A notice to proceed (NTP) is the owner’s written order telling the contractor to start work: under AIA A101-2017 §3.1 it can fix the date of commencement, and the Contract Time is counted from that date.
Key takeaways
- AIA A101-2017 §3.1 offers 3 boxes for the date of commencement: the Agreement date, “a date set forth in a notice to proceed issued by the Owner,” or a custom rule; if none is checked, the Agreement date governs (A101-2017, Oakton Community College copy).
- A201-2017 §8.1.1 measures the Contract Time to Substantial Completion, and §8.1.4 makes every “day” a calendar day unless the contract says otherwise (A201-2017 sample).
- Federal fixed-price construction contracts use FAR 52.211-10 (Apr 1984): the contractor must start within a set number of calendar days after it receives the notice to proceed.
- Federal bonds must reach the Contracting Officer “in any event, before starting work” under FAR 52.228-15(c), and the Miller Act requires them on construction contracts over $150,000 (FAR 28.102-1).
- Public owners commonly allow 10 calendar days from the NTP to start work: New Mexico State University, the New Mexico Public School Facilities Authority and Wisconsin DOT all use 10 (NM PSFA form 00 5501, rev. Nov 2025).
What is a notice to proceed in construction?
A notice to proceed is a short letter from the owner, or the owner’s contracting officer, that authorizes the contractor to begin the work in a signed contract and names the day the schedule starts. Los Angeles’s Bureau of Engineering puts it plainly: “The NTP date is the first day of the contract period” (LA Project Delivery Manual §14.7, rev. May 2018).
The NTP is a separate step from the award. Cobb County School District awarded its $36,711,400 Eastvalley Elementary replacement on March 25, 2022 and issued the NTP 7 days later, on April 1, 2022, the same day the Owner/Contractor Agreement was fully signed (Cobb County NTP letter). Three similar-sounding notices do different jobs:
| Document | Who issues it | What it does | Source |
|---|---|---|---|
| Notice of award | Owner | Tells the low or best bidder it won; starts the window to sign the contract and deliver bonds (10 days after receipt of the forms on federal jobs) | FAR 52.228-1(d) |
| Notice to proceed | Owner or contracting officer | Authorizes work under a signed contract; can set the date of commencement that starts the Contract Time | A101-2017 §3.1; FAR 52.211-10 |
| Limited notice to proceed | Owner | Authorizes only named early work, such as design, permits or long-lead orders, up to a dollar cap | DC DGS letter contract template |
| Notice of commencement (Florida) | Owner, recorded with the county | A lien-law filing under Florida Statutes §713.13; it does not authorize work or start contract time | Fla. Stat. §713.13 |
The Florida filing is a different instrument with its own deadlines, covered in our guide to the Florida notice of commencement.
How does a notice to proceed start contract time?
Under AIA documents the NTP starts the clock only if the agreement says so. A201-2017 §8.1.2 states that “the date of commencement of the Work is the date established in the Agreement,” and A101-2017 §3.2 measures the Contract Time from that date. The owner chooses the trigger by checking one of 3 boxes in A101 §3.1.
If the §3.1 box for “a date set forth in a notice to proceed” is not checked and no other rule is written in, the printed fallback makes the Agreement date the date of commencement (A101-2017 §3.1). That means days can run while permits or bonds are still pending. Our AIA A101 guide walks through every blank in Articles 3 to 7.
Federal contracts work the same way with different words. FAR 52.211-10 requires the contractor to “commence work under this contract within” a number of calendar days “after the date the Contractor receives the notice to proceed,” and to finish by a stated date or number of days. Under Alternate I, when the completion date is a fixed calendar date, it moves one day for each day the NTP arrives late, unless the delay came from the contractor’s failure to sign or deliver its performance and payment bonds (FAR 11.404(b)).

Worked example: what a late NTP does to the completion date
Take an A101 job with “Not later than 300 calendar days from the date of commencement” in §3.3.1 and a $3,000 daily liquidated damages rate, the rate Cobb County used. The arithmetic below counts calendar days per A201 §8.1.4, so weekends and holidays count.
| Scenario | Date of commencement | Contract Time | Substantial Completion due | Effect |
|---|---|---|---|---|
| A: §3.1 NTP box checked, NTP dated Monday, Feb 1, 2027 | Feb 1, 2027 | 300 calendar days | Nov 28, 2027 | Baseline |
| B: same box, permit slips and NTP is dated Feb 22, 2027 | Feb 22, 2027 | 300 calendar days | Dec 19, 2027 | Deadline moves 21 days with the NTP; no claim needed |
| C: no box checked, Agreement signed Monday, Jan 4, 2027, work starts Feb 1 | Jan 4, 2027 (printed fallback) | 300 calendar days | Oct 31, 2027 | Contractor loses 28 days; finishing on the Scenario A date would expose it to 28 x $3,000 = $84,000 unless it wins a time extension |
Scenario C is the case for checking the §3.1 NTP box on any job where the permit, bonds or financing are not in hand when the Agreement is signed. Every date in the table falls on the same weekday because 300 days is 42 weeks and 6 days. The construction schedule the contractor submits under A201 §3.10.1 must show the date of commencement as its first milestone.
What must be in place before an owner issues an NTP?
Most owners issue the NTP only after 5 things are confirmed: a fully signed agreement, delivered bonds, insurance certificates, the owner’s own property insurance and the permit. Wisconsin DOT’s manual says an NTP “should never be issued by the region before the execution of a contract” (WisDOT CMM 2-22 §222.1, Oct 2026), and Los Angeles issues it only after its Risk Manager approves bonds and insurance.
| Prerequisite | Rule | Source |
|---|---|---|
| Agreement signed by both parties | No NTP before contract execution | WisDOT CMM §222.1 |
| Performance and payment bonds | Federal: 100% of the original contract price each, delivered before starting work; required above $150,000 | FAR 52.228-15(b), (c); FAR 28.102-1(a) |
| Contractor insurance certificates | Delivered “prior to commencement of the Work”; contractor may not knowingly start before insurance is effective | A101 Exhibit A §A.3.1.1; A201 §8.2.2 |
| Owner’s builder’s risk policy | Owner secures it and gives evidence before commencement, unless shifted to the contractor | A101 Exhibit A §A.2.1, §A.2.3.1 |
| Building permit | Contractor secures and pays for it unless the contract says otherwise | A201 §3.7.1 |
| Owner financing evidence | On written request, the contractor need not start until the owner shows it can pay; Contract Time extends | A201 §2.2.1 |
| Purchase order and pre-work documents | No work “on the site, off the site” before bonds, certificate of insurance and a purchase order | NM PSFA form 00 5501 |
| Preconstruction conference | Federal: attendance required if the contracting officer calls one; UC schedules it in the NTP letter | FAR 52.236-26; UC NTP form |
The bond side of this list is covered in our guides to the bid bond, which secures the promise to sign and bond, and the performance bond, which must be in the owner’s hands before the NTP and on federal jobs equals 100% of the original contract price. The builder’s risk start date matters too: the University of California’s builder’s risk program starts coverage “on the Notice to Proceed date for the construction phase” (UC builder’s risk FAQ), and our builder’s risk insurance guide covers who buys it.
What is the difference between a limited NTP and a full NTP?
A limited notice to proceed (LNTP) authorizes only named early work, with a dollar cap, before the full price is settled. A full NTP authorizes all the contract work and usually starts the Contract Time. The DC Department of General Services template caps one at $950,000. Owners use limited notices on design-build and construction manager at risk jobs where design, permits or long-lead orders must start before the guaranteed maximum price (GMP) is signed.
| Point | Limited NTP | Full NTP | Source |
|---|---|---|---|
| Scope | Named tasks only, such as design advance, permits, long-lead materials | All work in the contract documents | DC DGS template ¶2 |
| Price | Not-to-exceed cap; DC DGS template: $950,000 | Contract Sum or GMP | DC DGS template ¶4 |
| Real example | Portland Community College early work amendment: $480,220 for long-lead materials, board authorized $528,242 with 10% contingency (July 16, 2020) | Followed once the GMP was approved | PCC Board resolution 21-007 |
| End point | Merges into the final contract or ends on a stated date | Runs to Substantial Completion | DC DGS template ¶1, ¶6 |
| Contract Time | Starts only if the contract says so: write it in A101 §3.1 “Established as follows” | Starts on the stated date of commencement | A101-2017 §3.1 |
The cap is the owner’s main protection. Paragraph 4 of the DC Department of General Services template says the design-builder is not “entitled to receive more than this amount” without advance written approval from a Contracting Officer, and the letter terminates when the definitized contract is signed. Our comparison of design-build vs design-bid-build explains why early packages are more common on design-build jobs.
What goes in a notice to proceed letter?
A notice to proceed letter is usually 1 page with 10 elements: who, which project, which contract, the start date, the Contract Time, the completion date, the delay rate, the documents still owed, the meeting and a signature block. The public forms below were compared line by line, and the table lists each element with the form that uses it.
| Element | Example wording or value | Form that uses it |
|---|---|---|
| Date of the notice | “Date of Notice to Proceed” | NMSU form, rev. Apr 2020 |
| Contractor, project name, project and contract numbers | Project title, RFP number, project number | Cobb County NTP |
| Contract amount | “Amount of Contract: $36,711,400.00” | Cobb County NTP |
| Reference to the signed agreement | “Pursuant to your Construction Contract dated …” | City of Saint Paul form |
| Date of commencement or start window | “commence work … within ten (10) calendar days of the above date” | NM PSFA form 00 5501 |
| Contract Time and completion date | “Substantial Completion [#] calendar days thereafter, which shall be [Date]” | NM PSFA form 00 5501 |
| Liquidated damages | $3,000 per consecutive calendar day | Cobb County NTP |
| Documents still owed | Bonds, certificate of insurance, purchase order before any work | NM PSFA form 00 5501 |
| Preconstruction conference | Location, date and time | UC NTP form |
| Owner contact and contractor acknowledgment | “Please acknowledge acceptance of this notice … and mail back one copy” | City of Saint Paul form |
Sample notice to proceed text
The sample below combines the elements above for a private A101 job where §3.1 ties commencement to the NTP. Replace every bracket; the 10-day start window and calendar-day count follow the public forms cited. Send it by a method the contract’s notice clause accepts, because FAR 52.211-10 counts from the day the contractor receives it.
[Owner letterhead] [Date of this notice]
To: [Contractor legal name, address]. Re: [Project name], [Project number], Agreement dated [date] (AIA A101-2017), Contract Sum $[amount].
This letter is the Notice to Proceed under §3.1 of the Agreement. The date of commencement of the Work is [date]. Under §3.3.1, Substantial Completion is due not later than [number] calendar days from that date, which is [date], subject to adjustments under the Contract Documents. Liquidated damages of $[amount] per calendar day apply under §4.5.
We have received your performance and payment bonds and the certificates of insurance required by Exhibit A §A.3.1.1. The building permit [number] was issued on [date]. A preconstruction meeting will be held at [location] on [date and time].
Owner’s representative: [name, phone, email]. Please sign below to acknowledge receipt and return one copy within [number] days.
[Owner signature, title] Received by Contractor: [signature, title, date]
How many days do public agencies allow after an NTP?
The window between the NTP and the required start is short. Across the public forms reviewed, 10 calendar days is the most common figure, Saint Paul uses 7 working days, and Los Angeles issues the NTP 5 to 15 days after its Risk Manager approves the insurance. Completion periods are set project by project, from 45 days for a roof to 395 days for a school.
| Agency or form | Start rule after the NTP | Completion rule | Source |
|---|---|---|---|
| New Mexico State University | Commence within 10 days of the NTP date | Blank number of consecutive calendar days from the NTP date | NMSU form, rev. Apr 2020 |
| New Mexico PSFA (school districts) | Within 10 calendar days | Substantial Completion a stated number of calendar days later | Form 00 5501, Nov 2025 |
| Wisconsin DOT | Contract starting date is the start of operations or the 10th calendar day after notice, whichever is earlier | Working day, calendar day or completion date contracts | CMM §222.1 |
| City of Saint Paul, MN | Be prepared to begin within 7 working days of receipt | Completion date written into the notice | Saint Paul NTP form |
| City of Los Angeles, Bureau of Engineering | NTP usually issued 5 to 15 days after Risk Management approves insurance; NTP date is day 1 | Contract period set in the bid package | Project Delivery Manual §14.7 |
| Washington County, MD roof replacement (2022) | Not stated in the agenda report | Substantially complete within 45 consecutive calendar days of the NTP; complete within 150 days; $250 per day liquidated damages | Agenda report PUR-1557 |
| Cobb County School District, GA (2022) | Commencement on the NTP date, April 1, 2022 | Substantial Completion: tennis courts January 3, 2023 (277 days), school May 1, 2023 (395 days); final July 3, 2023 (458 days); $3,000 per day | Cobb County NTP letter |
| Federal fixed-price construction | Contracting Officer fills in the number of calendar days | Days after NTP receipt or a calendar date; liquidated damages per calendar day under FAR 52.211-12 | FAR 52.211-10; FAR 52.211-12 |
The Contract Time ends at Substantial Completion, not final completion, under A201 §8.1.1; the certification steps are in our guide to substantial completion.
What are the risks of starting work without a notice to proceed?
Work done before the NTP is usually at the contractor’s cost and risk. Los Angeles (Project Delivery Manual §14.7) states that “any work undertaken by the Contractor before issuance of the NTP is done so at the Contractor’s own risk,” and New Mexico PSFA bars any work or expense before bonds, insurance and a purchase order are in place. The owner carries risk too, mainly lost days and uninsured work.
- No payment: New Mexico PSFA will not accept an invoice dated before the purchase order or before the schedule of values is approved (form 00 5501).
- No insurance: A201 §8.2.2 bars the contractor from knowingly starting before the required insurance is effective, unless the owner instructs it in writing (A201-2017). Federal jobs on a government installation require written notice that insurance is in place before work starts (FAR 52.228-5(b)).
- No bond: on federal jobs, bonds are due “before starting work,” and work done without them can support default termination under FAR 52.228-1(d) if forms are not returned within 10 days.
- Lost days for the contractor: if A101 §3.1 is left unchecked, the clock runs from the Agreement date even while the site is closed (Scenario C above).
- No time relief for contractor-caused delay: FAR 52.211-10 Alternate I extends the completion date for a late NTP except when the delay came from the contractor’s failure to sign or deliver bonds.
This is general information about standard forms and public examples, not legal advice; ask a construction attorney licensed in the project’s state to review your agreement’s §3.1 choice and any early-work letter before work begins.
Should you issue a full NTP, a limited NTP, or wait?
Use the decision table when the agreement is signed but one item is still open. The thresholds come from the A201 and FAR clauses cited above; a limited NTP is the tool when early orders cannot wait, and the full NTP waits for bonds, insurance and the permit.
| If | Then | Rule |
|---|---|---|
| Agreement not yet signed by both parties | Issue nothing; use a signed letter contract with a cap if work must start | WisDOT §222.1; DC DGS template |
| Signed, bonds and insurance in, permit pending, long-lead equipment needed | Limited NTP for submittals and orders, named scope, not-to-exceed amount | PCC resolution 21-007 |
| Signed, everything in hand except site access | Wait, or issue the NTP with a later commencement date stated | A101 §3.1 |
| Federal contract over $150,000, bonds not delivered | No NTP; bonds are due before work | FAR 52.228-15(c) |
| Contractor requests financing evidence in writing | Provide it before the commencement date or expect a time extension | A201 §2.2.1 |
| All 5 checks clear | Full NTP with the date of commencement, Contract Time and completion date | NM PSFA form |
Once work starts, money moves through the lender process in our construction draw schedule guide, and public jobs add the weekly reports in our certified payroll guide.
How we compiled this
We read the AIA A101-2017, A101 Exhibit A and A201-2017 texts as posted by public owners, 10 FAR provisions on Acquisition.gov, 2 agency manuals (Wisconsin DOT, City of Los Angeles) and 8 public notice to proceed forms, letters and board items from 7 public owners, all accessed in November 2026. We excluded vendor templates and blog guidance, and we did not count federal rules as binding on private owners.
Frequently asked questions
Is a notice to proceed the same as a notice of award?
No. A notice of award tells the bidder it won and starts the clock to sign the contract and deliver bonds, which is 10 days after receipt of the forms under FAR 52.228-1(d). The notice to proceed comes after that and authorizes work. Cobb County awarded its Eastvalley Elementary job on March 25, 2022 and issued the NTP on April 1, 2022.
Is a notice to proceed legally required?
Only if the contract calls for one. AIA A101-2017 §3.1 lets the parties tie the date of commencement to a notice to proceed; if no box is checked, the Agreement date is the date of commencement and no NTP is needed to start the clock. Federal fixed-price construction contracts use FAR 52.211-10, which counts the start window from receipt of the NTP.
Who signs the notice to proceed?
The owner or its authorized representative signs it. In Los Angeles, the Executive Officer of the Board of Public Works issues it after the Risk Manager approves bonds and insurance. New Mexico PSFA forms carry signatures from both the school district and the PSFA, and the Saint Paul form asks the contractor to countersign and return one copy.
Can a contractor refuse to start after receiving an NTP?
Under A201-2017 §2.2.1, a contractor that asks in writing for reasonable evidence of the owner’s financing has no obligation to start until it is provided, and the Contract Time is extended. A201 §8.2.2 also bars knowingly starting before the required insurance is effective, unless the owner instructs otherwise in writing.
What happens if the owner delays the notice to proceed?
If the contract counts time from the NTP, the completion date moves with it. FAR 52.211-10 Alternate I extends a fixed completion date one calendar day for each day the NTP arrives after the assumed date, unless the contractor caused the delay by not signing or not delivering bonds. Long owner delays can also support a price claim under the contract’s changes clause.
Does builder's risk insurance start on the notice to proceed date?
It often does. The University of California’s program states that builder’s risk coverage begins on the Notice to Proceed date for the construction phase. Under AIA A101-2017 Exhibit A §A.2.1, the owner must secure its property insurance and show evidence before commencement of the Work, so the policy should be bound before the NTP date.
Sources
- AIA A101-2017 Standard Form of Agreement (Oakton Community College copy), accessed 2026-11-09
- AIA A201-2017 General Conditions (University of Maine System sample), accessed 2026-11-09
- AIA A101-2017 Exhibit A, Insurance and Bonds (Sauk County, WI copy), accessed 2026-11-09
- FAR 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984), accessed 2026-11-09
- FAR 11.404 Contract clauses, accessed 2026-11-09
- FAR 52.211-12 Liquidated Damages, Construction (Sept 2000), accessed 2026-11-09
- FAR 52.228-15 Performance and Payment Bonds, Construction (Jun 2020), accessed 2026-11-09
- FAR 52.228-1 Bid Guarantee (Sept 1996), accessed 2026-11-09
- FAR 28.102-1 General (Miller Act threshold), accessed 2026-11-09
- FAR 52.228-5 Insurance, Work on a Government Installation (Jan 1997), accessed 2026-11-09
- FAR 52.236-26 Preconstruction Conference (Feb 1995), accessed 2026-11-09
- Wisconsin DOT Construction and Materials Manual, Section 222 Notice to Proceed, accessed 2026-11-09
- City of Los Angeles Bureau of Engineering Project Delivery Manual §14.7, accessed 2026-11-09
- University of California Facilities Manual, Notice to Proceed form, accessed 2026-11-09
- University of California, Builder’s Risk FAQs, accessed 2026-11-09
- New Mexico State University Notice to Proceed form, accessed 2026-11-09
- New Mexico PSFA form 00 5501 Notice to Proceed (Nov 2025), accessed 2026-11-09
- City of Saint Paul Notice to Proceed form, accessed 2026-11-09
- Cobb County School District, Notice to Proceed, Eastvalley Elementary (Apr 1, 2022), accessed 2026-11-09
- Washington County, MD Agenda Report PUR-1557 (Aug 2022), accessed 2026-11-09
- DC Department of General Services, Notice to Proceed and Letter Contract template, accessed 2026-11-09
- Florida Statutes §713.13 Notice of commencement, accessed 2026-11-09
- Portland Community College Board resolution 21-007 (Jul 16, 2020), accessed 2026-11-09