Land clearing cost per acre on commercial sites ran $3,800 to $12,880 for heavily wooded ground with stumps removed across 12 public bid prices dated 2025 and 2026 (median $7,175). Separate debris disposal bids ran $1,900 to $5,000 per acre.
Key takeaways
- Seven contractors bid $6,800 to $12,880 per acre to clear and grub heavily wooded land, stumps and roots removed and debris chipped and hauled off, at Colton Municipal Utility District No. 1 in Montgomery County, Texas on July 15, 2026; the median bid was $7,500.
- The Tennessee Department of Transportation 2025 average unit price report lists clearing and grubbing by the acre at $7,500.00 for 13 acres in Region 4.
- Debris disposal is often a separate line: burning on site was bid at $1,900 to $2,300 per acre and chip and haul off site at $1,900 to $4,200 per acre at Winfield Lakes, Fort Bend County, Texas in March 2025.
- Clearing 1 acre or more, or less inside a larger common plan, needs stormwater permit coverage under the Clean Water Act construction stormwater program, with a written SWPPP before the Notice of Intent.
- In wetlands, grubbing or mechanized land clearing that redeposits soil counts as a discharge under 33 CFR 323.2(d); cutting vegetation above ground without disturbing roots does not.
How much does land clearing cost per acre for a commercial site?
Public bids from 2025 and 2026 put heavy clearing and grubbing at $3,800 to $12,880 per acre, light clearing at $250 to $5,776, and open-field grubbing at about $511. The spread comes from scope: whether stumps come out, whether debris leaves the site, how many acres share the fixed costs, and whether the land is wooded or already open.
Each of the 11 rows below is a dated public record from 7 sources, with its size and scope. CB&C divided award totals by stated acres where an award gave only a total. Texas utility district bids dominate because their engineers publish unit prices per acre; read them as Gulf Coast prices.
| Scope in the record | Place and date | Acres | Per acre | Source |
|---|---|---|---|---|
| Heavily wooded clearing and grubbing, stumps out, chip and haul off site (7 bids) | Montgomery County, TX, Jul 15, 2026 | 9.47 | $6,800 to $12,880 (median $7,500) | Colton MUD 1 bid tab |
| Heavy clearing and grubbing with root raking, disposal priced separately (2 bids) | Fort Bend County, TX, Mar 28, 2025 | 37.8 | $5,200 to $7,521.62 | Fort Bend MUD 24 bid tab |
| Light clearing and mowing, disposal priced separately (2 bids) | Fort Bend County, TX, Mar 28, 2025 | 27.4 | $3,976.62 to $4,500 | Fort Bend MUD 24 bid tab |
| Heavy clearing and grubbing, disposal separate (2 bids) | Fort Bend County, TX, Aug 19, 2025 | 5.9 | $3,800 to $5,776 | Fort Bend MUD 213 bid tab |
| Medium clearing and grubbing (2 bids) | Fort Bend County, TX, Aug 19, 2025 | 74.7 | $3,280 to $5,776 | Fort Bend MUD 213 bid tab |
| Light clearing and grubbing (2 bids) | Fort Bend County, TX, Aug 19, 2025 | 26.3 | $1,340 to $5,776 | Fort Bend MUD 213 bid tab |
| Light clearing, grubbing and mowing as directed (2 bids) | Fort Bend County, TX, Aug 19, 2025 | 10 | $250 to $300 | Fort Bend MUD 213 bid tab |
| Clearing and grubbing, state average | Tennessee DOT Region 4, 2025 | 13 | $7,500 | TDOT item 201-01.03 |
| Tree clearing and mulching, federal award | Eielson AFB, AK, Dec 16, 2025 | about 44 | $5,636 (CB&C arithmetic) | Award W911KB26CA003 |
| Grubbing at two Navy airfield sites | Meridian, MS, Sep 21, 2025 | 669.5 | $511 (CB&C arithmetic) | Award N6945025F1391 |
| Clearing, grubbing and grading after a tornado (4 bids) | North Little Rock, AR, Jul 27, 2023 | about 157 | $2,000 to $5,500 | Bid 23-3824 summary |
The median of the 12 heavy prices (11 Texas heavy bids plus the Tennessee average) is $7,175 per acre. Bid totals for these Texas jobs ran $114,680 to $2,005,396.40, so the per-acre price is only part of the contract.
What do state DOTs pay per acre for clearing and grubbing?
Most state transportation departments price clearing as a lump sum, so per-acre items are rare. Where they exist, recent averages run $2,420 to $14,000 per acre: Tennessee $7,500 in 2025, Wisconsin $3,500 for clearing alone in fiscal 2025, and Vermont $14,000 for an airport clearing and grubbing item averaged over October 2024 to October 2026.
| Agency item | Unit | Average price | Period | Source |
|---|---|---|---|---|
| Tennessee DOT 201-01.03 clearing and grubbing | Acre | $7,500.00 (13 acres) | Jan to Dec 2025 | TDOT 2025 average unit prices |
| Tennessee DOT 201-01 clearing and grubbing | Lump sum | $211,005.19 per contract (58 contracts) | Jan to Dec 2025 | TDOT 2025 average unit prices |
| Wisconsin DOT 201.0115 clearing | Acre | $6,800 (FY2023), $2,420 (FY2024), $3,500 (FY2025) | FY2023 to FY2025 | WisDOT average unit price list, Oct 21, 2025 |
| Wisconsin DOT 201.0215 grubbing | Acre | $1,220 (FY2023), $3,400 (FY2024) | FY2023 to FY2024 | WisDOT list |
| Wisconsin DOT 201.0110 clearing | Square yard | $9.60 (FY2025), equal to $46,464 per acre | FY2025 | WisDOT list |
| Vermont AOT 699.0800 (FAA item P-151) clearing and grubbing | Acre | $14,000.00 (1 contract) | Oct 2024 to Oct 2026 | VTrans 2 year averaged price list |
| Vermont AOT 699.0750 (FAA item P-151) clearing only | Acre | $12,000.00 (1 contract) | Oct 2024 to Oct 2026 | VTrans list |
| Arkansas DOT 201 clearing | Station (100 ft) | $2,002.58 weighted average | Jun 2025 to Jun 2026 | ArDOT weighted average unit prices |

Small patches cost far more per acre. Wisconsin’s $9.60 per square yard clearing price works out to $46,464 per acre at 4,840 square yards per acre, about 13 times its $3,500 per-acre price the same year. Highway averages also bundle mobilization into short roadside strips, so treat them as a cross-check against a site bid, not a substitute.
Is it cheaper to burn, chip and haul, or mulch the debris?
Burning on site was the cheapest disposal in two 2025 Texas bid sets, at $1,900 to $2,300 per acre. Chipping and hauling the material off site ran $1,900 to $5,000 per acre, and chipping it into an on-site stockpile for the owner ran $3,500 to $4,500. Burning needs an authorization in many states, and the Winfield Lakes burn item allowed no extra pay or time if burning was suspended.
| Disposal method | Project and date | Acres | Bid per acre | Source |
|---|---|---|---|---|
| Burn on site (permits, burn pits, ash haul, backfill) | Winfield Lakes, TX, Mar 2025 | 65.2 | $1,900 and $2,300 | Fort Bend MUD 24 bid tab |
| Chip and haul off site (alternate to burning) | Winfield Lakes, TX, Mar 2025 | 65.2 | $1,900 and $4,200 | Fort Bend MUD 24 bid tab |
| Burn on site | Manor Lakes, TX, Aug 2025 | 106.9 | $1.00 and $2,200 | Fort Bend MUD 213 bid tab |
| Chip and haul off site (alternate 1) | Manor Lakes, TX, Aug 2025 | 106.9 | $3,958 and $5,000 | Fort Bend MUD 213 bid tab |
| Chip and stockpile on site for owner pickup, 4,000 ft max haul (alternate 2) | Manor Lakes, TX, Aug 2025 | 106.9 | $3,500 and $4,500 | Fort Bend MUD 213 bid tab |
| Forestry mulching of understory in pine stands (federal) | Davy Crockett National Forest, TX, Aug 2024 | 440 | $500 | Award 12444224F0237 |
| Drum mulching of fuel-load vegetation (federal) | Covington County, AL, May 2026 | 118.5 | $812 | Award 12444726P0005 |
The $1.00 burn bid at Manor Lakes is a placeholder: that bidder put $0.01 per linear foot on 12,600 feet of silt fence too, which moves cost into other items. Compare bidders on the total for the method you will actually use, as our guide on how to compare construction bids explains.
Forestry mulching is a different job. The federal mulching awards above, $190 to $812 per acre including a 700-acre Kisatchie National Forest award in Louisiana, thin understory and leave the stumps and root mat in place. A building pad still needs grubbing and root removal so the geotechnical engineer can approve the subgrade, as the Winfield Lakes item requires.
What else moves the price per acre?
After tree density and disposal, the biggest swings in these records come from grubbing depth, water crossings, pipelines and project size. Fixed lump sums do not shrink with acreage: Colton’s two staking items cost $21,320 each on 9.47 acres. Each row shows the dollar effect found in a public record.
| What moves the price | Evidence | Dollar effect | Source |
|---|---|---|---|
| Tree density | Same low bidder, Manor Lakes 2025: light, medium, heavy | $1,340, $3,280, $3,800 per acre | Fort Bend MUD 213 |
| Grubbing (stumps and roots) | Vermont airport items: clearing vs clearing and grubbing | $12,000 vs $14,000 per acre (+$2,000) | VTrans list |
| Above-ground work only | Mowing and light clearing as directed, Manor Lakes | $250 to $300 per acre | Fort Bend MUD 213 |
| Open ground, grubbing only | Navy airfield grubbing, 669.5 acres | $511 per acre | Award N6945025F1391 |
| Creek or ditch crossings | Temporary low water crossing, Colton 2026; coffer dam, Winfield 2025 | $1,000 to $23,900 each; $2,979 to $10,000 each | Colton MUD 1, MUD 24 |
| Pipeline in the clearing area | Air bridge matting for pipeline protection, Winfield 2025 | $5,434 to $10,000 lump sum | Fort Bend MUD 24 |
| Small project size | Staking and re-staking at $21,320 each on 9.47 acres vs $10,400 staking on 65.2 acres | $4,503 vs $160 per acre (CB&C arithmetic) | Colton MUD 1, MUD 24 |
| Scattered single trees | Wisconsin DOT per inch of trunk diameter, FY2025; Vermont per tree | $75.34 clearing plus $14.98 grubbing per inch; $331.70 medium, $1,540 large tree | WisDOT, VTrans |
Terrain and soil show up as separate items too. Colton priced drainage swales at $2.58 to $14.00 per linear foot, and Winfield Lakes required root raking and back dragging to the approval of the geotechnical engineer. Order soil borings and a Phase I environmental site assessment before clearing so buried debris or fill does not surface as a change order.
Which permits come with clearing 1 acre or more?
Clearing 1 acre or more, or less than 1 acre inside a larger common plan of development that will disturb 1 acre or more, needs construction stormwater permit coverage. Wetland grubbing can need a Corps permit, local codes can protect individual trees, and burning needs its own authorization in many states. This is general information, not legal advice; confirm triggers with your civil engineer and the local permit office.
| Rule | Trigger | What it requires | Timing or fee | Source |
|---|---|---|---|---|
| Construction stormwater (federal rule, issued by most states) | 1 acre or more disturbed, or part of a common plan that will disturb 1 acre or more | Written SWPPP, then a Notice of Intent (NOI); erosion and sediment controls; inspections | Where EPA permits: NOI at least 14 days before work | EPA 2022 CGP as modified, Part 1.1.1, Table 1 |
| Florida construction generic permit | 1 acre or more | SWPPP and NOI to Florida DEP | NOI 2 days before work; $250 for 1 to 5 acres, $400 for 5 acres or more | Florida DEP CGP page |
| Texas construction general permit TXR150000 | Small sites 1 to under 5 acres; large sites 5 acres or more | Stormwater pollution prevention plan before construction; site notice | Permit expires March 5, 2028 | TCEQ construction stormwater |
| Wetlands, Clean Water Act Section 404 (federal) | Mechanized land clearing or grubbing that redeposits soil in waters of the United States | U.S. Army Corps of Engineers authorization | Cutting above ground without disturbing roots is excluded | 33 CFR 323.2(d) |
| Local tree protection (example: Tampa) | Most non-exempt trees 5 inches DBH or more; grand trees 32 inches or more | Tree removal permit, replacement or mitigation payment | DBH is measured 4.5 feet above grade | City of Tampa Chapter 27 definitions |
| Open burning (example: Florida) | Land clearing burns; piles over 8 feet across | Florida Forest Service burn authorization | Issued by the local field unit | Florida Forest Service |
Who issues the stormwater permit?
EPA issues the construction general permit itself only in Massachusetts, New Hampshire, New Mexico, the District of Columbia, Puerto Rico, other territories and Indian country, per CGP Appendix B. Other states run their own version, such as Florida DEP and the Texas Commission on Environmental Quality. EPA’s 2022 permit expires February 16, 2027, and a proposed 2027 permit was published for comment on August 3, 2026.
Do you need a building permit first?
Usually not. Many cities issue a separate site clearing or land disturbance permit, and in Florida, section 713.135(1)(e)4 lets land clearing permits issue before a notice of commencement is recorded. Our guides to commercial building permits and the Florida notice of commencement cover the rest of the sequence.
What order does the clearing work follow?
On a commercial site of 1 acre or more, the paperwork comes before the dozer. Under the EPA permit the SWPPP is written first, perimeter controls go in before clearing, and any ground left idle 14 days or more must be stabilized within 14 calendar days. The steps below carry the deadlines and the 2025 unit prices bid for each control.
- Write the SWPPP. EPA CGP Part 7.1 requires it before the NOI is filed.
- File the NOI. Where EPA permits, at least 14 calendar days before work; Florida DEP needs it 2 days before, with a $250 or $400 fee.
- Install perimeter controls. Silt fence was bid at $2.12 to $3.00 per linear foot and a stabilized construction exit at $3,548 to $8,250 at Winfield Lakes in 2025.
- Protect what stays. Fence trees to keep, and keep a 50-foot undisturbed natural buffer, or equivalent controls, for waters within 50 feet (CGP Part 2.2.1).
- Clear and grub. Heavy clearing ran $3,800 to $12,880 per acre in the 2025 and 2026 bids above.
- Dispose of debris. Burn, chip and haul, or stockpile: $1,900 to $5,000 per acre, excluding one $1.00 placeholder bid.
- Inspect. Every 7 calendar days, or every 14 days and within 24 hours of a storm of 0.25 inches or more (CGP Part 4.2).
- Stabilize. Start immediately on ground idle 14 days or more and finish within 14 calendar days (CGP Table 2, sites disturbing 5 acres or less at a time).
Clearing also runs on a short clock: the bid forms listed contract times of 25/5 calendar days for 9.47 acres at Colton, 60/75 days for 65.2 acres at Winfield Lakes and 60/70 days for 106.9 acres at Manor Lakes. Build those durations into the schedule for new commercial construction before the pad work starts.
What does clearing a 10-acre commercial site cost? A worked example
A hypothetical 10-acre Gulf Coast site with 6 wooded acres and 4 acres of brush comes to about $99,711, or $9,971 per acre, using the 2025 and 2026 Texas bid prices above. Clearing and disposal are $74,153 of that, 74.4%. Stormwater controls and staking make up the rest.
| Line item | Quantity | Unit price used | Total | Price basis |
|---|---|---|---|---|
| Heavy clearing and grubbing, stumps out, chip and haul | 6 acres | $7,500 | $45,000.00 | Median of 7 bids, Colton MUD 1, Jul 2026 |
| Light clearing and mowing | 4 acres | $4,238.31 | $16,953.24 | Average of 2 bids, Winfield Lakes, Mar 2025 |
| Chip and haul disposal for the light acres | 4 acres | $3,050 | $12,200.00 | Average of 2 bids, Winfield Lakes alternate |
| Silt fence around the site | 2,640 LF | $2.56 | $6,758.40 | Average of 2 bids, Winfield Lakes; square 10-acre perimeter |
| Stabilized construction exit | 1 | $5,899 | $5,899.00 | Average of 2 bids, Winfield Lakes |
| SWPPP compliance, inspections, NOI and NOT | 1 | $2,500 | $2,500.00 | Both bids, Manor Lakes, Aug 2025 |
| Construction staking | 1 | $10,400 | $10,400.00 | Both bids, Winfield Lakes |
| Total | 10 acres | $99,710.64 | $9,971.06 per acre |
The example excludes grading, fill, survey of the boundary, permit fees outside Florida, and any water crossing. A 10-acre square has a perimeter of about 2,640 feet (660 feet a side); an irregular tract needs more fence. Moving the disposal to on-site burning at the $1,900 to $2,300 Winfield bids would cut the light-acre disposal by $3,000 to $4,600, if a burn authorization is available.
Why do residential lot quotes look different?
Consumer cost guides mostly quote homeowner jobs from quote aggregators, not bid tabulations. Their heavily wooded ranges top out near $5,600 to $8,000 per acre, while 10 of the 12 heavy commercial prices above exceed $5,600. Small residential jobs priced by the tree run much higher per acre.
| Claim in a top-ranking guide | What the public record shows | Source |
|---|---|---|
| A home-improvement guide updated February 2023: heavily wooded land costs $3,000 to $5,600 per acre | 10 of 12 heavy commercial prices from 2025 and 2026 exceed $5,600; median $7,175 | Colton, Winfield, Manor Lakes, TDOT |
| The same guide also gives $250 to $1,000 per acre for clearing | That fits mowing and open-ground grubbing ($250 to $511), not wooded land | Manor Lakes, Navy award |
| A home-improvement guide lists land clearing permits at up to about $200 | Commercial bids carry SWPPP compliance at $1,313 to $3,500 plus silt fence and exits; Florida’s NOI fee alone is $250 or $400 | Winfield, Florida DEP |
| Contrast: residential and tree-by-tree work | 0.83 acre of tree removal with stump grinding in Bethel, Ohio cost $38,787.09 in October 2024, or $46,731 per acre | USDA APHIS award 12639525F0015 |
The Ohio award is a labelled contrast, not a site-clearing price: it removed high-risk Asian longhorned beetle host trees on a 0.83-acre work plan and ground the stumps. Work priced per tree or per small patch costs far more per acre than mass clearing, so a residential lot quote and a commercial tract bid should not be used to budget each other.
Which clearing approach fits your site?
Match the scope to what will be built. Building pads and paving need full grubbing; open space and future phases may only need mowing or mulching. These thresholds come from the bid scopes and federal rules cited above, with the price each choice carried in 2025 and 2026.
| If your site is | Then specify | Typical public bid per acre | Source |
|---|---|---|---|
| Under a building pad or paving | Clearing and grubbing with stumps and roots removed, root raking to the geotech’s approval | $3,800 to $12,880 | Winfield, Colton |
| Open field or pasture | Grubbing or mowing only | $250 to $511 | Manor Lakes, Navy award |
| Wooded land kept as open space or a future phase | Forestry mulching, stumps left | $190 to $812 | Kisatchie, Alabama award |
| In or next to wetlands | Cut above ground only until a Section 404 decision | No public per-acre benchmark found | 33 CFR 323.2 |
| 1 acre or more of total disturbance | SWPPP, NOI, silt fence, construction exit in the same bid | SWPPP lump sum $1,313 to $3,500 | EPA CGP, Winfield |
| Burning allowed and permitted | Burn on site as base bid, chip and haul as alternate | $1,900 to $2,300 burn vs $1,900 to $5,000 haul | Winfield, Manor Lakes |
For a warehouse or distribution site, line these items up against the shell budget in our warehouse construction guide, and against the all-in ranges in commercial construction cost per square foot; the 10-acre example above came to $9,971 per acre before grading.
Soil borings usually follow clearing, and our geotechnical report guide explains what they cost and what they decide.
The construction permit ends at stabilization, but the permanent stormwater pond, its slopes and its inspection schedule are covered in our guide to the retention pond.
The plan itself, its 11 required sections and its inspection deadlines are covered in our guide to the SWPPP for construction sites.
How we compiled this
We read 4 public bid tabulations (Texas 2025 and 2026, Arkansas 2023), 4 state DOT average price lists, 6 federal awards on USAspending.gov, the EPA 2022 Construction General Permit as modified in April 2025, and state and local permit pages, all accessed November 1, 2026. CB&C arithmetic divides a stated total by stated acres. We excluded figures seen only in search snippets, such as a Montana DOT average we could not open.
Frequently asked questions
How much does it cost to clear 1 acre of land?
For a wooded commercial acre with stumps removed, 2025 and 2026 public bids ran $3,800 to $12,880, with a median of $7,175 across 12 prices. Light brush ran $250 to $5,776 per acre. A single acre usually costs more per acre than a large tract, because staking, mobilization and stormwater controls are spread over fewer acres.
How long does it take to clear an acre of land?
Public bids set whole-project clocks rather than per-acre times. Colton MUD 1 in Texas listed a contract time of 25/5 calendar days for 9.47 heavily wooded acres in 2026, and Winfield Lakes listed 60/75 days for 65.2 acres in 2025. Weather, burn bans and Corps or tree permit reviews can stretch those windows.
Do I need a permit to clear less than 1 acre?
Federal stormwater coverage applies at 1 acre or more, or below 1 acre when the clearing is part of a larger common plan that will disturb 1 acre or more. Local codes can still apply below that line: Tampa, for example, requires a tree removal permit for most trees of 5 inches DBH or more.
Can I clear land in a wetland without a permit?
Under 33 CFR 323.2, cutting vegetation above ground with mowers, rotary cutters or chainsaws, without substantially disturbing roots, is not a discharge. Grubbing, root raking or mechanized pushing that redeposits soil in waters of the United States is, and needs U.S. Army Corps of Engineers review. Ask your engineer for a wetland delineation first.
Is forestry mulching cheaper than clearing and grubbing?
Yes per acre, but it does a different job. Federal mulching awards ran $190 to $812 per acre in 2024 to 2026, against $3,800 to $12,880 for heavy clearing and grubbing. Mulching leaves stumps and roots, so building pads and paving still need grubbing to meet the geotechnical engineer’s subgrade approval.
Does land clearing include grading?
Usually not. The 2025 and 2026 Texas bids priced clearing, disposal, silt fence, staking and seeding as separate lines, and grading of the pad comes later under the earthwork contract. Some bids add small grading items, such as drainage swales at $2.58 to $14.00 per linear foot at Colton MUD 1 in 2026.
Sources
Bid tabulations and price lists
- Bid tabulation: Clearing and grubbing to serve Permian Parkway Phase 2, Colton MUD No. 1 (July 15, 2026), LJA Engineering for Colton Municipal Utility District No. 1. Accessed November 1, 2026.
- Bid tabulation: Clearing and grubbing, Winfield Lakes Phase 1, Fort Bend County MUD No. 24 (March 28, 2025), LJA Engineering for Fort Bend County MUD No. 24. Accessed November 1, 2026.
- Bid tabulation: Clearing and grubbing to serve Manor Lakes Estates, Fort Bend County MUD No. 213 (August 19, 2025), LJA Engineering for Fort Bend County MUD No. 213. Accessed November 1, 2026.
- Bid 23-3824 summary: Clearing, grubbing and grading Burns Park acreage (July 27, 2023), City of North Little Rock. Accessed November 1, 2026.
- Average Unit Prices, January 1 to December 31, 2025, awarded contracts, Tennessee Department of Transportation. Accessed November 1, 2026.
- Average Unit Price List (October 21, 2025), Wisconsin Department of Transportation. Accessed November 1, 2026.
- 2 Year Averaged Price List, October 2024 to October 2026, Vermont Agency of Transportation. Accessed November 1, 2026.
- Weighted Average Unit Prices, June 25, 2025 to June 24, 2026, Arkansas Department of Transportation. Accessed November 1, 2026.
Federal awards
- Award W911KB26CA003: tree clearing and mulching, Eielson AFB, USAspending.gov. Accessed November 1, 2026.
- Award N6945025F1391: grubbing at Joe Williams airfield and Sea Ray target range, USAspending.gov. Accessed November 1, 2026.
- Award 12444224F0237: understory mulching, Davy Crockett National Forest, USAspending.gov. Accessed November 1, 2026.
- Award 12444225F0050: midstory mulching, Kisatchie National Forest, USAspending.gov. Accessed November 1, 2026.
- Award 12444726P0005: drum mulching, Covington County, Alabama, USAspending.gov. Accessed November 1, 2026.
- Award 12639525F0015: host tree removal and stump grinding, Ohio, USAspending.gov. Accessed November 1, 2026.
Permits, statutes and rules
- Stormwater discharges from construction activities, U.S. Environmental Protection Agency. Accessed November 1, 2026.
- 2022 Construction General Permit, as modified April 2025, U.S. Environmental Protection Agency. Accessed November 1, 2026.
- 2022 CGP Appendix B: areas of permit coverage, U.S. Environmental Protection Agency. Accessed November 1, 2026.
- Construction Activity (CGP), Florida Department of Environmental Protection. Accessed November 1, 2026.
- Stormwater permits for construction (TXR150000), Texas Commission on Environmental Quality. Accessed November 1, 2026.
- 33 CFR 323.2, Definitions (discharge of dredged material), eCFR, U.S. Army Corps of Engineers regulations. Accessed November 1, 2026.
- Definitions and links, Chapter 27 tree code, City of Tampa. Accessed November 1, 2026.
- Burn authorizations, Florida Forest Service, FDACS. Accessed November 1, 2026.
- Florida Statutes 713.135, Notice of commencement and applicability of lien, Florida Legislature. Accessed November 1, 2026.