Office building construction cost for a new, fully built private office in Texas ran a median $190 per square foot in October 2026 dollars, with the middle half at $132 to $269, across 356 state registrations from 2024 to 2026.
Key takeaways
- Private, fully built new offices registered with Texas from January 2024 to November 2026 had a median filed cost of $175 per square foot, or $190 after escalation with the BLS office-building price index (n=356, TDLR TABS project registrations).
- Shell and core-and-shell office buildings, delivered without tenant interiors, ran a median $124 per square foot in October 2026 dollars (n=93), about $66 less than fully built.
- Two-story private offices ran a median $255 per square foot against $192 for one-story offices, in the 27 and 41 filings whose scope stated the story count.
- Public office buildings (county, state and school district) ran a median $475 per square foot (n=33), 2.5 times the private median.
- New office building prices rose 5.4% from October 2025 to October 2026 on the BLS producer price index for new office building construction (series PCU236223236223, October 2026 preliminary).
How much does it cost to build an office building per square foot?
A new office building costs about $130 to $270 per square foot for the building alone in Texas, with a median of $190, based on 356 private, fully built projects registered with the Texas Department of Licensing and Regulation (TDLR) from January 2024 to November 2026 and escalated to October 2026. Land, design fees, furniture and financing are extra.
Texas requires owners to register any building or facility project of $50,000 or more for an accessibility review, per the TDLR Architectural Barriers FAQ, and the public record shows the owner’s estimated construction cost, the square footage, dates and a scope line. Those figures are owner and architect estimates at registration, not audited final costs. The table uses private new construction only; shells, renovations and finish-outs are counted separately.
| Building size (gross sq ft) | Projects | Median $/sq ft (Oct 2026 $) | Middle half $/sq ft | Median total cost (as filed) | Median schedule |
|---|---|---|---|---|---|
| 1,000 to 4,999 | 193 | $197 | $133 to $269 | $525,000 | 8 months |
| 5,000 to 9,999 | 84 | $190 | $148 to $278 | $1,225,000 | 10 months |
| 10,000 to 24,999 | 57 | $171 | $106 to $259 | $2,275,000 | 11 months |
| 25,000 and up | 22 | $168 | $119 to $242 | $5,712,500 | 14 months |
| All private, fully built | 356 | $190 | $132 to $269 | $900,000 | 9 months |
The per-foot price falls with size: offices of 25,000 square feet and up came in $29 per square foot below the smallest band at the median, because restrooms, mechanical rooms, stairs and the entry are spread over more floor area. For the national, all-building-type view, our commercial construction cost per square foot guide compares offices with warehouses, hospitals and retail.
How much more does a two-story or mid-rise office cost?
Going from one story to two raised the Texas median from $192 to $255 per square foot in October 2026 dollars, about 33% more, in filings that stated the story count. Two-story offices need stairs, a second-floor structure, more fire separation and often an elevator, and a smaller roof and slab do not offset that on buildings under about 30,000 square feet.
| Height | Private filings | Median $/sq ft (Oct 2026 $) | Middle half | Median schedule | Typical construction type |
|---|---|---|---|---|---|
| 1 story | 41 | $192 | $122 to $278 | 10 months | Type V wood or pre-engineered metal |
| 2 stories | 27 | $255 | $165 to $313 | 12 months | Type V wood, Type II-B steel or tilt-wall |
| 3 to 4 stories | 4 | $278 | $214 to $337 | 13 months | Type II-B or Type IB steel or concrete |
With only 4 mid-rise filings, named projects are a better guide: a 4-story, 71,000 sq ft division office in Montgomery County filed at $25,000,000 ($352 per sq ft, TABS2026025482), a 3-story, 40,520 sq ft headquarters in Fort Bend County at $12,000,000 ($296, TABS2024008849) and a 3-story, 36,940 sq ft multi-tenant office in Ellis County at $8,400,000 ($227, TABS2027003564). A 17-level, 458,000 sq ft core-and-shell tower in Dallas County filed at $110,000,000, or $240 per sq ft before tenant interiors (TABS2025022562).
Structure is the reason mid-rise costs more. The GSA Unit Cost Study, Shell and Core: Office Building models its low-rise office as sprinklered Type IIIA construction on spread footings, and its mid-rise and high-rise offices as Type IB with a 2-hour structural frame on deep foundations, because at an allowable soil bearing pressure of 2 tons per sq ft there was no feasible spread-footing design for the taller buildings. Order a geotechnical report before pricing anything above two stories.
What do shell, core and shell, and fully built include?
A shell is the structure, roof, exterior walls and utility stubs with no finished interior. Core and shell adds the lobby, stairs, elevators, restrooms, central HVAC, main electrical and sprinklers. Fully built adds the tenant interiors: offices, ceilings, lighting and finishes. Texas shell and core-and-shell filings ran a median $124 per square foot, against $190 fully built.
| Scope delivered | Private filings | Median $/sq ft (Oct 2026 $) | Middle half | Median size | What still has to be paid for |
|---|---|---|---|---|---|
| Shell or core and shell (scope says “shell”) | 93 | $124 | $89 to $163 | 5,445 sq ft | Tenant interiors, usually through a TI allowance |
| Fully built | 356 | $190 | $132 to $269 | 4,684 sq ft | Furniture, IT, signage, move |
| Difference | $66 | Roughly what interiors added in these filings |
The GSA core-and-shell definition also counts a site improvement allowance, central plant, standpipe and sprinkler system and finished ceilings and lighting in common areas. Developers of multi-tenant buildings usually stop at core and shell and fund interiors suite by suite. If you are leasing rather than building, our tenant improvement allowance guide shows how that interior money is split, and our office renovation cost guide covers rebuilding an existing suite.
What does a new office cost in Dallas, New York or San Francisco?
Outside Texas, the best free city benchmark is the Rider Levett Bucknall Quarterly Construction Cost Report, Q3 2026, which lists hard construction cost per square foot of gross floor area for prime and secondary offices in 18 U.S. cities. Secondary offices run $165 to $240 in Dallas and $380 to $600 in San Francisco; prime offices top out at $1,010 in New York.
| City | Prime office $/sq ft | Secondary office $/sq ft | Source |
|---|---|---|---|
| Austin | $260 to $435 | $170 to $235 | RLB Q3 2026, hard cost per sq ft of gross floor area |
| Boston | $470 to $745 | $290 to $435 | |
| Charlotte | $370 to $615 | $265 to $370 | |
| Chicago | $360 to $585 | $220 to $355 | |
| Dallas | $265 to $445 | $165 to $240 | |
| Denver | $350 to $575 | $250 to $350 | |
| Honolulu | $400 to $675 | $260 to $390 | |
| Las Vegas | $290 to $515 | $210 to $275 | |
| Los Angeles | $280 to $425 | $220 to $315 | |
| Miami | $265 to $455 | $175 to $245 | |
| Minneapolis | $440 to $720 | $310 to $440 | |
| Nashville | $380 to $625 | $270 to $380 | |
| New York | $435 to $1,010 | $250 to $625 | |
| Phoenix | $275 to $475 | $185 to $250 | |
| Portland | $350 to $450 | $325 to $425 | |
| San Francisco | $480 to $840 | $380 to $600 | |
| Seattle | $390 to $690 | $255 to $360 | |
| Washington, D.C. | $355 to $590 | $245 to $385 |
The Texas filings line up with RLB’s secondary-office ranges: the TABS fully built median of $190 sits inside RLB’s Dallas ($165 to $240) and Austin ($170 to $235) secondary bands. Use the prime column only for a glass-heavy, amenity-rich building.
What else goes into the total project cost?
The building price is roughly 70% to 85% of what an owner spends. The University of Alaska Anchorage project budget rules (Appendix 7.4b) budget construction at about 70% of a total project, professional services at 10% to 15% of construction cost, construction contingency at 10% and furniture and equipment at 3% to 6%. Parking, land, financing and escalation sit on top.
| Budget line | Rule of thumb | Hard or soft | Source |
|---|---|---|---|
| Building (shell, core, interiors) | $132 to $269 per sq ft, median $190 (Texas, Oct 2026 $) | Hard | TDLR TABS, 356 filings |
| Surface parking | $6,250 per space, 410 sq ft of paving per space | Hard (site) | TDLR TABS, 17 Texas lots, 2025 to 2026 |
| Professional services (design, permits, testing, inspection) | 10% to 15% of construction cost | Soft | UAA Appendix 7.4b |
| Construction contingency | About 10% of construction cost for new work | Soft (owner reserve) | UAA Appendix 7.4b |
| Furniture, equipment and move-in | 3% to 6% of construction cost | Soft | UAA Appendix 7.4b |
| Escalation to construction start | 5.4% per year at the latest 12-month rate | Soft (allowance) | BLS PPI PCU236223236223 |
| Land and financing | Priced from your site and lender | Neither | Not estimated here |
Parking ratios come from the local zoning code, and offices commonly need 3 to 4 spaces per 1,000 square feet where a minimum applies; our parking space dimensions guide lists the city rules and the $6,250 per-space median. Some TABS filings already include parking in the building estimate, so read the scope line before adding it twice. For how much reserve to carry and who controls it, see our construction contingency guide.
Worked example: what does a 20,000 sq ft two-story office cost?
A 20,000 sq ft, two-story, fully built private office on a suburban Texas lot budgets at about $7.4 million before land, or $371 per square foot all in, using the TABS two-story median, 80 parking spaces, the UAA soft-cost rules and one year of escalation. The low and high cases run $4.5 million to $9.2 million.
| Line | Input | Low case | Base case | High case |
|---|---|---|---|---|
| Building | 20,000 sq ft x $165 / $255 / $313 per sq ft (TABS two-story quartiles and median) | $3,300,000 | $5,100,000 | $6,260,000 |
| Parking | 60 / 80 / 80 spaces x $6,250 (3 or 4 per 1,000 sq ft) | $375,000 | $500,000 | $500,000 |
| Construction subtotal | Building + parking | $3,675,000 | $5,600,000 | $6,760,000 |
| Construction contingency | 10% of subtotal | $367,500 | $560,000 | $676,000 |
| Professional services | 10% / 12.5% / 15% of subtotal | $367,500 | $700,000 | $1,014,000 |
| Furniture and equipment | 3% / 4.5% / 6% of subtotal | $110,250 | $252,000 | $405,600 |
| Escalation | 0% (start now) / 5.38% / 5.38% of subtotal | $0 | $301,280 | $363,688 |
| Total project cost before land | $4,520,250 | $7,413,280 | $9,219,288 | |
| All-in cost per sq ft | Total / 20,000 | $226 | $371 | $461 |
In the base case the building and parking are 83% of the $7,413,280 total, above the UAA 70% guide, which the UAA notes runs higher on smaller projects. Two filed Texas projects near this size bracket the result: a 23,000 sq ft two-story office in Collin County at $5,000,000 ($217 per sq ft, TABS2026000901) and a 17,519 sq ft two-story office in Harris County at $4,700,000 ($268, TABS2026016684).
Under the 2010 ADA Standards, Section 206.2.3, a private building of fewer than three stories does not need an accessible route between floors unless it houses a health care provider’s office, a shopping center or a transit station; state and local codes can be stricter. If you add one anyway, our commercial elevator cost guide found a $225,000 median for single-elevator additions in 18 Texas filings.
How fast are office construction prices rising?
New office building prices rose 5.38% from October 2025 to October 2026 and 11.3% from January 2024, on the BLS producer price index for new office building construction. To move an older quote to today, multiply it by the current index over the index in the month of the quote; that is how every TABS figure on this page was put into October 2026 dollars.
| Month | PPI, new office building construction | Change to Oct 2026 | Multiply a quote from this month by |
|---|---|---|---|
| January 2024 | 205.116 | 11.29% | 1.1129 |
| October 2024 | 210.003 | 8.70% | 1.0870 |
| October 2025 | 216.623 | 5.38% | 1.0538 |
| October 2026 (preliminary) | 228.273 | 0% | 1.0000 |
Example: a $3,000,000 office quote from October 2024 is $3,000,000 x 228.273 / 210.003 = $3,260,996 in October 2026 dollars. BLS builds the index from priced model buildings plus contractor margins, not your design. Our commercial construction price index compares the office series with warehouses, schools and health care buildings.
Which number should you budget with?
Pick the benchmark that matches what you are actually buying: a shell for lease, a fully built owner-occupied office, a public building or a big-city tower. Each row pairs a situation from 2024 to 2026 data with the add-ons the figure leaves out.
| If you are building | Start with | Then add |
|---|---|---|
| A single-story owner-occupied office under 10,000 sq ft in Texas or a similar market | $192 per sq ft (one-story median), $122 to $278 range | Parking, 10% to 15% professional services, 10% contingency |
| A two-story office of 10,000 to 30,000 sq ft | $255 per sq ft (two-story median), $165 to $313 range | Same, plus an elevator decision under ADA 206.2.3 |
| A multi-tenant spec building you will lease | $124 per sq ft shell or core and shell, $89 to $163 range | Tenant improvement allowances per suite |
| A county, city, state or school district office | $475 per sq ft (public median), $314 to $744 range | Public bid and prevailing-wage rules where they apply |
| A 3-story or taller office, or any office in a coastal gateway city | RLB Q3 2026 secondary or prime range for the nearest city | Geotechnical work for deep foundations, soft costs, escalation |
| A budget from a quote more than 6 months old | The quote x (228.273 / PPI in the quote month) | Escalation from today to the midpoint of construction |
Schedule follows size: the median filing planned 8 months for offices under 5,000 sq ft and 14 months at 25,000 sq ft and up. Our construction schedule guide shows how to sequence design, permit and build time.
How we compiled this
We pulled every TDLR TABS registration from January 1, 2024 to November 20, 2026 whose project name contained “office”, “headquarters” or “corporate” (3,702 records), kept 931 new construction and addition records of $100,000 or more after a first name screen, and read each public record page on November 21, 2026. We dropped renovations, finish-outs, office-warehouse and shop buildings, clinics, mixed uses, additions, 94 duplicate unit filings and anything under 1,000 sq ft or outside $60 to $1,500 per sq ft, leaving 482 projects. Costs were escalated to October 2026 with BLS series PCU236223236223; city ranges are from RLB Q3 2026, and soft-cost rules from the UAA budget appendix.
Frequently asked questions
How much does it cost to build an office building?
A new, fully built private office in Texas ran a median $190 per square foot in October 2026 dollars across 356 TDLR TABS registrations from 2024 to 2026, with the middle half at $132 to $269. A 5,000 sq ft office at the median is about $950,000 for the building, before parking, design fees, contingency, furniture and land.
How much does it cost to build a 10,000 sq ft office building?
At the Texas median of $171 to $190 per square foot for 5,000 to 24,999 sq ft offices, a 10,000 sq ft building runs about $1.7 to $1.9 million for construction. Adding 10% contingency, 10% to 15% professional services and 3% to 6% furniture puts the project near $2.1 to $2.5 million before parking and land.
Is a shell office building cheaper to build?
Yes, for the owner up front. Texas shell and core-and-shell office filings ran a median $124 per square foot in October 2026 dollars (93 projects), against $190 for fully built offices. The roughly $66 difference moves to the tenant improvement stage, where the landlord, the tenant or both pay for interior walls, ceilings, lighting and finishes.
Why do public office buildings cost more per square foot?
Public office filings in TABS (county, state and school district buildings) ran a median $475 per square foot against $190 for private offices. They often include courtrooms, emergency operations or secure areas, longer service-life specifications, public bidding rules and site work in the same contract, such as the $90,000,000 Williamson County headquarters of 119,452 sq ft.
How long does it take to build an office building?
Texas TABS filings planned a median of 9 months from construction start to completion for private, fully built offices. Offices under 5,000 sq ft planned 8 months, 10,000 to 24,999 sq ft planned 11 months, and 25,000 sq ft and up planned 14 months. Design and permitting usually come before that start date and are not included.
How do I update an old office construction estimate?
Multiply the old figure by the BLS office-building index for October 2026 (228.273, preliminary) divided by the index in the month of the estimate. A $3,000,000 estimate from October 2024, when the index was 210.003, becomes $3,260,996. Then add escalation from today to the midpoint of construction.
Sources
- Texas Department of Licensing and Regulation, TDLR TABS project registrations, public search and project pages, accessed November 21, 2026.
- TDLR Architectural Barriers FAQ ($50,000 registration threshold), accessed November 21, 2026.
- U.S. Bureau of Labor Statistics, BLS producer price index for new office building construction, series PCU236223236223, flat file pc.data.75.Construction, accessed November 21, 2026.
- Rider Levett Bucknall Quarterly Construction Cost Report, Q3 2026, indicative construction costs, accessed November 21, 2026.
- University of Alaska Anchorage project budget rules (Appendix 7.4b), accessed November 21, 2026.
- U.S. General Services Administration, GSA Unit Cost Study, Shell and Core: Office Building, via WBDG, accessed November 21, 2026.
- U.S. Department of Justice, 2010 ADA Standards, Section 206.2.3, accessed November 21, 2026.