Submittals in Construction: Types, Who Reviews, Review Times and a Log Template

Site office table with drawing binder, brick and carpet samples, steel frame visible through the window

Submittals in construction are the shop drawings, product data, samples and mock-ups a contractor sends the architect before ordering or building, to show how it will meet the contract documents; AIA A201-2017 §3.12 sets the rules.

Key takeaways

  • AIA A201-2017 defines three submittal types in §3.12.1 to §3.12.3 (shop drawings, product data and samples) and says in §3.12.4 they “are not Contract Documents,” so approving one does not change the contract (A201-2017, University of Maine System copy).
  • The architect reviews submittals “only for the limited purpose of checking for conformance with information given and the design concept” (AIA B101-2017 §3.6.4.2; A201 §4.2.7). Dimensions, quantities, means and methods stay with the contractor.
  • A201 sets no review deadline. Public owners write one in: 30 calendar days in UFGS 01 33 00 (August 2026), 15 business days in VA Section 01 33 23 (November 2023) and 14 calendar days in the Universities of Wisconsin A201 edition (2022).
  • Extra review rounds cost money: B101-2017 §4.2.3.1 leaves a blank for how many reviews of each submittal the architect’s fee covers, and the University of Maine System A201 (§3.12.11) reviews an initial submission and two resubmittals, then deducts further review fees from the contractor’s payment.
  • No work that needs a submittal may start before approval (A201 §3.12.7); on federal jobs FAR 52.236-21(e) puts “any work done before such approval” at the contractor’s risk.
  • In the July 17, 1981 Hyatt Regency walkway collapse, which left 113 people dead and 186 injured, the fabricator’s shop drawings had changed the hanger-rod design and carried review stamps from the contractor, structural engineer and architect (NBSIR 82-2465, 1982).

What are submittals in construction?

A submittal is any document or physical item the contract requires the contractor to send for review before or during the work. AIA A201-2017 §3.12 names three: shop drawings prepared for this project, product data published by a maker, and samples that set the standard the finished work is judged against. Federal specifications split the same idea into 11 numbered categories, SD-01 to SD-11.

TypeWhat it isExampleAIA A201-2017UFGS 01 33 00 code
Shop drawingsDrawings, diagrams and schedules prepared for this project by the contractor, a subcontractor, fabricator or supplierSteel connection details, curtain wall elevations, sprinkler layout§3.12.1SD-02
Product dataPublished illustrations, performance charts, instructions and brochures for a material or piece of equipmentRooftop unit cut sheet marked with model, options and capacity§3.12.2SD-03
SamplesPhysical examples that set the standard the work will be judged byBrick, carpet tile, paint draw-down, hardware finish§3.12.3SD-04
Mock-upsField-built samples or partial assembliesWall panel with window, flashing and claddingCovered as a sample; the Wisconsin edition adds “such as mock-ups” to §3.12.3SD-04 (field samples and mock-ups)
Design dataCalculations, mix designs and delegated-design packagesConcrete mix design; sealed stair or curtain wall calculations§3.12.10.1 (seal required for delegated design)SD-05
Tests, certificates, instructionsLab reports, maker certificates, installation instructions and field reportsFire test report; manufacturer’s installation manual“Similar Submittals” in §3.12.4SD-06 to SD-09
O&M and closeoutOperation and maintenance data, warranties, record drawingsChiller O&M manual; as-built setCloseout articles, not §3.12SD-10, SD-11

Specifications also split submittals into action and informational items. DASNY Section 013300 (the Dormitory Authority of the State of New York) defines action submittals as items that need the reviewer’s responsive action and informational submittals as items that do not, and A201 §3.12.4 lets the documents mark informational items the same way. On federal jobs, a “G” after an item in UFGS 01 33 00 §1.3 means the Government approves it; items without a G go through the contractor’s quality control system.

Some submittals come before any field work. UFGS 01 33 00 lists SD-01 preconstruction submittals such as insurance certificates, surety bonds, the baseline schedule, the submittal register and the schedule of prices, due within 30 calendar days of award when the Government approves them (USACE and NAVFAC Pacific projects). The schedule of prices is the federal name for the document described in our schedule of values guide.

Who reviews submittals, and what does each party check?

Under AIA A201-2017 the contractor reviews, approves and stamps each submittal before it goes to the architect (§3.12.5), and the architect then checks it only against the design concept (§4.2.7). Dimensions, quantities, installation and safety stay with the contractor. The owner usually enters only when a color selection, a substitution or a cost is involved.

PartyDoesDoes notClause
Subcontractor, fabricator or supplierPrepares shop drawings, product data and samplesSend submittals straight to the architect; communications with subcontractors run through the contractorA201 §3.12.1, §4.2.4
General contractorReviews, verifies field measurements, coordinates trades, approves and submits on the submittal scheduleForward packages unchecked; by submitting it represents it has done all three checksA201 §3.12.5, §3.12.6
Architect and consultantsApprove or take other action for conformance with the design concept; keep a record of submittalsCheck dimensions, quantities, installation or safety; approving one item does not approve its assemblyA201 §4.2.7; B101 §3.6.4.2, §3.6.4.5
Contractor’s delegated design engineerSeals shop drawings and calculations the contract requires it to designRely on the architect to check its engineering beyond the stated criteriaA201 §3.12.10.1
OwnerMakes selections, consents to substitutions, pays for architect Additional ServicesApprove shop drawings itself unless the contract says soA201 §3.4.2; B101 §4.2.2
Federal QC manager and Contracting OfficerQC manager approves items without a G; Contracting Officer approves G itemsLet the QC manager approve G itemsUFGS 01 33 00 §1.11.1 (NAVFAC)
Submittal review path under AIA A201-20171. Subcontractor or supplierprepares the submittal2. General contractor reviews,stamps and submits (A201 3.12.5)3. Architect and consultantsreview design concept (A201 4.2.7)4. Action stamp returnedApproved, as noted, resubmit, not reviewed5a. Approved or approved as notedOrder and fabricate; work onlyafter approval (A201 3.12.7)5b. Revise and resubmitFix, flag every change (A201 3.12.9);same review period againApprovedResubmitresubmittal6. Log the dates, action code and revision number in the submittal log
Submittal review path under AIA A201-2017: contractor review and stamp (§3.12.5), architect review for design concept only (§4.2.7), no work before approval (§3.12.7), changes flagged on resubmittal (§3.12.9). Source: A201-2017, accessed November 2026.
  1. The subcontractor, fabricator or supplier prepares the submittal.
  2. The general contractor reviews, stamps and submits it (A201 §3.12.5).
  3. The architect and consultants review it against the design concept (A201 §4.2.7).
  4. The action stamp comes back: approved, approved as noted, revise and resubmit, or not reviewed.
  5. If approved or approved as noted, order and fabricate; no work starts before approval (A201 §3.12.7). If revise and resubmit, correct it, flag every change (A201 §3.12.9) and send it back through the contractor; the same review period applies again.
  6. Log the dates, action code and revision number in the submittal log.

A201 is the general conditions form that carries these clauses; our AIA A201 guide maps its other 14 articles.

How long does submittal review take?

AIA A201-2017 gives no number of days: the architect acts under the approved submittal schedule or “with reasonable promptness” (§4.2.7), so the review period is whatever the contract or specification says. The 7 published specifications below set 10 to 30 days for a first review, and every one that addresses resubmittals restarts the same clock.

DocumentOwnerFirst reviewResubmittalOther periodsSource
AIA A201-2017 §4.2.7 and B101-2017 §3.6.4.1Private standard formPer the approved submittal schedule, or “reasonable promptness”SameNo day countAIA via University of Maine System, 2019
UFGS 01 33 00 §1.11U.S. Department of Defense30 calendar days (Contracting Officer, default)Same as initial14 more days for variations (§1.10.4)WBDG, August 2026
UFGS 01 33 00 §1.11.d and e, Navy optionU.S. Navy15 working days (QC manager); 20 working days (Contracting Officer), 30 if the job runs 180+ calendar daysSame as initial30 working days for fire protection engineer reviewWBDG, August 2026
VA 01 33 23 §1.10U.S. Department of Veterans Affairs15 business daysSame as initialRFIs: 10 business daysWBDG, November 2023
DASNY 013300 §1.4.BNew York State public authority15 days15 days21 days for sequential reviewDASNY, posted June 2023
Northwestern University 01 3300Private university15 days15 days21 days sequential; 15 days concurrent consultantNorthwestern, March 2017
Universities of Wisconsin A201-2017 §3.12.4.2Public university system14 calendar days, or written notice of a longer timeNot statedNoneUW edition, June 2022
Mile High Flood District 01 33 00Colorado special district14 calendar daysNot statedNoneMHFD, revised August 2015
East Central College 013300Missouri community college10 days10 days15 days concurrent consultantECC, posted November 2014
First-review periods in seven published specificationsBar chart: first-review periods range from 30 calendar days in UFGS 01 33 00 to 10 days at East Central CollegedaysUFGS 01 33 00, Contracting Officer (calend30.0DASNY 013300, sequential review (days)21.0UFGS 01 33 00, Navy Contracting Officer (w20.0DASNY 013300, initial review (days)15.0Northwestern University 01 3300 (days)15.0VA 01 33 23 (business)15.0Universities of Wisconsin A201 edition (ca14.0Mile High Flood District 01 33 00 (calenda14.0East Central College 013300 (days)10.0
Public specifications give reviewers 10 to 30 days for a first review; AIA A201-2017 gives no number. Sources: UFGS 01 33 00 (August 2026), VA 01 33 23 (November 2023), DASNY, Northwestern, UW, MHFD, ECC; accessed November 2026.

Read the unit before you plan. 15 business days at the VA is about 3 calendar weeks, while 15 “days” in the DASNY and Northwestern sections does not say which kind of day it means. Every timed review on this list starts when the reviewer receives the package, not when the contractor sends it.

UFGS 01 33 00 paragraph 1.11 with the 30 calendar day Contracting Officer review period boxed
UFGS 01 33 00 Submittal Procedures (August 2026), §1.11 Scheduling: “Contracting Officer review will be completed within [30] calendar days after the date of submission.” WBDG, accessed November 1, 2026.

The same federal section states the flip side: “No delay damages or time extensions will be allowed for time lost in late submittals,” and the contractor owns the added time that resubmittals cause (UFGS 01 33 00 §1.11.a). VA 01 33 23 §1.4.C says the same for late resubmittals, and A201 §3.10.2 denies time or money for review delays when the contractor ignores its own submittal schedule.

When should each submittal go in?

Work backward from the date the material must be on site: subtract fabrication and delivery time, then every review and resubmittal cycle the contract allows. A201 §3.10.2 requires a submittal schedule that leaves the architect “reasonable time to review,” and a contractor that misses that schedule gets no added time or money for review delays.

The example below uses an item needed on site June 1, 2027 and a 56-day fabrication and delivery lead time after approval. Both are example inputs, not market figures: use the lead time your supplier quotes in writing. Review periods come from DASNY 013300 and UFGS 01 33 00; the 7-day resubmittal turnaround is the period Yuba Community College District Division 01 (2023) gives contractors. DASNY’s “days” are treated as calendar days.

ScenarioFirst reviewContractor resubmitsSecond reviewLead timeTotal days before need dateLatest submit date
A. Approved first time (DASNY)15005671March 22, 2027
B. One resubmittal (DASNY)157155693February 28, 2027
C. Sequential review, one resubmittal (DASNY)217155699February 22, 2027
D. Federal 30-day review, one resubmittal (UFGS)3073056123January 29, 2027
Back-scheduled submittal dates for four review scenariosLatest submit date for an item needed on site June 1, 2027Need date: June 1, 2027A. Approved first time (DASNY 15-day review)71 days: submit by Mar 22, 2027review 15fabricate and deliver 56B. One resubmittal (DASNY)93 days: submit by Feb 28, 202715715fabricate and deliver 56C. Sequential review, one resubmittal99 days: submit by Feb 22, 202721715fabricate and deliver 56D. Federal UFGS 30-day review, one resubmittal123 days: submit by Jan 29, 202730730fabricate and deliver 56Teal: reviewer days. Rust: 7 days for the contractor to resubmit (YCCD 01 33 00). Navy: 56-day example lead time.
Back-scheduling one item needed June 1, 2027 with a 56-day example lead time: 71 days with first-time approval and 93 days with one resubmittal (DASNY periods), 123 days under the 30-day UFGS period. Inputs: DASNY 013300, UFGS 01 33 00, YCCD 01 33 00.

One resubmittal adds 22 days under the DASNY periods (93 against 71). Under the 30-day federal period it adds 37 days, because a first-time approval needs 30 + 56 = 86 days and scenario D needs 123. DASNY 013300 §1.4.A also asks for an initial submittal list covering everything needed in the first 60 days of construction, which is where long-lead items such as switchgear, elevators and curtain wall belong.

What goes in a submittal log?

A submittal log, which federal specifications call a submittal register, lists every submittal the specifications require with its section, type, reviewer, planned dates and actual dates. UFGS 01 33 00 §1.9 names the fields contractors and reviewers must fill, and the template below adapts them to a private job so the column headings can be copied straight into a spreadsheet.

ColumnWhat to enterExample row (illustrative)Basis
Submittal no.Spec section plus a letter; resubmittals add _R1, _R208 44 13A_R1YCCD 01 33 00 §1.3.K
Spec section and paragraphWhere the requirement sits08 44 13, 1.4.BUFGS §1.9.1
DescriptionWhat is being submittedCurtain wall shop drawings, north elevationUFGS §1.9.1
TypeShop drawing, product data, sample, mock-up, closeout; SD code on federal jobsShop drawing (SD-02)UFGS §1.2.1
Action or informationalWhether a stamp is neededActionDASNY §1.3
ReviewerArchitect, consultant, owner, or G / QC on federal jobsArchitect and envelope consultantUFGS §1.9.1
Schedule activity no.Matching activity in the CPM scheduleA1420UFGS §1.9.3(1)
Submit-by dateBack-scheduled date (see scenario B)2027-02-28UFGS §1.9.3(2)
Approval-needed-by dateLast day approval still meets the lead time2027-04-06UFGS §1.9.3(3)
Material-needed-by dateOn-site need date2027-06-01UFGS §1.9.3(4)
Lead time (days)Supplier’s written quote56Supplier quote
Date sent / received / returnedActual dates for each round2027-02-26 / 2027-02-28 / 2027-03-15UFGS §1.9.4, §1.9.5
Action codeA, AN, RR, NR or RARRUFGS §1.9.6.1
Ball in courtWho holds it nowContractorLog convention
Deviations and notesEvery deviation, stated in writingMullion depth differs from 3/A-501A201 §3.12.8

Copy-ready header row: Submittal No. | Spec Section | Description | Type | Action/Info | Reviewer | Activity No. | Submit By | Approval Needed By | Material Needed By | Lead Time (days) | Date Sent | Date Received | Date Returned | Action Code | Ball in Court | Deviations / Notes.

In the example row, the approval-needed-by date is 2027-02-28 plus 15 + 7 + 15 days, which gives April 6, 2027; adding the 56-day lead time lands on June 1, 2027. UFGS 01 33 00 §1.11.c asks for the register to be annotated monthly with actual submission and approval dates, and the YCCD section asks for a status summary at each construction meeting. Owners should ask for the log with the baseline schedule, as listed in our commercial project checklist.

Submittal, RFI or substitution request: what is the difference?

An RFI asks what the contract documents mean, a submittal shows how the contractor will meet them, and a substitution request asks to use something other than what they specify. Under AIA A201-2017 the three run on different clauses (§3.2.2 and §4.2.14, §3.12, §3.4.2), and only the substitution route ends in a Change Order or Construction Change Directive by design.

ItemRFISubmittalSubstitution request
PurposeResolve a gap, conflict or error in the documentsShow how a specified item will be built or suppliedUse a different product or method than specified
A201-2017 clause§3.2.2, §4.2.14§3.12, §4.2.7§3.4.2
Division 01 section (YCCD numbering)01 26 1301 33 0001 25 00
Typical formAIA G716Transmittal; AIA G810 for samples (YCCD); ENG Form 4025 on federal jobsThe spec’s substitution request form
Who decidesArchitect answers in writingArchitect takes actionOwner consents after the architect evaluates
Changes price or time?Not by itselfNo; not a Contract Document (§3.12.4)Yes, through a Change Order or CCD
Federal clock (VA, UFGS)10 business days (VA)15 business days (VA); 30 calendar days (UFGS)14 extra days for variations (UFGS §1.10.4)
Architect’s extra fee trigger (B101-2017)§4.2.2.2: RFIs answerable from the documents§4.2.2.1 out-of-sequence review; §4.2.3.1 reviews over the limit§4.2.2.5: evaluating substitutions

A substitution hidden inside a shop drawing does not count. YCCD 01 33 00 §1.4.C says substitutions “will not be considered when indicated or implied on shop drawings” without a separate written request, and the University of Maine System A201 §3.4.2.1 deducts the architect’s substitution review fees from the contractor’s payment. Owner-driven product swaps to cut cost follow a different route, set out in our value engineering guide. Fields, forms and response days for questions are covered in our guide to RFIs in construction.

Why do submittals get rejected?

The specifications we read return submittals for administrative reasons before anyone checks the design: no contractor stamp, missing pieces, items nobody asked for, or deviations nobody flagged. These come back “without action” or “not reviewed,” and the resubmittal gets the same review period again under UFGS 01 33 00 §1.11.a and VA 01 33 23 §1.10.C.

ReasonWhat happensClause
No contractor review stampReturned without action, or marked “not reviewed”DASNY §3.2.A; UFGS §1.12.1.d; VA §1.10.F.4
Incomplete packageTreated as nonresponsive and returned without reviewDASNY §3.2.E; VA §1.5.B
Not every item for a spec section sent togetherReturned without reviewYCCD 01 33 00 §1.3.P
Spec sections combined in one packageNot allowedYCCD 01 33 00 §1.3.M
Submittal the documents never requiredMay be returned without action or discardedA201 §3.12.4; DASNY §3.2.F
Too much irrelevant dataReturned without reviewVA 01 33 23 §1.5.D
Depends on a later submittalReturned without reviewUFGS §1.11.2 (NAVFAC)
Deviation not flagged in writingApproval does not cover it; federal owners may order removal at the contractor’s costA201 §3.12.8; UFGS §1.13; FAR 52.236-21(f)
Substitution shown only on the shop drawingNot consideredYCCD 01 33 00 §1.4.C
Unflagged changes on a resubmittalApproval does not apply to themA201 §3.12.9
Delegated design without the engineer’s sealDoes not meet the contractA201 §3.12.10.1

When a submittal is reviewed, the stamp tells you whether work can move. UFGS 01 33 00 §1.9.6.1 uses five codes, and VA 01 33 23 §1.10.F uses the same wording for the first four.

CodeMeaningCan you order and build?Source
AApproved as submittedYesUFGS §1.9.6.1, §1.12.1.a
ANApproved as notedYes, if you take no exception to the correctionsUFGS §1.12.1.b; VA §1.10.F.2
RRDisapproved as submitted; resubmitNo; East Central College bars purchasing and fabrication tooUFGS §1.12.1.c; ECC 013300
NRNot reviewedNo; fix the stated reason and resubmitUFGS §1.12.1.d; VA §1.10.F.4
RAReceipt acknowledgedInformation-only itemsUFGS §1.12.1.e

Does an approved submittal change the contract or shift liability?

Not by default. A201-2017 §3.12.4 says submittals are not Contract Documents, and §3.12.8 keeps the contractor responsible for deviations and errors after approval unless it flagged the deviation in writing and received a written minor change, Change Order or Construction Change Directive. The architect’s approval of one item is not approval of the assembly it sits in (§4.2.7).

Common assumptionWhat the primary source saysSource
“Approved” means the architect checked dimensions and quantitiesReview “is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities”A201-2017 §4.2.7
An approved shop drawing showing a different product approves the swapOnly if the deviation was flagged at submittal and approved as a minor change, Change Order or CCDA201 §3.12.8; YCCD §1.4.C
Slow reviews always earn the contractor more timeNo time or money for review time if the contractor has no submittal schedule or misses itA201 §3.10.2; UFGS §1.11; VA §1.4.C
The architect reviews every resubmittal at no extra costReviews over the number written in B101 §4.2.3.1 are Additional Services; Maine passes them to the contractor after two resubmittalsB101-2017; Maine A201 §3.12.11
Every reviewer must stamp or seal a submittalThe contractor stamps every one; a design professional’s seal is required where the contract calls for delegated designA201 §3.12.5, §3.12.10.1; DASNY §3.1.B
Once approved, approval cannot be withdrawnThe federal government reserves the right to rescind inadvertent approval of submittals with unnoted variationsUFGS 01 33 00 §1.10.2

The NBS investigation of the Kansas City Hyatt Regency shows why the limits matter. The original design hung both walkways from a single set of rods; the steel fabricator’s shop drawings used two sets, so the fourth-floor box beams carried the second-floor walkway too, and “these shop drawings were reviewed by the contractor, structural engineer and architect” according to their stamps (NBSIR 82-2465, 1982). This page describes standard contract language and public specifications, not legal advice; your signed contract and its modifications control.

Which document should you send?

Pick the document by what you need from the reviewer: an answer, an approval of how you will comply, permission to deviate, or a change in price or time. The decision table holds the same logic as the flowchart below it, with the A201-2017 clause and the review clock that applies on the public jobs listed earlier on this page.

IfThenClauseClock
The drawings or specs conflict, leave a gap or contain an errorSend an RFIA201 §3.2.2, §4.2.1410 business days (VA)
You must show how a specified item will be built or supplied, with no deviationSend a submittalA201 §3.1210 to 30 days in the 7 specifications above
Your submittal differs from the documents in any detailFlag the deviation in writing at submittal; it binds only once approved as a minor change, Change Order or CCDA201 §3.12.814 extra days for variations (UFGS)
You want a different product than specifiedSend a substitution request on the spec’s form, never only on a shop drawingA201 §3.4.2; YCCD §1.4Per the spec’s 01 25 00 section
The answer or deviation changes price, time or scopeChange Order, or Construction Change Directive if price is not agreedA201 §7.2.1, §7.3.1Claim notice within 21 days (§15.1.3.1)
No price or time change and consistent with design intentArchitect’s written order for a minor changeA201 §7.4None set
A submittal came back revise and resubmitDo not buy or fabricate; correct, flag all changes, resubmitA201 §3.12.9; ECC 0133007 days to resubmit (YCCD)
You are the owner and the contractor is on its third resubmittalCheck the review limit in B101 §4.2.3.1; above it the architect bills Additional Services unless your A201 passes the cost onB101 §4.2.3.1; Maine A201 §3.12.11Initial plus 2 resubmittals (Maine)
Which document to send: RFI, submittal, substitution or changeQ1. Do the documents leave a gap,conflict or error?Send an RFIA201 3.2.2 and 4.2.14YesQ2. Must you show how a specifieditem will be built or supplied?NoQ3. Is it the specified productwith no deviation?YesSend a submittalA201 3.12, spec 01 33 00YesSubstitution requestA201 3.4.2, spec 01 25 00NoQ4. Does it change price,time or scope?NoChange Order or CCDA201 7.2 and 7.3Minor change in writingA201 7.4YesNo
Which document to send: RFI (A201 §3.2.2, §4.2.14), submittal (§3.12), substitution request (§3.4.2), Change Order or CCD (§7.2, §7.3) or minor change (§7.4). Source: AIA A201-2017, accessed November 2026.

Delivery method changes who drafts the list. On Army design-build jobs the Designer of Record builds the submittal list during design and the contractor submits the register within 30 calendar days after Notice to Proceed (UFGS 01 33 00 §1.9.2); the wider trade-offs are in our comparison of design-build vs design-bid-build. Where submittals fall in the full sequence from preconstruction to closeout is laid out in our commercial construction process guide.

Approved shop drawings also feed closeout: UFGS lists record and as-built drawings under SD-11, and the record set should match the last approved revision. Our guide to what as-built drawings must show covers that hand-off, and our AIA contract documents guide lists the B101, G716 and G810 forms named here.

Submittal dates only work when they are tied to activities in the construction schedule, where a late approval can move the critical path.

A framing submittal that lists only “20 gauge” can mean a 30 mil or a 33 mil stud, so check the mil value against our metal stud sizes and gauge table.

How we compiled this

We read the submittal clauses of AIA A201-2017 in two owner-edited copies (University of Maine System, 2019, and Universities of Wisconsin, 2022) compared clause by clause, the AIA B101-2017 preview, 7 public submittal specifications (UFGS 01 33 00, VA 01 33 23, DASNY, Northwestern University, East Central College, Mile High Flood District and Yuba Community College District), FAR 52.236-21 and NBSIR 82-2465: 12 documents, all accessed in November 2026. We did not survey contractors or architects; the review periods are what the documents require, not measured turnaround times.

Frequently asked questions

What are the three main types of submittals in construction?

AIA A201-2017 names three: shop drawings (§3.12.1), drawn for the project by the contractor or a fabricator; product data (§3.12.2), the maker’s published cut sheets and charts; and samples (§3.12.3), physical pieces that set the standard the work is judged by. Federal specifications add design data, test reports, certificates, instructions, field reports, O&M data and closeout items as SD-05 to SD-11 in UFGS 01 33 00.

Who approves submittals in construction?

The general contractor reviews, approves and stamps each submittal first (A201-2017 §3.12.5), then the architect and its consultants approve or take other action, checking only conformance with the design concept (§4.2.7). On federal jobs under UFGS 01 33 00, items marked “G” go to the Contracting Officer and the rest to the contractor’s quality control manager.

How long does an architect have to review a submittal?

AIA A201-2017 sets no number: the architect follows the approved submittal schedule or acts “with reasonable promptness” (§4.2.7). Specifications fill the gap: 30 calendar days in UFGS 01 33 00 (August 2026), 15 business days at the VA, 15 days at DASNY, 14 calendar days in the Universities of Wisconsin A201 edition and 10 days at East Central College.

Can a contractor start work before a submittal is approved?

Not for work the contract says needs a submittal. AIA A201-2017 §3.12.7 bars any such work until the architect approves the submittal, and on federal contracts FAR 52.236-21(e) says any work done before approval is at the contractor’s risk. VA 01 33 23 §1.4.D requires approval before the specified work activity starts.

What is the difference between an RFI and a submittal?

An RFI asks the architect what the drawings or specifications mean when they conflict or leave a gap (A201-2017 §3.2.2 and §4.2.14). A submittal shows how the contractor will build or supply what they already specify (§3.12). Neither changes price or time by itself; that takes a Change Order or Construction Change Directive under A201 Article 7.

How many times can a submittal be resubmitted?

AIA A201-2017 sets no limit, but AIA B101-2017 §4.2.3.1 has a blank for how many reviews of each submittal the architect’s fee covers; reviews beyond it are Additional Services the owner pays. The University of Maine System A201 reviews an initial submission and two resubmittals, then deducts further review fees from the contractor’s next payment.

What is a submittal log?

A submittal log, called a submittal register in UFGS 01 33 00 §1.9, lists every required submittal with its spec section, type, reviewer, submit-by date, approval-needed-by date, material-needed-by date, actual sent and returned dates, and action code. Federal contractors update it monthly (§1.11.c); DASNY has the contractor fill in submittal dates no later than 30 days after the CPM schedule is approved.