Parking lot paving cost runs about $4.20 to $5.50 per sq ft for new full-depth asphalt, $1.40 to $1.80 to mill and overlay, and $10.40 to $13.50 for 6-inch concrete, priced from 2023 to 2026 public bids.
Per stall at 344 sq ft of pavement each, that is about $1,450 to $1,900 for new asphalt, $480 to $610 for a mill and overlay and $3,580 to $4,640 for concrete, before curb, drainage and lighting.
Key takeaways
- A 2026 municipal bid in Park Forest, Illinois priced hot mix asphalt (HMA) at $75.50 to $99.00 per ton across six bidders (Village of Park Forest bid tabulation, March 4, 2026); at 110 lb per square yard per inch, that is $0.46 to $0.61 per sq ft for each inch of asphalt.
- One city standard for a parking lot is 1.5 inches of HMA surface and 2.5 inches of binder over 8 inches of aggregate base, and 10 inches of base for heavy duty (Crystal Lake, Illinois Section A-700).
- A real 13,300 square yard county parking lot was milled and overlaid with 1,700 tons of HMA for a low bid of $268,517 in July 2023, about $1.94 per sq ft after removing allowances and paint (Tioga County, New York bid tab).
- The Colorado DOT asphalt cement index rose from $490.93 per ton in February 2026 to $579.20 in October 2026, up 18 percent, which adds about $4.45 to every ton of mix at 5 percent binder (CDOT Asphalt Cement Cost Adjustment).
- Full-depth asphalt patching bid at $7.40 to $8.80 per sq ft at Missouri State University in 2025 and $7.90 in 2026 (FY25 and FY26 bid tabs), so a lot that needs patches on roughly half its area is cheaper to rebuild.
How much does parking lot paving cost per square foot in 2026?
New full-depth asphalt costs about $4.21 to $5.52 per sq ft for the pavement section alone, using 2024 to 2026 public unit prices for excavation, 8 inches of aggregate base and 4 inches of HMA. A mill and 2-inch overlay costs about $1.40 to $1.79 per sq ft, and 6-inch concrete on 4 inches of base about $10.39 to $13.50.
The per-stall figures assume 344 sq ft of pavement per space, the area our parking space dimensions guide worked out for a 120-space lot with 90-degree stalls, 63 ft modules and end aisles. Lots with angled stalls or long entry drives use more pavement per space, so price per square foot first and per stall second.
| Approach | Pavement section | $ per sq ft | $ per stall (344 sq ft) | Basis | Source |
|---|---|---|---|---|---|
| Mill and overlay | Mill, tack, 2 in HMA | $1.40 to $1.79 | $483 to $614 | CB&C estimate, 100-stall lot | Tioga County 2023, Park Forest 2026 |
| Mill and overlay, actual lot | Mill 13,300 sq yd, 1,700 tons HMA | $1.94 as bid (2023), $2.22 escalated | $667 as bid | Low bid, July 14, 2023 | Tioga County, NY |
| Remove and repave, small lot | Asphalt paving line only, 7,800 sq ft | $2.75 to $3.00 | $946 to $1,032 | 2 bids, August 8, 2025 | Park District of Highland Park, IL |
| New full-depth asphalt | 4 in HMA on 8 in aggregate base | $4.21 to $5.52 | $1,450 to $1,897 | CB&C estimate, 100-stall lot | Worked estimate below |
| Full-depth asphalt patching | Remove and replace in spots | $7.40 to $8.80 | not a per-stall item | 2025 and 2026 bids | Missouri State University |
| New concrete | 6 in concrete on 4 in aggregate base | $10.39 to $13.50 | $3,576 to $4,643 | CB&C estimate, 100-stall lot | Park Forest 2026 |
Some consumer cost guides on page one quote $2.50 to $4.50 per sq ft for a new asphalt lot without saying what thickness, base or year the number covers. The public bids above show why a single range misleads: the 8-inch base alone costs about $1.73 per sq ft, and the base is the line most likely to be thinned when a quote comes in low.
What do public bids pay for asphalt, base and concrete?
Recent public bids put hot mix asphalt at $75.50 to $99.00 per ton on a 2,176-ton Illinois job in March 2026, crushed aggregate base at $35 to $36 per ton in place in Missouri, and 6-inch concrete pavement at $78.75 to $99.00 per square yard. Smaller quantities cost more: South Dakota’s small-job asphalt item averaged $185.87 per ton.
| Pay item | Quantity bid | Unit price | Date and place | Source |
|---|---|---|---|---|
| HMA binder course, IL-19.0, N50 | 1,209 tons | $75.50 to $89.00 per ton (6 bids) | March 4, 2026, Park Forest, IL (street) | Park Forest bid tab |
| HMA surface course, IL-9.5, Mix D, N50 | 967 tons | $77.65 to $99.00 per ton (6 bids) | March 4, 2026, Park Forest, IL | Park Forest bid tab |
| 12.5 F3 top course HMA, parking lot | 1,700 tons | $85.00 and $87.50 per ton (2 bids) | July 14, 2023, Tioga County, NY | Tioga County bid tab |
| Asphalt concrete, binder paid separately | 1,127,222 tons (group) | $56.38 per ton average | 2024, South Dakota DOT | SDDOT 2024 Bid Item Price Report |
| Asphalt binder, PG grades | 56,812 tons (group) | $723.56 per ton average | 2024, South Dakota DOT | SDDOT 2024 report |
| Asphalt concrete composite (small jobs) | 67,081 tons, 60 bids | $185.87 per ton average low bid | 2024, South Dakota DOT | SDDOT 2024 report |
| 6 in base material, type 1, compacted in place | unit price | $35.00 and $36.00 per ton (2025); $36.00 (2026) | Springfield, MO, parking lots | Missouri State FY25, FY26 |
| Granular base course | 421,050 tons (group) | $27.86 per ton average | 2024, South Dakota DOT | SDDOT 2024 report |
| Cold milling, parking lot | 13,300 sq yd | $2.95 and $3.60 per sq yd | July 14, 2023, Tioga County, NY | Tioga County bid tab |
| Cold milling asphalt concrete, highway | 4,896,456 sq yd | $1.38 per sq yd average | 2024, South Dakota DOT | SDDOT 2024 report |
| Portland cement concrete driveway pavement, 6 in | 642 sq yd | $78.75 to $99.00 per sq yd (6 bids) | March 4, 2026, Park Forest, IL | Park Forest bid tab |
| 8 in nonreinforced concrete pavement | 77,114 sq yd | $88.20 per sq yd average | 2024, South Dakota DOT | SDDOT 2024 report |
| Pavement removal | 9,493 sq yd | $3.00 to $5.00 per sq yd (5 bids above $0.01) | March 4, 2026, Park Forest, IL | Park Forest bid tab |
Check what each per-ton price includes. South Dakota DOT pays binder separately, so its $56.38 mix price plus binder at 5.04 percent of mix weight (56,812 over 1,127,222 tons in 2024) is about $92.85 per ton, close to the Illinois and New York prices. A 100-stall lot needs about 840 tons, and the $185.87 small-job item shows how unit prices climb on short paving days.
How do you convert asphalt price per ton to price per square foot?
Multiply the thickness in inches by 110 lb per square yard per inch, divide by 2,000 to get tons per square yard, multiply by the price per ton and divide by 9. At $80 per ton, each inch of compacted asphalt costs about $0.49 per sq ft, and a 4-inch section about $1.96.
The 110 lb figure comes from the U.S. Navy Equipment Operator Basic training manual, which uses 146 lb per cubic foot of compacted hot mix and notes a range of 140 to 160 lb (Navy manual, Compute Plant-Mix Materials). One square yard 1 inch thick is 0.75 cubic feet, and 0.75 times 146 is 109.5 lb. Use the mix design’s density from the job’s submittals when it differs.
| Step | Arithmetic | Result |
|---|---|---|
| Weight per sq yd per inch | 9 sq ft x (1/12) ft x 146 lb per cu ft | 109.5 lb, rounded to 110 lb |
| Tons per sq yd, 1 inch | 110 / 2,000 | 0.055 ton |
| Tons per 1,000 sq ft, 1 inch | 0.055 / 9 x 1,000 | 6.11 tons |
| Tons per sq yd, 4 inch section | 4 x 0.055 | 0.22 ton |
| $ per sq ft per inch at $75.50 per ton | 75.50 x 0.055 / 9 | $0.46 |
| $ per sq ft per inch at $99.00 per ton | 99.00 x 0.055 / 9 | $0.61 |
| Aggregate base, tons per sq yd, 8 inch (assumes 2.0 tons per compacted cu yd) | 9 x (8/12) cu ft x 148 lb / 2,000 | 0.444 ton |
| Aggregate base $ per sq ft, 8 inch at $35 per ton | 0.444 x 35 / 9 | $1.73 |
The aggregate base density of 2.0 tons per compacted cubic yard is a CB&C planning input, not a published standard; ask the base supplier for the tons per cubic yard their crushed stone compacts to and replace it. Asphalt plants weigh every load, so the ton count on the delivery tickets is what the owner pays on unit-price contracts.
How thick should a commercial parking lot pavement be?
Crystal Lake, Illinois sets a standard parking lot at 1.5 inches of HMA surface and 2.5 inches of HMA binder over 8 inches of CA-6 aggregate base, and a heavy-duty lot at the same asphalt over 10 inches of base. A concrete lot is 6 inches of Class PV concrete over 4 inches of base, for heavy duty too.
The city lets designers substitute any section whose structural number (SN) meets the minimum: 2.2 for a parking lot and 2.7 for a heavy-duty lot (Section A-700, amended by Ordinance 7200, March 1, 2016). SN adds up each layer’s thickness times its coefficient: 0.40 for HMA surface, 0.33 for binder, 0.25 for bituminous base and 0.13 for aggregate base.
| Section (Crystal Lake A-700) | Layers | SN arithmetic | SN | Minimum SN |
|---|---|---|---|---|
| Asphalt parking lot | 1.5 in surface, 2.5 in binder, 8 in CA-6 base | 1.5 x 0.40 + 2.5 x 0.33 + 8 x 0.13 | 2.465 | 2.2 |
| Heavy-duty asphalt parking lot | 1.5 in surface, 2.5 in binder, 10 in CA-6 base | 1.5 x 0.40 + 2.5 x 0.33 + 10 x 0.13 | 2.725 | 2.7 |
| Thin alternate (fails) | 1.5 in surface, 1.5 in binder, 6 in base | 1.5 x 0.40 + 1.5 x 0.33 + 6 x 0.13 | 1.875 | 2.2 |
| Concrete parking lot, including heavy duty | 6 in Class PV concrete, 4 in CA-6 base | 6 x 0.50 + 4 x 0.13 | 3.52 | not set for concrete |
The thin alternate row is the kind of section a low quote can hide: 3 inches of asphalt on 6 inches of stone scores 1.875, below the 2.2 minimum. Upgrading a standard lot to heavy duty adds 2 inches of base, about 0.111 tons per square yard or $0.43 to $0.44 per sq ft at $35 to $36 per ton, for drive lanes used by refuse trucks and deliveries.
Subgrade strength sets the real design, and a soils engineer’s boring logs and pavement recommendations in a geotechnical report override any city minimum on weak clay. Ask the engineer for the design traffic, the subgrade CBR or resilient modulus they assumed and the section they recommend for car stalls and for truck lanes separately.
What does a 100-stall parking lot cost to pave?
A new 100-stall asphalt lot of 34,400 sq ft (3,822 square yards) costs about $145,000 to $190,000 for the pavement section, or $1,450 to $1,900 per stall, using public unit prices from 2024 to 2026. The same lot in 6-inch concrete costs about $358,000 to $464,000, and a mill and overlay of an existing lot about $48,000 to $61,000.
The section is the Crystal Lake standard: a 12-inch box cut, 8 inches of aggregate base, 2.5 inches of binder and 1.5 inches of surface. Tack coat uses the Tioga County ratio of 1,200 gallons for 13,300 square yards, and mobilization is 4 percent, the maximum the New York pay item in the Tioga tab allows.
| Line (new asphalt, 34,400 sq ft) | Quantity | Unit price | Cost | Price source |
|---|---|---|---|---|
| Excavation, 12 in box cut | 1,274 cu yd | $8.74 to $20.00 per cu yd | $11,135 to $25,481 | SDDOT 2024 to Park Forest 2026 low bid |
| Subgrade preparation | 3,822 sq yd | $1.00 to $4.25 per sq yd | $3,822 to $16,244 | Park Forest 2026 |
| Aggregate base, 8 in | 1,697 tons | $35.00 to $36.00 per ton | $59,397 to $61,094 | Missouri State 2025 and 2026 |
| HMA binder course, 2.5 in | 526 tons | $75.50 to $89.00 per ton | $39,679 to $46,774 | Park Forest 2026 |
| HMA surface course, 1.5 in | 315 tons | $77.65 to $99.00 per ton | $24,486 to $31,218 | Park Forest 2026 |
| Tack coat between lifts | 345 gal | $2.50 to $4.75 per gal | $862 to $1,638 | Tioga County 2023 |
| Subtotal | $139,382 to $182,451 | |||
| Mobilization at 4 percent | $5,575 to $7,298 | Tioga County pay item 699.040001 | ||
| Total, pavement section | 34,400 sq ft | $4.21 to $5.52 per sq ft | $144,957 to $189,749 | $1,450 to $1,897 per stall |
Aggregate base is the largest line at about $60,000, 41 percent of the low total, which is why base thickness is the first thing to compare between two quotes. The HMA lines total $64,165 to $77,992 for 841 tons.
| Alternative for the same 100 stalls | Lines | Total with 4% mobilization | $ per sq ft | $ per stall |
|---|---|---|---|---|
| 6 in concrete on 4 in base | 3,822 sq yd concrete at $78.75 to $99.00; 849 tons base at $35 to $36; 1,062 cu yd excavation; subgrade prep | $357,552 to $464,283 | $10.39 to $13.50 | $3,576 to $4,643 |
| Mill and 2 in overlay | 3,822 sq yd milling at $3.38 to $4.13 (Tioga 2023 x 1.147 BLS escalation); 420 tons HMA at $77.65 to $99.00; tack | $48,286 to $61,410 | $1.40 to $1.79 | $483 to $614 |
The milling price was escalated from July 2023 to October 2026 by the BLS producer price index for asphalt paving mixture manufacturing, 390.751 to 448.167 preliminary, a factor of 1.147 (BLS series PCU324121324121). The other unit prices are used as bid because they date from 2024 to 2026. For a full budget with design, permits and owner costs, our guide on how to estimate construction costs lays out the layers that sit above these direct costs.
How much do asphalt binder prices move a paving bid?
Binder is about 5 percent of the mix by weight but drives most short-term price swings. The Colorado DOT asphalt cement index went from $490.93 per short ton in February 2026 to $579.20 in October 2026, an 18 percent rise, which adds about $4.45 per ton of mix, $0.11 per sq ft of a 4-inch section and $3,700 to the 100-stall lot.
CDOT publishes monthly averages of weekly Poten and Partners and Argus Media assessments and uses them to adjust contract prices when the index moves more than 10 percent from the bid month (CDOT Asphalt Cement Cost Adjustment). The broader BLS producer price index for asphalt paving mixtures rose 7.8 percent from October 2025 (415.920) to October 2026 (448.167, preliminary).
| Month | CDOT asphalt cement index, $ per short ton | Change vs February 2026 | Added cost per ton of mix at 5.04% binder |
|---|---|---|---|
| February 2026 | $490.93 | base | base |
| April 2026 | $571.05 | +$80.12 | +$4.04 |
| June 2026 | $584.93 | +$94.00 | +$4.74 |
| August 2026 | $582.25 | +$91.32 | +$4.60 |
| October 2026 | $579.20 | +$88.27 | +$4.45 |
On a private contract, ask the paver to state the binder index and month their price is based on, and whether they will accept a two-way adjustment tied to a named state DOT index, the way Tioga County’s bid carried an asphalt price adjustment item (NYSDOT item 698.04). The 2022 peak in the CDOT series, $733.63 in August 2022, is the stress case for a lot bid in spring and paved in late summer.
Mill and overlay, full-depth or concrete: which should you choose?
Mill and overlay when the base is sound and cracking is limited to the surface; rebuild full depth when full-depth patches would cover roughly 35 to 58 percent of the lot, where patching plus overlay costs as much as reconstruction; use concrete for dumpster pads, truck aprons and lots where the owner values a longer service life over first cost.
The break-even comes from the prices on this page: reconstruction is $4.54 to $6.08 per sq ft including removal at $3.00 to $5.00 per square yard, an overlay is $1.40 to $1.79, and full-depth patching is $7.40 to $8.80. At midpoints, patching about 46 percent of the area plus an overlay matches the cost of a new section.
| If | Then | Cost signal | Rule or record |
|---|---|---|---|
| Cores show the asphalt and base intact; cracks are top-down | Mill 1.5 to 2 in and overlay | $1.40 to $1.79 per sq ft | CB&C estimate from Tioga County and Park Forest bids |
| Alligator cracking or potholes in isolated areas | Full-depth patch those areas, then overlay | $7.40 to $8.80 per sq ft of patch | Missouri State FY25 and FY26 |
| Patches would cover about 35 to 58 percent of the lot | Price full-depth reconstruction side by side | $4.54 to $6.08 per sq ft with removal | CB&C break-even arithmetic |
| New lot, car traffic only | SN 2.2 or more, such as 4 in HMA on 8 in base | $4.21 to $5.52 per sq ft | Crystal Lake A-700 |
| Drive lanes with refuse trucks or deliveries | Heavy-duty section, SN 2.7, such as 10 in base | +$0.43 to $0.44 per sq ft | Crystal Lake A-700 |
| Dumpster pads, truck aprons, fuel islands | 6 in concrete on 4 in base | $10.39 to $13.50 per sq ft | Crystal Lake A-700, Park Forest bids |
| Work disturbs 1 acre or more | Budget a SWPPP and construction stormwater permit | Separate line | EPA 2022 CGP Part 1.1.2 |
The construction permit trigger matters for lot size: 43,560 sq ft is 1 acre, about 127 stalls at 344 sq ft each before landscaping and grading beyond the pavement edge. Our SWPPP guide covers the plan, the Notice of Intent and what inspections cost.
What is not included in a parking lot paving price?
A paving price covers the pavement section. Curb and gutter, storm drainage and detention, lighting, landscaping islands, accessible stalls and permits sit outside it, and they are why owner estimates for new Texas surface lots ran a median of $6,250 per space in 2025 and 2026 registrations, about 3.3 to 4.3 times the pavement section alone.
| Item outside the paving price | Public price or rule | Source |
|---|---|---|
| Combination concrete curb and gutter, M-4.12 | $27.45 to $35.00 per ft (6 bids, 6,456 ft, March 2026) | Park Forest bid tab |
| New Texas surface lots, all-in owner estimates | median $6,250 per space, 17 registrations, 2025 to 2026 | TDLR TABS registrations |
| Florida stormwater permit trigger | more than 4,000 sq ft of new vehicular impervious surface | Fla. Admin. Code 62-330.020 |
| Federal construction stormwater coverage | 1 acre or more of disturbance | EPA 2022 CGP Part 1.1.2 |
| Small-lot extras, Park District of Highland Park | $28,200 block retaining wall on a $70,000 lot alternate (August 2025) | PDHP bid tab |
A 100-stall lot of 34,400 sq ft is new vehicular impervious area well above the 4,000 sq ft Florida trigger, so it will usually need a stormwater system; our retention pond guide covers sizing rules and pond cost per impervious acre. Accessible stall counts and van spaces come from the 2010 ADA Standards, covered in our ADA parking requirements guide.
For the concrete pads in the decision table, slab prices per square foot by thickness are in our guide to concrete slab cost per square foot. Carry a construction contingency on paving too: the Tioga County bid set aside a $30,000 field change allowance on a $268,517 job, 11 percent.
Budget the finish work too: parking lot striping cost and the subgrade compaction tests inspectors require before paving.
How we compiled this
We priced the pavement from 7 public bid documents and price reports (South Dakota DOT 2024 averages; Park Forest, Illinois, March 2026; Park District of Highland Park, August 2025; Tioga County, New York, July 2023; Missouri State University, May 2025 and April 2026), the Crystal Lake section standard, the CDOT binder index and the BLS paving mixture index, all accessed in November 2026. Quantities and per-square-foot results are CB&C arithmetic shown in the tables; the aggregate density is a stated planning input. Striping and pavement markings are excluded.
Frequently asked questions
How much does it cost to pave a 100-space parking lot?
At about 344 sq ft of pavement per space, 100 stalls is 34,400 sq ft. Public unit prices from 2024 to 2026 put a new 4-inch asphalt section on 8 inches of base at $145,000 to $190,000, or $1,450 to $1,900 per stall. Six-inch concrete runs $358,000 to $464,000. Curb, drainage, lighting and permits are extra.
How many tons of asphalt per square foot?
Compacted hot mix weighs about 110 lb per square yard per inch, from the U.S. Navy Equipment Operator Basic manual’s 146 lb per cubic foot. That is 0.055 tons per square yard per inch, or 6.11 tons per 1,000 sq ft per inch. A 4-inch lot needs about 24.4 tons per 1,000 sq ft.
Is concrete or asphalt cheaper for a parking lot?
Asphalt is cheaper to build. In the CB&C 100-stall estimate, 4 inches of asphalt on 8 inches of base costs $4.21 to $5.52 per sq ft and 6-inch concrete on 4 inches of base costs $10.39 to $13.50, using March 2026 Park Forest, Illinois bids of $78.75 to $99.00 per square yard for 6-inch concrete.
How much does it cost to resurface a parking lot?
A mill and 2-inch overlay costs about $1.40 to $1.79 per sq ft in the CB&C estimate. Tioga County, New York milled 13,300 square yards and placed 1,700 tons of asphalt on a parking lot for a July 2023 low bid of $268,517, about $1.94 per sq ft after removing the allowance and paint lines.
How thick should asphalt be for a commercial parking lot?
Crystal Lake, Illinois Section A-700 sets 1.5 inches of surface and 2.5 inches of binder, 4 inches of asphalt, over 8 inches of aggregate base for a parking lot, and 10 inches of base for heavy duty. Alternates must reach a structural number of 2.2, or 2.7 for heavy duty. A geotechnical report can require more.
Does a new parking lot need a SWPPP?
Under EPA’s 2022 Construction General Permit Part 1.1.2, construction that disturbs 1 acre or more, or less inside a larger common plan, needs permit coverage and a SWPPP. One acre is 43,560 sq ft, about 127 stalls at 344 sq ft each, before grading outside the pavement. States with their own permits use similar triggers.
Sources
- Village of Park Forest, Talala Street Reconstruction tabulation of bids, project 26-0117-07, March 4, 2026 (accessed November 15, 2026)
- South Dakota Department of Transportation, 2024 Bid Item Price Report (accessed November 15, 2026)
- Tioga County, New York, HHS Building Parking Lot bid tabulation, July 14, 2023 (accessed November 15, 2026)
- Park District of Highland Park, 2025 Asphalt Improvements Project bid tabulation, August 8, 2025 (accessed November 15, 2026)
- Missouri State University, FY25 Parking Lot Maintenance bid tabulation, May 13, 2025 (accessed November 15, 2026)
- Missouri State University, FY26 Parking Lot Maintenance bid tabulation, April 9, 2026 (accessed November 15, 2026)
- City of Crystal Lake, Illinois, Unified Development Ordinance Section A-700, Pavement design and construction (Ord. 7200, 2016) (accessed November 15, 2026)
- Colorado Department of Transportation, Asphalt Cement Cost Adjustment monthly averages (accessed November 15, 2026)
- U.S. Bureau of Labor Statistics, PPI series PCU324121324121, Asphalt paving mixture and block manufacturing (accessed November 15, 2026)
- U.S. Navy, Equipment Operator Basic training manual, Compute Plant-Mix Materials (accessed November 15, 2026)
- U.S. EPA, 2022 Construction General Permit as modified (accessed November 15, 2026)
- Florida Administrative Code Rule 62-330.020 (accessed November 15, 2026)
- Texas Department of Licensing and Regulation, TABS project registrations (as compiled in our parking space dimensions guide, November 2026)