A pay when paid clause sets only when a subcontractor is paid: if the owner never pays, the general contractor still owes the sub within a reasonable time. Pay if paid makes owner payment a condition, shifting that risk.
Key takeaways
- Courts read an unclear pay-when-paid clause as a timing rule with payment due “within a reasonable time,” the rule of Thos. J. Dyer Co. v. Bishop International Engineering, 303 F.2d 655 (6th Cir. 1962).
- A pay-if-paid clause shifts owner nonpayment risk only if it is clear: the Florida Supreme Court in DEC Electric v. Raphael Construction (1990) put “the burden of clear expression” on the general contractor.
- Pay-if-paid is void, unenforceable or overridden in at least 8 states we checked at the primary source: California, New York, North Carolina, South Carolina, Wisconsin, Virginia (except owner insolvency), Massachusetts (narrow exceptions) and Nevada (a stop-work right applies despite the clause).
- Maryland, Missouri and Kansas let the clause stand between the parties but bar it as a defense to a mechanics lien or bond claim (Md. Real Prop. 9-113, RSMo 431.183, K.S.A. 16-1803(c)).
- On federal jobs, FAR 52.232-27(c)(1) requires every subcontract to pay subs within 7 days of the prime being paid, and a sub unpaid 90 days after its last work can sue on the Miller Act bond (40 U.S.C. 3133(b)).
This page explains contract terms in general and is not legal advice; for a live dispute, ask a construction attorney licensed in the project’s state which statute (for example Va. Code 11-4.6 or Wis. Stat. 779.135) governs the subcontract and whether the clause is read as timing or as a condition.
| Key number | What it means | Source |
|---|---|---|
| 7 days | Federal prime must pay subs after it is paid | FAR 52.232-27(c)(1); 31 U.S.C. 3905(b) |
| 7 days or 60 days | Virginia: GC pays the sub by the earlier of 7 days after being paid or 60 days after the sub’s invoice | Va. Code 11-4.6(B)(2) |
| 7 business days, 18% | Kansas private jobs: GC pays the sub after receipt; 18% a year interest after that | K.S.A. 16-1803(f), (g) |
| 10 days | Median deadline for a prime to pay subs on state and local public work (41 jurisdictions) | Our prompt payment registry, statutes checked October 8, 2026 |
| 90 days | Unpaid federal sub may sue on the Miller Act payment bond | 40 U.S.C. 3133(b)(1) |
What is the difference between pay when paid and pay if paid?
Pay when paid answers “when”: the general contractor pays the sub a set number of days (7 in the AIA forms) after the owner pays, and if the owner never pays, the debt is still due after a reasonable time. Pay if paid answers “whether”: owner payment is a condition precedent, so if the owner never pays, the sub may never be paid. The words “condition precedent” and an express risk transfer separate them.
A condition precedent is an event that must happen before a duty to perform exists. In a pay-if-paid subcontract, the duty to pay the sub does not arise until the owner pays the general contractor, which is why courts in 1962 (Dyer) and 1990 (DEC Electric) demanded plain wording before reading a clause that way.
| Question | Pay when paid | Pay if paid | Source |
|---|---|---|---|
| What it controls | Timing of payment | Whether payment is owed at all | DEC Electric (Fla. 1990) |
| Owner pays on time | Sub paid within the stated days | Sub paid within the stated days | Contract terms |
| Owner never pays | GC pays within a reasonable time | GC owes nothing, where the clause is clear and the state allows it | Dyer (6th Cir. 1962); DEC Electric |
| Who carries owner default risk | General contractor | Subcontractor | West-Fair (N.Y. 1995) |
| How an ambiguous clause is read | As written | As pay when paid | DEC Electric (Fla. 1990) |
| Enforceable | Most states, subject to prompt payment deadlines | Void or overridden in at least 8 states; limited for liens in 3 more | State table below |
What does sample pay-when-paid and pay-if-paid language look like?
The two sample clauses below are illustrative drafting examples written for this page, not quotes from a form or a court record. The third row is the AIA subcontract wording as quoted in a 2015 construction-law bulletin. Compare the second row with the first: the words “condition precedent” and “assumes the risk” are what turn a timing clause into a pay-if-paid clause.
| Clause type | Sample wording | How a court is likely to read it |
|---|---|---|
| Pay when paid (illustrative) | “Contractor shall pay Subcontractor within 7 days after Contractor receives payment from Owner for Subcontractor’s Work.” | Timing only; payment due within a reasonable time if the owner never pays (Dyer rule) |
| Pay if paid (illustrative) | “Receipt of payment by Contractor from Owner for Subcontractor’s Work is a condition precedent to Contractor’s obligation to pay Subcontractor. Subcontractor assumes the risk of Owner’s nonpayment.” | Condition precedent where the state allows it and the wording is clear (DEC Electric) |
| AIA A401 progress payment | “The Contractor shall pay the Subcontractor each progress payment no later than seven working days after the Contractor receives payment from the Owner” (as quoted by Taft Stettinius, February 2015) | Timing language; no condition-precedent wording in the quoted sentence |
How do courts read a pay-when-paid clause?
Most courts start from the Dyer rule: a promise to pay the sub “when” the owner pays is a promise to pay within a reasonable time, because forcing the sub to wait for a payment “which may never occur” is an unreasonable reading. The Sixth Circuit applied that rule under Ohio law in 1962, and later courts in Florida and Louisiana have cited it as the leading case.
The Florida Supreme Court set the two-way test in DEC Electric, Inc. v. Raphael Construction Corp., 558 So.2d 427 (1990): a clear and unambiguous clause is a condition precedent; an ambiguous one fixes a reasonable time. The court put the burden of clear expression on the general contractor, reasoning that small subcontractors who need payment to stay in business do not usually agree to carry the owner’s credit risk.
- Words that point to timing: “within 7 days after,” “when,” “upon receipt,” with no statement of risk.
- Words that point to a condition: “condition precedent,” “only if,” “subcontractor assumes the risk of owner nonpayment,” “sole source of payment.”
- How long is reasonable: no fixed number in Dyer or DEC Electric; where a state sets one, the statute controls, such as Virginia’s 60 days after the invoice under Va. Code 11-4.6(B)(2).
Which states void or limit pay-if-paid clauses?
We confirmed 8 states where a pay-if-paid condition is void, unenforceable or overridden by statute and 3 more where it cannot defeat a mechanics lien or bond claim, each against the statute or court opinion linked below (read November 15, 2026). Wisconsin’s statute is the clearest on the split: it voids the condition but expressly allows a clause that delays payment until the prime is paid.
| State | Rule | Pay when paid (timing) | Primary source |
|---|---|---|---|
| California | Pay-if-paid unenforceable: an indirect waiver of constitutionally protected mechanics lien rights | Not addressed in the holding we read | Wm. R. Clarke Corp. v. Safeco Ins. Co., 15 Cal.4th 882 (1997) |
| New York | A clause that forces the sub to assume owner nonpayment risk is void under Lien Law 34, even when labelled pay when paid | Valid only as timing | West-Fair Elec. Contractors v. Aetna, 87 N.Y.2d 148 (1995) |
| North Carolina | Owner payment is not a condition precedent; contrary agreement unenforceable | A 2025 bill (H383) proposed voiding delays over 30 days; enactment not confirmed | N.C. Gen. Stat. 22C-2; 2025 H383 |
| South Carolina | Owner payment is not a condition precedent; contrary agreement not enforceable (2000 Act No. 295) | Not addressed | S.C. Code 29-6-230 |
| Wisconsin | Condition precedent void | Expressly allowed: a clause “may delay a payment” until the prime is paid | Wis. Stat. 779.135(3) |
| Virginia | Not a condition precedent unless the paying party is insolvent or in bankruptcy; contrary provision unenforceable | Capped: earlier of 7 days after GC is paid or 60 days after invoice | Va. Code 11-4.6(B)(2) |
| Massachusetts | Conditional payment void except uncured sub default or third-party insolvency within 90 days with lien steps taken; never a defense to a ch. 254 lien. Prime contracts of $3 million or more only | Not addressed in the text we read | M.G.L. c.149, s.29E(e) |
| Nevada | Higher tier pays within 10 days after it is paid; lower tier may stop work if unpaid 45 days after the 25th of the billing month, even with an if-or-when-paid clause | Overridden by the stop-work right | NRS 624.624 to 624.628 |
| Maryland | Clause may not waive mechanics lien or bond rights; such a provision is void | Allowed between the parties | Md. Real Prop. 9-113(b), (c) |
| Missouri | Contingent payment is no defense to a mechanics lien claim (private owner) | Allowed between the parties | RSMo 431.183 |
| Kansas | No defense to a lien or bond claim; GC pays within 7 business days of receipt | Capped by the 7-business-day rule | K.S.A. 16-1803(c), (f) |
| Florida (contrast) | Enforced if clear and unambiguous; ambiguous clause read as reasonable time | Allowed | DEC Electric v. Raphael (Fla. 1990) |
Lien rights sit underneath every row: even where a pay-if-paid clause is enforced against the sub, the lien deadlines in our mechanics lien laws by state report still run from the sub’s last work, not from the owner’s payment.
What do some guides get wrong about these state rules?
Ranking guides on this query disagree on which states ban which clause: the lists we saw named 4, 6 and 11 states, and none we read links a statute. The table sets three common claims against the primary text checked on November 15, 2026, so you can see where the shortcut goes wrong.
| What several guides say | What the primary source says | Source |
|---|---|---|
| A few states void both pay-if-paid and pay-when-paid clauses, often including Wisconsin | Wisconsin voids the condition but says the statute “does not prohibit contract provisions that may delay a payment” until the prime is paid | Wis. Stat. 779.135(3) |
| The label decides: “pay when paid” is safe, “pay if paid” is risky | New York voided a clause labelled pay when paid because it made the sub carry owner nonpayment risk | West-Fair, 87 N.Y.2d 148 (1995) |
| An enforceable pay-if-paid clause wipes out the sub’s lien | Maryland, Missouri, Kansas and Massachusetts bar the clause as a defense to a lien or bond claim | Md. Real Prop. 9-113; RSMo 431.183; K.S.A. 16-1803(c); M.G.L. c.149 s.29E |
When did each of these rules arrive?
The rules built up over six decades, from one federal appeals case in 1962 to the Kansas statute in 2005, which is why older guides list fewer states. Each date below comes from the opinion or the statute history line.
- 1962: Thos. J. Dyer Co. v. Bishop (6th Cir.) reads pay when paid as payment within a reasonable time.
- 1990: DEC Electric v. Raphael (Fla.) requires clear wording for a condition precedent.
- 1991: North Carolina House Bill 1027 adds the condition-precedent ban now in G.S. 22C-2.
- 1995: New York’s West-Fair decision voids risk-shifting clauses; Missouri’s RSMo 431.183 takes effect August 28.
- 1997: California’s Wm. R. Clarke decision voids pay-if-paid.
- 2000: South Carolina Act No. 295 enacts S.C. Code 29-6-230.
- 2005: Kansas enacts K.S.A. 16-1803 (L. 2005, ch. 156), amended 2009.
Do prompt payment laws override a pay-when-paid clause?
Yes, where they apply: a prompt payment statute sets an outside deadline that a timing clause cannot stretch. On state and local public work, primes must pay subs a median 10 days after being paid; 16 of 50 verified jurisdictions require 7 days, per our public construction prompt payment and retainage registry (statutes checked October 8, 2026).
| Prime-to-sub deadline after the prime is paid (public work) | Jurisdictions | Examples |
|---|---|---|
| 7 days | 16 | California, New York, North Carolina, South Carolina, Virginia, Wisconsin |
| 8 to 10 days | 14 | Florida, Georgia, Kansas, Maryland, Nevada, Texas |
| 11 to 15 days | 6 | Connecticut, Illinois, Missouri, Pennsylvania |
| 16 to 30 days | 4 | Kentucky, South Dakota, Tennessee, Utah |
| Over 30 days | 1 | North Dakota |
| No fixed deadline located | 9 | Delaware, Indiana, Massachusetts, Michigan |
Private jobs have fewer rules. Virginia’s Va. Code 11-4.6 covers private construction contracts and adds a 50-day written notice before a GC may withhold, and it flows the same terms to lower tiers on non-residential projects over $500,000. Kansas’s Fairness in Private Construction Contract Act gives owners 30 days to pay the GC and GCs 7 business days to pay subs, each with 18% a year interest. Retainage runs on its own clock; our guide to retainage in construction covers release deadlines.
What does federal law require on government jobs?
On a federal construction contract, a pay-if-paid clause cannot delay the 7-day rule once the government pays the prime. FAR 52.232-27(c) and 31 U.S.C. 3905(b) require every subcontract to pay subs for satisfactory work within 7 days “out of such amounts as are paid” to the prime, with interest at the Treasury rate if late, flowed down to every tier.
- Day 0: the prime submits a proper payment request. The government’s due date for a progress payment is 14 days after the billing office receives it (FAR 52.232-27(a)(1)(i)(A)).
- Within 7 days of receiving that payment, the prime pays each sub its share (FAR 52.232-27(c)(1)).
- Late payment carries interest at the Prompt Payment Act rate, 4.75% a year for July 1 to December 31, 2026 per Treasury: $351.37 on $90,000 paid 30 days late.
- A prime may withhold for deficient work only after written notice to the sub and the contracting officer (FAR 52.232-27(c) and (d)).
- If still unpaid 90 days after its last labor or material, the sub may sue on the Miller Act payment bond regardless of the payment clause (40 U.S.C. 3133(b)(1)); second-tier claimants must give written notice to the prime within 90 days.
Owners and primes bidding federal work, where FAR 52.232-27 applies, can see where that money goes in our federal construction contracts by state report, and our construction surety bonds report explains how payment bonds back the sub’s claim.
How does the AIA A401 subcontract handle payment timing?
The AIA A401-2017 subcontract uses timing language, not a condition precedent: as quoted in a 2015 construction-law bulletin, the contractor pays each progress payment “no later than seven working days after the Contractor receives payment from the Owner.” That wording reads as pay when paid unless the parties add condition-precedent language in the blanks or a rider.
The prime contract points the same way. AIA A201-2017 §9.6.2 requires the contractor to pay each subcontractor no later than 7 days after receiving payment from the owner, and our AIA A201 guide lists the related stop-work clock in §9.7. Pay applications usually run on the AIA G702 payment application, and each payment is traded for a conditional then unconditional lien waiver.
What does a pay-when-paid clause do to a subcontractor’s cash flow?
Under a pay-when-paid clause the sub’s cash arrives one link after the owner’s, so a 37-day owner delay becomes a 44-day wait for the sub. The worked example uses Virginia because Va. Code 11-4.6(B)(2) sets both clocks: 7 days after the GC is paid, or 60 days after the sub’s invoice, whichever is earlier. Amounts are illustrative.
| Step | Date | Arithmetic | Rule |
|---|---|---|---|
| Sub invoices the GC for work through January | Mon Feb 1, 2027 (day 0) | $100,000 billed less 10% contract retainage = $90,000 due | Subcontract terms (illustrative) |
| Owner pays the GC | Wed Mar 10, 2027 (day 37) | Owner’s own 60-day clock from the GC’s invoice | Va. Code 11-4.6(B)(1) |
| GC must pay the sub | Wed Mar 17, 2027 (day 44) | Mar 10 + 7 days, earlier than Apr 2 | Va. Code 11-4.6(B)(2) |
| Last day for a written withholding notice | Tue Mar 23, 2027 (day 50) | Feb 1 + 50 days | Va. Code 11-4.6(B)(2) |
| Outside date if the owner never pays | Fri Apr 2, 2027 (day 60) | Feb 1 + 60 days | Va. Code 11-4.6(B)(2); pay-if-paid unenforceable unless owner insolvent |
| Same $90,000 in Kansas, paid 30 days after the 7-business-day deadline | Not dated | $90,000 x 18% x 30/365 = $1,331.51 interest | K.S.A. 16-1803(g) |
For a sub carrying payroll every week, the gap from day 0 to day 44 is the working capital it must finance. Owners can shorten it by funding draws on a fixed calendar, as set out in our construction draw schedule guide.
Which payment clause should you sign or ask for?
Match the clause to the state and to who you are, using the 11 state rules above. A sub should strike “condition precedent” language or add an outside date; a GC that needs owner-default protection must use clear condition-precedent wording and confirm the project state enforces it. Owners gain from pay-when-paid terms because subs price owner credit risk into bids.
| If | Then | Rule behind it |
|---|---|---|
| The job is federal | Expect 7-day flow-down; keep Miller Act notice dates (90 days) | FAR 52.232-27(c); 40 U.S.C. 3133(b) |
| The job is in CA, NY, NC, SC, WI, VA, MA or NV | Treat any pay-if-paid wording as timing only; know the statutory deadline | State table above |
| You are a sub and the clause says “condition precedent” | Ask to replace it with “within 7 days after receipt, and in any event within 45 days after invoice” | Dyer reasonable-time rule; Va. Code 11-4.6 60-day model |
| You are a GC and need owner-default protection | Use express condition-precedent and risk-transfer words; ambiguity is read against you | DEC Electric (Fla. 1990) |
| The job is in MD, MO, KS or MA and payment stalls | Keep lien and bond deadlines; the clause is no defense | Md. Real Prop. 9-113; RSMo 431.183; K.S.A. 16-1803(c); M.G.L. c.149 s.29E |
| You are an owner | Require subcontracts to pay within 7 days of each draw; collect conditional and unconditional waivers | AIA A201-2017 §9.6.2 |
Owners comparing general contractors can ask how many days each one takes to pay its subs (7 is the AIA A201 benchmark) and whether its subcontract uses a pay-if-paid clause; our checklist on how to choose a commercial contractor lists the other payment red flags.
Payment timing also turns on retainage and on the conditional lien waivers exchanged with each draw.
How we compiled this
We read 19 primary documents in November 2026: 9 state statutes, 4 court opinions, FAR 52.232-27, 31 U.S.C. 3905, 40 U.S.C. 3133, AIA A201-2017 and the Treasury rate table, plus the deadlines in our October 2026 prompt payment registry. All 9 statutes were read in full (4 rechecked November 21, 2026); the four opinions through extracts. We left out states commonly listed elsewhere (Texas, Illinois, Indiana, Ohio, Delaware, Montana, Utah, Kentucky) because we could not open their primary text this month.
Frequently asked questions
Is a pay when paid clause legal?
Yes, in most states a pay when paid clause is legal as a timing term. Courts following Thos. J. Dyer Co. v. Bishop (6th Cir. 1962) read it as payment within a reasonable time, and statutes such as Va. Code 11-4.6 cap the wait at 60 days after the invoice. What many states void is the pay-if-paid version that makes owner payment a condition.
What is the difference between pay if paid and pay when paid?
Pay when paid sets when the sub is paid, usually a set number of days after the owner pays the general contractor, and the debt survives if the owner defaults. Pay if paid makes owner payment a condition precedent, so the sub carries the risk. The Florida Supreme Court in DEC Electric (1990) reads any ambiguous clause as pay when paid.
Which states prohibit pay if paid clauses?
We confirmed 8 at the primary source in November 2026: California (Clarke, 1997), New York (West-Fair, 1995), North Carolina (G.S. 22C-2), South Carolina (29-6-230), Wisconsin (779.135(3)), Virginia (11-4.6, except owner insolvency), Massachusetts (c.149 s.29E, narrow exceptions) and Nevada (NRS 624 stop-work right). Maryland, Missouri and Kansas bar the clause only as a defense to liens or bond claims.
How long is a reasonable time under a pay when paid clause?
Courts have not fixed one number; Dyer (1962) and DEC Electric (1990) leave it to the facts. Statutes often fill the gap: Virginia sets the earlier of 7 days after the GC is paid or 60 days after the invoice, Kansas sets 7 business days after receipt, and federal subcontracts require 7 days under FAR 52.232-27.
Does a pay if paid clause stop a subcontractor from filing a mechanics lien?
Not in several states. Maryland Real Property 9-113, RSMo 431.183, K.S.A. 16-1803(c) and Massachusetts c.149 s.29E say the clause is no defense to a lien or bond claim, and California’s Clarke decision (1997) voided pay-if-paid because it worked as a lien waiver. Lien deadlines still run from the last day of work.
Does pay when paid apply on federal construction projects?
Only within the federal 7-day rule. FAR 52.232-27(c)(1) and 31 U.S.C. 3905(b) require every subcontract to pay subs within 7 days after the prime is paid, with Treasury-rate interest when late. A sub unpaid 90 days after its last work can sue on the Miller Act payment bond under 40 U.S.C. 3133(b).
Sources
- Code of Virginia 11-4.6, Required contract provisions in construction contracts, Virginia LIS, accessed November 15, 2026.
- S.C. Code 29-6-230, South Carolina Legislature, accessed November 15, 2026.
- Md. Code, Real Property 9-113, Maryland General Assembly, accessed November 15, 2026.
- RSMo 431.183, Missouri Revisor of Statutes, accessed November 15, 2026.
- K.S.A. 16-1803, Kansas Office of Revisor of Statutes, accessed November 15, 2026.
- N.C. Gen. Stat. 22C-2 and 2025 House Bill 383, North Carolina General Assembly, accessed November 15, 2026.
- Wis. Stat. 779.135, Wisconsin Legislature, accessed November 15, 2026.
- NRS chapter 624, Nevada Legislature, accessed November 15, 2026.
- M.G.L. c.149, s.29E, Massachusetts Legislature, accessed November 15, 2026.
- FAR 52.232-27 Prompt Payment for Construction Contracts (Jan 2017), Acquisition.gov, accessed November 15, 2026.
- 31 U.S.C. 3905 and 40 U.S.C. 3133, Legal Information Institute, accessed November 15, 2026.
- Prompt Payment interest rates, U.S. Treasury Bureau of the Fiscal Service, accessed October 8, 2026.
- West-Fair Elec. Contractors v. Aetna, 87 N.Y.2d 148 (1995); Wm. R. Clarke Corp. v. Safeco, 15 Cal.4th 882 (1997); Thos. J. Dyer Co. v. Bishop, 303 F.2d 655 (6th Cir. 1962); DEC Electric v. Raphael, 558 So.2d 427 (Fla. 1990), Justia, accessed November 15, 2026.
- AIA A201-2017 standard form, sample copy, City of Rochester, NH bid attachment, accessed October 19, 2026; AIA A401-2017 store page, AIA Contract Documents.
- What Difference Does It Make? Pay If Paid vs. Pay When Paid, Taft Stettinius and Hollister law bulletin, February 16, 2015, accessed November 15, 2026.