Skip to content

Types of Construction Contracts: 5 Ways to Pay, 3 Ways to Deliver

Commercial building steel frame under construction with a tower crane and site office trailer

The main types of construction contracts are five pricing methods: lump sum, unit price, cost plus fee, guaranteed maximum price and time and materials. Each sits inside a delivery method such as design-bid-build, design-build or CM at risk.

Key takeaways

  • Pricing type decides who pays an overrun. Under a guaranteed maximum price, costs above the cap “shall be paid by the Contractor without reimbursement by the Owner” (AIA A102-2017 §5.2.1); under AIA A103-2017 there is no cap and the owner pays every overrun.
  • Federal construction is almost all fixed price: 93.08% of $51.12 billion in fiscal year 2025 federal construction contract obligations was firm fixed price, and time and materials was 0.06% (USAspending API, FY2025).
  • Unit price shifts quantity risk to the owner. On City of Tampa contract 26-C-00023 (bids opened August 18, 2026), 4-inch concrete sidewalk was bid at $72.00 to $85.00 per square yard, paid on measured quantity (Tampa bid tabulation).
  • A real GMP fee: Henderson County, North Carolina accepted a $21,852,605 CM-at-risk GMP in April 2018 with a 3.75% fee ($730,978) on a $19,492,757 cost of the work (Henderson County board packet).
  • Neither AIA’s current document list nor the ConsensusDocs comparison matrix includes an owner agreement for time and materials; the federal model requires a ceiling price “that the contractor exceeds at its own risk” (FAR 16.601(d)(2)).

What are the main types of construction contracts?

Construction contracts are sorted two ways. Pricing type sets how the builder is paid: a fixed lump sum, a rate per unit, actual cost plus a fee with or without a guaranteed maximum price (GMP), or hourly rates plus materials. Delivery method sets who designs and when the builder joins. The table covers the 5 pricing types, the cost risk each carries, and the 2026 standard forms.

Pricing typeHow the builder is paidWho pays a cost overrunAIA formConsensusDocs formFits whenSource
Lump sum (stipulated sum)One price for the defined scope, changed only by change orderContractor, within the scopeA101-2017; A104-2017 abbreviated200; 205 short formDrawings are complete and bid-readyA101 §4.1; ConsensusDocs matrix
Unit priceRate per unit times measured quantityOwner for quantity growth; contractor for its unit rateUnit price table in A101-2017 §4.4210 (public works, optional unit price)Quantities are known in kind but not in amountA101 §4.4; FAR 36.207(b)
Cost plus fee, no GMPActual cost of the work plus a fixed or percentage feeOwnerA103-2017; A134-2019 (CM)235; 510 (CM)Scope is still moving and the owner can auditA103-2017; ConsensusDocs 235
Cost plus fee with GMPActual cost plus fee, capped at the GMPContractor above the GMP; owner below itA102-2017; A133-2019 (CM)230; 500 (CM); 410 (design-build)Owner wants a ceiling before design is finishedA102 §5.2.1; ConsensusDocs 230
Time and materialsFixed hourly rates (including overhead and profit) plus materials at costOwner, up to any ceilingNo owner agreement in AIA’s listNone in the matrixNobody can estimate the extent or duration of the workFAR 16.601; AIA list
Cost risk by construction contract pricing typeFive pricing types ordered from most owner cost risk (time and materials) to most contractor cost risk (lump sum), with the AIA and ConsensusDocs form for each.Who pays a cost overrun under each pricing typeRead left to right: the owner's share of cost risk falls as the contractor's risesTime andmaterialsOwner, up tothe ceilingNo AIA formNo ConsensusDocs formCost plus feeno GMPOwner paysevery overrunAIA A103-2017ConsensusDocs 235Cost plus feewith GMPContractor paysabove the GMPAIA A102-2017ConsensusDocs 230Unit priceOwner: quantityContractor: rateAIA A101 §4.4ConsensusDocs 210Lump sum(stipulated sum)Contractor payswithin scopeAIA A101-2017ConsensusDocs 200More cost risk on the ownerMore cost risk on the contractorOrder reflects the overrun clause in each standard form; your contract's terms decide.Sources: AIA A101, A102, A103 (2017); ConsensusDocs comparison matrix; FAR 16.601. Accessed Nov 2026.
Who pays an overrun: the owner under time and materials and cost plus without a GMP, the contractor above a GMP (AIA A102-2017 §5.2.1) and within a lump sum (A101-2017). Forms per AIA and ConsensusDocs, November 2026.

AIA sells a one-time license for an agreement such as A101-2017 at $179.99 (AIA Contract Documents store, November 2026). Which general conditions, exhibits and payment forms travel with each agreement is set out in our guide to AIA contract documents.

Key numberWhat it measuresSource
93.08%Firm-fixed-price share of FY2025 federal construction contract obligations (NAICS 23, $51.12 billion)USAspending
15%Quantity swing on a unit-priced item, above or below the estimate, that lets either side demand a price adjustment (federal contracts only)FAR 52.211-18
14 daysLatest notice of concealed site conditions after first observance under the A201-2017 general conditionsA201-2017 §3.7.4
3.75%CM fee on the cost of the work in Henderson County’s 2018 CM-at-risk GMPHenderson County
10%Fee cap on a cost-plus-fixed-fee contract, as a share of estimated cost (federal contracts only)FAR 15.404-4(c)(4)(i)
69.4%Fixed-price share of Tutor Perini’s $5.54 billion 2025 revenueForm 10-K, FY2025

How does a lump sum (stipulated sum) contract work?

A lump sum contract fixes one price for a defined scope at signing. AIA calls it a stipulated sum: under AIA A101-2017 §4.1 the owner pays the Contract Sum, adjusted only by change orders, so the contractor keeps savings and absorbs overruns inside the scope. The owner still carries its own changes, design gaps and concealed site conditions.

The price is less fixed than it looks. A101-2017 has three places that move it: alternates in §4.2, allowances in §4.3 and unit prices in §4.4. The A201-2017 general conditions add a fourth: if the builder finds concealed conditions that “differ materially” from the drawings, it must give notice no later than 14 days after first seeing them, and the architect recommends an equitable adjustment (§3.7.4). How the A201 handles changes and claims is covered in our guide to the AIA A201 general conditions.

ClauseWhat can change the lump sumSource
Change orderOwner, contractor and architect agree a new price and timeA201-2017 Article 7
Construction change directivePrice set by lump sum, unit prices, or cost plus a fixed or percentage feeA201-2017 §7.3.3
Concealed or unknown conditionsEquitable adjustment if notice is given within 14 daysA201-2017 §3.7.4
AllowancesPlaceholder sums trued up to actual costA101-2017 §4.3
AlternatesPriced options the owner may accept after signingA101-2017 §4.2
Unit pricesRates applied to measured quantitiesA101-2017 §4.4

ConsensusDocs 200 puts the agreement and general conditions in one document, where AIA splits them into A101 and A201 (ConsensusDocs comparison matrix). Federal agencies start here: FAR 36.207(a) says “Generally, firm-fixed-price contracts shall be used to acquire construction” (FAR 36.207). Because allowances are the softest number in a lump sum bid, check them first when you read how to compare construction bids.

When does a unit price contract make sense?

A unit price contract fixes a rate per unit of work, such as dollars per square yard of sidewalk, and pays for the quantity actually installed. The contractor carries the risk that its rate is too low; the owner carries the risk that quantities grow. Federal rules prefer it only where quantities such as excavation “cannot be estimated with sufficient confidence” (FAR 36.207(b)).

The City of Tampa’s sidewalk maintenance contract 26-C-00023 shows the format. Four bidders priced the same 23 line items at the same estimated quantities, and the city stated its intent to award to the lowest total (Tampa itemized bid tabulation, opened August 18, 2026). The spread is wide: the highest total, $501,341.00, was 64.8% above the lowest, $304,280.00.

Item (unit)Estimated quantityLow bidder’s unit priceRange across 4 bidsSource
Concrete sidewalk and driveways, 4″ thick (SY)1,400$72.00$72.00 to $85.00Tampa 26-C-00023
Concrete sidewalk and driveways, 6″ thick (SY)400$76.00$76.00 to $113.95Tampa 26-C-00023
Removal of existing concrete flatwork (SY)2,000$30.00$20.00 to $42.03Tampa 26-C-00023
Concrete curb and gutter, Type E (LF)300$32.00$32.00 to $50.92Tampa 26-C-00023
Detectable warnings (SF)350$25.00$25.00 to $46.00Tampa 26-C-00023
Contingency allowance (lump sum)1$10,000.00$10,000.00 (set by the city)Tampa 26-C-00023
Total bid$304,280.00$304,280.00 to $501,341.00Tampa 26-C-00023

The bid total is an estimate, not a price. The worked example applies the low bidder’s $72.00 rate for 4-inch sidewalk to three field quantities; the rate stays fixed while the line total follows the measured square yards.

ScenarioSquare yards installedUnit priceLine totalChange from bid line
As bid1,400$72.00$100,800None
Quantity overrun1,700$72.00$122,400$21,600 more (21.4%)
Quantity underrun1,150$72.00$82,800$18,000 less (17.9%)

Both swings exceed 15%. On a federal job, FAR 52.211-18 lets either side demand an equitable adjustment when a unit-priced quantity varies more than 15% above or below the estimate (FAR 52.211-18); a city contract follows its own terms. In standard forms, unit prices sit in the A101-2017 §4.4 table or in ConsensusDocs 210, the public works agreement with an optional unit price. Tutor Perini bills unit price work monthly “based on actual quantity of work performed” and reported $417.2 million of it in 2025, none in its Building segment (Form 10-K, FY2025).

How do cost-plus and guaranteed maximum price contracts differ?

Both pay the contractor its actual cost of the work plus a fee. A guaranteed maximum price adds a ceiling: under AIA A102-2017 §5.2.1, costs that would exceed the GMP are “paid by the Contractor without reimbursement by the Owner.” Without a GMP, as in AIA A103-2017, the owner pays every overrun and relies on its right to audit the job-cost records.

The fee can be “a lump sum, percentage of Cost of the Work, or other provision” (A102-2017 §5.1.1). ConsensusDocs splits the same choice into ConsensusDocs 230, cost of the work plus a fee with a GMP, and ConsensusDocs 235, which “does not include a guaranteed maximum price.” Henderson County’s 2018 GMP for Edneyville Elementary shows how the cap is built from its parts.

GMP lineAmountRate shown in the summarySource
Trade packages and site work$19,110,546Henderson County, Apr 4, 2018
Construction contingency$382,2112.00%Henderson County
Cost of work subtotal$19,492,757Henderson County
Insurances and builder’s risk$284,0841.30%Henderson County
Payment and performance bond$174,8210.80%Henderson County
General conditions$1,169,9655.35% of GMP (CB&C arithmetic)Henderson County
CM fee$730,9783.75% of the cost of work subtotalHenderson County
Guaranteed maximum price$21,852,605$243.80 per sq ft on 89,635 sq ftHenderson County

The county set this GMP from a 100% design development estimate, before construction documents were finished, which is the reason owners choose a GMP over a lump sum. Fee and general conditions together were $1,900,943, or 8.70% of the GMP. Fee structures, cost-of-the-work rules and audit deadlines under A102 and A103 are compared in our guide to the cost-plus contract.

Federal contracts only: the cost-plus-a-percentage-of-cost system “shall not be used” (FAR 16.102(c)), and a cost-plus-fixed-fee contract’s fee is capped at 10% of estimated cost (FAR 15.404-4(c)(4)(i)). Private owners may use a percentage fee, but at 5% every extra $1,000,000 of cost adds $50,000 of fee.

What is a time and materials contract, and why does it need a ceiling?

A time and materials contract pays fixed hourly labor rates, which already include overhead and profit, plus materials at cost. It suits work nobody can scope yet, such as emergency repairs. Neither AIA nor ConsensusDocs lists a standard owner agreement for it, so owners borrow the federal model: a ceiling price the contractor exceeds at its own risk (FAR 16.601(d)(2)).

Federal ruleWhat it saysWrite into a private T&M agreementSource
Hourly ratesFixed rates that “include wages, overhead, general and administrative expenses, and profit”A rate schedule by trade, so markup is not added twiceFAR 16.601(b)(1)
When allowedOnly when the extent or duration of the work cannot be estimatedA defined trigger, such as unknown damage behind finishesFAR 16.601(c)
JustificationContracting officer finds that no other contract type is suitableA date to convert to a lump sum or GMP once scope is knownFAR 16.601(d)(1)
CeilingCeiling price the contractor exceeds at its own riskA not-to-exceed sum and written notice before it is reachedFAR 16.601(d)(2)
TermHead of contracting activity approval if base plus options exceed 3 yearsAn end dateFAR 16.601(d)(1)

Federal use is rare and usually small. In fiscal year 2025, time and materials made up $28.5 million, or 0.06%, of federal construction obligations. One example is a U.S. Army time and materials order for renovations at Picatinny Arsenal, New Jersey: $6,306,918.66 obligated, one offer, not competed, running from February 17, 2025 to March 20, 2028 (USAspending award W15QKN25CA006). Inside an AIA contract, time and materials shows up only as a change pricing method: A201-2017 §7.3.4 prices a disputed change on labor, materials, equipment rental, bonds and permit costs plus overhead and profit, with an itemized accounting (A201-2017).

How do delivery methods change the contract?

A delivery method decides who designs, who builds and when the builder joins; the pricing type decides how the builder is paid. The two combine. Design-build under AIA A141-2024 can carry a stipulated sum or the cost of the work with or without a GMP, set in its Exhibit B Design-Build Amendment (AIA A141-2024 summary).

Delivery methodOwner signs withBuilder joinsUsual pricingAIA formsConsensusDocsSource
Design-bid-buildArchitect, then builderAfter design is completeLump sum; unit price for civil workB101 with A101 and A201200, 210AIA list; matrix
CM at riskArchitect and construction managerDuring designCost plus fee with GMP, or withoutA133-2019 (GMP), A134-2019 (no GMP)500, 510AIA list; matrix
Design-buildOne design-builderAt the startLump sum, or cost plus fee with or without GMPA141-2024410 (GMP), 415 (lump sum)A141-2024; matrix
CM as adviser (agency)Architect, CM adviser and each trade contractorDuring design, as adviserAdviser paid a fee; trades priced separatelyC132-2019 adviser, A132-2019 trades830AIA list; ConsensusDocs 830
Integrated project deliveryMulti-party agreementAt the startSet in the multi-party agreementA195-2008 with A295-2008; C191-2009300AIA list; matrix
Standard contract forms by delivery method and pricing typeGrid of AIA and ConsensusDocs form numbers for design-bid-build, CM at risk and design-build under lump sum, cost plus without GMP and cost plus with GMP.Which standard form fits each delivery method and pricing typeLump sumCost plus fee, no GMPCost plus fee with GMPDesign-bid-buildAIA A101-2017ConsensusDocs 200AIA A103-2017ConsensusDocs 235AIA A102-2017ConsensusDocs 230CM at riskNo AIA formAIA A134-2019ConsensusDocs 510AIA A133-2019ConsensusDocs 500Design-buildAIA A141-2024, Exhibit BConsensusDocs 415AIA A141-2024, Exhibit BAIA A141-2024, Exhibit BConsensusDocs 410CM as adviser: the owner signs each trade contract on AIA A132-2019 and the adviser on AIA C132-2019;ConsensusDocs 830 covers a CM agent. The adviser guarantees no price.Unit prices sit inside a lump sum form: AIA A101-2017 §4.4 or ConsensusDocs 210 (public works).Time and materials: neither AIA's current list nor the ConsensusDocs matrix has an owner agreement for it.Sources: AIA list of current documents; AIA A141-2024 summary; ConsensusDocs comparison matrix. Accessed Nov 2026.
Design-build under AIA A141-2024 takes a lump sum or cost of the work with or without a GMP; CM at risk uses A133-2019 or A134-2019. AIA list and ConsensusDocs matrix, accessed November 1, 2026.

The best published comparison of the three main methods is a 2018 study of 212 U.S. building projects, 53 design-bid-build, 78 CM at risk and 81 design-build, by Keith Molenaar and Bryan Franz for the Charles Pankow Foundation (Revisiting Project Delivery Performance). Holding project traits constant, design-build was delivered 102% faster than design-bid-build at about the same unit cost.

Measure (regression-predicted)Design-build vs design-bid-buildCM at risk vs design-bid-buildSource
Unit cost0.3% less1.6% morePankow 2018, Table 3
Cost growth3.8% less1.4% lessTable 3
Construction speed36% faster20% fasterTable 4
Delivery speed102% faster25% fasterTable 4

A federal design-build job shows pricing and delivery combined: the Army’s 2023 design-build award for the Veterans Affairs health care center in El Paso, Texas is a firm-fixed-price contract with $620,602,660 obligated after full and open competition with 2 offers (USAspending award W9126G24C0004). How the two methods split design risk is covered in design-build vs design-bid-build, and the GMP process from preconstruction to buyout in construction management at risk. Adviser, at-risk and general contractor firms and the fees public owners pay them are compared in our guide to construction management companies.

How common is each type of construction contract?

No public dataset counts private construction contracts by type. Two filed sources come close. Federal procurement records code every award by pricing type, and in fiscal year 2025 firm fixed price covered 93.08% of $51.12 billion in construction obligations. One listed builder’s 10-K shows a private-heavy mix: 69.4% fixed price and 18.5% GMP in 2025.

Pricing type (federal code)All construction, NAICS 23ShareCommercial and institutional building, NAICS 236220ShareSource
Firm fixed price (J)$47,584.0M93.08%$30,481.2M99.48%USAspending
Cost plus incentive fee (V)$1,057.2M2.07%$0.0M0.00%USAspending
Fixed price with economic price adjustment (K)$350.3M0.69%$0.9M0.00%USAspending
Cost plus award fee (R)$272.7M0.53%$0.1M0.00%USAspending
Cost plus fixed fee (U)$111.8M0.22%$18.0M0.06%USAspending
Fixed price incentive (L)$83.7M0.16%$79.6M0.26%USAspending
Time and materials (Y)$28.5M0.06%$11.8M0.04%USAspending
No pricing code recorded$1,520.8M2.97%$49.2M0.16%USAspending
Total obligations, FY2025$51,123.2M100%$30,641.0M100%USAspending
Federal construction obligations by pricing typeBar chart: firm fixed price was 93.08% of FY2025 federal construction obligations; time and materials was 0.06%.% of obligationsFirm fixed price93.1No pricing code recorded2.97Cost plus incentive fee2.07Fixed price with economic price adjustment0.69Cost plus award fee0.53Cost plus fixed fee0.22Fixed price incentive0.16Time and materials0.06
Firm fixed price covered 93.08% of $51.12 billion in fiscal year 2025 federal construction contract obligations (NAICS 23). USAspending, accessed November 1, 2026.

Commercial building is even more fixed price than construction as a whole: 99.48% of FY2025 federal obligations under NAICS 236220. Cost-type federal work sits mostly in civil and specialty projects. Federal construction spending by state is mapped in our federal construction contracts by state report.

Contract typeTutor Perini total revenue, 2025ShareBuilding segment, 2025Backlog share, Dec 31, 2025Source
Fixed price$3,846.1M69.4%$749.7M79%Form 10-K, FY2025
Guaranteed maximum price$1,023.5M18.5%$973.0M13%Form 10-K
Unit price$417.2M7.5%$02%Form 10-K
Cost plus fee and other$256.3M4.6%$129.6M6%Form 10-K
Tutor Perini 2025 revenue by contract typeBar chart: fixed price was $3,846.1M of Tutor Perini 2025 revenue, but GMP led its Building segment at $973.0M.01,0002,0003,0004,0005,000$ millions3,846750Fixed price1,024973Guaranteed maximum price4170Unit price256130Cost plus fee and otherTotal revenueBuilding segment
Fixed price was 69.4% of Tutor Perini’s $5.54 billion 2025 revenue, but GMP was the largest type in its Building segment at $973.0 million. Form 10-K, fiscal year 2025.

In the Building segment, GMP was the largest type at $973.0 million of $1,852.2 million, ahead of fixed price at $749.7 million. The company says its cost plus fee contracts “serve to minimize the Company’s financial risk, but may also limit profits.”

Which type of construction contract should you choose?

Choose by how much of the scope is known and who should carry an overrun. Complete drawings point to a lump sum; measured quantities that may swing more than 15% point to unit prices; an unfinished design with a need for a ceiling points to a GMP; and work nobody can estimate points to time and materials with a written cap. Federal agencies default to fixed price (FAR 36.207(a)).

IfUseStandard formThreshold or reasonSource
Nobody can estimate the extent or duration of the workTime and materials with a ceilingCustom agreement; rate scheduleCeiling the contractor exceeds at its own riskFAR 16.601
Work is measured units whose totals may swingUnit priceA101 §4.4; ConsensusDocs 210Quantity may move more than 15% from the estimateFAR 52.211-18; 36.207(b)
Drawings are complete and you want competitive bidsLump sum, design-bid-buildA101 with A201; ConsensusDocs 200Price fixed at bid; concealed conditions notice within 14 daysA201 §3.7.4
Design is unfinished and you need a ceilingCost plus fee with GMP (CM at risk)A133-2019 or A102-2017; ConsensusDocs 500 or 230Henderson County set its GMP at 100% design developmentHenderson County
You want one firm for design and price, schedule firstDesign-buildA141-2024; ConsensusDocs 410 or 415102% faster delivery than design-bid-build in 212 projectsPankow 2018
Scope keeps moving and you can audit monthlyCost plus fee without GMPA103-2017 or A134-2019; ConsensusDocs 235 or 510Owner pays every overrunA103-2017
The buyer is a federal agencyFirm fixed priceAgency forms under the FAR93.08% of FY2025 construction obligationsUSAspending
Construction contract type decision flowchartFour yes or no questions route a project to time and materials, unit price, lump sum, cost plus with a GMP or cost plus without a GMP.Choosing a pricing type: four questions in order1. Can nobody estimate the scope yet?Emergency repair, unknown damage, investigationYesTime and materials with a ceilingRates include overhead and profit (FAR 16.601 model)No2. Is the work mostly measured quantitiesthat may move? Earthwork, paving, sidewalk repairYesUnit priceAIA A101 §4.4 table; ConsensusDocs 210No3. Are drawings complete enoughfor firm lump sum bids?YesLump sum, design-bid-buildAIA A101-2017 with A201-2017; ConsensusDocs 200No4. Do you need a price ceilingbefore construction starts?YesCost plus fee with a GMPAIA A102, A133 or A141; ConsensusDocs 230, 500, 410NoCost plus fee without a GMPAIA A103-2017 or A134-2019; ConsensusDocs 235 or 510; audit the job-cost recordsBuilder needed during design? Answer 4 also fits CM at risk (A133) and design-build (A141); see the forms matrix.CB&C decision aid built from AIA, ConsensusDocs and FAR 36.207 and 16.601 text, November 2026. Not legal advice.
Four questions route a project to a pricing type and its standard form; the decision table holds the same logic with thresholds. CB&C decision aid from AIA, ConsensusDocs and FAR text, November 2026.

This page describes standard forms and public records; it is not legal advice. Before signing, ask a construction attorney two things: which A201-2017 clauses your state’s lien and prompt payment statutes override, and whether the fee applies to change orders under §5.1.2 of A102-2017 or the matching clause of your form.

The fixed-price owner agreement most private jobs use is explained blank by blank in our AIA A101 guide, and the site overhead inside a cost-plus price in our guide to general conditions.

How we compiled this

We read 4 top-ranking guides to find what they leave out, then compiled 24 primary documents: AIA and ConsensusDocs form texts and catalog pages, 5 FAR sections, USAspending fiscal year 2025 obligations by pricing type, a 2026 City of Tampa bid tabulation, a 2018 Henderson County GMP, Tutor Perini’s FY2025 10-K and the 2018 Pankow study, accessed in November 2026. We did not survey contractors or review private contracts, and federal rules are labelled federal.

Frequently asked questions

What are the 4 main types of construction contracts?

Lists of four usually name lump sum, unit price, cost plus fee and time and materials, and treat a guaranteed maximum price as a cost-plus contract with a ceiling, which is how AIA titles A102-2017. Lists of five split the GMP out. Design-build and CM at risk are delivery methods, not pricing types, and each can carry more than one pricing type.

Which type of construction contract is riskiest for the contractor?

A lump sum carries the most cost risk for the contractor, because it absorbs any overrun inside the agreed scope. A GMP comes close: under AIA A102-2017 §5.2.1, costs above the ceiling are paid by the contractor. Owner changes, and concealed conditions reported within 14 days under A201-2017 §3.7.4, can still raise either price.

Which construction contract type is best for the owner?

No type wins on every project; the trade is price certainty against flexibility. A lump sum gives the firmest price but needs complete drawings. A GMP gives a ceiling earlier, as Henderson County did at 100% design development in 2018. Cost plus without a GMP and time and materials leave the owner paying every overrun, so they need audit rights and a ceiling.

Is a not-to-exceed price the same as a GMP?

Not always. A GMP is a defined term in AIA A102-2017 and A133-2019: the cost of the work plus the fee, guaranteed not to exceed a stated sum, with costs above it paid by the contractor. Not-to-exceed is a looser label often put on a time and materials order; FAR 16.601(d)(2) calls it a ceiling price the contractor exceeds at its own risk.

Can one construction contract mix pricing types?

Yes. AIA A101-2017 is a lump sum agreement with a table for unit prices in §4.4 and allowances in §4.3, and FAR 36.207(a)(3) allows a combination of lump-sum and unit pricing on federal work. City of Tampa contract 26-C-00023 mixed 22 unit-priced items with a $10,000 lump sum contingency allowance in its August 2026 bid.

What type of contract does the federal government use for construction?

Federal agencies default to firm fixed price: FAR 36.207(a) says such contracts “shall be used to acquire construction”, priced as lump sum, unit price or both. In fiscal year 2025, 93.08% of $51.12 billion in federal construction contract obligations was firm fixed price and 0.06% was time and materials, according to USAspending records.

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.

← Back to all articles