in our construction draw schedule guide, and public jobs add the weekly reports in our certified payroll guide.

How we compiled this

We read the AIA A101-2017, A101 Exhibit A and A201-2017 texts as posted by public owners, 10 FAR provisions on Acquisition.gov, 2 agency manuals (Wisconsin DOT, City of Los Angeles) and 8 public notice to proceed forms, letters and board items from 7 public owners, all accessed in November 2026. We excluded vendor templates and blog guidance, and we did not count federal rules as binding on private owners.

Frequently asked questions

Is a notice to proceed the same as a notice of award?

No. A notice of award tells the bidder it won and starts the clock to sign the contract and deliver bonds, which is 10 days after receipt of the forms under FAR 52.228-1(d). The notice to proceed comes after that and authorizes work. Cobb County awarded its Eastvalley Elementary job on March 25, 2022 and issued the NTP on April 1, 2022.

Is a notice to proceed legally required?

Only if the contract calls for one. AIA A101-2017 §3.1 lets the parties tie the date of commencement to a notice to proceed; if no box is checked, the Agreement date is the date of commencement and no NTP is needed to start the clock. Federal fixed-price construction contracts use FAR 52.211-10, which counts the start window from receipt of the NTP.

Who signs the notice to proceed?

The owner or its authorized representative signs it. In Los Angeles, the Executive Officer of the Board of Public Works issues it after the Risk Manager approves bonds and insurance. New Mexico PSFA forms carry signatures from both the school district and the PSFA, and the Saint Paul form asks the contractor to countersign and return one copy.

Can a contractor refuse to start after receiving an NTP?

Under A201-2017 §2.2.1, a contractor that asks in writing for reasonable evidence of the owner’s financing has no obligation to start until it is provided, and the Contract Time is extended. A201 §8.2.2 also bars knowingly starting before the required insurance is effective, unless the owner instructs otherwise in writing.

What happens if the owner delays the notice to proceed?

If the contract counts time from the NTP, the completion date moves with it. FAR 52.211-10 Alternate I extends a fixed completion date one calendar day for each day the NTP arrives after the assumed date, unless the contractor caused the delay by not signing or not delivering bonds. Long owner delays can also support a price claim under the contract’s changes clause.

Does builder's risk insurance start on the notice to proceed date?

It often does. The University of California’s program states that builder’s risk coverage begins on the Notice to Proceed date for the construction phase. Under AIA A101-2017 Exhibit A §A.2.1, the owner must secure its property insurance and show evidence before commencement of the Work, so the policy should be bound before the NTP date.

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.