Skip to content

SWPPP: When a Construction Site Needs One, What Goes In It and What It Costs

Graded commercial site with silt fence along the downslope edge and a stone construction exit

A SWPPP (stormwater pollution prevention plan) is the written erosion, sediment and pollution control plan a construction operator must finish before filing a Notice of Intent when work disturbs 1 acre or more.

Key takeaways

  • Coverage starts at 1 acre of disturbance, or less than 1 acre inside a common plan that will disturb 1 acre or more, under EPA 2022 Construction General Permit Part 1.1.2.
  • In EPA-permitted areas the SWPPP comes first, then the Notice of Intent (NOI) at least 14 calendar days before work starts (CGP Part 1.4.1 and Table 1); Florida DEP asks for 2 days and a $250 or $400 fee.
  • A qualified person inspects every 7 calendar days, or every 14 days plus within 24 hours of 0.25 inches of rain (CGP Part 4.2); a new or replacement control must work within 7 calendar days of discovery (Part 5.2.1).
  • In 43 bids on 8 Texas district contracts opened in September and October 2026, the SWPPP compliance lump sum ran $100 to $9,600, median $1,508 (LJA bid tabulations); Oklahoma DOT averaged $10,268.73 across 192 lump-sum awards.
  • Civil penalties reach $68,445 per day per violation under 40 CFR 19.4; an EPA expedited settlement worksheet for a 12.75-acre Colorado school site totaled $21,900.

What is a SWPPP?

A SWPPP is a site-specific document, not a form. It names every operator and the stormwater team, maps the site and the waters it drains to, and specifies each erosion control, sediment control and pollution prevention measure with its design, maintenance routine and install date. Under the 2022 CGP, Part 7 sets the minimum contents, and the permit itself sets the enforceable limits.

The Construction General Permit (CGP) is a general permit under the Clean Water Act’s National Pollutant Discharge Elimination System (NPDES). Coverage is needed by each “operator”: the party that controls the plans and specifications, and the party with day-to-day control of the site (CGP Part 1.1.1). On a commercial job that can mean both the owner or developer and the general contractor; subcontractors generally are not operators. Texas calls the same document a SWP3 under TCEQ permit TXR150000.

Several operators may share one group SWPPP, but each stays responsible if another fails to act (CGP Part 7.1, footnote 84). The numbers below are the ones a project team works to most often.

ItemFigureRule
Disturbance trigger1 acre, or less inside a common plan of 1 acre or moreCGP Part 1.1.2
NOI lead time, EPA areasAt least 14 calendar days before workCGP Table 1
Routine inspectionEvery 7 days, or every 14 days and within 24 hours of 0.25 in of rainCGP Part 4.2
Corrective actionNext business day; 7 calendar days for a new or replacement controlCGP Part 5.2.1
Stabilization after work stops 14+ daysComplete within 14 days, or 7 days if over 5 acres are openCGP Table 2
Record retention3 years for inspection reports and the corrective action logCGP Parts 4.7.4, 5.4.4
Notice of Termination (NOT)Within 30 calendar days of final stabilizationCGP Part 8.4
Maximum civil penalty$68,445 per day per violation40 CFR 19.4

When does a construction site need a SWPPP?

A site needs a SWPPP when it needs construction stormwater permit coverage, and the federal trigger is disturbing 1 acre or more, or less than 1 acre inside a common plan of development or sale that will ultimately disturb 1 acre or more (EPA construction stormwater program). The Texas, Florida and California permits use the same 1-acre floor.

Disturbance means clearing, grading, excavating and similar earthwork, so the clock usually starts with the clearing crew. Prices for that first phase are in our guide to land clearing cost per acre. Routine maintenance that keeps the original line, grade and capacity of a facility is excluded under 40 CFR 122.26(b)(15). For example, a 0.8-acre outparcel inside a shopping center plan that will disturb 12 acres in total is covered.

Sites under 5 acres can sometimes skip coverage with a rainfall erosivity waiver: 40 CFR 122.26(b)(15)(i)(A) lets the permitting authority waive the requirements where the rainfall erosivity factor R is below 5 for the construction period. Texas offers it as the Low Rainfall Erosivity Waiver. The flowchart and table below run the same four questions.

Decision flowchart: does a construction site need a SWPPP, and which permit applies1. Will the work disturb 1 acre or more?2. Is it part of a common plan that willdisturb 1 acre or more in total?3. Under 5 acres, and is the rainfallerosivity factor R below 5 for the schedule?No construction stormwater permit.Check local grading or erosion rules.Erosivity waiver may apply under40 CFR 122.26(b)(15). Confirm withthe permitting authority.4. Is EPA the permitting authority?MA, NH, NM, DC, PR, Indian country orfederal land listed in CGP Appendix BEPA 2022 CGP: write the SWPPP,then file the NOI in NeT at least14 days before work startsState permit: write the SWPPP(SWP3 in Texas), then file the stateNOI or post the site noticeNoYesYesNoYesNoYesNo
Four questions decide whether a site needs a SWPPP and which permit it files under: 1 acre or common plan (CGP Part 1.1.2), the R below 5 waiver (40 CFR 122.26(b)(15)) and EPA or state authority (CGP Appendix B), as of November 2026.
QuestionIf yesIf noRule
1. Will the work disturb 1 acre or more?Go to question 3Go to question 2CGP Part 1.1.2
2. Is it part of a common plan that will disturb 1 acre or more in total?Go to question 3No construction stormwater permit. Check local grading or erosion rules.40 CFR 122.26(b)(15)
3. Under 5 acres, and is the rainfall erosivity factor R below 5 for the schedule?Erosivity waiver may apply under 40 CFR 122.26(b)(15). Confirm with the permitting authority.Go to question 440 CFR 122.26(b)(15)(i)(A)
4. Is EPA the permitting authority? MA, NH, NM, DC, PR, Indian country or federal land listed in CGP Appendix BEPA 2022 CGP: write the SWPPP, then file the NOI in NeT at least 14 days before work startsState permit: write the SWPPP (SWP3 in Texas), then file the state NOI or post the site noticeCGP Appendix B

Who issues construction stormwater permits in your state?

EPA issues the 2022 CGP itself only where no state runs the program: statewide in Massachusetts, New Hampshire, New Mexico, the District of Columbia and Puerto Rico, plus Indian country, listed federal facilities and Pacific territories (CGP Appendix B). Every other state issues its own construction general permit, with its own NOI form, fee and deadlines.

The state permits follow the same federal minimums in 40 CFR 450.21, so the SWPPP structure carries over, but the paperwork does not. This summary of public permit text is not legal advice; the permit your site is covered under controls.

JurisdictionPermitPlan nameNotice before workEnds withSource
EPA areas (MA, NH, NM, DC, PR, Indian country, listed federal land)2022 CGP, expires February 16, 2027SWPPPNOI in NeT at least 14 calendar days before workNOT within 30 daysEPA CGP Table 1, Part 8.4
TexasTXR150000, effective March 5, 2023, expires March 5, 2028SWP3Small sites (1 to under 5 acres) post a site notice; large sites (5+ acres) file an NOI in STEERSNOT in STEERSTCEQ
FloridaDEP construction generic permit, 5-year termSWPPPNOI at least 2 calendar days before; $250 for 1 to 5 acres, $400 for 5+ acresNOT within 14 days after final stabilizationFlorida DEP
CaliforniaOrder 2022-0057-DWQ, effective September 1, 2023SWPPPFiled in SMARTS; Lake Tahoe Basin uses Lahontan Order R6T-2016-0010Per the orderState Water Board

What must a SWPPP contain?

Under CGP Part 7.2, a SWPPP has 11 required sections, from a list of every operator to a signed certification, and 10 of them are written before the NOI is filed. The site map and the control descriptions carry most of the work: each control needs a design specification, a maintenance routine and an installation date. EPA publishes a free 2022 CGP SWPPP template in Word format.

The right column shows what EPA’s 2023 construction stormwater expedited settlement schedule charges when that section is missing, which shows how EPA weighs each gap. Section numbers follow the 2025 modified permit.

CGP partSectionWhat it must showEPA settlement amount if missing
7.2.1All site operatorsEvery other operator and the area each controls$600
7.2.2Stormwater team and training proofNames, roles, who inspects, inspector training certificates (Part 6.3)$300
7.2.3Nature of construction activitiesProperty size; disturbed area to the nearest quarter acre; most area open at one time; schedule from clearing to removal of controls; pollutant sources; business hours$120 to $600 per item
7.2.4Site mapBoundaries, slopes, stockpiles, exits, receiving waters within 1 mile downstream, drainage before and after grading, control locations$600 with no map; $60 per missing feature
7.2.5Non-stormwater dischargesAuthorized ones that will occur, such as Part 1.2.2 discharges$600
7.2.6Stormwater control descriptionsEach control, its design specification, maintenance and install schedule$300 per missing control, capped at $900 per group
7.2.7Inspection and corrective actionInspection schedule, rain gauge or weather station, checklists$600; $120 per omission
7.2.8Turbidity monitoring (dewatering)Sampling procedures where Part 3.3 appliesPriced under dewatering items
7.2.9Species, historic, UIC recordsEndangered species, historic property and underground injection documentation$600 each
7.2.10Signed certificationSignature under Appendix G, Part G.11$600
7.2.11NOI, NeT letter, permit copyAdded after authorization$300 each
Diagram of the eleven SWPPP sections required by 2022 CGP Part 7.2What a 2022 CGP SWPPP must contain (Part 7.2)Written before the NOIAdded after authorization7.2.1All site operators7.2.2Stormwater team and training proof7.2.3Nature of construction activities7.2.4Site map7.2.5Non-stormwater discharges7.2.6Stormwater control descriptions7.2.7Inspection and corrective action7.2.8Turbidity monitoring (dewatering)7.2.9Species, historic, UIC records7.2.10Signed certification7.2.11NOI, NeT letter, permit copyThen keep current:inspection reports (24 h),corrective action log,edits within 7 days(Part 7.4), kept on siteor easily accessible(Part 7.3)
A 2022 CGP SWPPP has 11 sections: 7.2.1 to 7.2.10 are written before the NOI and 7.2.11 is added after authorization. Source: EPA 2022 CGP as modified April 2025, Part 7.2, accessed November 2, 2026.

After authorization the plan becomes a working file: inspection reports (24 h), corrective action log, edits within 7 days (Part 7.4), kept on site or easily accessible (Part 7.3). A missing on-site copy is a $600 item in the same EPA Region 8 settlement worksheet. Known hazardous materials such as PCBs and asbestos must be listed under Part 7.2.3, and the site history behind that list often comes from a Phase I environmental site assessment.

How often must you inspect, and how fast must problems be fixed?

Under CGP Part 4.2, a qualified person must inspect at least once every 7 calendar days, or once every 14 calendar days and within 24 hours of a storm producing 0.25 inches of rain in 24 hours. Routine maintenance must be finished by the close of the next business day, and a new or replacement control must be working within 7 calendar days of discovery.

EPA 2022 CGP Part 4.2 text with the 7-day and 14-day plus 0.25 inch storm inspection schedules boxed
EPA 2022 Construction General Permit, Part 4.2 (page 30): inspect every 7 calendar days, or every 14 days and within 24 hours of 0.25 inches of rain. Accessed November 2, 2026.
EventDeadlineCGP part
Before the NOIWrite and sign the SWPPP1.4.1, 7.1
NOI: 14+ days aheadAt least 14 calendar days before work in EPA areas; Florida 2 daysTable 1
Day 0: work startsPerimeter, exit and inlet controls in place where work begins2.1.3
Every 7 daysOr every 14 days and within 24 hours of 0.25 in of rain4.2
Impaired or Tier 2, 2.5 or 3 receiving waterEvery 7 days and within 24 hours of 0.25 in of rain4.3
Area fully stabilizedTwice in the first month, then monthly4.4.1
Inspection reportWithin 24 hours of the inspection4.7.1
Problem foundFix by next business day; new control or big repair within 7 days2.1.4, 5.2.1
Corrective action log entryWithin 24 hours of finding and of finishing5.4.1
SWPPP edits after a changeWithin 7 calendar days5.2.1, 7.4.1
Sediment tracked onto a paved roadRemoved by end of the same business day2.2.4
Work stops 14+ daysStart by next business day; stabilize within 14 days; 7 days if over 5 acres are open at one timeTable 2
NOT within 30 daysAfter final stabilization (70% cover) with photos8.2.1, 8.4
Timeline of 2022 EPA Construction General Permit deadlines from SWPPP to Notice of Termination1Before the NOIWrite and sign the SWPPP(CGP Parts 1.4.1, 7.1)2NOI: 14+ days aheadEPA areas; Florida 2 days(CGP Table 1)3Day 0: work startsPerimeter, exit and inletcontrols in place(CGP Part 2.1.3)4Every 7 daysor every 14 days andwithin 24 hours of0.25 in of rain5Problem foundFix by next business day;new control or big repairwithin 7 days6Work stops 14+ daysStabilize within 14 days;7 days if over 5 acresare open at one time7NOT within 30 daysAfter final stabilization(70% cover) with photos2022 EPA CGP deadlines, from plan to termination
Seven 2022 CGP deadlines run from the signed SWPPP and a 14-day NOI to an NOT within 30 days of final stabilization. Source: EPA 2022 CGP Parts 1.4, 2.1.3, 2.2.14, 4.2, 5.2 and 8.4; Florida DEP, accessed November 2, 2026.

Who counts as a qualified inspector?

For projects covered on or after February 17, 2023, the inspector must have passed EPA’s construction inspection course and exam, or hold a current certification that covers erosion and sediment control principles, installation and maintenance (CGP Part 6.3). Inspections are only required during normal working hours (Part 4.2, footnote 67), and a site on the 14-day schedule must name in its SWPPP the rain gauge or weather station that triggers storm inspections (Part 7.2.7).

How do the Notice of Intent and Notice of Termination work?

The NOI is the operator’s application for coverage, and the NOT ends it. In EPA areas both are filed in the NPDES eReporting Tool (NeT): the NOI at least 14 calendar days before work and only after the SWPPP is done, and the NOT within 30 calendar days of final stabilization. Coverage under the 2022 CGP ends at midnight on the day a complete NOT is submitted (Part 8.5).

  1. Confirm the permitting authority in CGP Appendix B and the size class; Texas splits small (1 to under 5 acres) and large (5 acres or more) sites.
  2. Complete and sign the SWPPP (Parts 7.1 and 7.2.10), form the stormwater team and finish inspector training (Part 6).
  3. File the NOI in NeT at cdx.epa.gov at least 14 calendar days before work; authorization starts 14 calendar days after EPA confirms a complete NOI (Table 1). Florida needs 2 days and a $250 or $400 fee.
  4. Post a sign visible from the nearest public road with the NPDES ID, a contact name and phone number, and how to get the SWPPP (Part 1.5).
  5. Add the NOI, the NeT acknowledgment letter and a copy of the permit to the SWPPP (Part 7.2.11).
  6. If the operator changes, the new operator files an NOI at least 14 days before the transfer and the old operator files an NOT (Part 1.4.4).
  7. At the end, reach final stabilization (70 percent of native vegetative cover, or permanent non-vegetative cover), remove temporary controls that are not biodegradable, take before and after photos, and file the NOT within 30 calendar days (Parts 8.2.1, 8.4). Florida’s deadline is 14 days after final stabilization.

Timing matters for long jobs: the 2022 CGP expires February 16, 2027, and the proposed 2027 CGP was noticed in the Federal Register on August 3, 2026, with comments due September 17, 2026 (EPA). Sites still under construction after expiry need coverage under the replacement permit (CGP Part 1.4.5). The NOT and its photos fit naturally into closeout, next to the paperwork for substantial completion.

Which BMPs does the CGP require, and what do they cost?

BMPs (best management practices) are the physical controls and housekeeping rules a SWPPP specifies. The CGP sets minimums: perimeter controls downslope, stabilized exits, inlet protection, stockpile barriers, sediment basins sized for 3,600 cubic feet per acre drained, leak-proof concrete washout and stabilization deadlines. Public bid prices from 2025 and 2026 show what each costs to install.

BMPCGP rulePublic price (scope, place, date)Source
Silt fence or other perimeter controlDownslope of disturbed soil; remove sediment at one-half of its height; ends turned upslope (2.2.3)$3.27 per LF average over 1,635,270 LF, Oklahoma highways, April 2025 to September 2026; $0.50 to $4.00 per LF installed, maintained and removed, Waller County MUD 69, Texas, September 2026ODOT item 221(B)2300; LJA tab 5454-2604
Stabilized construction exitEvery exit onto a paved road; track-out removed the same business day (2.2.4)$500 to $3,304 each, Waller County MUD 69, September 2026; $1,525 and $4,500 each, Plum Creek MD 1A, October 2026LJA 5454-2604; LJA 3301-3007
Inlet protectionAt inlets carrying site water; clear sediment same or next business day (2.2.10)$1 to $143 each for 50 Stage II inlets, Waller County MUD 69, September 2026LJA 5454-2604
Concrete washoutLeak-proof container or lined pit, away from inlets and waters (2.3.4)$827 to $11,215 each, Waller County MUD 69; $500 and $610 each, Plum Creek MD 1A, 2026LJA 3301-3007
Sediment basin2-year, 24-hour storm or 3,600 cubic feet per acre drained; surface outlet (2.2.12)$2,811.48 each average over 32 temporary basins, Oklahoma, 2025 to 2026ODOT item 221(D)2500
StabilizationStart by next business day once work stops 14+ days; final cover 70 percent (2.2.14)Seeding $1,726.20 per acre over 1,089.98 acres; solid slab sod $2.94 per SY, Oklahoma, 2025 to 2026ODOT items 232(B)9300, 230(A)7200
Natural buffer50-foot undisturbed buffer, or equivalent controls, for waters within 50 feet (2.2.1)Not bid as a line item; it holds a 50-foot strip out of the work areaCGP Part 2.2.1

The sediment basin in CGP Part 2.2.12 is a construction control: under Part 8.2.1 it comes out before the NOT unless it is kept for long-term use. Permanent post-construction detention or retention ponds are a separate design item set by local stormwater rules. Soil data for both designs can come from the geotechnical report.

How much does a SWPPP cost?

In 43 bids on 8 Texas utility district contracts opened between September 2 and October 8, 2026, the SWPPP compliance lump sum ran $100 to $9,600, median $1,508. Oklahoma DOT paid an average of $10,268.73 for SWPPP documentation and management across 192 lump-sum awards on state transportation contracts from April 2025 to September 2026. The controls themselves cost more than the paperwork.

In these Texas bid sets the SWPPP line pays the contractor to administer, maintain and remove controls shown on the engineer’s plans; the Pomona lift station line reads “to be maintained until contractor’s notice of termination is submitted.” The fee for writing the plan does not appear in these 8 tabulations, so ask the civil engineer to quote it as a separate line.

Project (bid opening)WorkBidsLowMedianHighLow base bidSource
Fort Bend County MUD 134C, Westmoor Court Sec. 2 (Sep 2, 2026)Water, sewer, drainage, paving11$150$1,000$3,250$2,931,350.30LJA 1680-114102A&B
Harris County MUD 539, Anniston Sec. 21 (Oct 7, 2026)Water, sewer, drainage9$500$1,500$3,366.47$732,000.00LJA 0390-2511
Brazoria County MUD 40, Pomona Commercial Area A (Sep 9, 2026)Water, sewer, drainage, paving6$1,200$1,745$3,239.84$1,017,160.78LJA 2149-3925
Waller County MUD 69, 11th Street utilities (Sep 22, 2026)Street and off-street utilities4$1,800$2,640$5,099$6,196,666.66LJA 5454-2604
Plum Creek MD 1A, commercial conveyance (Oct 8, 2026)Detention and drainage2$3,474$5,487$7,500$2,005,000.00LJA 3301-3007
Montgomery County MUD 113, Woodforest Sec. 110 (Sep 18, 2026)Water, sewer, drainage3$1,200$2,100$8,500$380,381.67LJA 1173-1114
Brazoria County MUD 40, Pomona lift station and WWTP (Sep 11, 2026)Lift station, 0.90 MGD plant4$500$1,125$9,600$926,148.00LJA 1840-5202
Harris County MUD 542, lift station generator (Oct 8, 2026)Generator install4$100$1,600$8,165.67$144,169.00LJA 2510-0023
Oklahoma DOT, 192 lump-sum awards (Apr 2025 to Sep 2026)SWPPP documentation and management192$1,750 (district-quarter average)$10,268.73 (average)$79,500 (district-quarter average)n/aODOT item 220 1100
What public owners paid for the SWPPP line, 2025 to 2026Bar chart: Oklahoma DOT averaged $10,268.73 per contract; Texas medians ran $1,000 to $5,487, pooled median $1,508.$ per contractOklahoma DOT, 192 lump-sum awards, average10,269Plum Creek MD 1A, detention and drainage, 5,487Waller County MUD 69, utilities, 4 bids2,640Montgomery County MUD 113, utilities, 3 bi2,100Brazoria County MUD 40, Pomona Commercial 1,745Harris County MUD 542, generator, 4 bids1,600All 43 Texas bids pooled1,508Harris County MUD 539, utilities, 9 bids1,500Brazoria County MUD 40, lift station and W1,125Fort Bend County MUD 134C, utilities and p1,000
The SWPPP compliance lump sum had a pooled median of $1,508 across 43 Texas bids in September and October 2026; Oklahoma DOT averaged $10,268.73 across 192 lump-sum awards. Sources: LJA bid tabulations, ODOT, accessed November 2, 2026.

Earlier tabulations land in the same band: Fort Bend County MUD 24 drew $1,313 and $3,500 in March 2025 (LJA 1931-124001), and MUD 213 drew $2,500 from both bidders in August 2025 for a line that included inspections, the NOI and the NOT (LJA 7777-1305G). Three 2026 tabs priced every SWPPP item, which shows the full cost of compliance.

ProjectAll SWPPP items, low bidderLow base bidSWPPP share (CB&C arithmetic)Largest item
Waller County MUD 69$8,856.00$6,196,666.66$8,856.00 / $6,196,666.66 = 0.14%9,412 LF silt fence, $4,706.00
Brazoria County MUD 40, Pomona Commercial Area A$4,796.78$1,017,160.78$4,796.78 / $1,017,160.78 = 0.47%Washout, $2,500.00
Plum Creek MD 1A$29,792.00$2,005,000.00$29,792.00 / $2,005,000.00 = 1.49%13,700 LF silt fence at $1.45, $19,865.00 (67%)

Silt fence footage moves the price most: at Plum Creek it was $19,865 of the $29,792 SWPPP group. Inspection frequency, project length and whether the line includes street sweeping and washout move the lump sum. Monthly pay applications show stormwater cost only if it has its own lines in the schedule of values. Check silt fence, exit and washout unit prices item by item when you compare construction bids.

What several guides say vs what the record shows

Three claims on pages that rank for SWPPP in November 2026 do not match the primary sources checked on November 2, 2026: an unsourced cost table, an outdated penalty figure, and a required section the 2022 CGP does not list for most sites. Each is described here without naming the publisher.

ClaimWhat a ranking page saysWhat the primary source saysSource
SWPPP costA form-hosting site dated June 2, 2026 lists $5,000 to $20,000 for a site under 1 acre and $20,000 to $100,000 for a mid-sized commercial site, with no sourceA stand-alone site under 1 acre needs no federal permit (CGP Part 1.1.2); public 2026 bids put the compliance line at $100 to $9,600 and all SWPPP items at 0.14% to 1.49% of the base bidLJA tabulations
Maximum penaltyA contractor software blog published January 8, 2025 cites $64,618 per violation per day$68,445 per day per violation for penalties assessed on or after January 8, 2025, and $66,712 for the year before40 CFR 19.4
Required partsA topic guide updated July 16, 2026 lists a sampling and analysis plan as a required componentPart 7.2 requires turbidity monitoring procedures only for dewatering sites under Part 3.3CGP Part 7.2.8

What are the penalties for SWPPP violations?

As of the January 8, 2025 inflation adjustment in 40 CFR 19.4, a court can impose up to $68,445 per day for each Clean Water Act violation, and EPA administrative penalties reach $342,218. Many construction cases settle far lower: EPA’s expedited settlement schedule prices a missing SWPPP at $6,000 and each missed inspection at $300.

RouteStatuteMaximum or scheduled amountSource
Civil judicial33 U.S.C. 1319(d)$68,445 per day per violation40 CFR 19.4, Table 1
Class I administrative33 U.S.C. 1319(g)(2)(A)$27,378 per violation, $68,445 total40 CFR 19.4
Class II administrative33 U.S.C. 1319(g)(2)(B)$27,378 per day, $342,218 total40 CFR 19.4
Expedited settlement: no SWPPP at inspectionCGP Part 7.1$6,000EPA 2023 construction ESA worksheet
Expedited settlement: SWPPP written after work startedCGP Part 7.1$1,000 per month, up to $6,000EPA ESA worksheet
Expedited settlement: discharge without coverageCWA 301$600 per monthEPA ESA worksheet
Expedited settlement: each missed inspectionCGP Parts 4.2 to 4.4$300EPA ESA worksheet
Expedited settlement: final stabilization not metCGP Part 2.2.14$1,200EPA ESA worksheet

One public example shows how the counts add up. EPA Region 8 inspected a 12.75-acre school construction site in Colorado Springs on April 11, 2024, and the settlement worksheet filed September 30, 2024 under docket CWA-08-2024-0013 totals $21,900: $16,200 for 27 dewatering violations at $600 each, $3,000 for 10 control-maintenance failures at $300 each, and smaller items for track-out, signage and report gaps (EPA Region 8 filing).

What should an owner put in the contract?

Owners settle 3 things before bid day: who files as operator, who writes and maintains the SWPPP, and how compliance is priced. The table pairs common situations with the action the permit text supports. The same stormwater scope then belongs in the bid form, the closeout checklist and the general conditions.

IfThenRule or record
The site disturbs 1 acre or more, or sits in a common plan of 1 acre or moreBudget for the SWPPP, NOI, inspections and NOT; require the plan before the NOICGP Parts 1.1.2, 1.4.1
The owner controls the plans and the GC runs the siteBoth file NOIs, or share a group SWPPP with written dutiesCGP Part 1.1.1; Part 7.1, footnote 84
The bid form has a single SWPPP lump sumAsk for silt fence per LF, exits, inlet protection and washouts as unit itemsPlum Creek: silt fence was $19,865 of $29,792
More than 5 acres will be open at one timePhase the grading or plan for 7-day stabilizationCGP Table 2
A receiving water is within 50 feet of disturbanceKeep a 50-foot natural buffer or design equivalent controlsCGP Part 2.2.1
The site drains to an impaired or Tier 2, 2.5 or 3 waterInspect every 7 days and after 0.25 in of rain; 7-day stabilizationCGP Parts 4.3, 2.2.14
Dewatering is plannedAdd turbidity monitoring; the benchmark is a 50 NTU weekly averageCGP Parts 3.3, 5.1.5
Work in an EPA area runs past February 16, 2027Plan to move coverage to the 2027 CGPCGP Part 1.4.5
Closeout is nearTie release of retainage to the NOT, photos and removal of controlsCGP Part 8.2.1

The closeout row works best when the contract ties the CGP Part 8.2.1 conditions to payment up front. How holdbacks are released is covered in our guide to retainage in construction. Local building and site permits are separate from the stormwater permit and are listed in our guide to commercial building permits.

Many sites also need a permanent stormwater pond after construction, explained in our retention pond guide.

How we compiled this

We read the EPA 2022 Construction General Permit as modified in April 2025 (Parts 1 to 8 and Appendix B), 40 CFR 19.4 and 122.26, an EPA Region 8 expedited settlement worksheet, three state program pages, Oklahoma DOT’s October 15, 2026 price report and 10 LJA Engineering bid tabulations: 21 primary documents, accessed November 2026. We excluded USAspending.gov SWPPP awards because they price industrial facility plans, not construction sites. No site visits or interviews; medians and shares are CB&C arithmetic.

Frequently asked questions

Who is responsible for the SWPPP on a construction site?

Every operator is responsible. Under EPA CGP Part 1.1.1 that is the party controlling the plans and specifications and the party with day-to-day control of the site, which can be both the owner and the general contractor. They may share one group SWPPP, but each remains liable if the other fails to act. Subcontractors generally are not operators.

Do I need a SWPPP for a project under 1 acre?

Only if the project is part of a larger common plan of development or sale that will disturb 1 acre or more in total, such as a pad site inside a retail center plan. A stand-alone project under 1 acre needs no federal construction stormwater permit, though city or county grading and erosion rules may still require an erosion control plan.

Is a SWPPP the same as an erosion control plan?

Not exactly. A SWPPP under CGP Part 7.2 covers erosion and sediment controls plus the operators, the stormwater team, pollution prevention for fuel, washout and waste, inspection procedures and permit records. Part 7.2.6 lets the SWPPP cite a local erosion and sediment control manual or ordinance as the design basis for each control, so the two documents often overlap.

How long must SWPPP records be kept?

Under the 2022 CGP, inspection reports and the corrective action log must be kept for at least 3 years (Parts 4.7.4 and 5.4.4). Inspection reports are due within 24 hours of each inspection, and corrective action entries within 24 hours of finding and of fixing the problem. Electronic copies count if they are as readable and accessible as paper.

Can a contractor write its own SWPPP?

Yes. EPA publishes a free Construction SWPPP Template in Word format aligned with the 2022 CGP, plus inspection report and corrective action log templates. The permit endorses no vendor (Part 7.1, footnote 85). Inspectors must still meet Part 6.3 training: the EPA construction inspection course and exam, or a current equivalent certification.

What changes when the 2022 Construction General Permit expires?

The 2022 CGP expires at 11:59 pm on February 16, 2027. EPA published the proposed 2027 CGP on August 3, 2026 and extended comments to September 17, 2026. Sites still under construction in EPA areas after expiry must obtain coverage under the replacement permit (Part 1.4.5), so long projects should budget a fresh NOI and SWPPP review.

Sources

All sources below were accessed on November 2, 2026, except the two 2025 LJA tabulations, accessed November 1, 2026.

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.

← Back to all articles