Submittals in construction are the shop drawings, product data, samples and mock-ups a contractor sends the architect before ordering or building, to show how it will meet the contract documents; AIA A201-2017 §3.12 sets the rules.
Key takeaways
- AIA A201-2017 defines three submittal types in §3.12.1 to §3.12.3 (shop drawings, product data and samples) and says in §3.12.4 they “are not Contract Documents,” so approving one does not change the contract (A201-2017, University of Maine System copy).
- The architect reviews submittals “only for the limited purpose of checking for conformance with information given and the design concept” (AIA B101-2017 §3.6.4.2; A201 §4.2.7). Dimensions, quantities, means and methods stay with the contractor.
- A201 sets no review deadline. Public owners write one in: 30 calendar days in UFGS 01 33 00 (August 2026), 15 business days in VA Section 01 33 23 (November 2023) and 14 calendar days in the Universities of Wisconsin A201 edition (2022).
- Extra review rounds cost money: B101-2017 §4.2.3.1 leaves a blank for how many reviews of each submittal the architect’s fee covers, and the University of Maine System A201 (§3.12.11) reviews an initial submission and two resubmittals, then deducts further review fees from the contractor’s payment.
- No work that needs a submittal may start before approval (A201 §3.12.7); on federal jobs FAR 52.236-21(e) puts “any work done before such approval” at the contractor’s risk.
- In the July 17, 1981 Hyatt Regency walkway collapse, which left 113 people dead and 186 injured, the fabricator’s shop drawings had changed the hanger-rod design and carried review stamps from the contractor, structural engineer and architect (NBSIR 82-2465, 1982).
What are submittals in construction?
A submittal is any document or physical item the contract requires the contractor to send for review before or during the work. AIA A201-2017 §3.12 names three: shop drawings prepared for this project, product data published by a maker, and samples that set the standard the finished work is judged against. Federal specifications split the same idea into 11 numbered categories, SD-01 to SD-11.
| Type | What it is | Example | AIA A201-2017 | UFGS 01 33 00 code |
|---|---|---|---|---|
| Shop drawings | Drawings, diagrams and schedules prepared for this project by the contractor, a subcontractor, fabricator or supplier | Steel connection details, curtain wall elevations, sprinkler layout | §3.12.1 | SD-02 |
| Product data | Published illustrations, performance charts, instructions and brochures for a material or piece of equipment | Rooftop unit cut sheet marked with model, options and capacity | §3.12.2 | SD-03 |
| Samples | Physical examples that set the standard the work will be judged by | Brick, carpet tile, paint draw-down, hardware finish | §3.12.3 | SD-04 |
| Mock-ups | Field-built samples or partial assemblies | Wall panel with window, flashing and cladding | Covered as a sample; the Wisconsin edition adds “such as mock-ups” to §3.12.3 | SD-04 (field samples and mock-ups) |
| Design data | Calculations, mix designs and delegated-design packages | Concrete mix design; sealed stair or curtain wall calculations | §3.12.10.1 (seal required for delegated design) | SD-05 |
| Tests, certificates, instructions | Lab reports, maker certificates, installation instructions and field reports | Fire test report; manufacturer’s installation manual | “Similar Submittals” in §3.12.4 | SD-06 to SD-09 |
| O&M and closeout | Operation and maintenance data, warranties, record drawings | Chiller O&M manual; as-built set | Closeout articles, not §3.12 | SD-10, SD-11 |
Specifications also split submittals into action and informational items. DASNY Section 013300 (the Dormitory Authority of the State of New York) defines action submittals as items that need the reviewer’s responsive action and informational submittals as items that do not, and A201 §3.12.4 lets the documents mark informational items the same way. On federal jobs, a “G” after an item in UFGS 01 33 00 §1.3 means the Government approves it; items without a G go through the contractor’s quality control system.
Some submittals come before any field work. UFGS 01 33 00 lists SD-01 preconstruction submittals such as insurance certificates, surety bonds, the baseline schedule, the submittal register and the schedule of prices, due within 30 calendar days of award when the Government approves them (USACE and NAVFAC Pacific projects). The schedule of prices is the federal name for the document described in our schedule of values guide.
Who reviews submittals, and what does each party check?
Under AIA A201-2017 the contractor reviews, approves and stamps each submittal before it goes to the architect (§3.12.5), and the architect then checks it only against the design concept (§4.2.7). Dimensions, quantities, installation and safety stay with the contractor. The owner usually enters only when a color selection, a substitution or a cost is involved.
| Party | Does | Does not | Clause |
|---|---|---|---|
| Subcontractor, fabricator or supplier | Prepares shop drawings, product data and samples | Send submittals straight to the architect; communications with subcontractors run through the contractor | A201 §3.12.1, §4.2.4 |
| General contractor | Reviews, verifies field measurements, coordinates trades, approves and submits on the submittal schedule | Forward packages unchecked; by submitting it represents it has done all three checks | A201 §3.12.5, §3.12.6 |
| Architect and consultants | Approve or take other action for conformance with the design concept; keep a record of submittals | Check dimensions, quantities, installation or safety; approving one item does not approve its assembly | A201 §4.2.7; B101 §3.6.4.2, §3.6.4.5 |
| Contractor’s delegated design engineer | Seals shop drawings and calculations the contract requires it to design | Rely on the architect to check its engineering beyond the stated criteria | A201 §3.12.10.1 |
| Owner | Makes selections, consents to substitutions, pays for architect Additional Services | Approve shop drawings itself unless the contract says so | A201 §3.4.2; B101 §4.2.2 |
| Federal QC manager and Contracting Officer | QC manager approves items without a G; Contracting Officer approves G items | Let the QC manager approve G items | UFGS 01 33 00 §1.11.1 (NAVFAC) |
- The subcontractor, fabricator or supplier prepares the submittal.
- The general contractor reviews, stamps and submits it (A201 §3.12.5).
- The architect and consultants review it against the design concept (A201 §4.2.7).
- The action stamp comes back: approved, approved as noted, revise and resubmit, or not reviewed.
- If approved or approved as noted, order and fabricate; no work starts before approval (A201 §3.12.7). If revise and resubmit, correct it, flag every change (A201 §3.12.9) and send it back through the contractor; the same review period applies again.
- Log the dates, action code and revision number in the submittal log.
A201 is the general conditions form that carries these clauses; our AIA A201 guide maps its other 14 articles.
How long does submittal review take?
AIA A201-2017 gives no number of days: the architect acts under the approved submittal schedule or “with reasonable promptness” (§4.2.7), so the review period is whatever the contract or specification says. The 7 published specifications below set 10 to 30 days for a first review, and every one that addresses resubmittals restarts the same clock.
| Document | Owner | First review | Resubmittal | Other periods | Source |
|---|---|---|---|---|---|
| AIA A201-2017 §4.2.7 and B101-2017 §3.6.4.1 | Private standard form | Per the approved submittal schedule, or “reasonable promptness” | Same | No day count | AIA via University of Maine System, 2019 |
| UFGS 01 33 00 §1.11 | U.S. Department of Defense | 30 calendar days (Contracting Officer, default) | Same as initial | 14 more days for variations (§1.10.4) | WBDG, August 2026 |
| UFGS 01 33 00 §1.11.d and e, Navy option | U.S. Navy | 15 working days (QC manager); 20 working days (Contracting Officer), 30 if the job runs 180+ calendar days | Same as initial | 30 working days for fire protection engineer review | WBDG, August 2026 |
| VA 01 33 23 §1.10 | U.S. Department of Veterans Affairs | 15 business days | Same as initial | RFIs: 10 business days | WBDG, November 2023 |
| DASNY 013300 §1.4.B | New York State public authority | 15 days | 15 days | 21 days for sequential review | DASNY, posted June 2023 |
| Northwestern University 01 3300 | Private university | 15 days | 15 days | 21 days sequential; 15 days concurrent consultant | Northwestern, March 2017 |
| Universities of Wisconsin A201-2017 §3.12.4.2 | Public university system | 14 calendar days, or written notice of a longer time | Not stated | None | UW edition, June 2022 |
| Mile High Flood District 01 33 00 | Colorado special district | 14 calendar days | Not stated | None | MHFD, revised August 2015 |
| East Central College 013300 | Missouri community college | 10 days | 10 days | 15 days concurrent consultant | ECC, posted November 2014 |
Read the unit before you plan. 15 business days at the VA is about 3 calendar weeks, while 15 “days” in the DASNY and Northwestern sections does not say which kind of day it means. Every timed review on this list starts when the reviewer receives the package, not when the contractor sends it.

The same federal section states the flip side: “No delay damages or time extensions will be allowed for time lost in late submittals,” and the contractor owns the added time that resubmittals cause (UFGS 01 33 00 §1.11.a). VA 01 33 23 §1.4.C says the same for late resubmittals, and A201 §3.10.2 denies time or money for review delays when the contractor ignores its own submittal schedule.
When should each submittal go in?
Work backward from the date the material must be on site: subtract fabrication and delivery time, then every review and resubmittal cycle the contract allows. A201 §3.10.2 requires a submittal schedule that leaves the architect “reasonable time to review,” and a contractor that misses that schedule gets no added time or money for review delays.
The example below uses an item needed on site June 1, 2027 and a 56-day fabrication and delivery lead time after approval. Both are example inputs, not market figures: use the lead time your supplier quotes in writing. Review periods come from DASNY 013300 and UFGS 01 33 00; the 7-day resubmittal turnaround is the period Yuba Community College District Division 01 (2023) gives contractors. DASNY’s “days” are treated as calendar days.
| Scenario | First review | Contractor resubmits | Second review | Lead time | Total days before need date | Latest submit date |
|---|---|---|---|---|---|---|
| A. Approved first time (DASNY) | 15 | 0 | 0 | 56 | 71 | March 22, 2027 |
| B. One resubmittal (DASNY) | 15 | 7 | 15 | 56 | 93 | February 28, 2027 |
| C. Sequential review, one resubmittal (DASNY) | 21 | 7 | 15 | 56 | 99 | February 22, 2027 |
| D. Federal 30-day review, one resubmittal (UFGS) | 30 | 7 | 30 | 56 | 123 | January 29, 2027 |
One resubmittal adds 22 days under the DASNY periods (93 against 71). Under the 30-day federal period it adds 37 days, because a first-time approval needs 30 + 56 = 86 days and scenario D needs 123. DASNY 013300 §1.4.A also asks for an initial submittal list covering everything needed in the first 60 days of construction, which is where long-lead items such as switchgear, elevators and curtain wall belong.
What goes in a submittal log?
A submittal log, which federal specifications call a submittal register, lists every submittal the specifications require with its section, type, reviewer, planned dates and actual dates. UFGS 01 33 00 §1.9 names the fields contractors and reviewers must fill, and the template below adapts them to a private job so the column headings can be copied straight into a spreadsheet.
| Column | What to enter | Example row (illustrative) | Basis |
|---|---|---|---|
| Submittal no. | Spec section plus a letter; resubmittals add _R1, _R2 | 08 44 13A_R1 | YCCD 01 33 00 §1.3.K |
| Spec section and paragraph | Where the requirement sits | 08 44 13, 1.4.B | UFGS §1.9.1 |
| Description | What is being submitted | Curtain wall shop drawings, north elevation | UFGS §1.9.1 |
| Type | Shop drawing, product data, sample, mock-up, closeout; SD code on federal jobs | Shop drawing (SD-02) | UFGS §1.2.1 |
| Action or informational | Whether a stamp is needed | Action | DASNY §1.3 |
| Reviewer | Architect, consultant, owner, or G / QC on federal jobs | Architect and envelope consultant | UFGS §1.9.1 |
| Schedule activity no. | Matching activity in the CPM schedule | A1420 | UFGS §1.9.3(1) |
| Submit-by date | Back-scheduled date (see scenario B) | 2027-02-28 | UFGS §1.9.3(2) |
| Approval-needed-by date | Last day approval still meets the lead time | 2027-04-06 | UFGS §1.9.3(3) |
| Material-needed-by date | On-site need date | 2027-06-01 | UFGS §1.9.3(4) |
| Lead time (days) | Supplier’s written quote | 56 | Supplier quote |
| Date sent / received / returned | Actual dates for each round | 2027-02-26 / 2027-02-28 / 2027-03-15 | UFGS §1.9.4, §1.9.5 |
| Action code | A, AN, RR, NR or RA | RR | UFGS §1.9.6.1 |
| Ball in court | Who holds it now | Contractor | Log convention |
| Deviations and notes | Every deviation, stated in writing | Mullion depth differs from 3/A-501 | A201 §3.12.8 |
Copy-ready header row: Submittal No. | Spec Section | Description | Type | Action/Info | Reviewer | Activity No. | Submit By | Approval Needed By | Material Needed By | Lead Time (days) | Date Sent | Date Received | Date Returned | Action Code | Ball in Court | Deviations / Notes.
In the example row, the approval-needed-by date is 2027-02-28 plus 15 + 7 + 15 days, which gives April 6, 2027; adding the 56-day lead time lands on June 1, 2027. UFGS 01 33 00 §1.11.c asks for the register to be annotated monthly with actual submission and approval dates, and the YCCD section asks for a status summary at each construction meeting. Owners should ask for the log with the baseline schedule, as listed in our commercial project checklist.
Submittal, RFI or substitution request: what is the difference?
An RFI asks what the contract documents mean, a submittal shows how the contractor will meet them, and a substitution request asks to use something other than what they specify. Under AIA A201-2017 the three run on different clauses (§3.2.2 and §4.2.14, §3.12, §3.4.2), and only the substitution route ends in a Change Order or Construction Change Directive by design.
| Item | RFI | Submittal | Substitution request |
|---|---|---|---|
| Purpose | Resolve a gap, conflict or error in the documents | Show how a specified item will be built or supplied | Use a different product or method than specified |
| A201-2017 clause | §3.2.2, §4.2.14 | §3.12, §4.2.7 | §3.4.2 |
| Division 01 section (YCCD numbering) | 01 26 13 | 01 33 00 | 01 25 00 |
| Typical form | AIA G716 | Transmittal; AIA G810 for samples (YCCD); ENG Form 4025 on federal jobs | The spec’s substitution request form |
| Who decides | Architect answers in writing | Architect takes action | Owner consents after the architect evaluates |
| Changes price or time? | Not by itself | No; not a Contract Document (§3.12.4) | Yes, through a Change Order or CCD |
| Federal clock (VA, UFGS) | 10 business days (VA) | 15 business days (VA); 30 calendar days (UFGS) | 14 extra days for variations (UFGS §1.10.4) |
| Architect’s extra fee trigger (B101-2017) | §4.2.2.2: RFIs answerable from the documents | §4.2.2.1 out-of-sequence review; §4.2.3.1 reviews over the limit | §4.2.2.5: evaluating substitutions |
A substitution hidden inside a shop drawing does not count. YCCD 01 33 00 §1.4.C says substitutions “will not be considered when indicated or implied on shop drawings” without a separate written request, and the University of Maine System A201 §3.4.2.1 deducts the architect’s substitution review fees from the contractor’s payment. Owner-driven product swaps to cut cost follow a different route, set out in our value engineering guide. Fields, forms and response days for questions are covered in our guide to RFIs in construction.
Why do submittals get rejected?
The specifications we read return submittals for administrative reasons before anyone checks the design: no contractor stamp, missing pieces, items nobody asked for, or deviations nobody flagged. These come back “without action” or “not reviewed,” and the resubmittal gets the same review period again under UFGS 01 33 00 §1.11.a and VA 01 33 23 §1.10.C.
| Reason | What happens | Clause |
|---|---|---|
| No contractor review stamp | Returned without action, or marked “not reviewed” | DASNY §3.2.A; UFGS §1.12.1.d; VA §1.10.F.4 |
| Incomplete package | Treated as nonresponsive and returned without review | DASNY §3.2.E; VA §1.5.B |
| Not every item for a spec section sent together | Returned without review | YCCD 01 33 00 §1.3.P |
| Spec sections combined in one package | Not allowed | YCCD 01 33 00 §1.3.M |
| Submittal the documents never required | May be returned without action or discarded | A201 §3.12.4; DASNY §3.2.F |
| Too much irrelevant data | Returned without review | VA 01 33 23 §1.5.D |
| Depends on a later submittal | Returned without review | UFGS §1.11.2 (NAVFAC) |
| Deviation not flagged in writing | Approval does not cover it; federal owners may order removal at the contractor’s cost | A201 §3.12.8; UFGS §1.13; FAR 52.236-21(f) |
| Substitution shown only on the shop drawing | Not considered | YCCD 01 33 00 §1.4.C |
| Unflagged changes on a resubmittal | Approval does not apply to them | A201 §3.12.9 |
| Delegated design without the engineer’s seal | Does not meet the contract | A201 §3.12.10.1 |
When a submittal is reviewed, the stamp tells you whether work can move. UFGS 01 33 00 §1.9.6.1 uses five codes, and VA 01 33 23 §1.10.F uses the same wording for the first four.
| Code | Meaning | Can you order and build? | Source |
|---|---|---|---|
| A | Approved as submitted | Yes | UFGS §1.9.6.1, §1.12.1.a |
| AN | Approved as noted | Yes, if you take no exception to the corrections | UFGS §1.12.1.b; VA §1.10.F.2 |
| RR | Disapproved as submitted; resubmit | No; East Central College bars purchasing and fabrication too | UFGS §1.12.1.c; ECC 013300 |
| NR | Not reviewed | No; fix the stated reason and resubmit | UFGS §1.12.1.d; VA §1.10.F.4 |
| RA | Receipt acknowledged | Information-only items | UFGS §1.12.1.e |
Does an approved submittal change the contract or shift liability?
Not by default. A201-2017 §3.12.4 says submittals are not Contract Documents, and §3.12.8 keeps the contractor responsible for deviations and errors after approval unless it flagged the deviation in writing and received a written minor change, Change Order or Construction Change Directive. The architect’s approval of one item is not approval of the assembly it sits in (§4.2.7).
| Common assumption | What the primary source says | Source |
|---|---|---|
| “Approved” means the architect checked dimensions and quantities | Review “is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities” | A201-2017 §4.2.7 |
| An approved shop drawing showing a different product approves the swap | Only if the deviation was flagged at submittal and approved as a minor change, Change Order or CCD | A201 §3.12.8; YCCD §1.4.C |
| Slow reviews always earn the contractor more time | No time or money for review time if the contractor has no submittal schedule or misses it | A201 §3.10.2; UFGS §1.11; VA §1.4.C |
| The architect reviews every resubmittal at no extra cost | Reviews over the number written in B101 §4.2.3.1 are Additional Services; Maine passes them to the contractor after two resubmittals | B101-2017; Maine A201 §3.12.11 |
| Every reviewer must stamp or seal a submittal | The contractor stamps every one; a design professional’s seal is required where the contract calls for delegated design | A201 §3.12.5, §3.12.10.1; DASNY §3.1.B |
| Once approved, approval cannot be withdrawn | The federal government reserves the right to rescind inadvertent approval of submittals with unnoted variations | UFGS 01 33 00 §1.10.2 |
The NBS investigation of the Kansas City Hyatt Regency shows why the limits matter. The original design hung both walkways from a single set of rods; the steel fabricator’s shop drawings used two sets, so the fourth-floor box beams carried the second-floor walkway too, and “these shop drawings were reviewed by the contractor, structural engineer and architect” according to their stamps (NBSIR 82-2465, 1982). This page describes standard contract language and public specifications, not legal advice; your signed contract and its modifications control.
Which document should you send?
Pick the document by what you need from the reviewer: an answer, an approval of how you will comply, permission to deviate, or a change in price or time. The decision table holds the same logic as the flowchart below it, with the A201-2017 clause and the review clock that applies on the public jobs listed earlier on this page.
| If | Then | Clause | Clock |
|---|---|---|---|
| The drawings or specs conflict, leave a gap or contain an error | Send an RFI | A201 §3.2.2, §4.2.14 | 10 business days (VA) |
| You must show how a specified item will be built or supplied, with no deviation | Send a submittal | A201 §3.12 | 10 to 30 days in the 7 specifications above |
| Your submittal differs from the documents in any detail | Flag the deviation in writing at submittal; it binds only once approved as a minor change, Change Order or CCD | A201 §3.12.8 | 14 extra days for variations (UFGS) |
| You want a different product than specified | Send a substitution request on the spec’s form, never only on a shop drawing | A201 §3.4.2; YCCD §1.4 | Per the spec’s 01 25 00 section |
| The answer or deviation changes price, time or scope | Change Order, or Construction Change Directive if price is not agreed | A201 §7.2.1, §7.3.1 | Claim notice within 21 days (§15.1.3.1) |
| No price or time change and consistent with design intent | Architect’s written order for a minor change | A201 §7.4 | None set |
| A submittal came back revise and resubmit | Do not buy or fabricate; correct, flag all changes, resubmit | A201 §3.12.9; ECC 013300 | 7 days to resubmit (YCCD) |
| You are the owner and the contractor is on its third resubmittal | Check the review limit in B101 §4.2.3.1; above it the architect bills Additional Services unless your A201 passes the cost on | B101 §4.2.3.1; Maine A201 §3.12.11 | Initial plus 2 resubmittals (Maine) |
Delivery method changes who drafts the list. On Army design-build jobs the Designer of Record builds the submittal list during design and the contractor submits the register within 30 calendar days after Notice to Proceed (UFGS 01 33 00 §1.9.2); the wider trade-offs are in our comparison of design-build vs design-bid-build. Where submittals fall in the full sequence from preconstruction to closeout is laid out in our commercial construction process guide.
Approved shop drawings also feed closeout: UFGS lists record and as-built drawings under SD-11, and the record set should match the last approved revision. Our guide to what as-built drawings must show covers that hand-off, and our AIA contract documents guide lists the B101, G716 and G810 forms named here.
Submittal dates only work when they are tied to activities in the construction schedule, where a late approval can move the critical path.
A framing submittal that lists only “20 gauge” can mean a 30 mil or a 33 mil stud, so check the mil value against our metal stud sizes and gauge table.
How we compiled this
We read the submittal clauses of AIA A201-2017 in two owner-edited copies (University of Maine System, 2019, and Universities of Wisconsin, 2022) compared clause by clause, the AIA B101-2017 preview, 7 public submittal specifications (UFGS 01 33 00, VA 01 33 23, DASNY, Northwestern University, East Central College, Mile High Flood District and Yuba Community College District), FAR 52.236-21 and NBSIR 82-2465: 12 documents, all accessed in November 2026. We did not survey contractors or architects; the review periods are what the documents require, not measured turnaround times.
Frequently asked questions
What are the three main types of submittals in construction?
AIA A201-2017 names three: shop drawings (§3.12.1), drawn for the project by the contractor or a fabricator; product data (§3.12.2), the maker’s published cut sheets and charts; and samples (§3.12.3), physical pieces that set the standard the work is judged by. Federal specifications add design data, test reports, certificates, instructions, field reports, O&M data and closeout items as SD-05 to SD-11 in UFGS 01 33 00.
Who approves submittals in construction?
The general contractor reviews, approves and stamps each submittal first (A201-2017 §3.12.5), then the architect and its consultants approve or take other action, checking only conformance with the design concept (§4.2.7). On federal jobs under UFGS 01 33 00, items marked “G” go to the Contracting Officer and the rest to the contractor’s quality control manager.
How long does an architect have to review a submittal?
AIA A201-2017 sets no number: the architect follows the approved submittal schedule or acts “with reasonable promptness” (§4.2.7). Specifications fill the gap: 30 calendar days in UFGS 01 33 00 (August 2026), 15 business days at the VA, 15 days at DASNY, 14 calendar days in the Universities of Wisconsin A201 edition and 10 days at East Central College.
Can a contractor start work before a submittal is approved?
Not for work the contract says needs a submittal. AIA A201-2017 §3.12.7 bars any such work until the architect approves the submittal, and on federal contracts FAR 52.236-21(e) says any work done before approval is at the contractor’s risk. VA 01 33 23 §1.4.D requires approval before the specified work activity starts.
What is the difference between an RFI and a submittal?
An RFI asks the architect what the drawings or specifications mean when they conflict or leave a gap (A201-2017 §3.2.2 and §4.2.14). A submittal shows how the contractor will build or supply what they already specify (§3.12). Neither changes price or time by itself; that takes a Change Order or Construction Change Directive under A201 Article 7.
How many times can a submittal be resubmitted?
AIA A201-2017 sets no limit, but AIA B101-2017 §4.2.3.1 has a blank for how many reviews of each submittal the architect’s fee covers; reviews beyond it are Additional Services the owner pays. The University of Maine System A201 reviews an initial submission and two resubmittals, then deducts further review fees from the contractor’s next payment.
What is a submittal log?
A submittal log, called a submittal register in UFGS 01 33 00 §1.9, lists every required submittal with its spec section, type, reviewer, submit-by date, approval-needed-by date, material-needed-by date, actual sent and returned dates, and action code. Federal contractors update it monthly (§1.11.c); DASNY has the contractor fill in submittal dates no later than 30 days after the CPM schedule is approved.
Sources
- AIA A201-2017 General Conditions, University of Maine System sample, American Institute of Architects / University of Maine System. Accessed November 1, 2026.
- AIA A201-2017 General Conditions, Universities of Wisconsin edition, American Institute of Architects / Universities of Wisconsin. Accessed November 1, 2026.
- AIA B101-2017 Owner-Architect Agreement (preview), AIA Contract Documents. Accessed November 1, 2026.
- UFGS 01 33 00 Submittal Procedures (August 2026), USACE / NAVFAC / AFCEC via WBDG. Accessed November 1, 2026.
- VA Section 01 33 23 Shop Drawings, Product Data, and Samples (November 2023), U.S. Department of Veterans Affairs via WBDG. Accessed November 1, 2026.
- Section 013300 Submittal Procedures, Dormitory Authority of the State of New York (DASNY). Accessed November 1, 2026.
- Section 01 3300 Submittal Procedures (March 2017), Northwestern University. Accessed November 1, 2026.
- Section 013300 Submittal Procedures, Hansen Hall lift replacement, East Central College. Accessed November 1, 2026.
- Section 01 33 00 Submittal Procedures (revised August 2015), Mile High Flood District. Accessed November 1, 2026.
- Division 01 Specifications, RFP 23-02 (2023), Yuba Community College District. Accessed November 1, 2026.
- FAR 52.236-21 Specifications and Drawings for Construction (February 1997), Acquisition.gov. Accessed November 1, 2026.
- Investigation of the Kansas City Hyatt Regency Walkways Collapse, NBSIR 82-2465 (1982), National Bureau of Standards (NIST). Accessed November 1, 2026.