Skip to content

Performance Bond: How Claims Work, What It Costs and When It Is Required

Partly built steel-frame commercial building with an idle crane and closed site trailer at dusk

A performance bond is a surety’s promise to the project owner that the contractor will finish the contract; if the contractor defaults, the surety completes the work or pays, up to the bond amount, usually 100% of the contract price.

Key takeaways

What is a performance bond and who are the three parties?

A performance bond is a three-party contract. The contractor (the principal) and the surety bind themselves jointly to the owner (the obligee) for the construction contract, and the bond stays void as long as the contractor performs. Federal jobs use Standard Form 25 (Rev. 10/2023); private and many public jobs use AIA A312-2010. The penal sum, the most the surety can owe, is usually 100% of the contract price.

PartyWho it isName on SF 25Name on A312-2010What it does
PrincipalThe contractorPrincipalContractorPerforms the work; signs the bond and, usually, an indemnity agreement with the surety
SuretyAn insurance companySurety(ies), each with a Liability Limit ($)SuretyCompletes or pays on default, up to the penal sum; federal sureties must be on Treasury Circular 570
ObligeeThe project ownerThe United States (the Government)OwnerDeclares the default and claims on the bond; under A312-2010 Section 9 only the owner has a right of action

A performance bond is credit extended to the contractor, not insurance for it. A 2005 Surety Information Office brochure says the surety prequalifies the contractor and may require personal or corporate indemnity, so a surety that pays an owner then looks to the contractor and its owners to repay it. For federal bonds, corporate sureties must appear on Treasury Circular 570, which listed 249 companies effective August 1, 2026.

On federal work, the SF 25 conditions make the obligation void if the principal performs every contract term during the original term, any extensions and the life of any guaranty the contract requires, and performs all authorized modifications, with notice of modifications to the surety waived.

SF 25 page 1 obligation and conditions, with the clause voiding the bond if the principal performs boxed
Standard Form 25 (Rev. 10/2023), page 1: the obligation is void if the principal performs all contract terms during the original term, extensions and any guaranty period. Source: GSA, accessed 2026-11-02.

This page summarizes statutes, regulations, forms and bid records checked by November 2, 2026. It is not legal, bonding or insurance advice: the bond attached to your contract controls, and a construction attorney or surety agent can apply it to your job. Bid security, including the 20% federal bid guarantee, is covered in our bid bond guide.

How does a performance bond claim work?

Under AIA A312-2010 the owner must take three steps before the surety owes anything: give notice that it is considering a default (Section 3.1), declare the default and terminate the contract (Section 3.2), and agree to pay the unpaid contract balance to the surety or a replacement contractor (Section 3.3). The surety must then promptly choose one of the Section 5 options.

  1. Notice (Section 3.1): the owner writes to the contractor and the surety, at the addresses on the signature page (Section 12), that it is considering declaring a Contractor Default, and says whether it wants a conference.
  2. Conference: if the owner does not ask for one, the surety may ask within 5 business days of receiving the notice; unless the owner agrees otherwise, the conference is held within 10 business days of that receipt. The three parties may agree to give the contractor a reasonable time to perform.
  3. Default and termination (Section 3.2): a Contractor Default is a failure to comply with a material term that has not been remedied or waived (Section 14.3). The owner declares it, terminates the contract and notifies the surety.
  4. Contract balance (Section 3.3): the owner agrees to pay the Balance of the Contract Price, the total payable less proper payments already made (Section 14.1), to the surety or the completing contractor.
  5. Surety’s election (Section 5): promptly and at its own expense, the surety takes one of the five actions in the table below.
  6. Follow-up notice (Section 6): if the surety does not proceed with reasonable promptness, it is deemed in default 7 days after a further written notice from the owner.
  7. Lawsuit (Section 11): filed where the work is located, within 2 years after the default declaration, after the contractor stopped working, or after the surety refused or failed to perform, whichever comes first.
SectionWhat the surety doesWhat the owner getsLiability cap (Section 8)
5.1Arranges for the original contractor to finish, with the owner’s consentThe original contractor completes the workBond amount
5.2Performs and completes the contract itself, through agents or independent contractorsCompleted work; the surety’s duties are no greater than the contractor’s (Section 7)Not listed in Section 8
5.3Obtains bids from qualified contractors acceptable to the owner, arranges a new contract backed by equivalent bonds, and pays damages above the contract balanceA new bonded contract the owner signs, plus the excess costBond amount
5.4.1Waives its right to complete, investigates, and pays what it determines it owesA cash payment; if the owner refuses it, the owner may sue (Section 6)Bond amount
5.4.2Denies liability in whole or in part, citing reasonsThe right to sue without further notice (Section 6)Not applicable
How a performance bond claim works under AIA A312-2010 Flowchart: owner notice under Section 3.1, optional conference within 10 business days, owner declares default and terminates under Section 3.2, agrees to pay the balance under Section 3.3, then the surety picks one of five Section 5 actions; Section 6 sets a 7 day surety default and Section 11 a 2 year suit limit from the earliest trigger date. Step 1, Section 3.1: owner notifies contractor and surety that it is considering declaring a Contractor Default Optional conference Surety may ask within 5 business days; held within 10 business days Step 2, Section 3.2: owner declares default, terminates the contract and notifies the surety Step 3, Section 3.3: owner agrees to pay the Balance of the Contract Price to the surety or its contractor Section 5: the surety must promptly take one action 5.1 Original contractor finishes, with owner consent 5.2 Surety takes over and completes the work itself 5.3 Tender: new bonded contractor, surety pays the excess 5.4.1 Investigate, then pay the owner what it owes 5.4.2 Deny liability in whole or part, with reasons Section 6: no prompt action means the surety is in default 7 days after a further written notice from the owner Section 11: sue within 2 years of the earliest trigger date
Under AIA A312-2010 the surety acts only after the owner’s Section 3 steps; it then picks one Section 5 option, is in default 7 days after a further notice if idle, and suit is due within 2 years. Source: A312-2010, accessed 2026-11-02.

Section 4 softens only the first step: a late Section 3.1 notice releases the surety only if it shows actual prejudice, and the form gives no such relief for Sections 3.2 and 3.3. Once the surety completes, Section 7 makes it answer for defective work, completion, added legal, design and delay costs, and liquidated damages; Section 8 caps it at the bond amount under 5.1, 5.3 and 5.4, but not 5.2.

Performance bond vs payment bond: what is the difference?

The performance bond protects the owner if the work is not finished; the payment bond protects the subcontractors, laborers and suppliers who are not paid. On federal jobs both are required above $150,000, each equals 100% of the original contract price under FAR 28.102-2, and the payment bond can never be smaller than the performance bond (40 U.S.C. 3131(b)(2)).

ItemPerformance bondPayment bondSource
ProtectsThe owner, against failure to performAll persons supplying labor and material40 U.S.C. 3131(b)
Who can claimThe owner only (A312-2010 Section 9)Anyone with a direct contract with the contractor or a subcontractor (A312-2010 Payment Bond Section 16.2)AIA A312-2010
Federal amount100% of the original contract price, plus 100% of increasesSame; never less than the performance bondFAR 28.102-2(b)
Federal formSF 25 (Rev. 10/2023)SF 25A (Rev. 10/2023)GSA forms pages
First formal stepSection 3.1 notice, then a declared defaultClaim to the surety; without a direct contract with the contractor, a notice of nonpayment within 90 days firstA312-2010 Payment Bond Section 5
Surety’s response timePromptly; deemed in default 7 days after a further noticeWritten answer within 60 days of the claim, and payment of undisputed amountsA312-2010 Performance Bond Section 6; Payment Bond Section 7
Deadline to sue2 years (Section 11)1 year (Section 12; 40 U.S.C. 3133(b)(4))40 U.S.C. 3133

The A312-2010 payment bond also protects the owner directly. Once the owner promptly notifies the contractor and surety of a claim, lien or suit by an unpaid supplier and tenders its defense, the surety must defend and indemnify the owner (Sections 3 and 4). If the surety misses the 60-day answer in Section 7.1, Section 7.3 makes it pay the claimant’s reasonable attorney’s fees from then on.

What are the payment bond claim deadlines?

Deadlines run from the claimant’s last day of work or delivery, and they differ by bond and state. On federal jobs a supplier or sub-subcontractor with no contract with the prime has 90 days to give written notice and 1 year to sue; Florida adds a notice within 45 days of starting work. The table lists the federal rule, the A312-2010 form and two state statutes.

Bond or statuteNoticeDeadline to sueSource
Federal payment bond (Miller Act)Claimant with a direct contract with a subcontractor only: written notice to the prime within 90 days of last labor or material. Others may sue once unpaid 90 days after last work1 year after last labor or material, in U.S. district court40 U.S.C. 3133(b)
AIA A312-2010 Payment BondNo direct contract with the contractor: notice of nonpayment to the contractor within 90 days, then a claim to the surety1 year from the claim or from the last work by anyone on the contract, whichever is firstSections 5.1, 12
Florida public workNot in privity with the contractor: notice within 45 days of starting; notice of nonpayment no later than 90 days after final furnishing1 year after the labor or final deliveryFla. Stat. 255.05
Florida private job with a lien-exempting bondSame 45-day and 90-day notices1 yearFla. Stat. 713.23
Virginia public workClaimant with a direct contract with a subcontractor only: written notice within 90 days by registered or certified mail1 year after last labor or materialVa. Code 2.2-4341
AIA A312-2010 Performance Bond (owner)Section 3.1 notice; conference within 10 business days if requested2 years from the earliest Section 11 triggerSections 3.1, 11
Performance bond and payment bond claim deadlines Two timelines. AIA A312-2010 performance bond: conference request within 5 business days, conference within 10 business days, surety in default 7 days after further notice, suit within 2 years. Federal Miller Act payment bond: suit allowed after 90 days unpaid, second-tier notice due by day 90, suit deadline 1 year after last work. Performance bond, AIA A312-2010 (owner’s claim) Notice Section 3.1 5 business days surety may ask for a conference 10 business days conference held unless owner agrees 7 days after further notice, idle surety in default (s.6) 2 years suit deadline (Section 11) Payment bond, federal Miller Act, 40 U.S.C. 3133 (supplier or sub’s claim) Day 0 last labor or material supplied Day 90 second-tier claimant’s written notice to the prime is due; unpaid claimants may sue after it 1 year suit deadline in U.S. district court Sources: AIA A312-2010 Performance Bond s.3.1, s.6, s.11; 40 U.S.C. 3133(b)(1), (b)(2), (b)(4). Not to scale.
Performance bond claims under A312-2010 run on business days and a 2 year limit; federal payment bond claims run 90 days for notice and 1 year to sue. Sources: AIA A312-2010; 40 U.S.C. 3133, accessed 2026-11-02.

A federal payment bond waiver is void unless written, signed and executed after the claimant furnished the work (40 U.S.C. 3133(c)); Virginia uses the same test (2.2-4341(D)). How waivers travel with progress payments is covered in our lien waiver guide. Without a payment bond, unpaid trades file liens instead, as compared in our mechanics lien laws by state report.

When is a performance bond required?

A performance bond is required by statute on most public construction and by contract on private jobs. Federally, FAR 28.102-1 requires performance and payment bonds on construction contracts exceeding $150,000, and from $35,000 to $150,000 the contracting officer picks two or more payment protections instead. States set their own thresholds in statutes often called Little Miller Acts.

The Miller Act itself, 40 U.S.C. 3131(b), still says bonds are due before award of any federal construction contract of more than $100,000. The $150,000 trigger is the figure the FAR applies as amended through FAC 2026-01, effective March 13, 2026. The statute leaves the performance bond amount to the contracting officer; FAR 28.102-2(b)(1) sets it at 100% of the original contract price unless the officer decides a lesser amount is adequate. Under FAR 52.228-15, the contractor delivers both bonds before starting work.

40 U.S.C. 3131(b) on the Cornell LII site with the more than $100,000 threshold sentence boxed
The Miller Act text, 40 U.S.C. 3131(b), still sets the bond trigger at contracts of more than $100,000; FAR 28.102-1 applies $150,000. Source: Legal Information Institute, accessed 2026-11-02.
JurisdictionPerformance bond required abovePayment bond required aboveSource (accessed)
Federal, statute text$100,000$100,00040 U.S.C. 3131 (2026-11-02)
Federal, as applied$150,000$150,000; two or more payment protections from $35,000 to $150,000FAR 28.102-1 (2026-11-02)
Virginia$500,000 nontransportation; $350,000 state-funded transportationSameVa. Code 2.2-4337 (2026-11-02)
Florida$100,000 on state contracts; local owners may exempt $200,000 or lessSame; one recorded payment and performance bondFla. Stat. 255.05 (2026-11-02)
Texas$100,000$25,000; $50,000 for municipalitiesGov. Code 2253.021 (2026-11-02)
Michigan$50,000$50,000MCL 129.201 (2026-10-18)
North Carolina$50,000 per contract on projects over $300,000SameG.S. 44A-26 (2026-10-18)
CaliforniaNot set by this section$25,000Civil Code 9550 (2026-10-18)
WashingtonNo dollar floor; 10% retainage option at $150,000 or lessSameRCW 39.08.010 (2026-10-18)
Virginia requires bonds above $500,000; Michigan and North Carolina above $50,000Bar chart: performance bond thresholds of $500,000 in Virginia, $150,000 federal, $100,000 in Florida and Texas, $50,000 in Michigan and North Carolina.$ thousandsVirginia, nontransportation500Virginia, state-funded transportation350Federal, FAR 28.102-1150Federal, statute text (40 U.S.C. 3131)100Florida, state contracts100Texas100Michigan50.0North Carolina (projects over $300,000)50.0
Public performance bond thresholds run from $50,000 (Michigan, North Carolina) to $500,000 (Virginia nontransportation); federal work uses $150,000. Sources: statutes and FAR 28.102-1, accessed 2026-10-18 and 2026-11-02.

Bond amounts follow the contract, not just the threshold. Virginia sets each bond at the sum of the contract amount, and on federal jobs FAR 28.102-2 adds 100% of any price increase. The full 10-state threshold table, including New York, Georgia and Ohio, is in our construction surety bond statistics. Where federal construction dollars land by state is mapped in our federal construction contracts by state report.

Do private projects need a performance bond?

On private work no statute read for this page requires a performance bond; the owner’s contract, the lender or the general contractor’s subcontract decides, usually naming the form. Florida gives private owners a reason to require a payment bond: under Fla. Stat. 713.23, a bond of at least the original contract price, attached to the recorded notice of commencement, exempts the owner from liens.

On construction manager at risk jobs the bond can be a priced line inside the guaranteed maximum price (GMP): Henderson County, North Carolina’s 2018 school GMP carried it at 0.80%. How GMP contracts are built is explained in our construction manager at risk guide.

How much does a performance bond cost?

Public records put the combined performance and payment bond premium at 0.10% to 1.77% of the bid on 10 priced bid lines from 2014 to 2018, and at 0.80% on a 2018 school GMP. Published ranges run higher: 0.5% to 3% of the contract amount (Surety Information Office, 2005) and 1.5% to 3.0% (CRS R42037, July 2025). The public records price both bonds as one line.

Public recordDateBid or GMPBond lineRateSource
Transbay Joint Powers Authority (TJPA), structural concrete, bidder 1Feb 11, 2014$48,174,750$289,0490.60%TJPA TG07.2 tab
TJPA, structural concrete, bidder 2Feb 11, 2014$78,741,515$787,4151.00%TJPA TG07.2 tab
TJPA, fireproofing, bidder 1Sep 18, 2014$8,594,839$64,4610.75%TJPA TG16.8 tab
TJPA, fireproofing, bidder 2Sep 18, 2014$8,908,096$8,9080.10%TJPA TG16.8 tab
TJPA, fireproofing, bidder 3Sep 18, 2014$7,253,160$87,0381.20%TJPA TG16.8 tab
TJPA, miscellaneous metalsJan 22, 2015$11,528,241$115,2821.00%TJPA TG07.3 tab
Henderson County, NC, Edneyville Elementary GMP (CM at risk)Apr 4, 2018$21,852,605$174,8210.80%Board packet
City of Longview, TX, street striping, low bidJul 25, 2018$68,224.72$1,0081.48%Bid 1718-25 tab
Longview, second bidJul 25, 2018$70,846.51$7051.00%Bid 1718-25 tab
Longview, third bidJul 25, 2018$107,936.96$1,0000.93%Bid 1718-25 tab
Longview, fourth bidJul 25, 2018$169,290.48$3,0001.77%Bid 1718-25 tab

TJPA asked bidders for their bond rate and computed a potential cost; Longview priced the bond as a bid item; Henderson County’s GMP listed 0.80% beside 1.25% ($235,933) for subcontractor bonds. Longview and Henderson rates are our arithmetic.

Bonds were priced at 0.10% to 1.77% of the bid on public recordsBar chart: bond rates from 1.77% on a $169,290 Longview bid down to 0.10% on an $8.91 million TJPA bid, with a 0.80% school GMP.% of bid or GMPLongview TX striping, $169,290 bid (2018)1.77Longview TX striping, $68,225 low bid (2011.48TJPA fireproofing, $7.25M bid (2014)1.2TJPA concrete, $78.7M bid (2014)1TJPA metals, $11.5M bid (2015)1Longview TX striping, $70,847 bid (2018)1Longview TX striping, $107,937 bid (2018)0.93Henderson Co. NC school GMP, $21.9M (2018)0.8TJPA fireproofing, $8.59M bid (2014)0.75TJPA concrete, $48.2M bid (2014)0.6TJPA fireproofing, $8.91M bid (2014)0.1
On 10 public bid lines and one GMP from 2014 to 2018, combined performance and payment bonds cost 0.10% to 1.77% of the price; the small Longview bids sat at the high end. Sources: TJPA, City of Longview, Henderson County, accessed 2026-11-02.

Two patterns show in these records. Size: the four Longview bids under $170,000 averaged 1.30%, against 0.78% for the six TJPA bids above $7 million (our arithmetic on a small sample). Contractor: on the same TJPA fireproofing package, bidders stated 0.10%, 0.75% and 1.20%, consistent with the Surety Information Office’s note that premiums depend on the size, type and duration of the project and on the contractor.

Rates are regulated, not negotiated freely. Under 13 CFR 115.32(a), a surety on an SBA-guaranteed bond may not charge more than the rate the state insurance department authorizes, and losses are a small share of premium: the Surety & Fidelity Association of America put the 2024 direct loss ratio for all surety lines at 23.5% (preliminary).

What does a bond cost on a $5 million contract?

On a $5,000,000 contract, the public-record rates above imply $30,000 to $50,000 for both bonds, and the top of the published range implies $150,000. If SBA guarantees the bonds, the contractor adds a $30,000 fee, and a $500,000 change order adds $5,000 of premium at 1.00% plus $3,000 of SBA fee. Every line below shows its rate and source.

LineRateAmountSource
Premium at the TJPA low bid’s rate0.60%$30,000TJPA TG07.2, 2014
Premium at 1.00%1.00%$50,000TJPA TG07.3, 2015
Premium at the top of the published range3.0%$150,000CRS R42037, 2025; SIO, 2005
SBA contractor fee, if SBA guarantees the bonds0.6% of contract price$30,000SBA; 13 CFR 115.32(b)
SBA fee the surety pays, at a 1.00% premium20% of premium$10,000CRS R42037
$500,000 change order: added bond amount100% of the increase$500,000FAR 28.102-2(b)
Added premium on the change order1.00%$5,000SIO, 2005 (premium adjusts with contract amount)
Added SBA contractor fee on the change order0.6%$3,00013 CFR 115.32(d)

The contractor pays the premium when the bond is executed but prices it into the bid, so the owner pays through the contract sum. On an SBA-guaranteed job, a $500,000 change also hits the 13 CFR 115.32(d) reporting trigger of 25% or $500,000, whichever is less. How bonding capacity limits which jobs a contractor can chase is covered in how to win commercial construction bids.

Which standard forms do owners use?

Federal agencies use Standard Form 25 for the performance bond and Standard Form 25A for the payment bond, both at revision 10/2023 and prescribed by FAR 53.228. Private owners and many public owners use AIA A312-2010, one document holding a Performance Bond and a separate Payment Bond. Florida public bonds must also list the contractor, surety, owner, contract number and bond number on the front page (Fla. Stat. 255.05(1)(a)).

FormPublisher and editionUsed onTerms that matter in a claim
SF 25, Performance BondGSA, Rev. 10/2023, FAR 53.228(b)Federal constructionVoid if the principal performs through the term, extensions and guaranty; notice of modifications waived
SF 25A, Payment BondGSA, Rev. 10/2023, FAR 53.228(c)Federal constructionProtects persons supplying labor and material; Miller Act notice and suit rules apply
A312-2010, Performance BondAIA, 2010 editionPrivate and many public jobsSection 3 conditions; Section 5 options; Section 10 waives notice of changes; Section 11 two-year limit
A312-2010, Payment BondAIA, 2010 editionPrivate and many public jobsSection 5.1 90-day notice; Section 7.1 60-day answer; Section 12 one-year limit
Florida statutory bondFla. Stat. 255.05Florida public buildings and worksRecorded in the county public records; certified copy to the owner before work starts

The AIA form flags when its author has revised the printed text, so read the copy attached to the contract. When a bond meets a statute, A312-2010 Section 13 deletes conflicting terms and reads in the statutory ones. Where A312 sits among the other AIA forms is explained in our AIA contract documents guide.

What do several guides get wrong about performance bonds?

Four claims in top-ranking pages do not match the primary sources: the Miller Act threshold, two premium ranges and who a payment bond protects. Each is stated neutrally below, with the source that settles it. One more, a widely repeated share of bond claims that are payment bond claims, had no primary source we could find, so it is left out of this page.

What a ranking page saysWhat the primary source saysSource
The Miller Act applies to federal construction contracts over $150,000 (an encyclopedia entry, read November 2026)The statute still reads more than $100,000; $150,000 is the threshold FAR 28.102-1(a) applies today40 U.S.C. 3131(b); FAR 28.102-1
Premiums run 1% to 15% of the bond amount (the same entry, marked citation needed)Public bid records priced both bonds at 0.10% to 1.77% of the bid (2014 to 2018); the highest published range found is 0.5% to 3%Cost table above; SIO, 2005
Premiums run 0.5% to 3% (several surety seller pages, no source given)That range traces to a 2005 industry brochure; the latest government source, CRS R42037 (July 2025), cites 1.5% to 3.0% from a 2007 SBA noticeSIO, 2005; CRS R42037
A payment bond protects the property owner (a payment bond guide updated 2025)By statute it protects all persons supplying labor and material; the A312-2010 payment bond adds a duty to defend and indemnify the owner against their claims (Sections 3, 4)40 U.S.C. 3131(b)(2); AIA A312-2010

Which bond rule applies to your project?

Start with who the owner is and the contract value, then the role you hold on the job. The table pairs common situations with the rule and its threshold or deadline. Where no statute applies, the bond clause in the contract and the form it names decide, so read that clause before relying on any row.

IfThenRule
Federal construction contract over $150,000Furnish SF 25 and SF 25A, each 100% of the original contract price, before starting workFAR 28.102-1; 52.228-15
Federal contract over $35,000 up to $150,000Expect two or more payment protections, such as a payment bond or irrevocable letter of credit; furnish oneFAR 28.102-1(b)
Virginia nontransportation public contract over $500,000Both bonds in the sum of the contract amountVa. Code 2.2-4337
Florida state public work over $100,000 (local: may be exempt at $200,000 or less)Record one payment and performance bond before work; give the owner a certified copyFla. Stat. 255.05
Texas public workPerformance bond over $100,000; payment bond over $25,000, or $50,000 for a cityGov. Code 2253.021
Florida private owner who wants lien protectionRequire a payment bond of at least the contract price, attached to the notice of commencementFla. Stat. 713.23
Owner with a failing contractor on an A312 bondSend the Section 3.1 notice, hold the conference within 10 business days if asked, declare default and terminate, commit the contract balanceAIA A312-2010 Sections 3, 12
Surety has not acted after the defaultSend a further written demand; the surety is in default 7 days after receiptA312-2010 Section 6
Unpaid sub-subcontractor or supplier on a federal jobWritten notice to the prime within 90 days of last work; sue within 1 year40 U.S.C. 3133(b)
Contract price rises on a federal jobBond protection rises by 100% of the increaseFAR 28.102-2(b)
Small contractor that cannot get bonded on standard termsAsk a surety about SBA’s guarantee: contracts up to $9 million ($14 million federal), 0.6% feeSBA

Bonds protect against a contractor failing to finish; injury and property damage claims fall to the policies covered in our general liability insurance for contractors guide.

How we compiled this

We read 29 primary documents: federal statutes, regulations and forms, the AIA A312-2010 text, SBA rules, a CRS report, nine state statutes, four bid tabulations, a county GMP and two industry documents, most on November 2, 2026 and six on October 18. Seller-site premium figures and an unsourced claim-share statistic were left out. Rates for Longview and Henderson County, averages and the worked example are our arithmetic, under our editorial standards.

Frequently asked questions

Who pays for a performance bond?

The contractor buys the bond and pays the premium, generally when the bond is executed, and builds the cost into its price, per a 2005 Surety Information Office brochure. The owner pays it indirectly: Henderson County, North Carolina’s 2018 school GMP carried a 0.80% payment and performance bond line of $174,821. If SBA guarantees the bond, the contractor also pays SBA 0.6% of the contract price.

How much is a performance bond on a $1 million contract?

At the 0.60% to 1.20% rates most bidders stated on Transbay Joint Powers Authority bid forms in 2014 and 2015, about $6,000 to $12,000 for the performance and payment bonds together. At the 1.5% to 3.0% range the Congressional Research Service cited in July 2025, $15,000 to $30,000. Add $6,000 if SBA guarantees the bonds, at its 0.6% fee.

Is a performance bond the same as insurance?

No. Insurance pays the insured’s own losses; a performance bond is a guarantee to the owner, and the surety expects the contractor to repay what it pays out. The Surety Information Office describes the premium as mainly a fee for prequalifying the contractor and notes that sureties may require personal or corporate indemnity. Federal sureties must be on Treasury Circular 570, which listed 249 companies on August 1, 2026.

How long does a performance bond last?

Standard Form 25 binds the surety through the original contract term, any extensions and the life of any guaranty the contract requires, which can reach into the warranty period. Under AIA A312-2010 Section 11, the owner must sue within 2 years after declaring a default, after the contractor stopped working or after the surety failed to perform, whichever comes first, unless local law sets a different minimum.

Can a subcontractor make a claim on a performance bond?

Generally no. AIA A312-2010 Section 9 gives a right of action on the performance bond only to the owner and its successors. Unpaid subcontractors and suppliers claim on the payment bond instead: on federal jobs, those without a contract with the prime contractor must give written notice within 90 days of their last work and sue within 1 year under 40 U.S.C. 3133.

What happens to the bond when the contract price changes?

On federal jobs the bond grows with the contract: FAR 28.102-2 requires added protection equal to 100% of any price increase. AIA A312-2010 Section 10 has the surety waive notice of changes, including time changes. Premiums adjust to the new contract amount, per the Surety Information Office, and on SBA-guaranteed bonds the surety reports increases of 25% or $500,000, whichever is less.

Can a small contractor get a performance bond?

Yes, through the regular surety market or with SBA backing. The SBA Surety Bond Guarantee Program guarantees bid, performance and payment bonds on contracts up to $9 million, or $14 million on federal work, for firms that meet the surety’s credit, capacity and character standards. SBA covers 90% of a surety’s loss on contracts of $100,000 or less and 80% on most larger ones (CRS R42037, July 2025).

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.

← Back to all articles