Parking lot striping cost $2,736 to $7,547 for a 100-stall commercial lot in our worked estimate, about $27 to $75 per stall, from 2021 to 2025 public bids of $0.52 to $1.75 per foot of 4 in paint.
Key takeaways
- Four bidders on Clark County, Washington Quote #0358 (May 2023) priced 5,028 LF of standard parking lot paint striping at $0.52, $1.50, $2.00 and $4.10 per linear foot, before 8.5 percent sales tax.
- A 100-stall lot of 9 ft x 18 ft stalls at 90 degrees needs about 106 lines and 1,908 LF of 4 in line, or 19.08 LF per stall, by our count of the layout drawn below.
- An accessible car space added $269 to $608 in the same bids once the symbol, half an access aisle and an R7-8 sign on a post were priced; the University City, Missouri bid (January 2021) put signs at $155 to $630 each.
- At highway volumes, NCDOT contract PR17207 (February 2025) priced 4 in, 90 mil thermoplastic at a median $0.54 per LF against $0.145 for 4 in paint: about 3.7 times the price.
- Small jobs pay a premium: a 511 LF line item in Four Rivers, Illinois Bid 25-402 (June 2024) drew $4.00 to $10.00 per LF, while 1,360 LF in University City drew $0.31 to $0.72.
- Mobilization alone ran $425 to $2,500 in the Clark County quote; one 2025 park district proposer bid a flat $1,350 per lot.
How much does parking lot striping cost?
Parking lot striping cost $0.31 to $4.10 per linear foot of 4 in painted line in four public parking lot bids from 2021 to 2024, which works out to roughly $20 to $61 per stall for a restripe and $27 to $75 per stall once accessible signs, symbols and mobilization are added. Lot size and the number of bidders move the price most.
The table below collects the unit prices a commercial owner will see on a striping quote, each from a public bid tab or federal award with its date and quantity. None of these figures is escalated to 2026; the range across bidders on the same job is wider than any index change over these years.
| Item | Unit price in the bids | Quantity bid | Date and place | Source |
|---|---|---|---|---|
| 4 in white stall line, paint | $0.31 to $0.72 per LF (median $0.50, 9 bids) | 1,360 LF | January 2021, University City, MO | SC20-1193 bid tab |
| Standard striping, paint | $0.52 to $4.10 per LF (median $1.75, 4 bids) | 5,028 LF | May 2023, Clark County, WA | Quote #0358 |
| White reflectorized paint, 15 mils | $0.45 and $1.05 per LF (2 bids) | 13,500 LF | July 2023, Tioga County, NY | HHS lot bid tab |
| 4 in line, small lot | $4.00 to $10.00 per LF (3 bids) | 511 LF | June 2024, Four Rivers, IL | Bid 25-402 |
| Accessible symbol (ISA) | $25 to $78 each (2021); $70 to $975 each (2023) | 3 and 4 each | University City, MO; Clark County, WA | SC20-1193; Quote #0358 |
| Access aisle hatching | $0.98 to $8.45 per sq ft | 720 sq ft | May 2023, Clark County, WA | Quote #0358 |
| R7-8 accessible sign with post and base | $155 to $630 each (median $330) | 3 each | January 2021, University City, MO | SC20-1193 |
| Mobilization, striping-only job | $425 to $2,500 lump sum | 1 job | May 2023, Clark County, WA | Quote #0358 |
How much does striping cost per linear foot?
A 4 in painted stall line bid at $0.31 to $0.72 per linear foot on a 1,360 LF parking lot in University City in 2021 and $0.52 to $4.10 on a 5,028 LF lot in Clark County in 2023. Highway-scale paint is far cheaper, $0.10 to $0.18 per LF on 800,000 LF in North Carolina in 2025, because the truck runs for miles without stopping.
Quantity is the first lever. The same 4 in white line drew a $4.00 low bid on 511 LF in Four Rivers in June 2024, almost eight times the $0.52 low bid on 5,028 LF in Clark County. Crews price a short job to cover the trip, the striper setup and layout time, so the per-foot rate climbs as footage drops. Ask each bidder to state both the per-LF price and the total LF they measured, then check it against your own count.
| Job | Material | Footage bid | Low bid per LF | High bid per LF | Bidders | Source |
|---|---|---|---|---|---|---|
| NCDOT Division 2 markings contract, 2025 | Paint, 4 in | 800,000 LF | $0.10 | $0.18 | 4 | PR17207 item 18 |
| NCDOT Division 2 markings contract, 2025 | Thermoplastic, 4 in, 90 mils | 250,000 LF | $0.39 | $0.67 | 4 | PR17207 item 4 |
| Tioga County HHS parking lot, 2023 | Paint, 15 mils | 13,500 LF | $0.45 | $1.05 | 2 | Tioga bid tab |
| Clark County Klineline lot, 2023 | Paint | 5,028 LF | $0.52 | $4.10 | 4 | Quote #0358 |
| University City golf course lot, 2021 | Paint, 4 in white | 1,360 LF | $0.31 | $0.72 | 9 | SC20-1193 |
| Four Rivers administration lot, 2024 | 4 in line (material not stated) | 511 LF | $4.00 | $10.00 | 3 | Bid 25-402 |
What does it cost to stripe one parking stall?
One standard stall cost $20.94 to $61.27 to restripe in our 100-stall estimate built from 2023 Clark County unit prices, and $59.33 per space in a 2023 National Park Service award for 315 spaces. NCDOT’s 2025 contract carried a separate “parking lot stall” item bid at $40.00 to $150.00 each on 100 stalls.
A 9 ft x 18 ft stall at 90 degrees takes one 18 ft line per stall plus one closing line per row, so a row of 25 stalls needs 26 lines and 468 LF. At the Clark County low bid of $0.52 per LF that is $9.36 of paint per stall line; at the median $1.75 it is $31.50. Mobilization and symbols are what push the per-stall figure above the line cost on small lots.
| Award or bid | Scope stated | Price | Per stall | Source |
|---|---|---|---|---|
| National Park Service, Gateway (Jamaica Bay), NY, 2023 | Paint 305 standard 9 ft x 18 ft spaces, 10 accessible spaces, 5 accessible aisles; no demolition or grinding; 4 offers | $18,690 | $59.33 (315 spaces) | Award 140P4523P0032 |
| NCDOT Division 2, 2025 | “Parking lot stall”, 100 each, inside a statewide markings contract | $40.00 to $150.00 each (median $75.28) | $40.00 to $150.00 | PR17207 item 44 |
| Puget Sound VA Medical Center, WA, 2025 | Restripe 45 ADA parking stalls; 19 offers | $9,927.90 | $220.62 | Award 36C26025P0371 |
| VA, Tacoma WA area, 2020 to 2025 | Parking lot striping, 1,139 stalls, base year plus 4 option years; 3 offers | $181,965 over the term | $159.76 over 5 years | Award 36C26020P0725 |
| CB&C worked estimate, 100 stalls | Restripe lines, symbols, aisles, arrows, mobilization (no signs) | $2,093.56 to $6,126.50 | $20.94 to $61.27 | Clark County 2023 and NCDOT 2025 unit prices |
What does an accessible stall cost with the symbol and sign?
An accessible car space added $269.10 at the lowest bid prices and $607.88 at the median, priced as one International Symbol of Accessibility (ISA), half of a shared 5 ft x 18 ft access aisle (45 sq ft of hatching) and one R7-8 sign on a post with a concrete base. The sign is the largest item, which is why a $25 “handicap stall” price on a quote usually means paint only.
| Item | Low bid | Median bid | Source and date |
|---|---|---|---|
| Accessible symbol (ISA), paint | $70.00 | $135.00 | Clark County Quote #0358, May 2023 (4 bids) |
| Half of a shared aisle, 45 sq ft hatching | $44.10 ($0.98 per sq ft) | $142.88 ($3.175 per sq ft) | Clark County Quote #0358, May 2023 |
| R7-8 sign, post and concrete base | $155.00 | $330.00 | University City SC20-1193, January 2021 (9 bids) |
| Accessible car space, added cost | $269.10 | $607.88 | CB&C arithmetic |
| Van accessible plaque (R7-8P), add for 1 in 6 spaces | $22.23 | $100.00 | University City SC20-1193, January 2021 |
Sign height, symbol size and aisle width are set by the 2010 ADA Standards and by state law, not by the striper. Our guide to ADA sign rules covers mounting and the sign face, and the 2010 ADA Standards for Accessible Design set the van space at 132 in wide with a 60 in aisle (section 502.2).
Is thermoplastic worth paying for over paint?
Thermoplastic cost about 3.7 times as much as paint per linear foot in NCDOT’s February 2025 markings contract: a median $0.54 per LF for 4 in, 90 mil thermoplastic against $0.145 for 4 in paint, with the same four bidders on both lines. Thermoplastic goes down hot at 90 mils in the NCDOT contract, six times the 15 mil paint film Tioga County specified in 2023, and owners buy it to restripe less often.
We found no 2021 to 2026 public parking lot bid that priced thermoplastic stall lines next to paint, so the parking lot premium is an estimate. On our 1,908 LF example, applying NCDOT’s 3.72 ratio to the Clark County median of $1.75 per LF would put thermoplastic stall lines near $6.51 per LF, or about $12,420 for lines alone. That is a CB&C estimate, not a bid; ask bidders for both as alternates.
| Material, 4 in line | Thickness in the bid | Bids per LF | Median per LF | Symbol, each (median) | Source |
|---|---|---|---|---|---|
| Paint | Not stated in PR17207 (Tioga 2023 specified 15 mils) | $0.10 to $0.18 | $0.145 | $79.00 | NCDOT PR17207, February 2025 |
| Hot spray thermoplastic | 60 mils | $0.29 to $0.58 | $0.33 | n/a | NCDOT PR17207 item 31 |
| Thermoplastic | 90 mils | $0.39 to $0.67 | $0.54 | $125.00 | NCDOT PR17207 items 4 and 10 |
Does a new layout cost more than a restripe?
A new layout costs more because someone has to measure and mark every stall before painting, and a changed layout needs the old lines removed or blacked out. Ogden, Utah’s March 2024 striping contract priced layout at $80.00 per hour, and NCDOT’s 2025 contract priced 4 in line removal at $0.12 to $0.30 per LF.
| Adder | Bid price | On the 1,908 LF example | Source |
|---|---|---|---|
| Layout before painting | $80.00 per hour (40 hours bid) | Hours set by the crew; ask for the estimate | Ogden 2024 Citywide Striping |
| Remove old 4 in lines | $0.12 to $0.30 per LF | $228.96 to $572.40 | NCDOT PR17207 item 36, 2025 |
| Black out old lines with paint | $0.18 to $0.80 per LF | $343.44 to $1,526.40 | NCDOT PR17207 item 19, 2025 |
| Paint removal up to 1 ft wide | $1.23 per LF | $2,346.84 | Ogden 2024 Citywide Striping |
On fresh asphalt there is nothing to remove, but the layout must follow the approved site plan. Stall widths, aisle widths and angles come from local zoning (the 9 ft x 18 ft stall in our example is one common size, not a rule); our article on parking space dimensions lists the common module sizes, and a new lot is a good time to confirm them before paint goes down.
Is there a minimum charge for a small lot?
Yes, in practice: mobilization and setup make a small lot cost far more per stall. Clark County’s 2023 bidders priced mobilization at $425 to $2,500 before painting a single line, and in October 2025 one proposer to the Park District of Highland Park, Illinois bid a flat $1,350 for each of seven small park lots.
| Bid | What was priced | Price | Source |
|---|---|---|---|
| Clark County, WA, May 2023 | Mobilization, striping-only job | $425, $1,000, $1,720, $2,500 | Quote #0358 |
| Clark County, WA, May 2023 | Temporary traffic control | $1,500 to $5,000 | Quote #0358 |
| Park District of Highland Park, IL, October 2025 | Restripe one small park lot, per location | $935 to $6,200 (one proposer flat $1,350) | 2025 District Wide Striping tab |
| Ogden, UT, March 2024 | Parking lot striping by the hour | $80.00 per hour | Ogden 2024 Citywide Striping |
Bundling helps. If the lot is also being sealcoated or patched, striping under the same contract shares one mobilization: Missouri State University bid sealing and striping together at $0.25 and $0.33 per sq ft in May 2025. Our guide on how to compare construction bids shows how to line up unit prices from different bidders.
Worked estimate: what does a 100-stall lot cost to stripe?
A 100-stall lot with four accessible spaces cost $2,735.79 at the lowest bid prices and $7,546.50 at the median bid prices in our estimate, or $27.36 to $75.47 per stall. The count below assumes 9 ft x 18 ft stalls at 90 degrees in four rows, single 4 in lines, four arrows and one striping-only mobilization.
| Row | Stalls | Lines | Line length | Linear feet |
|---|---|---|---|---|
| Rows 1 to 3 | 25 standard each (75) | 26 each (78) | 18 ft | 1,404 |
| Row 4, standard group | 21 standard | 22 | 18 ft | 396 |
| Row 4, accessible group (car, aisle, car, car, aisle, van) | 4 accessible | 6 | 18 ft | 108 |
| Total | 100 | 106 | 1,908 LF (19.08 per stall) |
The number of accessible spaces comes from Table 208.2 of the 2010 ADA Standards: a lot of 76 to 100 spaces needs 4, and 1 in every 6 must be van accessible, so one van space. Our article on ADA parking requirements covers the full table and the van rules.
| Line item | Quantity | Low bid unit | Low total | Median unit | Median total | Unit price source |
|---|---|---|---|---|---|---|
| 4 in stall lines, paint | 1,908 LF | $0.52 | $992.16 | $1.75 | $3,339.00 | Clark County 2023 |
| Access aisle hatching | 180 sq ft | $0.98 | $176.40 | $3.175 | $571.50 | Clark County 2023 |
| Accessible symbols | 4 | $70.00 | $280.00 | $135.00 | $540.00 | Clark County 2023 |
| R7-8 signs with posts | 4 | $155.00 | $620.00 | $330.00 | $1,320.00 | University City 2021 |
| R7-8P van plaque | 1 | $22.23 | $22.23 | $100.00 | $100.00 | University City 2021 |
| Directional arrows, paint | 4 | $55.00 | $220.00 | $79.00 | $316.00 | NCDOT 2025 |
| Mobilization | 1 | $425.00 | $425.00 | $1,360.00 | $1,360.00 | Clark County 2023 |
| Total | $2,735.79 | $7,546.50 | ||||
| Per stall | 100 | $27.36 | $75.47 |
Leave out the five signs on a restripe where the posts stay, and the total falls to $2,093.56 to $6,126.50, or $20.94 to $61.27 per stall. Add 8.5 percent if your state taxes the work the way Washington did in the Clark County quote, and add traffic control ($1,500 to $5,000 there) if the lot stays open during striping.
Which striping option should you price?
Pick the scope from the condition of the pavement and whether the layout changes. A plain restripe on sound asphalt, at $0.31 to $4.10 per LF in the 2021 to 2024 lot bids, is the cheapest line on any bid; a new layout, a lot with faded accessible signs or a busy lot that must stay open adds layout, sign and traffic control items with their own prices.
| If | Then price | Cost signal from the bids |
|---|---|---|
| Lines are faded but the layout is right | Restripe in place, paint, unit price per LF with the LF stated | $0.31 to $4.10 per LF (2021 to 2024 lots) |
| Less than about 1,000 LF of line | A lump sum per lot, or bundle with sealcoat or patching | $935 to $6,200 per small lot (2025); $4.00 to $10.00 per LF on 511 LF (2024) |
| Stall count, width or angle will change | Layout hours plus removal or black-out of old lines | $80.00 per hour layout; $0.12 to $0.30 per LF removal |
| Accessible spaces are short of Table 208.2 | Symbols, aisle hatching, R7-8 signs and van plaque as separate items | $269.10 to $607.88 per accessible car space |
| Traffic wears paint out within a season | Thermoplastic as an alternate next to paint | About 3.7 times paint per LF at highway volume (2025) |
| Lot must stay open during work | Phasing and traffic control as a separate line | $1,500 to $5,000 (2023) |
Does restriping a lot trigger ADA parking rules?
It can. The Department of Justice says that when a business restripes its parking spaces it must provide accessible spaces as required by the 2010 ADA Standards, while the U.S. Access Board treats refreshing existing striping in place for a few spaces as maintenance. A full restripe is the cheapest moment to add missing accessible spaces.
The DOJ compliance brief on restriping parking spaces adds that restriping is “relatively inexpensive” and so readily achievable in most cases. The Access Board guide to ADA parking says resurfacing, resealing and adding spaces are alterations that must include the accessible spaces in the scoping table (Table 208.2). This is general information, not legal advice; for a lot near the threshold, ask your architect or attorney whether your project counts as an alteration. If the lot is being assessed for a purchase, a property condition assessment often flags missing accessible stalls.
Striping is usually bid with the pavement itself, so compare it against parking lot paving cost and the ADA parking requirements.
How we compiled this
We read nine public bid tabulations and three federal awards dated January 2021 to October 2025 (University City MO, Clark County WA, Missouri State University, Tioga County NY, Four Rivers IL, Ogden UT, Park District of Highland Park IL, NCDOT, and USAspending awards from the National Park Service and Department of Veterans Affairs), all opened in November 2026. Prices are as bid, not escalated. The 100-stall line count and every per-stall figure are CB&C arithmetic shown in the tables; the thermoplastic parking lot price is an estimate, labelled as such. We did not survey contractors.
Frequently asked questions
How much does it cost to stripe a 100 space parking lot?
In our worked estimate, a 100-stall lot with 1,908 LF of 4 in paint, four accessible spaces, four arrows and one mobilization cost $2,735.79 at the lowest 2021 to 2025 public bid prices and $7,546.50 at the median, or $27.36 to $75.47 per stall. Without new signs the range drops to $2,093.56 to $6,126.50.
How much does parking lot striping cost per linear foot?
Public parking lot bids priced 4 in painted line at $0.31 to $0.72 per LF on 1,360 LF in University City, Missouri (2021) and $0.52 to $4.10 on 5,028 LF in Clark County, Washington (2023). A 511 LF job in Four Rivers, Illinois drew $4.00 to $10.00 per LF in 2024.
How many linear feet of striping is in a parking stall?
A 9 ft x 18 ft stall at 90 degrees uses one 18 ft line plus a share of the closing line at the end of its row. A row of 25 stalls needs 26 lines, or 468 LF. Our 100-stall example needs 106 lines and 1,908 LF, which is 19.08 LF per stall.
How much does a handicap parking space cost to stripe?
Priced as a symbol, half of a shared 5 ft x 18 ft aisle and an R7-8 sign on a post, an accessible car space added $269.10 at the lowest bids and $607.88 at the median (Clark County 2023, University City 2021). A 2025 VA award restriped 45 ADA stalls for $9,927.90, or $220.62 each.
Is thermoplastic striping more expensive than paint?
Yes. In NCDOT’s February 2025 markings contract, 4 in, 90 mil thermoplastic bid at a median $0.54 per LF against $0.145 for 4 in paint from the same four bidders, about 3.7 times as much. Parking lot quantities cost more per foot for both materials, so ask for thermoplastic as a priced alternate.
Does restriping a parking lot require adding accessible spaces?
The DOJ restriping brief says a business that restripes must provide accessible spaces as required by the 2010 ADA Standards, while the U.S. Access Board treats refreshing a few spaces in place as maintenance. For 76 to 100 spaces, Table 208.2 requires 4 accessible spaces, one of them van accessible. This is not legal advice.
Sources
- University City, Missouri: Golf Course Parking Lot Resurfacing bid tab, SC20-1193 (January 12, 2021), accessed November 15, 2026
- Clark County, Washington: Limited Small Works Quote #0358, Klineline Parking Lot Striping Project (opened May 10, 2023), accessed November 15, 2026
- Tioga County, New York: HHS Building Parking Lot bid tabulation (July 14, 2023), accessed November 15, 2026
- NCDOT Division 2: PR17207 bid results, ID/IQ maintenance of pavement markings (opened February 26, 2025), accessed November 15, 2026
- Four Rivers, Illinois: Bid Doc. 25-402 bid tabulation (opened June 18, 2024), accessed November 15, 2026
- Ogden City, Utah: 2024 Citywide Striping bid tab (March 11, 2024), accessed November 15, 2026
- Park District of Highland Park, Illinois: 2025 District Wide Striping Project tabulation (October 9, 2025), accessed November 15, 2026
- Missouri State University: FY25 Parking Lot Maintenance bid tabulation, 250206-081 (May 13, 2025), accessed November 15, 2026
- USAspending.gov: award 140P4523P0032, Gateway Jamaica Bay parking lot striping (2023), accessed November 15, 2026
- USAspending.gov: award 36C26020P0725, VA parking lot striping, 1,139 stalls (2020 to 2025), accessed November 15, 2026
- USAspending.gov: award 36C26025P0371, Puget Sound VA ADA stall restriping (2025), accessed November 15, 2026
- U.S. Department of Justice: 2010 ADA Standards for Accessible Design, accessed November 2026
- U.S. Access Board: Guide to the ADA Standards, Chapter 5, Parking, accessed November 2026
- U.S. Department of Justice: ADA Compliance Brief, Restriping Parking Spaces (updated February 28, 2020), accessed November 2026