Change Order in Construction: A201 Rules, Pricing, Time and a Log Template

Office tenant build-out with new metal stud framing for an added room and drawings on a sawhorse table

A change order is a written agreement, signed by the owner, contractor and architect, that changes the work, the contract sum or the contract time; under AIA A201-2017 §7.2 it is issued on form G701.

Key takeaways

  • AIA A201-2017 Article 7 gives three ways to change the work: a Change Order signed by three parties (§7.2), a Construction Change Directive signed by owner and architect (§7.3) and a minor change by the architect alone (§7.4), per the A201-2017 standard form.
  • A201 sets no markup percentage: §7.3.4 allows overhead and profit as set in the Agreement or a reasonable amount, and the A102 and A103 forms leave the fee-on-changes line blank (§5.1.2), per the A102-2017 preview.
  • Named public schedules cap markup: the Department of Veterans Affairs allows at most 10% overhead and 10% profit on the first $20,000 of a change, falling to 5% and 5% above $50,000, under VAAR 852.243-70 (September 2019).
  • The South Florida Water Management District reported approved change orders of 19.2% of original contract value for October 2023 to March 2024, or 4.8% without two outlier contracts, in its Inspector General review.
  • Time grows faster than money: nine Fort Worth contracts sampled in a March 4, 2022 city audit went from 3,160 to 4,795 contract days, a 52% increase.

What is a change order in construction?

A change order is the signed record of an agreed change to scope, price or schedule after the contract is signed. A201-2017 §7.2.1 says it must state three things: the change in the work, the adjustment to the Contract Sum and the adjustment to the Contract Time. The architect prepares it (§4.2.8) and the owner, contractor and architect all sign it, per the A201-2017 form.

Two other instruments sit beside it in Article 7. A Construction Change Directive (CCD) orders the work before price or time is agreed, and an order for a minor change lets the architect adjust details that cost nothing and add no days. An RFI (request for information) only asks what the documents mean; it changes nothing until one of these three instruments is issued.

InstrumentA201-2017 sectionAIA formWho signsPrice and timeSource
Change Order§7.2G701-2017Owner, contractor, architectAgreed before signingA201 §7.1.2, §7.2.1
Construction Change Directive§7.3G714-2017Owner and architect (contractor optional)Set later by a §7.3.3 method or the architect (§7.3.4)A201 §7.3.1 to §7.3.10
Order for a minor change§7.4G710-2017 Architect’s Supplemental InstructionsArchitect aloneNo change allowedAIA document list
Request for information (RFI)§3.2.2, §4.2.14G716-2004Contractor asks, architect answersNone by itselfAIA document list
Flowchart choosing between a minor change, a change order and a construction change directive under AIA A201-2017 A change to the work is needed Does it change the Contract Sum or the Contract Time? No Minor change A201 §7.4, form G710 Architect signs alone Notify first if price or time is affected, or the claim is waived Yes Do owner, contractor and architect agree on price and time? Yes Change Order A201 §7.2, form G701 Owner, contractor and architect all sign No Construction Change Directive A201 §7.3, form G714 Owner and architect sign Contractor proceeds promptly (§7.3.6) Price set later by a §7.3.3 method Agreement reached: recorded as a Change Order (§7.3.7, §7.3.10)
A201-2017 Article 7 routes every change by two questions: does it move price or time, and do all three parties agree. AIA A201-2017 §7.2 to §7.4, accessed November 8, 2026.

What does AIA A201 Article 7 require?

Article 7 of A201-2017 lets the owner change the work without voiding the contract, as long as the change stays within the general scope (§7.1.1, §7.3.1). The contractor must proceed promptly with any change unless the instrument says otherwise (§7.1.3). Our guide to every A201-2017 article and deadline places Article 7 in the full form.

§7.2 Change orders: agreement on all three terms

A Change Order needs agreement on the change, the price and the time, all in one signed document (§7.2.1). If the parties agree on the work but not the money, the form cannot be signed, and A201 §7.3.2 sends the change to a Construction Change Directive instead. The G701 form adds that it is not valid until all three parties sign, per the AIA G701-2017 sample.

§7.3 Construction change directives: work first, price later

A CCD lets the owner keep the job moving when price talks stall. On receipt the contractor proceeds (§7.3.6) and states whether it agrees with the pricing method. §7.3.3 lists four methods: an itemized lump sum, unit prices, cost plus an agreed fixed or percentage fee, or the architect’s determination under §7.3.4. Disputed time goes to a claim under Article 15 (§7.3.5).

If the contractor does not respond or disagrees, the architect sets the price from reasonable expenditures and savings, and §7.3.4 limits recoverable cost to five categories unless the contract says otherwise. Work done under a CCD can be billed on the next pay application at the architect’s interim figure (§7.3.9, §9.3.1.1), and once both sides agree the CCD is recorded as a Change Order (§7.3.7, §7.3.10).

§7.3.4 cost itemWhat it includesWhat it excludes or limits
.1 LaborWages plus payroll taxes, required fringe benefits, workers’ compensation and other employee costs the architect approvesHome office staff (covered by markup)
.2 Materials, supplies, equipmentCost including transportation, whether built in or consumedItems not attributable to the change
.3 Machinery and equipment rentalRental from the contractor or othersHand tools
.4 Bonds, insurance, permits, taxesPremiums, permit fees and sales or use taxes directly related to the changeGeneral policy premiums not tied to the change
.5 SupervisionSupervision and field office personnel directly attributable to the changeSupervision the job would carry anyway

§7.4 Minor changes: the waiver trap

The architect may order a minor change in writing if it fits the design intent and changes neither price nor time (§7.4). If the contractor thinks the order does affect price or time, it must tell the architect and not start; a contractor that does the work without that notice waives any adjustment. AIA issues minor changes on form G710-2017, Architect’s Supplemental Instructions.

What goes on a G701 change order form?

The G701-2017 form carries the project and contract names, the change order number and date, a written description of the change with any exhibits, and seven price and time lines. AIA sells it for $59.99 per single use as of November 2026 on its G701-2017 store page. The arithmetic lines let anyone audit the running contract total in one glance.

  1. The original Contract Sum or Guaranteed Maximum Price.
  2. The net change from change orders already signed.
  3. The Contract Sum before this change order (line 1 plus line 2).
  4. The increase, decrease or no change from this change order.
  5. The new Contract Sum including this change order.
  6. The change in Contract Time, in days.
  7. The new date of Substantial Completion.

The form notes that amounts authorized by a CCD stay off these lines until owner and contractor agree on cost and time; at that point a Change Order supersedes the directive. The lines below use the worked example later on this page, with an assumed $1,240,000 contract and three earlier change orders worth $38,600.

G701 change order lines from a $1,240,000 original contract sum to a $1,292,911.90 new sum plus 3 days G701-2017 contract sum and time lines, worked example (Change Order 004) 1. Original Contract Sum$1,240,000.00 2. Net change by previously authorized Change Orders (001 to 003)+$38,600.00 3. Contract Sum prior to this Change Order (line 1 + line 2)$1,278,600.00 4. Increased by this Change Order+$14,311.90 5. New Contract Sum including this Change Order$1,292,911.90 6. Contract Time increased by3 days 7. New date of Substantial CompletionMarch 18, 2027 Change orders to date: $52,911.90, or 4.27% of the original Contract Sum. Not valid until owner, contractor and architect sign.
Worked example on the G701-2017 lines: a $14,311.90 change takes the contract to $1,292,911.90 and adds 3 days. Assumed inputs; form lines from the AIA G701-2017 sample, accessed November 8, 2026.

How are change orders priced, and what markup is allowed?

Change orders are priced as direct cost (labor, materials, equipment, subcontracts, bonds) plus a markup for overhead and profit. A201-2017 §7.3.4 uses the markup written in the Agreement, or a reasonable amount if none is written. A102-2017 and A103-2017 leave three blanks for this: fee adjustment for changes (§5.1.2), subcontractor overhead and profit limits (§5.1.3) and owned-equipment rental rates (§5.1.4), per the A103-2017 preview.

Public owners fill those blanks with fixed schedules. The table compares four dated, named schedules on a commercial owner’s terms: who performs the work and what percentage applies.

Owner document (date)Self-performed workMarkup on subcontracted workOther limitsSource
AIA A201-2017 §7.3.4 (default)Amount set in the Agreement, else “reasonable”Same ruleFive cost categories onlyA201-2017
AIA A102-2017 / A103-2017Blank §5.1.2, owner fills itBlank §5.1.3Equipment rental cap % blank §5.1.4A102 preview
Dept. of Veterans Affairs, VAAR 852.243-70 (Sept 2019)Up to 10% overhead and 10% profit on first $20,000; 7.5% and 7.5% on next $30,000; 5% and 5% above $50,000Same declining scale, up to three tiersChanges over $500,000 priced under FAR 15.403-5; credits deducted before markupeCFR
Washington State DOT M 41-10, 2027 edition, §1-09.6Labor +29%; materials +21%; equipment +21%12% to $50,000; 10% from $50,000 to $200,000; 7% at $200,000 and upMarkup covers overhead, profit, bonding, insurance and B&O taxWSDOT
Case Western Reserve University, Section 00410 (rev. May 21, 2014)One markup, not over 10%, at any tierSupervising contractor up to 5% of lower-tier net changeOwned equipment at 75% of AED Green Book monthly rate / 176; no contingency in change pricingCWRU Facilities

Credits follow a separate rule. Under A201 §7.3.8 a pure deduction is credited at actual net cost, and when a change mixes additions and credits, overhead and profit apply only to the net increase. An AIA counsel article dated August 17, 2022 explains that on a pure deduction the contractor keeps the markup it priced on the deleted work, per AIA Contract Documents. The VA clause reaches the opposite result for credit-only changes, allowing a reasonable overhead and profit allowance in the downward adjustment.

On cost-plus and GMP jobs the fee on changes is the §5.1.2 blank, so the owner should fill it before signing. Our cost-plus contract guide covers fixed and percentage fee structures, and our comparison of construction contract types shows how lump sum, unit price and T&M jobs reprice.

What does a priced change order look like, line by line?

The example below prices one owner-requested change, a 400 sq ft secure storage room added to an office tenant build-out after framing, under two schedules. The inputs are assumed for illustration: 64 carpentry hours at a $68 burdened rate, $2,860 of materials, a $5,400 electrical subcontract and a 1% bond and insurance premium. The schedules are the Case Western caps and the VA declining scale.

LineOwner schedule (10% self, 5% on subs)VA schedule (VAAR 852.243-70, 10% + 10%)
GC labor: 64 h x $68$4,352.00$4,352.00
GC materials$2,860.00$2,860.00
GC direct cost$7,212.00$7,212.00
GC overhead and profit on own work$721.20 (10%)$721.20 overhead + $793.32 profit
Electrical sub direct cost$5,400.00$5,400.00
Sub’s own markup$540.00 (10%)$540.00 overhead + $594.00 profit
GC markup on sub price$297.00 (5% of $5,940)$653.40 overhead + $718.74 profit
Subtotal$14,170.20$16,632.66
Bond and insurance, 1% (assumed)$141.70$166.33
Change order amount$14,311.90$16,798.99
Markup as % of $12,612 direct cost13.5%33.2%

The same work costs $2,487.09 more under the VA schedule because it allows separate overhead and profit at each tier, with profit computed on cost plus overhead. Under the owner schedule the change adds 3 days and $14,311.90, taking the contract from $1,278,600.00 to $1,292,911.90 and Substantial Completion from March 15 to March 18, 2027 (assumed dates); change orders to date reach $52,911.90, or 4.27% of the $1,240,000 original. Owners can pay for that from the budget line described in our guide to construction contingency and how it is drawn down.

How often do change orders happen on public projects?

Public audits put change orders at about 3% to 5.4% of original contract value on routine programs, with single projects far higher. The South Florida Water Management District’s Inspector General counted 58 change orders on 21 contracts from October 1, 2023 to March 31, 2024: $121,798,023 approved against $633,575,371 original, or 19.2%, falling to 4.8% without two outliers, per its Project 24-16 review.

Owner and periodScopeChange orders as % of originalSource
SFWMD, Oct 2023 to Mar 202421 contracts, $633,575,371 original19.2% (4.8% without 2 outliers)SFWMD OIG, 2024
SFWMD, 2015 to 2020District construction contracts4% averageSFWMD OIG, 2024
Missouri DOT, 2002 auditHighway program3%Missouri State Auditor 2002-96
Kansas, Iowa, Illinois DOTs (cited 2002)Highway programs2% to 5%; 5.4%; 4% to 7%Missouri State Auditor 2002-96
One state DOT with FHWA, 200128 projects, $91,675,260 original3.5%; some projects over 21%FHWA process review
University of Illinois, English Building slate roof$3,818,000 original63.36%UI Board report, July 2019
University of Illinois, Turner Hall classrooms$4,439,000 original17.65%UI Board report, July 2019
Change orders as a share of original contract valueBar chart: SFWMD change orders 19.2% of original in 2023 to 2024, 4.8% without outliers; DOT programs 3% to 5.4%.%SFWMD Oct 2023 to Mar 2024, all 21 contrac19.2Iowa DOT (cited 2002)5.4SFWMD Oct 2023 to Mar 2024, without 2 outl4.8SFWMD 2015 to 2020 average4One state DOT with FHWA, 28 projects (20013.5Missouri DOT (2002)3
Routine public programs report change orders of 3% to 5.4% of original contract value; two large contracts lifted SFWMD’s 2023 to 2024 figure to 19.2%. SFWMD OIG (2024), Missouri State Auditor (2002), FHWA (2001), accessed November 8, 2026.

Some public owners cap the total. Fort Worth’s audit notes that Texas Local Government Code §252.048 limits increases to 25% of the original contract price, and the University of Illinois reports any construction change over 5% to its Board of Trustees. Private owners face no statutory cap, so the Texas cap is a useful benchmark rather than a rule for them. The University of Illinois list shows only contracts above its 5% trigger, so it overstates a typical rate.

SFWMD Inspector General table showing change orders at 19.2% of original contract value, 4.8% without outliers
South Florida Water Management District OIG, Monitoring Review of Construction Change Orders as of March 31, 2024 (Project 24-16), Change Order Summary table, page 4. Accessed November 8, 2026.

How do change orders add time to the schedule?

A change order adds time only if the G701 says so, so the day count belongs on the form, not in a later letter. A201-2017 §8.3.1 extends Contract Time for delays caused by the owner or architect, by changes ordered in the work, by weather documented under §15.1.6.2 and by other causes beyond the contractor’s control. Days are calendar days unless the contract says otherwise (§8.1.4), per the A201-2017 form.

A time claim needs notice within 21 days of the event (§15.1.3.1), an estimate of cost and the probable effect on progress (§15.1.6.1), and for weather, data showing conditions were abnormal for the period and could not have been anticipated (§15.1.6.2). A contractor that wants more money must give notice before doing the work, except in an emergency (§15.1.5).

Federal jobs run on FAR 52.243-4 (June 2007): the contractor asserts its right to an adjustment within 30 days of a written change order, costs incurred more than 20 days before notice of a constructive change are not recovered, and nothing is allowed after final payment, per acquisition.gov. These federal rules apply only to federal contracts.

Fort Worth’s internal auditors sampled contracts with change orders approved from October 1, 2019 to June 30, 2020 and found contract days rose 52%. One time-only change order added 444 days and was approved two months after the city’s final acceptance letter, per the 2022 audit. The table lists the nine contracts with day counts.

Sample contractOriginal daysDays added by change orderDays added by allowance requestIncrease
12705640208.9%
230036060140.0%
4365253917.5%
527045016.7%
6480140029.2%
71801512698.3%
85404508.3%
94253007.1%
10330150045.5%
Total3,1601,51012552%

The 125 days added through allowance requests broke the city’s own rule, General Conditions §12.02, that contract time changes only by change order. Track each change’s days against the critical path in your commercial construction schedule and its float.

What should a change-order log track?

A change-order log lists every potential change from the day it is raised until it is signed, rejected or folded into another change, with money and days in separate columns. It should show the running total as a percentage of the original contract, because that is the number public owners report and caps such as Texas’s 25% are measured against, per the Fort Worth audit.

  1. Open a row when a change is raised: owner request, RFI answer or concealed condition, with notice inside 14 days under A201 §3.7.4.
  2. Issue a Proposal Request (AIA G709-2018) describing the change.
  3. Record the contractor’s priced proposal: itemized cost, markup at the contract rate and days requested.
  4. Record the reviewed amount and days after the architect and owner check quantities and rates.
  5. Execute a G701 if all three agree, or a G714 directive if not, and log the instrument number.
  6. Bill approved amounts on the next G702/G703 pay application, submitted at least 10 days before payment (§9.3.1), and update the cumulative percentage.
Six-step change order process from identifying a change to billing it on a G702 pay application 1. Identify Owner request,RFI answer orconcealedconditionNotice within14 days (§3.7.4) 2. Request Architect issuesa ProposalRequest,G709-2018 3. Price Itemized cost+ agreed markup+ days requestedClaim notice21 days (§15.1.3.1) 4. Review Architect andowner checkquantities, ratesand schedule 5. Execute G701 signed byall three, orG714 directiveif no agreement 6. Bill and log Next G702/G703pay application,10 days beforepayment (§9.3.1) A201-2017 days are calendar days (§8.1.4). Work under a directive can be billed before the price is final (§9.3.1.1). Every step gets a row in the change-order log.
A change moves from notice to proposal request, pricing, review, a signed G701 or G714 directive, then billing and the log. AIA A201-2017 §3.7.4, §9.3.1, §15.1.3.1; AIA G709-2018. Accessed November 8, 2026.

The template below uses the worked example and three earlier changes on the same assumed $1,240,000 contract. Copy the columns into a spreadsheet and add a row per potential change order (PCO).

PCORaisedOriginDescriptionInstrumentRequestedApprovedDays asked / approvedStatusCumulative % of original
0012027-01-08RFI 004Add blocking for owner AV mountsCO 001 (G701)$9,850.00$9,400.000 / 0Signed0.76%
0022027-01-15Concealed condition, §3.7.4Remove abandoned slab conduitCCD 001 (G714), then CO 002$24,300.00$22,100.004 / 2Signed2.54%
0032027-01-29Owner requestUpgrade lobby door hardwareCO 003 (G701)$7,600.00$7,100.000 / 0Signed3.11%
0042027-02-12Owner requestSecure storage room, 400 sq ftCO 004 (G701)$14,311.90$14,311.903 / 3Signed4.27%

Rows 001 to 003 total $38,600, the line 2 figure on the G701 shown earlier. Our RFI guide shows when an RFI answer becomes a change order, and our G702 pay application guide shows where approved changes are billed.

Which change instrument fits your situation?

Pick the instrument from two questions: does the change move price or time, and do all three parties agree on both? The table adds the thresholds that public owners and the federal clause attach to each choice. This page explains standard contract forms and public records; it is not legal advice, and your signed contract and any state statute control.

IfThenRule
The change costs nothing and adds no days, and fits the design intentArchitect issues a minor change (G710)A201 §7.4
Contractor believes a minor change does affect price or timeNotify the architect and do not startA201 §7.4 (waiver if it proceeds)
Owner, contractor and architect agree on scope, price and daysSign a G701 Change OrderA201 §7.2.1
Work must start before price or days are agreedOwner and architect issue a G714 directive; contractor proceedsA201 §7.3.2, §7.3.6
Contractor wants more money for a changeGive claim notice before doing the workA201 §15.1.5
Concealed condition found on siteNotify before disturbing it, no later than 14 daysA201 §3.7.4
Cumulative changes would pass 25% on a Texas local government contractThe statute does not allow increases above 25% of the original priceTexas LGC §252.048
Federal VA change over $500,000Submit the proposal under FAR 15.403-5VAAR 852.243-70(a)
Your contract is cost plus a fee or GMPFill A102/A103 §5.1.2 and §5.1.3 before signingA102-2017, A103-2017

Our map of AIA contract documents shows which change forms go with each contract family, including G731 for construction manager as adviser jobs and G741 for design-build.

How we compiled this

We read the AIA A201-2017 standard form, the A102-2017, A103-2017 and G701-2017 samples, AIA’s current document list and one AIA counsel article, two federal clauses (FAR 52.243-4, VAAR 852.243-70), one state DOT specification and one university pricing standard: 17 primary documents, accessed November 2026. Change-order rates come from five public audits and board reports dated 2001 to 2024. The worked example uses assumed inputs, labelled as such, and our own arithmetic; we did not survey contractors or owners.

Frequently asked questions

Who signs a change order?

Under AIA A201-2017 §7.2.1 a change order is signed by the owner, the contractor and the architect, and the G701 form states it is not valid until all three sign. A Construction Change Directive needs only the owner and architect (§7.3.1), and a minor change under §7.4 is signed by the architect alone.

Can a contractor refuse a change order?

A contractor can refuse to sign a G701 if it disagrees on price or time, but under A201-2017 it cannot refuse the work. The owner and architect then issue a Construction Change Directive, the contractor proceeds promptly under §7.3.6, and the price is set later by agreement, by the architect under §7.3.4, or through an Article 15 claim.

What is a reasonable markup on a change order?

A201-2017 sets no percentage; §7.3.4 uses the amount in the Agreement or a reasonable amount. Written schedules range from 10% on self-performed work and 5% on subcontracted work at Case Western Reserve University to 29% on labor and 21% on materials at Washington State DOT, and the VA allows up to 10% overhead plus 10% profit on the first $20,000.

What is the difference between a change order and a construction change directive?

A change order (A201 §7.2, form G701) records full agreement on the change, the price and the time. A construction change directive (A201 §7.3, form G714) orders the work before price or time is agreed, so the job keeps moving. Once owner and contractor agree, the directive is recorded as a change order under §7.3.7 or §7.3.10.

Is there a limit on how much change orders can add to a contract?

Private contracts under A201-2017 have no percentage cap, but changes must stay within the general scope of the contract (§7.3.1). Some public owners cap totals: Texas Local Government Code §252.048 limits increases to 25% of the original price on local government contracts, and the University of Illinois reports changes over 5% to its Board of Trustees.

Does a change order have to be signed before the work starts?

Not always. A201-2017 §15.1.5 requires notice before the contractor proceeds with work it wants paid as extra, and §7.4 makes a contractor that performs a minor change without notice waive any adjustment. Work can start before a signed price only under a Construction Change Directive, which owner and architect sign first.

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.