Payment Bond: Who Can Claim, Miller Act and State Deadlines, and What It Costs

Concrete-frame public building under construction with material pallets and a boom lift behind a fence

A payment bond is a surety’s guarantee that the contractor will pay its subcontractors, laborers and suppliers; if it does not, an unpaid claimant collects from the surety, up to the bond amount, usually 100% of the contract price.

Key takeaways

  • Federal construction contracts over $150,000 need a payment bond equal to 100% of the original contract price under FAR 28.102-2; the Miller Act text, 40 U.S.C. 3131, still reads more than $100,000.
  • From $35,000 to $150,000, a federal contracting officer picks two or more payment protections, such as a payment bond or an irrevocable letter of credit, under FAR 28.102-1(b).
  • A sub-subcontractor or a supplier to a subcontractor on a federal job must give the prime written notice within 90 days of its last work and sue within 1 year, under 40 U.S.C. 3133(b).
  • State Little Miller Act notice windows in our sample run from 90 days (Virginia, Florida, Arizona) to 120 days (New York State Finance Law 137) and 180 days (ORS 279C.605, Oregon); Texas counts in months.
  • Public bid records from 2014 to 2018 priced the combined payment and performance bond at 0.10% to 1.77% of the bid (Transbay Joint Powers Authority, City of Longview, Texas).

What does a payment bond guarantee, and who are the parties?

A payment bond guarantees that people who supply labor, materials and equipment to the job get paid. The contractor (principal) and the surety bind themselves to the owner (obligee), and the claimants are the subcontractors and suppliers. On federal work the bond is Standard Form 25A (Rev. 10/2023); on private and many public jobs it is the AIA A312-2010 Payment Bond.

RoleWho it isWhat the bond does for itSource
PrincipalThe prime contractorBuys the bond and is bound jointly and severally with the surety to pay for labor, materials and equipmentA312-2010 Section 1; 40 U.S.C. 3131(b)
SuretyAn insurance company; federal bonds need one of the 249 companies on Treasury Circular 570 (effective Aug. 1, 2026)Pays valid claims up to the penal sumFAR 52.228-15(d)
ObligeeThe project ownerKeeps unpaid trades off its property and out of its budget; under A312-2010 the surety must defend and indemnify the owner against those claims (Sections 3 and 4)AIA A312-2010
ClaimantSubcontractors, sub-subcontractors, suppliers, laborers; under A312-2010 also equipment rental, utilities and design servicesGets a right to sue the surety instead of liening public propertyA312-2010 Section 16.2; 40 U.S.C. 3133(b)

The bond amount is usually the full contract price. Federal law sets the payment bond at the total amount payable under the contract unless the contracting officer finds in writing that this is impractical, and never less than the performance bond (40 U.S.C. 3131(b)(2)). California sets it at not less than 100% of the total payable (Cal. Civ. Code 9550 to 9554), and Texas at the contract amount (Gov’t Code 2253.021(c)).

The bond does not protect the owner against a contractor that stops work; that is the job of the performance bond, compared side by side in our performance bond guide. This page summarizes statutes, regulations, bond forms and bid records checked in November 2026. It is not legal advice: the bond attached to your contract and the statute in your state control, and a construction attorney can apply them to your claim.

Who can claim on a payment bond?

On a federal job, anyone with a direct contract with the prime contractor or with one of its subcontractors can claim. That covers first-tier subcontractors and suppliers, plus sub-subcontractors and suppliers to subcontractors, who must also give the 90-day notice. Someone further down, such as a supplier to a supplier, has no direct contract with either and falls outside the text of 40 U.S.C. 3133(b).

Who can claim on a federal payment bond Tier diagram. Owner (obligee) contracts with the prime contractor (principal), whose surety issues the payment bond. First tier: subcontractors and suppliers with a direct contract with the prime, claim after 90 days unpaid, no notice needed. Second tier: anyone with a direct contract with a subcontractor, written notice to the prime within 90 days. Third tier and below: no direct contract with the prime or a subcontractor, outside the text of 40 U.S.C. 3133(b). Owner (obligee) federal agency on a Miller Act job Prime contractor principal on the bond Surety issues SF 25A payment bond Tier 1: covered Subcontractors and suppliers with a direct contract with the prime No notice needed; may sue once unpaid 90 days after last labor or material (3133(b)(1)) Tier 2: covered with notice Anyone with a direct contract with a subcontractor (sub-subcontractor or supplier) Written notice to the prime within 90 days, third-party verified delivery (3133(b)(2)) Tier 3 and below: outside the statute text No direct contract with the prime or a subcontractor, for example a supplier to a supplier
On a federal job, tier 1 claimants sue once unpaid 90 days, tier 2 claimants must also give the prime notice within 90 days, and tier 3 falls outside the statute text. Source: 40 U.S.C. 3133(b), accessed 2026-11-15.
ClaimantFederal (Miller Act)AIA A312-2010 (private)Texas public work
Subcontractor or supplier with a contract with the primeCovered; sue once unpaid 90 days after last workCovered; send a Claim to the surety (Section 5.2)Covered; claim notice to prime and surety by the 15th day of the third month (2253.041)
Sub-subcontractor or supplier to a subcontractorCovered; written notice to prime within 90 daysCovered; notice of non-payment to the contractor within 90 days, then a Claim (Section 5.1)Covered; adds a second-month notice to the prime (2253.047)
Supplier to a supplier, or a sub of a sub-subcontractorOutside the statute text (no direct contract with the prime or a subcontractor)Covered only if it rightfully asserted a mechanic’s lien claim (Section 16.2)Outside the statute text: beneficiaries need a direct contract with the prime or a subcontractor (2253.021(c))
Laborer employed by the prime or a subCoveredCovered (Section 5.2 for the contractor’s employees)Covered; the 2253.047 notice does not apply to an individual claiming wages

Whether a given company counts as a “subcontractor” or only a “supplier” is decided by courts on the facts of each job, so the tier test can be closer than the table suggests. The federal statute and the Virginia statute (Va. Code 2.2-4341(B)) use the same direct-contract wording, which is why the 90-day notice applies only to the second tier.

What does the Miller Act require?

The Miller Act, now 40 U.S.C. 3131 to 3134, requires a performance bond and a payment bond before award of a federal construction contract. The statute says more than $100,000; the Federal Acquisition Regulation applies $150,000 as amended through FAC 2026-01, and from $35,000 to $150,000 it requires alternative payment protection. The bonds are delivered before work starts (FAR 52.228-15(c)).

Contract value (federal construction)Payment protection requiredAmountSource
$35,000 or lessNone required by FAR 28.102Not applicableFAR 28.102-1
Over $35,000 to $150,000Contracting officer selects two or more of: payment bond, irrevocable letter of credit, tripartite escrow, certificates of deposit, 28.204 securities; contractor furnishes one100% of the original contract price plus 100% of increasesFAR 28.102-1(b); 28.102-2(c)
Over $150,000Payment bond (SF 25A) and performance bond (SF 25)100% of the original contract price plus 100% of increases; payment bond never below the performance bondFAR 28.102-2(b)
Statute textBonds on contracts over $100,000; alternatives over $25,000 up to $100,000Total amount payable by the contract40 U.S.C. 3131; 3132
WaiversWork in a foreign country; certain cost-type and vessel contracts of the military departments, Transportation and CommerceNot applicable3131(d); 40 U.S.C. 3134

What must a Miller Act notice say, and how is it served?

A second-tier claimant’s notice must reach the prime within 90 days of its last labor or material, state the amount claimed “with substantial accuracy” and name the party it supplied or worked for (40 U.S.C. 3133(b)(2)). It must be served by any means that gives written third-party verification of delivery, such as certified mail or a courier signature, or the way a U.S. marshal serves a summons.

  1. Name of the claimant and of the party it furnished labor or material to.
  2. Amount claimed, stated with substantial accuracy.
  3. Delivery to the prime at any office or place of business, or its residence, with third-party proof of delivery.
  4. Timing: counted from the last day of labor or material for which the claim is made, not from invoice or due dates.

Where and when must a Miller Act suit be filed?

A Miller Act suit must be filed within 1 year after the claimant’s last labor or material, in the U.S. District Court for the district where the contract was performed, regardless of the amount (40 U.S.C. 3133(b)(3), (4)). It is filed in the name of the United States for the use of the claimant, and the Government pays none of its costs (3133(b)(5)).

A waiver of the right to sue is void unless it is in writing, signed by the claimant and executed after the claimant furnished the work (3133(c)), so a waiver clause signed in a subcontract before work starts does not bar a Miller Act claim. How waivers travel with progress payments is explained in our lien waiver guide. Federal agencies also may not withhold progress payments because subs are unpaid; after completion, on the surety’s written notice, the contracting officer withholds final payment (FAR 28.106-7).

What are the Little Miller Act payment bond rules by state?

States set their own payment bond statutes for public work, called Little Miller Acts, because mechanics liens generally cannot attach to public property. Thresholds in the eight jurisdictions we read run from $25,000 (California, Texas) to $500,000 (Virginia), and lower-tier notice windows from 90 to 180 days. The table links each statute; local rules and agency specs can add bonds below these floors.

JurisdictionPayment bond required on contractsNotice from a claimant without a contract with the primeDeadline to sueStatute (read Nov. 2026)
FederalOver $150,000 (FAR); over $100,000 (statute text)Written notice to the prime within 90 days of last work1 year after last work, U.S. District Court40 U.S.C. 3133
ArizonaCovered public contracts under 34-222(A), at the full contract amount; NASBP lists $100,000 (non-highway)Preliminary 20-day notice plus a 90-day notice with third-party verified delivery1 year after last workA.R.S. 34-222; 34-223
CaliforniaOver $25,000 (not state entities)Preliminary notice to the public entity and direct contractor (9300); if missed, notice to surety and principal within 15 days after a recorded notice of completion, or 75 days after completionNo later than 6 months after the stop payment notice period endsCiv. Code 9550; 9300; 9560; 9558
FloridaOver $100,000 on state contracts; local owners may exempt $200,000 or lessNotice to the contractor within 45 days of starting; sworn notice of nonpayment from day 45 after first furnishing to 90 days after final furnishing1 year after last labor or deliveryFla. Stat. 255.05
New York (state)Required; may be dispensed with under $100,000Written notice within 120 days of last work, personally or by registered mail1 year after the public owner completes and accepts the workState Finance Law 137
OregonOver $100,000 ($50,000 transportation)Every claimant: notice of claim within 180 days, registered or certified mail or hand delivery2 years after last workORS 279C.380, 279C.600 to 279C.610
TexasOver $25,000; over $50,000 for a cityEvery claimant: notice of claim to prime and surety by the 15th day of the third month after each month of work; lower tiers also a second-month notice to the primeFrom the 61st day after the notice to 1 year after it was mailedGov’t Code 2253.021, .041, .047, .073, .078
VirginiaOver $500,000 ($350,000 state-funded transportation)Written notice within 90 days by registered or certified mail; retainage claims exempt from that limit1 year after last workVa. Code 2.2-4337; 2.2-4341
Lower-tier notice windows run 90 to 180 daysBar chart: notice windows of 180 days in Oregon, 120 in New York, 90 federal and in Virginia, Arizona and Florida, 89 in a Texas example.daysOregon (ORS 279C.605)180New York (State Finance Law 137)120Federal (40 U.S.C. 3133)90.0Virginia (2.2-4341)90.0Arizona (34-223)90.0Florida (255.05, notice of nonpayment)90.0Texas, March 18 delivery (15th day of thir89.0
A claimant without a contract with the prime has 90 days to give notice on federal, Virginia, Arizona and Florida public jobs, 120 in New York and 180 in Oregon; Texas counts by month. Sources: statutes listed, accessed 2026-11-15.

The National Association of Surety Bond Producers’ survey of state bond thresholds (January 1, 2024) lists the other states, from $1,000 on some highway work to $500,000; it names Ohio and West Virginia as having no threshold. Treat that list as a pointer to the statute, not a substitute. A threshold table for federal work and 10 states, with Circular 570 surety counts, is in our construction surety bond statistics.

Payment bonds start at $25,000 in California and Texas, $500,000 in VirginiaBar chart: payment bond thresholds of $500,000 in Virginia, $150,000 federal, $100,000 in Florida, New York and Oregon, $25,000 in Texas and California.$ thousandsVirginia, nontransportation500Federal, FAR 28.102-1150Federal, statute text (40 U.S.C. 3131)100Florida, state contracts100New York, state (may be dispensed with bel100Oregon, non-transportation100Texas, cities50.0Texas, other public bodies25.0California, local public works25.0
Public payment bond thresholds in the jurisdictions read run from $25,000 (California, Texas) to $500,000 (Virginia nontransportation); federal work applies $150,000. Sources: statutes and FAR 28.102-1, accessed 2026-11-15.

How do payment bonds work on private jobs?

No statute read for this page makes a private owner require a payment bond; the owner’s contract, its lender or the GC’s subcontract does, usually naming the AIA A312-2010 form. On those jobs the bond’s own text sets the claim steps: a 90-day notice for lower tiers, a 60-day surety answer and a 1-year suit limit, with any conflicting statute reading in under Section 14.

  1. Get the bond: Section 15 makes the contractor and owner furnish a copy to any potential beneficiary who asks.
  2. Notice (no direct contract with the contractor): written notice of non-payment to the contractor within 90 days after last labor or materials, stating the amount and whom you supplied (Section 5.1.1). An owner’s notice also counts (Section 6).
  3. Claim to the surety at the address on its signature page (Sections 5.1.2, 5.2, 13), with the eight items in Section 16.1: your name, who you supplied, the contract or purchase order, a description, your last work date, total earned, payments received and amount unpaid.
  4. Surety answer: within 60 days after receiving the Claim, stating undisputed amounts and the basis for disputing the rest, and paying the undisputed amounts (Sections 7.1, 7.2). If it fails, it owes your reasonable attorney’s fees from then on (Section 7.3).
  5. Suit: in a court in the state where the project sits, within 1 year of the earlier of your Claim date or the last labor or materials furnished by anyone under the contract (Section 12).

The 1-year clock in Section 12 can start before your own Claim if the project finishes first, so a supplier who claims late in a job may have less than a year. Section 10 adds that the owner has no obligation to claimants under the bond. Where A312 sits among the other AIA forms is covered in our AIA contract documents guide.

Florida gives private owners a statutory reason to bond: a payment bond of at least the original contract price, attached to the recorded notice of commencement, exempts the owner from liens under Fla. Stat. 713.23, with the same 45-day and 90-day notices and a 1-year suit limit. The recording steps are in our Florida notice of commencement guide.

How does a payment bond claim work, step by step?

Every regime above follows the same order: get the bond, date your last work, serve the notice inside the window, send the claim to the surety, wait out the response period, then sue before the limit. The worked example uses one supplier whose last delivery was Wednesday, March 18, 2026, counted in calendar days with Python’s date library.

  1. Request the bond and the surety’s name and address. Federal: the contracting officer furnishes the surety name, penal amount and a copy on request (FAR 28.106-6), and a certified copy on an affidavit of nonpayment (40 U.S.C. 3133(a)). Texas bonds must print the surety’s notice address (2253.021(f)).
  2. Fix your last-work date from delivery tickets or daily logs; every federal, Arizona, Virginia and Oregon clock runs from it.
  3. Serve notice by a tracked method: third-party verified delivery (federal, Arizona), registered or certified mail (Virginia, Oregon), or mail to the prime and surety with a sworn statement of account (Texas 2253.041).
  4. Send the claim with the contract or purchase order, invoices, payments received and the unpaid balance.
  5. Track the response period: 60 days for an A312-2010 surety answer; in Texas, suit opens on the 61st day after the notice (2253.073).
  6. Sue before the limit, in the right court: U.S. District Court for federal jobs; state court where the project sits under A312-2010.
StepFederal (Miller Act)Texas public workPrivate, AIA A312-2010
Last deliveryMar 18, 2026March 2026 deliveriesMar 18, 2026
Early noticeNot requiredSecond-month notice to prime by May 15, 2026 (2253.047)Not required
Notice deadlineJun 16, 2026 (day 90)Claim notice to prime and surety by Jun 15, 2026 (2253.041)Notice of non-payment by Jun 16, 2026; claim sent Jun 10, 2026 in this example
Earliest suitJun 17, 2026 (unpaid after 90 days)Aug 15, 2026 (61st day after Jun 15 notice)After the surety’s answer, due Aug 9, 2026 (60 days)
Last day to sueMar 18, 2027Jun 15, 2027Jun 10, 2027, or earlier if the last work by anyone on the contract came before the claim
Rule40 U.S.C. 3133(b)Gov’t Code 2253.041, .047, .073, .078A312-2010 Sections 5, 7, 12
Worked payment bond claim dates for one unpaid supplier Three timelines for a supplier whose last delivery was March 18, 2026. Federal Miller Act: notice by June 16, 2026, suit from June 17, 2026 until March 18, 2027. Texas public work: second-month notice May 15, 2026, claim notice June 15, 2026, suit from August 15, 2026 until June 15, 2027. Private AIA A312-2010 bond: claim sent June 10, 2026, surety answer due August 9, 2026, suit by June 10, 2027 at the latest. Second-tier supplier, last delivery Wednesday, March 18, 2026 Federal job, Miller Act (40 U.S.C. 3133) Mar 18, 2026 last delivery Jun 16, 2026 day 90: notice to prime Jun 17: suit may start Mar 18, 2027 1-year suit deadline Texas public work (Gov’t Code ch. 2253), March deliveries Mar 2026 work month May 15 2nd-month notice to prime (.047) Jun 15 claim notice to prime and surety (.041) Aug 15 61st day: suit may start (.073) Jun 15, 2027 1 year after notice mailed (.078) Private job, AIA A312-2010 Payment Bond Mar 18, 2026 last delivery Jun 10, 2026 notice + Claim (s.5.1) Aug 9, 2026 surety answer (s.7.1) Jun 10, 2027 latest suit date (s.12) Dates are a worked example counted with calendar days; check the bond and statute on your job.
For a supplier whose last delivery was March 18, 2026: federal notice by June 16, 2026 and suit by March 18, 2027; Texas claim notice by June 15, 2026 and suit by June 15, 2027; A312 surety answer by August 9, 2026. Sources: 40 U.S.C. 3133; Tex. Gov’t Code 2253; AIA A312-2010.

The same delivery would give the supplier until July 16, 2026 to notify under New York’s 120-day rule and until September 14, 2026 under Oregon’s 180-day rule, with an Oregon suit due by March 18, 2028. If the supplier is also owed retainage, Virginia exempts retainage claims from its 90-day notice (2.2-4341(B)); how retainage is held and released is covered in our retainage guide.

How much does a payment bond cost?

Public bid records price the payment bond together with the performance bond as one line: 0.10% to 1.77% of the bid on 10 priced lines from 2014 to 2018, and 0.80% on a 2018 school GMP. The Congressional Research Service (R42037, July 2025) cites 1.5% to 3.0% of the contract amount. The contractor pays the premium and prices it into its bid.

Public recordDateBid or GMPPayment and performance bond lineRateSource
Transbay Joint Powers Authority (TJPA), structural concrete, two biddersFeb 11, 2014$48,174,750; $78,741,515$289,049; $787,4150.60%; 1.00%TJPA TG07.2 tab
TJPA, fireproofing, three biddersSep 18, 2014$8,594,839; $8,908,096; $7,253,160$64,461; $8,908; $87,0380.75%; 0.10%; 1.20%TJPA TG16.8 tab
TJPA, miscellaneous metalsJan 22, 2015$11,528,241$115,2821.00%TJPA TG07.3 tab
City of Longview, Texas, street striping, four bidsJul 25, 2018$68,224.72 to $169,290.48$705 to $3,0000.93% to 1.77% (our arithmetic)Bid 1718-25 tab
Henderson County, North Carolina, Edneyville Elementary GMPApr 2018$21,852,605$174,821; subcontractor bonds a further $235,933 at 1.25%0.80%Board packet

The small Longview bids, all under $170,000, ran 0.93% to 1.77%, while the TJPA bids above $7 million mostly ran 0.60% to 1.20%, consistent with rates falling as contract size rises (our reading of a small sample). If the SBA Surety Bond Guarantee Program backs the bonds, on contracts up to $9 million or $14 million federal, the contractor also pays SBA 0.6% of the contract price.

Line on a $2,000,000 public contractRateAmountSource
Bond premium at the TJPA low rate0.60%$12,000TJPA TG07.2, 2014
At the Henderson County GMP rate0.80%$16,000Henderson County, 2018
At 1.00%1.00%$20,000TJPA TG07.3, 2015
At the Longview high rate1.77%$35,400Longview, 2018
At the top of the CRS range3.0%$60,000CRS R42037, 2025
SBA contractor fee, if SBA guarantees the bonds0.6% of contract price$12,000SBA
$200,000 change order: added bond amount, federal job100% of the increase$200,000FAR 28.102-2(b)(2)
Added premium on that change at 1.00%1.00%$2,000Rate from TJPA TG07.3

Seller pages that call the payment bond free when bundled describe the same thing the bid tabs show: one premium covers both bonds. Where only a payment bond is required, such as a Texas county job between $25,000 and $100,000 (2253.021), it is priced on its own. Bid security comes earlier and is covered in our bid bond guide.

Payment bond vs performance bond vs mechanics lien: what is the difference?

A payment bond protects the people who supply the job; a performance bond protects the owner if the work is not finished; a mechanics lien is the unpaid trade’s claim against private property itself. On public work the payment bond replaces the lien, and on a bonded Florida private job it can replace it too (Fla. Stat. 713.23).

ItemPayment bondPerformance bondMechanics lien
ProtectsSubs, suppliers, laborersThe ownerThe unpaid claimant, secured by the property
Who claimsClaimants by tier (40 U.S.C. 3133(b); A312-2010 Section 16.2)Only the owner (A312-2010 Performance Bond Section 9)Claimants who meet the state lien statute
Public propertyYes, the usual remedyYesGenerally no
Federal amount100% of original price, never below the performance bond100% of original priceNot available
Typical suit limit1 year (federal, A312); 2 years (Oregon)2 years under A312-2010 Section 11Set by state; filing deadlines in our mechanics lien laws by state report

Which payment bond rule applies to your project?

Start with who owns the project, then the contract value, then your tier. The table pairs common situations with the rule, its deadline and its source. Where no statute applies, the bond attached to the contract decides, so read its notice and suit clauses before relying on any row.

IfThenRule
Federal construction contract over $150,000Miller Act bond (SF 25A) at 100%; tier 2 notice in 90 days, suit within 1 yearFAR 28.102-1; 40 U.S.C. 3133
Federal contract over $35,000 up to $150,000Bond or alternative, such as a letter of credit; ask the contracting officer which one was furnishedFAR 28.102-1(b)
State or local public jobThat state’s Little Miller Act; thresholds $25,000 to $500,000 and lower-tier notice 90 to 180 days in our sampleState table above
Texas public jobMonthly notices: 15th day of the second and third month after each month of workGov’t Code 2253.041, .047
Private job with a bond in the contractThe bond form; under AIA A312-2010: notice 90 days, answer 60 days, suit within 1 yearA312-2010 Sections 5, 7, 12
Private job with no bondMechanics lien on the property, by state statuteState lien deadlines
Asked to sign a bond-rights waiver before starting work on a federal jobVoid unless written, signed and executed after you furnished the work40 U.S.C. 3133(c)
Owner of a private Florida job that wants lien protectionRequire a bond of at least the contract price and attach it to the notice of commencementFla. Stat. 713.23
Which payment bond rule applies Decision flowchart. Federal construction contract over $150,000: Miller Act payment bond, 90-day notice and 1-year suit. Federal contract from $35,000 to $150,000: alternative payment protection, ask the contracting officer which. State or local public job: that state’s Little Miller Act statute. Private job with a payment bond: the bond form, such as AIA A312-2010, 90-day notice, 60-day answer, 1-year suit. Private job with no bond: mechanics lien statute. Who owns the project? Federal agency State or local body Private owner Over $150,000 Miller Act bond (SF 25A) tier 2: notice in 90 days suit within 1 year if smaller $35,000 to $150,000 bond or alternative, such as a letter of credit (FAR 28.102-1) Little Miller Act thresholds $25,000 to $500,000 lower-tier notice 90 to 180 days (Texas: monthly notices) Bond in the contract AIA A312-2010: notice 90 days answer 60 days suit within 1 year if none No bond mechanics lien on the property, by state statute First step on every bonded job: get a copy of the bond and the surety’s address 40 U.S.C. 3133(a) and FAR 28.106-6 (federal); A312-2010 Section 15 (private); Tex. Gov’t Code 2253.021(f)
Owner type and contract value decide the rule: Miller Act over $150,000, alternatives from $35,000, a state Little Miller Act, the bond form on private jobs, or a lien where there is no bond. Sources: FAR 28.102-1; 40 U.S.C. 3133; AIA A312-2010.

Most owners require it together with a performance bond, and subs on private jobs rely on lien waivers instead.

How we compiled this

We read 33 documents: four Miller Act sections, five FAR sections and the SF 25A form page, the AIA A312-2010 text, 14 statute sections from seven states, an industry threshold survey, five public bid records, a CRS report, the SBA program page and Treasury Circular 570, mostly on November 15, 2026 and the rest on November 2 and October 18. Seller-site premium figures and case law we did not read were left out. Bid-tab rates, the cost example and the dates are our arithmetic, under our editorial standards.

Frequently asked questions

Who pays for a payment bond?

The prime contractor buys the bond and pays the premium, then builds it into its price, so the owner pays through the contract sum. Public bid tabs show it as one line with the performance bond: 0.60% to 1.20% on Transbay Joint Powers Authority bids from 2014 to 2015 and 0.80% on Henderson County, North Carolina’s 2018 school GMP. If SBA guarantees the bond, the contractor also pays SBA 0.6% of the contract price.

How long do you have to file a Miller Act claim?

A supplier or sub-subcontractor without a contract with the prime must give the prime written notice within 90 days of its last labor or material. Any claimant must sue within 1 year after its last labor or material, in the U.S. District Court where the contract was performed, under 40 U.S.C. 3133(b). A first-tier claimant needs no notice but can sue only once 90 days pass unpaid.

Can a third-tier supplier claim on a payment bond?

On a federal job, 40 U.S.C. 3133(b) gives a right of action only to people with a direct contract with the prime or with a subcontractor, so a supplier to a supplier falls outside the text. Under the AIA A312-2010 private form, Section 16.2 adds anyone who rightfully asserted a mechanic’s lien claim, so a lower-tier claimant with lien rights may still qualify.

Is a payment bond required on private projects?

No statute read for this page makes a private owner require one; the contract, the lender or the GC’s subcontract does. Florida gives owners a reason: under Fla. Stat. 713.23, a payment bond of at least the original contract price, attached to the recorded notice of commencement, exempts the owner from liens, and claimants then follow 45-day and 90-day notices and a 1-year suit limit.

Can you sue the owner on a payment bond?

Generally no. The federal statute makes the Government liable for none of the costs of a Miller Act suit (40 U.S.C. 3133(b)(5)), Texas says the state is not liable for costs (Gov’t Code 2253.072), and AIA A312-2010 Section 10 says the owner has no obligations to claimants under the bond. The claim runs against the contractor and its surety, up to the bond amount.

How long does a surety have to answer a payment bond claim?

Under the AIA A312-2010 Payment Bond, the surety must answer within 60 days after receiving the Claim, stating undisputed amounts and the basis for disputing the rest, and pay the undisputed amounts (Sections 7.1 and 7.2). If it misses that duty, Section 7.3 makes it pay the claimant’s reasonable attorney’s fees incurred afterward. Texas lets the claimant sue if unpaid before the 61st day after notice.