Commercial Kitchen Inspection: Every Sign-Off Before Opening, in Order

Restaurant build-out near completion with exposed ductwork, wrapped stainless prep tables and work lights

A commercial kitchen inspection is not one visit but 9 sign-offs in a fixed order: health plan review, building rough-in and final, fire marshal hood and suppression tests, grease interceptor approval, then the health pre-opening inspection.

Key takeaways

  • The FDA Food Code requires approved plans before a food establishment is built, converted or remodeled (Section 8-201.11) and one or more preoperational inspections before it opens (Section 8-203.10) (FDA Food Code 2022).
  • The permit application is due at least 30 calendar days before the planned opening date under Food Code Section 8-302.11, so the paperwork clock starts before the build is finished (FDA Food Code 2022).
  • Los Angeles County reviews first plan submittals within 20 business days (10 expedited) and wants a preliminary inspection when the project is 80% complete (LA County Plan Check, 2026).
  • The grease duct needs a light test with a lamp of at least 100 watts before any part is concealed, and the hood needs a performance test before final approval (IMC 2018 Sections 506.3.2.5 and 507.6, quoted in an ICC 2019 handout).
  • Norfolk’s health department tells applicants to clear the fire marshal and the Fats, Oils and Grease (FOG) program before booking the health final (Norfolk Department of Public Health, 2026).
  • After opening, cold holding at 41°F or below was out of compliance in 79.8% of full-service restaurants FDA observed in 2017 to 2018, the most common miss of 10 risk items (FDA risk factor report, June 2023).
Key numberValueSource
Permit application before openingAt least 30 calendar daysFood Code 2022, 8-302.11
Health plan review, first submittal20 business days standard, 10 expeditedLA County Plan Check
Health preliminary inspectionAt 80% construction completeLA County Plan Check
Health pre-opening inspection booking2 weeks before opening (Anne Arundel, MD); at least 5 business days’ notice (Hampton, VA)County checklists
Fire suppression acceptance test bookingAt least 1 business day after the contractor’s pre-testKerrville Fire Marshal, item 21
Grease duct light test lampNot less than 100 wattsIMC 2018, 506.3.2.5
Routine health inspection intervalAt least once every 6 monthsFood Code 2022, 8-401.10
Correcting a priority violationOn the spot, or within 72 hours if the inspector agreesFood Code 2022, 8-405.11

Which inspections does a new commercial kitchen need, and in what order?

A new or gutted commercial kitchen passes 9 checkpoints run by 4 agencies: the health department reviews plans first, the building department inspects rough-in work before walls close, the fire marshal witnesses the hood suppression test, the sewer utility or FOG program signs off the grease interceptor, and the health department’s pre-opening inspection comes last, usually after the certificate of occupancy (CO).

The order matters because each agency checks the one before it. At step 8 of its process, Los Angeles County will not give final health approval without proof of a CO or a signed building inspection card (LA County Environmental Health), and Norfolk, Virginia asks for fire marshal and FOG clearance before its final. Our broader guide to the commercial kitchen covers the build requirements behind each of these checks.

Nine-step inspection sequence for a new commercial kitchen, from health plan review to routine inspections Commercial kitchen inspection sequence: new build or major remodel Who books each step and the lead time a published local rule gives DESIGN 1 Health department plan review Owner or operator submits plans and menu | Food Code 8-201.11; LA County: 20 business days DESIGN 2 Grease interceptor size approval Owner’s engineer, FOG or pretreatment program | Raleigh: before building plans; Austin: before purchase BUILD 3 Building rough-in inspections GC requests by permit number | Phoenix: request by 9 p.m. for next business day BUILD 4 Grease duct light test Permit holder performs, inspector watches | IMC 506.3.2.5: before duct is concealed BUILD 5 Health preliminary inspection Operator books with plan check | LA County: at 80% complete FINISH 6 Fire: suppression acceptance and hood test Installer pre-tests, then books fire marshal | Kerrville: 1 business day after pre-test; IMC 507.6 FINISH 7 Building finals, interceptor sign-off, CO GC, utilities or FOG program, building official | Norfolk: fire and FOG clear before health final OPEN 8 Health pre-opening inspection and permit Operator schedules; permit applied 30 days ahead | Anne Arundel: book 2 weeks out; Food Code 8-203.10 RUN 9 Routine health inspections Health department, unannounced | Food Code 8-401.10: at least every 6 months
The health pre-opening inspection comes after fire, grease and building sign-offs. Sources: FDA Food Code 2022 Sections 8-201.11, 8-203.10, 8-401.10; LA County, Phoenix, Kerrville, Norfolk and Anne Arundel documents, accessed 2026-11-21.
StepInspectionAgencyWho books itRule or local source
1Health plan reviewHealth departmentPermit applicant (owner or operator)Food Code 8-201.11
2Grease interceptor size approvalFOG or pretreatment programOwner’s engineerRaleigh: before building plans; Austin: before purchase
3Rough-in: under-slab plumbing, gas piping, rough electrical, HVACBuilding departmentGeneral contractor (GC)Phoenix: each stage before concealment
4Grease duct light testBuilding (mechanical)Permit holder performs itIMC 2018, 506.3.2.5
5Health preliminary inspectionHealth departmentOperatorLA County: at 80% complete
6Suppression acceptance test and hood performance testFire marshal; building officialSuppression installer; permit holderIFC 904.4; IMC 507.6
7Building finals, interceptor sign-off, COBuilding; utilitiesGCNorfolk: fire and FOG first
8Health pre-opening inspection, then permitHealth departmentOperatorFood Code 8-203.10, 8-301.11
9Routine inspectionsHealth departmentUnannouncedFood Code 8-401.10

What happens at health department plan review?

Health plan review is a paper inspection before construction: the reviewer checks the menu, food volume, layout, finish schedule and every piece of equipment by maker and model number against the Food Code. Food Code Section 8-201.12 lists the required contents, and Los Angeles County’s fee covers 2 plan reviews and 2 inspections, with extra fees for corrections caused by scope changes.

Plans are required before construction, conversion of an existing building, or a remodel the health department decides needs review (Food Code 8-201.11). The Conference for Food Protection’s 2025 plan review guidance adds the triggers most tenants hit: moving equipment or cabinetry, a menu change that adds equipment, and any equipment connected to gas, electricity or plumbing. Layout and clearance rules are covered in our guide to commercial kitchen design.

Item in the submittalFood Code 2022 referenceCommon reason it delays review
Intended menu8-201.12(A)Missing menu (LA County list of delay causes)
Anticipated volume of food8-201.12(B)Walk-in and hot water sized without a meal count
Layout, mechanical schematics, finish schedule8-201.12(C)Water heater location not shown (LA County)
Equipment types, makers, model numbers, dimensions8-201.12(D)No equipment schedule or spec sheets (LA County)
Standard operating procedures8-201.12(E)SOPs not written; checked again at 8-203.10

Which building inspections come before the kitchen is closed up?

Building inspections run at every stage before work is covered: under-slab plumbing, gas piping, rough electrical, HVAC and a kitchen exhaust inspection, then a final for each trade. Phoenix schedules any request made before 9 p.m. for the next business day, and Salt Lake City’s cutoff is 3:00 p.m. the workday before. Missing one inspection can mean opening a finished wall.

Phoenix lists kitchen exhaust as its own inspection type (code 254) alongside plumbing, mechanical and electrical finals, and says all required inspections must pass before permanent occupancy (City of Phoenix PDD). Salt Lake City names low-voltage and fire alarm wiring as the biggest offenders at penetration inspections, and warns that stamped approved plans must be on site (Salt Lake City Building Services). The permit side of a build-out is covered in our guide to commercial building permits.

Building inspectionWhen to call itWhat a kitchen addsSource
Under-slab plumbingBefore the slab is poured or patchedFloor sinks, trench drains, interceptor linesPhoenix inspection list
Gas pipingBefore concealmentRange, fryer and oven dropsPhoenix inspection list
Rough electrical and HVACBefore insulation and drywallHood fan circuits, shunt trip, make-up air unitPhoenix; Salt Lake City
Grease duct light testBefore any duct is concealed100-watt lamp through every joint, including hood-to-ductIMC 2018, 506.3.2.5
Kitchen exhaust (Phoenix code 254)Hood and duct installedClearances, cleanouts, terminationPhoenix inspection list
Trade finals and building finalAll work complete; other agencies signedFire and interceptor sign-offs firstPhoenix; Norfolk

How does the fire marshal test the hood and suppression system?

The fire marshal witnesses an acceptance test of the hood’s wet chemical suppression system after the installer has pre-tested it: piping is blown through with nitrogen or dry air, the fusible links and pull station must trip the system, and gas, make-up air and power must shut off (NFPA 17A Section 6.4.8). Separately, the hood gets a performance test of airflow and smoke capture before final approval.

The rules come from 3 documents. IFC 2018 Section 904.4.1 lists 6 items inspected before acceptance tests, from the hazard specification to operating instructions. NFPA 17A (2017) Section 6.4.8 sets the operational tests and 6.4.10.3 makes the installer sign an acceptance report. IMC 2018 Section 507.6 sets the hood test, which North Carolina’s Office of the State Fire Marshal says the code official or a professional engineer must witness. System details sit in our guide to the commercial kitchen fire suppression system.

TestWhat passesRuleWho runs it
Pre-acceptance inspectionHazard matches design; detectors, pull stations, nozzles, alarms and labels in placeIFC 2018, 904.4.1Fire code official
Piping integrityNitrogen or dry air discharges from every nozzle; no hydrostatic test of pipingNFPA 17A (2017), 6.4.4Installing contractor
System operational testAutomatic detection, manual release, gas shutoff, make-up air shutoff, power shutoff all workNFPA 17A (2017), 6.4.8Installer, witnessed
Acceptance reportSigned by the installing contractorNFPA 17A (2017), 6.4.10.3Installing contractor
Hood performance testExhaust airflow per 507.5 and make-up air per 508 verifiedIMC 2018, 507.6Permit holder supplies equipment
Capture and containmentSmoke candles or puffers show capture with all appliances hot; smoke bombs not allowedIMC 2018, 507.6.1Code official or engineer witnesses

Local fire marshals add steps. Kerrville, Texas requires a contractor pre-test before anyone calls, books the witnessed test at least 1 business day later, observes an air blow-out of the nozzles, requires dated fusible links changed every year, and wants a Class K extinguisher within 30 feet (Kerrville Fire Marshal, Section 4). The hood itself is covered in our guide to the commercial kitchen hood.

Who signs off on the grease interceptor?

The grease interceptor is approved at 2 points: its size is approved by the sewer utility’s FOG or pretreatment program during design, and the installed unit is inspected before the kitchen opens. Raleigh requires pretreatment approval before commercial building plans are submitted, Austin says not to buy a unit before plan approval, and Anne Arundel County, Maryland inspects the interceptor before opening.

The inspecting office depends on where the unit sits. Salt Lake City sends Public Utilities to inspect exterior grease interceptors and Building Services to inspect hydromechanical units inside the building (Salt Lake City). Austin rejects units holding under 100 gallons and requires at least 500 gallons for kitchens with a dishwasher (Austin Water). Anne Arundel requires exterior placement, outside food preparation and storage areas (Anne Arundel County Department of Health). Sizing methods are in our grease trap guide.

What fails a health department pre-opening inspection most often?

Health departments single out the same pre-opening problems: hot water that is not up to temperature, refrigerators not holding 41°F, missing light, sinks plumbed without air gaps, no sanitizer test strips, no certified food manager and missing agency sign-offs. Norfolk’s health department puts these items on its 2026 top-10 list, and the 4 other county checklists reviewed repeat most of them.

The table maps each item to its Food Code 2022 section and to the 5 published local checklists. Local rules can be stricter than the Food Code: Hampton, Teller, Craven and Anne Arundel checklists all state 100°F at hand sinks, the figure in the 2017 Food Code, while the 2022 edition requires at least 85°F. Build to the local number.

Norfolk health department top 10 pre-opening checklist with the External Agency Approvals item boxed
Norfolk’s list tells applicants to clear the fire marshal and the FOG program before the health final. Source: Norfolk Department of Public Health, Top 10 Checklist, file dated May 2026, accessed 2026-11-21.
Item the inspector checksFood Code 2022 sectionLocal checklist that names itDo this before you book
Hot water at hand sinks: 85°F minimum through a mixing valve (local: often 100°F; 110°F at the 3-compartment sink in Hampton)5-202.12(A)Norfolk top 10; Hampton; Teller; CravenFire the water heater a day ahead and measure at the farthest sink
Cold holding at 41°F or below, thermometer in the warmest spot3-501.16(A)(2); 4-204.112Norfolk; Hampton; Anne ArundelRun every unit 24 hours with a cup of water inside (Hampton)
Light: 50 fc at prep surfaces, 20 fc at hand sinks and reach-ins, 10 fc in walk-ins and dry storage6-303.11Norfolk; Craven; HamptonAll fixtures working and shielded
Indirect drains on prep sinks, 3-compartment sink, ice machine, dish machine; air gap at least 1 inch and twice the inlet diameter5-402.11; 5-202.13Norfolk; TellerPlumber confirms air gaps before the floor sinks are trimmed
Hand sinks stocked with soap, towels and a handwashing sign, never blocked6-301.11; 6-301.12; 6-301.14; 5-205.11Hampton; Teller; Craven; Anne ArundelMount dispensers and signs at every hand sink
Sanitizer and a matching test kit4-302.14Norfolk; Hampton; TellerStock strips for the sanitizer you will use
Certified food protection manager2-102.12Norfolk; Teller; Hampton ($15 registration)Register the manager before the inspection; Teller allows course completion within 90 days of the opening inspection
Thin-probe food thermometer4-302.12(B)Hampton (0°F to 220°F); Anne ArundelHave one on site
Equipment certified to an ANSI standard and installed as approved4-205.10; 8-203.10Anne Arundel; Craven; TellerGet health approval before substituting any unit
Self-closing, tight-fitting exterior doors6-202.15Teller; Craven; Anne ArundelInstall closers and door sweeps
Construction dust and debris gone6-501.12Craven; Anne Arundel; NorfolkFinal clean and sanitize food contact surfaces
Fire marshal and FOG sign-offs in hand8-203.10 (compliance with LAW)Norfolk; Anne ArundelBring the signed reports and the CO

Teller County, Colorado puts it plainly: if an applicant cannot check every box on its list, the facility is not ready for its opening inspection (Teller County checklist). Craven County, North Carolina asks that all refrigeration and the water heater be powered up and all construction material removed before the visit (Craven County, 2024). The Hampton Health Department will not honor same-day requests.

How long does each inspection take to schedule?

Lead times are set locally, but published rules give real anchors: 20 business days for a first health plan review in Los Angeles County, next business day for most building inspections, at least 1 business day after a pre-test for a Kerrville suppression test, and 2 weeks’ notice for an Anne Arundel pre-opening inspection. The Food Code adds a 30-day permit application rule.

StepPublished lead timeJurisdictionSource
Health plan review, first submittal20 business days standard; 10 expeditedLos Angeles County, CALA County Plan Check
Health plan review, corrected plans10 business daysLos Angeles County, CALA County Plan Check
Building inspection requestBefore 9 p.m. for the next business dayPhoenix, AZCity of Phoenix
Building inspection requestBy 3:00 p.m. the workday beforeSalt Lake City, UTSalt Lake City
Suppression acceptance testAt least 1 business day after the pre-testKerrville, TXKerrville Fire Marshal
Health permit applicationAt least 30 calendar days before openingFood Code modelFood Code 2022, 8-302.11
Health pre-opening inspectionSchedule 2 weeks before openingAnne Arundel County, MDAnne Arundel checklist
Health pre-opening inspectionAt least 5 business days’ notice; no same-dayHampton, VAHampton checklist
Countdown timeline of inspection lead times: 30 days permit, 14 days booking, 5 business days notice, 1 day Countdown to opening: published lead times Each marker is a rule from a named source; jurisdictions differ, so check yours Opening Before permits Health plan approval: 20 + 10 business days (LA County) During build Building inspections: next business day (Phoenix, by 9 p.m.) 30 days out Apply for the health permit (Food Code 8-302.11) 14 days out Book pre-opening inspection (Anne Arundel County, MD) 5 business days Minimum notice for pre-opening (Hampton, VA) 1 day out Refrigerators on for 24 hours with a water cup (Hampton) Fire marshal: book the suppression acceptance test at least 1 business day after the contractor’s pre-test (Kerrville, TX). Grease duct light test: before any duct is concealed (IMC 2018 Section 506.3.2.5).
Published lead times run from 30 business days of health plan review before permits to 24 hours of refrigerator run time before the visit. Sources: LA County, Phoenix, Food Code 2022 8-302.11, Anne Arundel, Hampton, Kerrville, accessed 2026-11-21.

Worked backward from a target opening date, those rules stack up. With a first review of 20 business days and one correction round of 10, health plan approval alone takes 30 business days, about 6 weeks, before building permits are pulled in Los Angeles County. The permit application goes in at least 30 calendar days before opening, and the pre-opening visit is booked 2 weeks out in Anne Arundel. A GC who tracks these dates on the punch list avoids a finished kitchen waiting on paperwork.

What do routine health inspections check after opening?

Once open, the health department inspects at least once every 6 months under Food Code Section 8-401.10, unless it runs a written risk-based schedule. The items that fail most often are operational, not built: FDA’s 2017 to 2018 study of 430 full-service restaurants found cold holding out of compliance in 79.8%, handwashing in 74.4% and cooling in 68.9%.

What full-service restaurants fail most oftenBar chart: cold holding failed in 79.8% of full-service restaurants, handwashing 74.4%, cooling 68.9%, cooking 21.3%% of restaurantsCold holding79.8Handwashing74.4Cooling68.9Date marking64.1Cross contamination57.4Food contact surfaces sanitized57.4Reheating35.6Hot holding31.3Bare-hand contact24.4Cooking temperatures21.3
Cold holding at 41°F or below was the most common failure, out of compliance in 79.8% of 430 full-service restaurants. Source: FDA risk factor report, Table 8, June 2023.
FDA data item (2017 to 2018)Full-service % outFast food % outFood Code 2022 section
Cold holding at proper temperature79.862.23-501.16(A)(2)
Proper handwashing74.458.72-301.12; 2-301.14
Proper cooling68.958.83-501.14
Date marking of ready-to-eat food64.134.63-501.17; 3-501.18
Protection from cross contamination57.430.23-302.11
Food contact surfaces cleaned and sanitized57.439.44-602.11; 4-702.11
Reheating for hot holding35.626.23-403.11
Hot holding31.324.73-501.16(A)(1)
No bare-hand contact with ready-to-eat food24.48.33-301.11
Cooking raw animal foods21.34.73-401.11

A violation’s class sets the deadline. Priority items must be fixed during the inspection, or within 72 hours if the inspector agrees; priority foundation items within 10 calendar days; core items within 90 calendar days (Food Code 2022, Sections 8-405.11 and 8-406.11). The FDA’s June 2023 report counted a restaurant out of compliance if a practice failed even once during the visit.

Where do common inspection checklists disagree with the Food Code?

Several popular checklists state rules that differ from the FDA Food Code or leave out the construction phase. The 2022 Food Code requires hand sink water of at least 85°F, not 100°F, and an inspection at least every 6 months, not once a year. Local law can be stricter, so the corrections below say which rule controls.

What a guide saysWhat the primary source saysSource
A trade magazine article (2017): inspectors make an unannounced visit at least once a yearAt least once every 6 months, unless a written risk-based schedule or HACCP plan allows longerFood Code 2022, 8-401.10
Several county checklists: hand sinks must reach 100°FFood Code 2022 sets 85°F minimum; 100°F was the 2017 figure and still applies where a state enforces itFood Code 2022 and 2017, 5-202.12(A)
Top-ranking checklists (2025 and 2026): inspection prep is cleaning, storage and staff hygieneNew kitchens also need plan approval, preoperational inspections and a permit applied for 30 days aheadFood Code 2022, 8-201.11, 8-203.10, 8-302.11
A property inspector’s hood checklist: no test procedure namedGrease duct light test before concealment and a witnessed hood performance test before final approvalIMC 2018, 506.3.2.5 and 507.6

Which inspections does your kitchen project trigger?

New construction, a converted building or a space never used for food triggers the full 9-step sequence. A remodel that moves equipment, adds a hood or touches gas, water or power triggers plan review plus the affected trade and fire tests. A change of ownership often triggers a health pre-opening inspection. Like-for-like finish swaps usually trigger none.

Flowchart of four yes or no questions that decide which kitchen inspections a project triggers Which inspections does your kitchen project trigger? New building, new location, or space never used for food? Yes Full sequence: steps 1 to 9 Plan review required: Food Code 8-201.11(A), (B) No Adding or moving a hood, or equipment on gas, water or power? Yes Plan review, trade inspections, fire test LA County and CFP 2025 plan review triggers No Change of ownership of an operating kitchen? Yes Health pre-opening inspection Anne Arundel: new, remodeled or change of ownership No Like-for-like swap of non-utility equipment or finishes? Yes Usually no plan review; routine inspections CFP 2025 guide: confirm with the health department Local law decides: the health department can require plans for any remodel it judges necessary (Food Code 8-201.11(C)).
New food use triggers all 9 steps; like-for-like finish swaps usually trigger none. Sources: FDA Food Code 2022 Section 8-201.11; CFP plan review guidance 2025; LA County; Anne Arundel County, accessed 2026-11-21.
If your project isThen plan forSource
New building, conversion or first food use of a spaceAll 9 steps, starting with health plan reviewFood Code 8-201.11(A), (B)
Installing or replacing an exhaust hoodHealth plan review, mechanical permit, light test, hood test, suppression acceptance testLA County triggers; IMC 506.3.2.5, 507.6
Moving equipment or cabinetry, or adding equipment on gas, electricity or plumbingHealth plan review and trade inspectionsCFP plan review guidance, 2025
Adding a fixture that drains grease (sink, dish machine)Ask the FOG program whether the interceptor size must be re-approvedRaleigh; Austin
Change of ownership, no constructionHealth pre-opening inspection; deep cleanAnne Arundel; Norfolk
Like-for-like refrigerator in the same footprint, or FRP replaced with FRP, tile or stainlessUsually no plan review; confirm in writingCFP plan review guidance, 2025

These requirements are drawn from model codes and 11 local documents, and your state may enforce an older Food Code edition or amended building codes; this is general information, not legal advice. Contractors who handle these sign-offs are listed in our guide to restaurant build-out contractors.

Plan the build so it passes: see kitchen lighting requirements and which wall panels pass in each zone.

How we compiled this

We read the FDA Food Code 2022 (January 18, 2023 version) and confirmed the same section numbers in the 2026 edition, then compiled 11 local documents: 6 health department checklists and process guides, 2 building department pages, 1 fire marshal guideline and 2 FOG program pages, plus an ICC handout quoting IMC and IFC 2018 text and NFPA 17A (2017). Failure rates come from the FDA’s June 2023 risk factor report. All were accessed November 2026; we did no inspections or surveys ourselves.

Frequently asked questions

What is a commercial kitchen inspection?

A commercial kitchen inspection is any check by the health, building or fire authority that a food establishment meets code. Before opening, that means health plan review, building rough-in and final inspections, a fire marshal suppression test, grease interceptor sign-off and a health preoperational inspection under FDA Food Code Section 8-203.10. After opening, health inspections recur at least every 6 months.

Who schedules the health department pre-opening inspection?

The operator applying for the food permit schedules it, once construction, the certificate of occupancy and the fire and grease sign-offs are done. Anne Arundel County, Maryland asks for scheduling 2 weeks before the expected opening date, and Hampton, Virginia asks for at least 5 business days’ notice and refuses same-day requests. The permit application is due 30 days before opening under Food Code 8-302.11.

Does the fire marshal have to test the hood suppression system before opening?

Yes, in most jurisdictions. IFC 2018 Section 904.4 requires automatic fire-extinguishing systems to be inspected and tested before acceptance, and NFPA 17A (2017) Section 6.4.8 lists the operational tests: detection, manual release, gas shutoff, make-up air shutoff and power shutoff. Kerrville, Texas requires a contractor pre-test first, then books the witnessed test at least 1 business day later.

What is a grease duct light test?

It is a leak test of the Type I hood’s grease duct required by IMC 2018 Section 506.3.2.5 before any part of the duct is concealed. A lamp of at least 100 watts is passed through the entire duct, including the hood-to-duct connection, to show that all welded and brazed joints are liquid tight. The permit holder supplies the equipment and performs it while the inspector watches.

How often is a restaurant kitchen inspected after it opens?

FDA Food Code Section 8-401.10 sets at least once every 6 months. A health department may stretch the interval if it uses a written risk-based schedule applied across the jurisdiction and contacts the establishment every 6 months, if the operation runs a validated HACCP plan, or if it serves only coffee and non-perishable packaged foods. Many states enforce older Food Code editions with the same rule.

What happens if a kitchen fails a health inspection?

It depends on the violation class. Under Food Code 2022 Section 8-405.11, priority and priority foundation violations must be corrected during the inspection, or within 72 hours for priority items and 10 calendar days for priority foundation items if the inspector agrees. Core items get up to 90 calendar days under Section 8-406.11. An imminent health hazard requires the operation to stop.