Land Clearing Cost per Acre: What Commercial Sites Paid in 2025 and 2026 Bids

Partly cleared wooded commercial site with an excavator, log and brush pile, silt fence and standing pines behind

Land clearing cost per acre on commercial sites ran $3,800 to $12,880 for heavily wooded ground with stumps removed across 12 public bid prices dated 2025 and 2026 (median $7,175). Separate debris disposal bids ran $1,900 to $5,000 per acre.

Key takeaways

How much does land clearing cost per acre for a commercial site?

Public bids from 2025 and 2026 put heavy clearing and grubbing at $3,800 to $12,880 per acre, light clearing at $250 to $5,776, and open-field grubbing at about $511. The spread comes from scope: whether stumps come out, whether debris leaves the site, how many acres share the fixed costs, and whether the land is wooded or already open.

Each of the 11 rows below is a dated public record from 7 sources, with its size and scope. CB&C divided award totals by stated acres where an award gave only a total. Texas utility district bids dominate because their engineers publish unit prices per acre; read them as Gulf Coast prices.

Scope in the recordPlace and dateAcresPer acreSource
Heavily wooded clearing and grubbing, stumps out, chip and haul off site (7 bids)Montgomery County, TX, Jul 15, 20269.47$6,800 to $12,880 (median $7,500)Colton MUD 1 bid tab
Heavy clearing and grubbing with root raking, disposal priced separately (2 bids)Fort Bend County, TX, Mar 28, 202537.8$5,200 to $7,521.62Fort Bend MUD 24 bid tab
Light clearing and mowing, disposal priced separately (2 bids)Fort Bend County, TX, Mar 28, 202527.4$3,976.62 to $4,500Fort Bend MUD 24 bid tab
Heavy clearing and grubbing, disposal separate (2 bids)Fort Bend County, TX, Aug 19, 20255.9$3,800 to $5,776Fort Bend MUD 213 bid tab
Medium clearing and grubbing (2 bids)Fort Bend County, TX, Aug 19, 202574.7$3,280 to $5,776Fort Bend MUD 213 bid tab
Light clearing and grubbing (2 bids)Fort Bend County, TX, Aug 19, 202526.3$1,340 to $5,776Fort Bend MUD 213 bid tab
Light clearing, grubbing and mowing as directed (2 bids)Fort Bend County, TX, Aug 19, 202510$250 to $300Fort Bend MUD 213 bid tab
Clearing and grubbing, state averageTennessee DOT Region 4, 202513$7,500TDOT item 201-01.03
Tree clearing and mulching, federal awardEielson AFB, AK, Dec 16, 2025about 44$5,636 (CB&C arithmetic)Award W911KB26CA003
Grubbing at two Navy airfield sitesMeridian, MS, Sep 21, 2025669.5$511 (CB&C arithmetic)Award N6945025F1391
Clearing, grubbing and grading after a tornado (4 bids)North Little Rock, AR, Jul 27, 2023about 157$2,000 to $5,500Bid 23-3824 summary
Land clearing cost per acre in public records, 2024 to 2026Bar chart of per-acre clearing prices: $14,000 Vermont airport item, $12,880 high Texas bid, $7,500 median, down to $511 grubbing and $500 mulching.$ per acreVermont AOT airport clearing and grubbing 14,000Colton MUD 1, TX, Jul 2026, heavy, chip an12,880Winfield Lakes, TX, Mar 2025, heavy, high 7,522Colton MUD 1, TX, Jul 2026, heavy, chip an7,500Tennessee DOT clearing and grubbing, 2025 7,500Eielson AFB, AK, Dec 2025, tree clearing a5,636Winfield Lakes, TX, Mar 2025, heavy, low b5,200Manor Lakes, TX, Aug 2025, heavy, low bid3,800Wisconsin DOT clearing only, FY2025 averag3,500Manor Lakes, TX, Aug 2025, light, low bid1,340Navy airfield grubbing, MS, Sep 2025, 669.511Forest Service understory mulching, TX, Au500
Heavy clearing and grubbing ran $3,800 to $12,880 per acre in 2025 and 2026 public bids; open-ground grubbing and mulching ran $500 to $511. Sources: LJA bid tabulations, state DOT price lists, USAspending.gov, accessed November 1, 2026.

The median of the 12 heavy prices (11 Texas heavy bids plus the Tennessee average) is $7,175 per acre. Bid totals for these Texas jobs ran $114,680 to $2,005,396.40, so the per-acre price is only part of the contract.

What do state DOTs pay per acre for clearing and grubbing?

Most state transportation departments price clearing as a lump sum, so per-acre items are rare. Where they exist, recent averages run $2,420 to $14,000 per acre: Tennessee $7,500 in 2025, Wisconsin $3,500 for clearing alone in fiscal 2025, and Vermont $14,000 for an airport clearing and grubbing item averaged over October 2024 to October 2026.

Agency itemUnitAverage pricePeriodSource
Tennessee DOT 201-01.03 clearing and grubbingAcre$7,500.00 (13 acres)Jan to Dec 2025TDOT 2025 average unit prices
Tennessee DOT 201-01 clearing and grubbingLump sum$211,005.19 per contract (58 contracts)Jan to Dec 2025TDOT 2025 average unit prices
Wisconsin DOT 201.0115 clearingAcre$6,800 (FY2023), $2,420 (FY2024), $3,500 (FY2025)FY2023 to FY2025WisDOT average unit price list, Oct 21, 2025
Wisconsin DOT 201.0215 grubbingAcre$1,220 (FY2023), $3,400 (FY2024)FY2023 to FY2024WisDOT list
Wisconsin DOT 201.0110 clearingSquare yard$9.60 (FY2025), equal to $46,464 per acreFY2025WisDOT list
Vermont AOT 699.0800 (FAA item P-151) clearing and grubbingAcre$14,000.00 (1 contract)Oct 2024 to Oct 2026VTrans 2 year averaged price list
Vermont AOT 699.0750 (FAA item P-151) clearing onlyAcre$12,000.00 (1 contract)Oct 2024 to Oct 2026VTrans list
Arkansas DOT 201 clearingStation (100 ft)$2,002.58 weighted averageJun 2025 to Jun 2026ArDOT weighted average unit prices
Tennessee DOT 2025 average unit price table with item 201-01.03 clearing and grubbing at $7,500 per acre boxed
Tennessee DOT’s 2025 average unit price report lists item 201-01.03, clearing and grubbing by the acre, at $7,500.00 for 13 acres in Region 4. Source: TDOT Average Unit Prices, January 1 to December 31, 2025, page 1, accessed November 1, 2026.

Small patches cost far more per acre. Wisconsin’s $9.60 per square yard clearing price works out to $46,464 per acre at 4,840 square yards per acre, about 13 times its $3,500 per-acre price the same year. Highway averages also bundle mobilization into short roadside strips, so treat them as a cross-check against a site bid, not a substitute.

Is it cheaper to burn, chip and haul, or mulch the debris?

Burning on site was the cheapest disposal in two 2025 Texas bid sets, at $1,900 to $2,300 per acre. Chipping and hauling the material off site ran $1,900 to $5,000 per acre, and chipping it into an on-site stockpile for the owner ran $3,500 to $4,500. Burning needs an authorization in many states, and the Winfield Lakes burn item allowed no extra pay or time if burning was suspended.

Disposal methodProject and dateAcresBid per acreSource
Burn on site (permits, burn pits, ash haul, backfill)Winfield Lakes, TX, Mar 202565.2$1,900 and $2,300Fort Bend MUD 24 bid tab
Chip and haul off site (alternate to burning)Winfield Lakes, TX, Mar 202565.2$1,900 and $4,200Fort Bend MUD 24 bid tab
Burn on siteManor Lakes, TX, Aug 2025106.9$1.00 and $2,200Fort Bend MUD 213 bid tab
Chip and haul off site (alternate 1)Manor Lakes, TX, Aug 2025106.9$3,958 and $5,000Fort Bend MUD 213 bid tab
Chip and stockpile on site for owner pickup, 4,000 ft max haul (alternate 2)Manor Lakes, TX, Aug 2025106.9$3,500 and $4,500Fort Bend MUD 213 bid tab
Forestry mulching of understory in pine stands (federal)Davy Crockett National Forest, TX, Aug 2024440$500Award 12444224F0237
Drum mulching of fuel-load vegetation (federal)Covington County, AL, May 2026118.5$812Award 12444726P0005
Debris disposal bids per acre, two Texas clearing jobs, 2025Grouped bars: burning $1,900 to $2,300 per acre, chip and haul $1,900 to $4,200 and $3,958 to $5,000, stockpile $3,500 to $4,500.02,0004,0006,000$ per acre1,9002,300Burn on site, WinfieldLakes, Mar 20251,9004,200Chip and haul off site,Winfield Lakes, Mar 20253,5004,500Chip and stockpile forowner, Manor Lakes, Aug…3,9585,000Chip and haul off site,Manor Lakes, Aug 2025Low bidHigh bid
Burning on site was bid at $1,900 to $2,300 per acre; chipping and hauling off site at $1,900 to $5,000. Sources: Fort Bend County MUD 24 and MUD 213 bid tabulations, 2025, accessed November 1, 2026.

The $1.00 burn bid at Manor Lakes is a placeholder: that bidder put $0.01 per linear foot on 12,600 feet of silt fence too, which moves cost into other items. Compare bidders on the total for the method you will actually use, as our guide on how to compare construction bids explains.

Forestry mulching is a different job. The federal mulching awards above, $190 to $812 per acre including a 700-acre Kisatchie National Forest award in Louisiana, thin understory and leave the stumps and root mat in place. A building pad still needs grubbing and root removal so the geotechnical engineer can approve the subgrade, as the Winfield Lakes item requires.

What else moves the price per acre?

After tree density and disposal, the biggest swings in these records come from grubbing depth, water crossings, pipelines and project size. Fixed lump sums do not shrink with acreage: Colton’s two staking items cost $21,320 each on 9.47 acres. Each row shows the dollar effect found in a public record.

What moves the priceEvidenceDollar effectSource
Tree densitySame low bidder, Manor Lakes 2025: light, medium, heavy$1,340, $3,280, $3,800 per acreFort Bend MUD 213
Grubbing (stumps and roots)Vermont airport items: clearing vs clearing and grubbing$12,000 vs $14,000 per acre (+$2,000)VTrans list
Above-ground work onlyMowing and light clearing as directed, Manor Lakes$250 to $300 per acreFort Bend MUD 213
Open ground, grubbing onlyNavy airfield grubbing, 669.5 acres$511 per acreAward N6945025F1391
Creek or ditch crossingsTemporary low water crossing, Colton 2026; coffer dam, Winfield 2025$1,000 to $23,900 each; $2,979 to $10,000 eachColton MUD 1, MUD 24
Pipeline in the clearing areaAir bridge matting for pipeline protection, Winfield 2025$5,434 to $10,000 lump sumFort Bend MUD 24
Small project sizeStaking and re-staking at $21,320 each on 9.47 acres vs $10,400 staking on 65.2 acres$4,503 vs $160 per acre (CB&C arithmetic)Colton MUD 1, MUD 24
Scattered single treesWisconsin DOT per inch of trunk diameter, FY2025; Vermont per tree$75.34 clearing plus $14.98 grubbing per inch; $331.70 medium, $1,540 large treeWisDOT, VTrans

Terrain and soil show up as separate items too. Colton priced drainage swales at $2.58 to $14.00 per linear foot, and Winfield Lakes required root raking and back dragging to the approval of the geotechnical engineer. Order soil borings and a Phase I environmental site assessment before clearing so buried debris or fill does not surface as a change order.

Which permits come with clearing 1 acre or more?

Clearing 1 acre or more, or less than 1 acre inside a larger common plan of development that will disturb 1 acre or more, needs construction stormwater permit coverage. Wetland grubbing can need a Corps permit, local codes can protect individual trees, and burning needs its own authorization in many states. This is general information, not legal advice; confirm triggers with your civil engineer and the local permit office.

RuleTriggerWhat it requiresTiming or feeSource
Construction stormwater (federal rule, issued by most states)1 acre or more disturbed, or part of a common plan that will disturb 1 acre or moreWritten SWPPP, then a Notice of Intent (NOI); erosion and sediment controls; inspectionsWhere EPA permits: NOI at least 14 days before workEPA 2022 CGP as modified, Part 1.1.1, Table 1
Florida construction generic permit1 acre or moreSWPPP and NOI to Florida DEPNOI 2 days before work; $250 for 1 to 5 acres, $400 for 5 acres or moreFlorida DEP CGP page
Texas construction general permit TXR150000Small sites 1 to under 5 acres; large sites 5 acres or moreStormwater pollution prevention plan before construction; site noticePermit expires March 5, 2028TCEQ construction stormwater
Wetlands, Clean Water Act Section 404 (federal)Mechanized land clearing or grubbing that redeposits soil in waters of the United StatesU.S. Army Corps of Engineers authorizationCutting above ground without disturbing roots is excluded33 CFR 323.2(d)
Local tree protection (example: Tampa)Most non-exempt trees 5 inches DBH or more; grand trees 32 inches or moreTree removal permit, replacement or mitigation paymentDBH is measured 4.5 feet above gradeCity of Tampa Chapter 27 definitions
Open burning (example: Florida)Land clearing burns; piles over 8 feet acrossFlorida Forest Service burn authorizationIssued by the local field unitFlorida Forest Service
Which permits come with clearing a commercial site Four yes or no questions: 1 acre or more of disturbance, wetlands, protected trees, and burning, each leading to the permit it triggers. Planning to clear a commercial site 1. Will the project disturb 1 acre or more, or sit in a common plan that will? No: no federal stormwater permit Yes: construction general permit Write the SWPPP first, then file the NOI. Where EPA permits: 14 days before work. Florida DEP: 2 days, $250 or $400 fee. 2. Are there wetlands or other waters on the tract? No: go to question 3 Yes: Section 404 review Grubbing, root raking or pushing soil there is a discharge (33 CFR 323.2). Cutting above ground only is not. 3. Does the local code protect trees on the site? No: go to question 4 Yes: tree removal permit Tampa protects most trees of 5 inches DBH and up; grand trees from 32 inches. Expect replacement or mitigation fees. 4. Will debris be burned on site? No: price chip and haul off site, or chip and stockpile for the owner Yes: burn authorization Florida Forest Service authorizes land clearing burns and piles over 8 feet. Other states set their own rules. Then bid the clearing with each trigger priced as its own line item: SWPPP compliance, silt fence per LF, construction exit, tree fence, disposal per acre, and any water crossing or pipeline protection. Yes Yes Yes Yes
Clearing 1 acre or more triggers construction stormwater coverage; wetland grubbing, protected trees and burning each add a permit. Sources: EPA 2022 CGP, 33 CFR 323.2, City of Tampa, Florida Forest Service, accessed November 1, 2026.

Who issues the stormwater permit?

EPA issues the construction general permit itself only in Massachusetts, New Hampshire, New Mexico, the District of Columbia, Puerto Rico, other territories and Indian country, per CGP Appendix B. Other states run their own version, such as Florida DEP and the Texas Commission on Environmental Quality. EPA’s 2022 permit expires February 16, 2027, and a proposed 2027 permit was published for comment on August 3, 2026.

Do you need a building permit first?

Usually not. Many cities issue a separate site clearing or land disturbance permit, and in Florida, section 713.135(1)(e)4 lets land clearing permits issue before a notice of commencement is recorded. Our guides to commercial building permits and the Florida notice of commencement cover the rest of the sequence.

What order does the clearing work follow?

On a commercial site of 1 acre or more, the paperwork comes before the dozer. Under the EPA permit the SWPPP is written first, perimeter controls go in before clearing, and any ground left idle 14 days or more must be stabilized within 14 calendar days. The steps below carry the deadlines and the 2025 unit prices bid for each control.

  1. Write the SWPPP. EPA CGP Part 7.1 requires it before the NOI is filed.
  2. File the NOI. Where EPA permits, at least 14 calendar days before work; Florida DEP needs it 2 days before, with a $250 or $400 fee.
  3. Install perimeter controls. Silt fence was bid at $2.12 to $3.00 per linear foot and a stabilized construction exit at $3,548 to $8,250 at Winfield Lakes in 2025.
  4. Protect what stays. Fence trees to keep, and keep a 50-foot undisturbed natural buffer, or equivalent controls, for waters within 50 feet (CGP Part 2.2.1).
  5. Clear and grub. Heavy clearing ran $3,800 to $12,880 per acre in the 2025 and 2026 bids above.
  6. Dispose of debris. Burn, chip and haul, or stockpile: $1,900 to $5,000 per acre, excluding one $1.00 placeholder bid.
  7. Inspect. Every 7 calendar days, or every 14 days and within 24 hours of a storm of 0.25 inches or more (CGP Part 4.2).
  8. Stabilize. Start immediately on ground idle 14 days or more and finish within 14 calendar days (CGP Table 2, sites disturbing 5 acres or less at a time).
Order of work for clearing a commercial site of 1 acre or more Eight steps from writing the SWPPP to stabilizing idle ground, with the deadlines and unit prices that apply to each. Order of work, from paperwork to stabilized ground 1. Write SWPPP Required before the NOI under EPA CGP Part 7.1 2. File the NOI EPA: 14 days before work Florida DEP: 2 days, $250 or $400 3. Perimeter Silt fence $2.12 to $3.00 per LF; construction exit $3,548 to $8,250 4. Protect Fence trees that stay; keep a 50 ft natural buffer from nearby waters 5. Clear and grub Heavy: $3,800 to $12,880 per acre in 2025 and 2026 public bids 6. Dispose Burn, chip and haul, or stockpile: $1,900 to $5,000 per acre 7. Inspect Every 7 days, or every 14 days and within 24 hours of 0.25 in of rain 8. Stabilize Ground idle 14+ days: start at once, finish within 14 calendar days Sources: EPA 2022 CGP as modified; Florida DEP; LJA bid tabulations, 2025 and 2026.
Under the EPA permit the SWPPP comes before the NOI, and idle ground must be stabilized within 14 calendar days. Sources: EPA 2022 CGP as modified, Florida DEP, LJA bid tabulations, accessed November 1, 2026.

Clearing also runs on a short clock: the bid forms listed contract times of 25/5 calendar days for 9.47 acres at Colton, 60/75 days for 65.2 acres at Winfield Lakes and 60/70 days for 106.9 acres at Manor Lakes. Build those durations into the schedule for new commercial construction before the pad work starts.

What does clearing a 10-acre commercial site cost? A worked example

A hypothetical 10-acre Gulf Coast site with 6 wooded acres and 4 acres of brush comes to about $99,711, or $9,971 per acre, using the 2025 and 2026 Texas bid prices above. Clearing and disposal are $74,153 of that, 74.4%. Stormwater controls and staking make up the rest.

Line itemQuantityUnit price usedTotalPrice basis
Heavy clearing and grubbing, stumps out, chip and haul6 acres$7,500$45,000.00Median of 7 bids, Colton MUD 1, Jul 2026
Light clearing and mowing4 acres$4,238.31$16,953.24Average of 2 bids, Winfield Lakes, Mar 2025
Chip and haul disposal for the light acres4 acres$3,050$12,200.00Average of 2 bids, Winfield Lakes alternate
Silt fence around the site2,640 LF$2.56$6,758.40Average of 2 bids, Winfield Lakes; square 10-acre perimeter
Stabilized construction exit1$5,899$5,899.00Average of 2 bids, Winfield Lakes
SWPPP compliance, inspections, NOI and NOT1$2,500$2,500.00Both bids, Manor Lakes, Aug 2025
Construction staking1$10,400$10,400.00Both bids, Winfield Lakes
Total10 acres$99,710.64$9,971.06 per acre

The example excludes grading, fill, survey of the boundary, permit fees outside Florida, and any water crossing. A 10-acre square has a perimeter of about 2,640 feet (660 feet a side); an irregular tract needs more fence. Moving the disposal to on-site burning at the $1,900 to $2,300 Winfield bids would cut the light-acre disposal by $3,000 to $4,600, if a burn authorization is available.

Why do residential lot quotes look different?

Consumer cost guides mostly quote homeowner jobs from quote aggregators, not bid tabulations. Their heavily wooded ranges top out near $5,600 to $8,000 per acre, while 10 of the 12 heavy commercial prices above exceed $5,600. Small residential jobs priced by the tree run much higher per acre.

Claim in a top-ranking guideWhat the public record showsSource
A home-improvement guide updated February 2023: heavily wooded land costs $3,000 to $5,600 per acre10 of 12 heavy commercial prices from 2025 and 2026 exceed $5,600; median $7,175Colton, Winfield, Manor Lakes, TDOT
The same guide also gives $250 to $1,000 per acre for clearingThat fits mowing and open-ground grubbing ($250 to $511), not wooded landManor Lakes, Navy award
A home-improvement guide lists land clearing permits at up to about $200Commercial bids carry SWPPP compliance at $1,313 to $3,500 plus silt fence and exits; Florida’s NOI fee alone is $250 or $400Winfield, Florida DEP
Contrast: residential and tree-by-tree work0.83 acre of tree removal with stump grinding in Bethel, Ohio cost $38,787.09 in October 2024, or $46,731 per acreUSDA APHIS award 12639525F0015

The Ohio award is a labelled contrast, not a site-clearing price: it removed high-risk Asian longhorned beetle host trees on a 0.83-acre work plan and ground the stumps. Work priced per tree or per small patch costs far more per acre than mass clearing, so a residential lot quote and a commercial tract bid should not be used to budget each other.

Which clearing approach fits your site?

Match the scope to what will be built. Building pads and paving need full grubbing; open space and future phases may only need mowing or mulching. These thresholds come from the bid scopes and federal rules cited above, with the price each choice carried in 2025 and 2026.

If your site isThen specifyTypical public bid per acreSource
Under a building pad or pavingClearing and grubbing with stumps and roots removed, root raking to the geotech’s approval$3,800 to $12,880Winfield, Colton
Open field or pastureGrubbing or mowing only$250 to $511Manor Lakes, Navy award
Wooded land kept as open space or a future phaseForestry mulching, stumps left$190 to $812Kisatchie, Alabama award
In or next to wetlandsCut above ground only until a Section 404 decisionNo public per-acre benchmark found33 CFR 323.2
1 acre or more of total disturbanceSWPPP, NOI, silt fence, construction exit in the same bidSWPPP lump sum $1,313 to $3,500EPA CGP, Winfield
Burning allowed and permittedBurn on site as base bid, chip and haul as alternate$1,900 to $2,300 burn vs $1,900 to $5,000 haulWinfield, Manor Lakes

For a warehouse or distribution site, line these items up against the shell budget in our warehouse construction guide, and against the all-in ranges in commercial construction cost per square foot; the 10-acre example above came to $9,971 per acre before grading.

Soil borings usually follow clearing, and our geotechnical report guide explains what they cost and what they decide.

The construction permit ends at stabilization, but the permanent stormwater pond, its slopes and its inspection schedule are covered in our guide to the retention pond.

The plan itself, its 11 required sections and its inspection deadlines are covered in our guide to the SWPPP for construction sites.

How we compiled this

We read 4 public bid tabulations (Texas 2025 and 2026, Arkansas 2023), 4 state DOT average price lists, 6 federal awards on USAspending.gov, the EPA 2022 Construction General Permit as modified in April 2025, and state and local permit pages, all accessed November 1, 2026. CB&C arithmetic divides a stated total by stated acres. We excluded figures seen only in search snippets, such as a Montana DOT average we could not open.

Frequently asked questions

How much does it cost to clear 1 acre of land?

For a wooded commercial acre with stumps removed, 2025 and 2026 public bids ran $3,800 to $12,880, with a median of $7,175 across 12 prices. Light brush ran $250 to $5,776 per acre. A single acre usually costs more per acre than a large tract, because staking, mobilization and stormwater controls are spread over fewer acres.

How long does it take to clear an acre of land?

Public bids set whole-project clocks rather than per-acre times. Colton MUD 1 in Texas listed a contract time of 25/5 calendar days for 9.47 heavily wooded acres in 2026, and Winfield Lakes listed 60/75 days for 65.2 acres in 2025. Weather, burn bans and Corps or tree permit reviews can stretch those windows.

Do I need a permit to clear less than 1 acre?

Federal stormwater coverage applies at 1 acre or more, or below 1 acre when the clearing is part of a larger common plan that will disturb 1 acre or more. Local codes can still apply below that line: Tampa, for example, requires a tree removal permit for most trees of 5 inches DBH or more.

Can I clear land in a wetland without a permit?

Under 33 CFR 323.2, cutting vegetation above ground with mowers, rotary cutters or chainsaws, without substantially disturbing roots, is not a discharge. Grubbing, root raking or mechanized pushing that redeposits soil in waters of the United States is, and needs U.S. Army Corps of Engineers review. Ask your engineer for a wetland delineation first.

Is forestry mulching cheaper than clearing and grubbing?

Yes per acre, but it does a different job. Federal mulching awards ran $190 to $812 per acre in 2024 to 2026, against $3,800 to $12,880 for heavy clearing and grubbing. Mulching leaves stumps and roots, so building pads and paving still need grubbing to meet the geotechnical engineer’s subgrade approval.

Does land clearing include grading?

Usually not. The 2025 and 2026 Texas bids priced clearing, disposal, silt fence, staking and seeding as separate lines, and grading of the pad comes later under the earthwork contract. Some bids add small grading items, such as drainage swales at $2.58 to $14.00 per linear foot at Colton MUD 1 in 2026.