Skip to content

Restaurant Construction Cost per Square Foot: 1,788 Texas Projects

Unfinished commercial tenant space with stud framing and ductwork during a restaurant build-out

Restaurant construction cost in 1,788 Texas project registrations from 2024 to 2026 ran a median $371 per sq ft for ground-up buildings, $146 to finish a shell and $125 to re-fit an existing restaurant, before land and equipment.

Key takeaways

  • Across 396 ground-up restaurant buildings registered in Texas from January 2024 to November 2026, the median estimated construction cost was $1,100,000, or $371 per sq ft, for a median 2,994 sq ft building (TDLR TABS).
  • Finishing a first-generation shell or converting a non-restaurant space ran a median $146 per sq ft in 547 records, and re-fitting a space that was already a restaurant ran $125 per sq ft in 577 records (TDLR TABS).
  • Small buildings cost the most per foot: ground-up restaurants under 2,500 sq ft had a median of $423 per sq ft, against $221 for buildings of 6,000 to 15,000 sq ft (TDLR TABS).
  • One kitchen hood with its grease duct cost $27,279.76 installed on a 2025 federal award in Texas, and one kitchen fire suppression system cost $9,249 to $62,834 on federal awards from 2022 to 2026 (USAspending FA302025C0002).
  • Texas requires a TABS registration for building projects with an estimated cost of $50,000 or more, which is why this dataset exists and why it starts at $50,000 (TDLR Architectural Barriers FAQ).

How much does restaurant construction cost per square foot?

The starting space sets the price more than the menu does. In Texas registrations filed January 2024 to November 2026, a new freestanding restaurant had a median estimated cost of $371 per sq ft, a shell finish-out $146, and work inside a space that was already a restaurant $125. The middle half of ground-up projects ran $207 to $580 per sq ft (TDLR TABS, pulled November 21, 2026).

Starting pointRecordsMedian $ per sq ftMiddle half, $ per sq ftMedian sizeMedian estimated costMedian planned monthsSource
Ground-up building (new construction)396$371$207 to $5802,994 sq ft$1,100,0006.0TDLR TABS
Addition to an existing restaurant49$175$107 to $2992,283 sq ft$325,000n/aTDLR TABS
First-generation shell finish-out or conversion547$146$87 to $2162,390 sq ft$300,0003.8TDLR TABS
Re-fit of an existing (second-generation) restaurant577$125$66 to $2002,495 sq ft$300,0003.0TDLR TABS
Renovation, starting point not stated219$147$90 to $2472,278 sq ft$275,000n/aTDLR TABS

Each figure is the estimated construction cost the owner or design professional entered when registering the project with the Texas Department of Licensing and Regulation (TDLR) under the Texas Architectural Barriers Act. It excludes land. Whether it includes cooking equipment, furniture and site work depends on the filer; 80 of the 396 ground-up scopes mention site work, parking or paving.

Restaurant construction cost per sq ft by starting pointBar chart: median restaurant construction cost is $371 per sq ft ground-up, $175 for additions, $146 for shell finish-outs and $125 for re-fits.0100200300400500$ per sq ft371Ground-up building (396)175Addition (49)146Shell finish-out orconversion (547)125Existing restaurantre-fit (577)
Ground-up restaurants had a median estimated cost of $371 per sq ft, about 2.5 times the $146 shell finish-out median. Source: TDLR TABS, 1,788 records registered January 2024 to November 2026, accessed November 21, 2026.

Planned schedules follow the same order. The median ground-up registration planned 6.0 months from start to completion (middle half 4.0 to 8.1), a shell finish-out 3.8 months and a re-fit 3.0 months, measured from the start and completion dates in each record (TDLR TABS).

What does a quick service, fast casual or full service restaurant cost?

Brand records show the format gap clearly. Ground-up quick service restaurants (QSR, the drive-thru burger, chicken and taco chains) had a median of $423 per sq ft and $1,200,000 per building, while 12 ground-up full service restaurants ran $229 per sq ft on larger 5,138 sq ft buildings (TDLR TABS). Format was assigned only where the record names a chain whose format is public; 945 independent or unnamed records sit in their own rows.

Format (assigned by chain name)Starting pointRecordsMedian $ per sq ftMiddle halfMedian sizeMedian estimated cost
Quick service (QSR)Ground-up191$423$287 to $6012,739 sq ft$1,200,000
Quick service (QSR)Shell finish-out66$186$142 to $3051,766 sq ft$300,000
Quick service (QSR)Existing restaurant re-fit210$148$94 to $2132,626 sq ft$337,500
Drive-thru coffeeGround-up22$561$352 to $6941,050 sq ft$732,123
CoffeeShell finish-out27$214$178 to $3512,226 sq ft$400,000
Fast casualGround-up30$414$265 to $5972,385 sq ft$1,000,000
Fast casualShell finish-out55$235$168 to $2912,406 sq ft$650,000
Fast casualExisting restaurant re-fit15$192$91 to $2552,600 sq ft$350,000
Full serviceGround-up12$229$162 to $3255,138 sq ft$1,150,000
Full serviceShell finish-out16$126$68 to $1723,960 sq ft$475,000
Full serviceExisting restaurant re-fit13$86$42 to $1253,052 sq ft$200,000
Independent or unnamedGround-up141$241$129 to $4404,233 sq ft$1,017,200
Independent or unnamedShell finish-out383$118$76 to $1902,400 sq ft$289,500
Independent or unnamedExisting restaurant re-fit294$97$58 to $1792,685 sq ft$250,000

Source for every row: TDLR TABS registrations, January 2024 to November 2026, medians computed by CB&C. Full service and fast casual re-fit rows rest on 12 to 16 records, so treat them as indicative.

Ground-up restaurant cost per sq ft by formatBar chart: ground-up median cost per sq ft is $561 for drive-thru coffee, $423 quick service, $414 fast casual, $241 independent and $229 full service.$ per sq ftDrive-thru coffee (22)561Quick service (191)423Fast casual (30)414Independent or unnamed (141)241Full service (12)229
Drive-thru coffee buildings had the highest median, $561 per sq ft on about 1,050 sq ft, and full service the lowest, $229 on about 5,138 sq ft. Source: TDLR TABS, registrations 2024 to 2026, accessed November 21, 2026.

Does a drive-thru change the cost?

Ground-up records that mention a drive-thru had a median of $421 per sq ft on a 2,728 sq ft building, against $336 per sq ft and 3,034 sq ft for the 274 that do not mention one (TDLR TABS). Part of the gap is size: the drive-thru lane, menu boards and canopy add cost without adding floor area, so the same site work is spread over fewer square feet.

Why do small restaurants cost more per square foot?

The kitchen, restrooms, utility services and site work cost nearly the same whether the dining room seats 40 or 140. In the ground-up records, buildings under 2,500 sq ft had a median of $423 per sq ft and a median total of $850,000; buildings of 6,000 to 15,000 sq ft had a median of $221 per sq ft but a median total of $2,156,825 (TDLR TABS).

Ground-up building sizeRecordsMedian $ per sq ftMiddle halfMedian sizeMedian estimated cost
Under 2,500 sq ft147$423$287 to $6132,106 sq ft$850,000
2,500 to 3,999 sq ft121$401$250 to $5973,000 sq ft$1,225,000
4,000 to 5,999 sq ft78$243$174 to $4484,923 sq ft$1,200,000
6,000 to 15,000 sq ft50$221$133 to $4248,756 sq ft$2,156,825
Ground-up restaurant cost per sq ft by building sizeBar chart: ground-up restaurant cost falls from $423 per sq ft under 2,500 sq ft to $221 per sq ft at 6,000 to 15,000 sq ft.0100200300400500$ per sq ft423Under 2,500 sq ft (147)4012,500 to 3,999 sq ft(121)2434,000 to 5,999 sq ft(78)2216,000 to 15,000 sq ft(50)
Restaurants under 2,500 sq ft had a median of $423 per sq ft, nearly twice the $221 median for buildings of 6,000 sq ft or more. Source: TDLR TABS, 396 ground-up registrations 2024 to 2026, accessed November 21, 2026.

Is a second-generation restaurant space cheaper than a first-generation shell?

Yes, but by less than most guides claim. The median re-fit of an existing restaurant was $125 per sq ft against $146 for a shell finish-out, a gap of $21 per sq ft, or about $50,000 on a 2,400 sq ft space (TDLR TABS). The saving is real only when the hood, suppression, grease interceptor and walk-in pass inspection for your menu; if they must be replaced, most of the gap disappears.

Have the builder and a licensed suppression contractor check each item below before signing the lease. The broader build-out process, health plan review and permit sequence are set out in our guide to restaurant build-out contractors.

Existing itemWhat to verifyRule behind the checkPublic price if it must be replacedSource
Type I hood and grease ductHood overhangs every grease-producing appliance on all open sides; duct is intact to the roofIMC Chapter 5, Section 507; NFPA 96$27,279.76, one hood plus grease duct, installed (2025)USAspending FA302025C0002
Kitchen fire suppressionSystem is listed to UL 300 and covers the new appliance layoutUL 300, Edition 4$9,249 to $62,834, one system (2022 to 2026)USAspending 47PE5526F0450, N4008022F4924
Grease interceptorSize meets the sewer utility’s sizing table for your fixturesLocal pretreatment ordinance$4,000 to $8,500, new 750 to 1,500 gallon unit, installedCity of Tampa FAQ
Walk-in cooler or freezerBox size fits your storage plan; refrigeration runs to temperatureFDA Food Code 2026, 3-501.16: cold holding at 41°F or less$26,373.20 (8 x 10 ft box) to $85,250 (14 x 18 ft, installed)W50S6Q24FA011, 12639523P0450
Electrical serviceAmps and phase carry the equipment scheduleUtility service rules$6,400 utility connection for three-phase up to 800 A vs $3,000 single-phase (one utility, 2026)Pend Oreille PUD fee schedule
RestroomsCount and layout meet accessibility rules for the seat count2010 ADA Standards, 213 and 604$35,000 per single-user toilet room (2024 estimate)Minnesota DLI memo

Which line items swing a restaurant budget the most?

Kitchen exhaust, cold storage and utility capacity move the number most, because a shell has none of them and a second-generation space may or may not have usable ones. Public records price one installed hood and duct at $27,279.76, a walk-in cooler and freezer pair at $68,572.45 and a 750 to 1,500 gallon grease interceptor at $4,000 to $8,500 (USAspending W50S9224PA023).

Line itemScope stated in the recordPublic priceDate and placeSource
Kitchen exhaust hoodEquipment purchase only$16,185.37June 2025, Langley AFB, Va.USAspending FA480025P0106
Hood plus grease ductReplace one hood and duct, installed, no makeup air$27,279.76Feb 2025, Sheppard AFB, Tex.USAspending FA302025C0002
Kitchen fire suppressionReplace or install one system$9,249 to $62,8342022 to 2026, Ga. and Md.47PE5526F0450, N4008022F4924
Grease trap, 0 to 100 galInstalled, average range$250 to $1,5002026, Tampa, Fla.City of Tampa
Grease interceptor, 750 to 1,500 galNew, installed, average range$4,000 to $8,5002026, Tampa, Fla.City of Tampa
Walk-in cooler, 8 x 10 ftOutdoor box, purchase$26,373.20Sept 2024, Ark.USAspending W50S6Q24FA011
Walk-in cooler 8 x 12 ft plus freezer 8 x 10 ftPair of boxes$68,572.45Sept 2024, Pa.USAspending W50S9224PA023
Walk-in cooler, 14 x 18 ftInstalled with evaporator and condenser$85,250Sept 2023, Gastonia, N.C.USAspending 12639523P0450
Three-phase electric serviceUtility connection up to 800 A (single-phase 200 or 400 A: $3,000)$6,400April 2026, Pend Oreille PUD, Wash.PUD fee schedule
Accessible single-user toilet roomNew construction cost estimate$35,000April 2024, MinnesotaMinnesota DLI
Health department plan reviewNew or remodel, 2,000 to 3,999 sq ft$1,865 ($1,044 to $2,723 by size)Rev. 11/2025, Los Angeles CountyLA County form

Hood sizing, exhaust rates and more award prices are in our guide to the commercial kitchen hood. Service intervals and the 2022 to 2026 award list for suppression are in our guide to the commercial kitchen fire suppression system.

Interceptor sizing by drainage fixture units and pumping prices are in our guide to the grease trap and grease interceptor. Restroom dimensions and the 20% cap on path-of-travel accessibility spending in alterations (28 CFR 36.403(f)) are in our guide to ADA bathroom requirements.

A cooking line that adds a second fryer bank or a conveyor oven can push a 200 A single-phase service past its limit; the voltage, amperage and utility charges for an upgrade are laid out in our guide to three-phase power. Cooking and refrigeration equipment itself sits outside most construction estimates and is priced in our guide to commercial kitchen equipment.

What did public airport, pier and park concession build-outs cost?

Public concession spaces cost more per foot than street restaurants because of small footprints, secure-side logistics and public bidding. Five Texas records registered 2024 to 2026 ran $161 to $822 per sq ft; the McAllen International Airport secure-side build-out was $1,800,000 for 2,190 sq ft. The 28 publicly funded restaurant records in the main dataset had a median of $322 per sq ft (TDLR TABS).

Project (TABS number)FundingScope as registeredSizeEstimated cost$ per sq ft
McAllen airport concessions, phase 3 (TABS2024017035)PublicSecure-side concessions build-out2,190 sq ft$1,800,000$822
Bob Hall Pier, Nueces County (TABS2026005844)PublicConcession stand addition and restaurant kitchen addition5,000 sq ft$3,800,000$760
McKinney commercial terminal (TABS2026028736)PublicConcessions space with cafeteria, bar and back of house1,660 sq ft$750,000$452
Harris County terminal addition (TABS2026018883)PrivateFour food tenant fit-outs plus shared seating9,647 sq ft$3,500,000$363
Cameron County terminal (TABS2025012641)PublicNew tenant build-out in existing terminal1,040 sq ft$167,000$161

At the top of the institutional scale, the Defense Department’s June 2026 pricing guide puts a new enlisted dining facility, kitchen equipment and installation included, at $841.18 per sq ft for a 50,434 sq ft reference building at October 2025 prices (UFS 3-701-01, Table 2). That is a contrast figure for large public kitchens, not a restaurant budget.

Worked example: what would a 2,400 sq ft fast casual restaurant cost?

Take a 2,400 sq ft fast casual restaurant, the median size of fast casual shell finish-outs in the Texas records. At the fast casual medians it costs about $564,000 to finish a first-generation shell and $460,800 to re-fit a second-generation space, or $622,265 and $508,745 after a plan review fee and a 10% owner contingency (TDLR TABS).

StepFirst-generation shellSecond-generation re-fitInput and source
1. Construction estimate2,400 x $235 = $564,0002,400 x $192 = $460,800Fast casual medians, TDLR TABS
2. Of which: kitchen systems a shell lacks$27,279.76 + $9,249 + $8,500 + $68,572.45 = $113,601$0 if the existing items pass inspectionHood and duct, one suppression system, interceptor (top of Tampa range), cooler and freezer pair; table above
3. Health plan review fee$1,865$1,865LA County, 2,000 to 3,999 sq ft
4. Owner contingency, 10% of step 1$56,400$46,080CB&C assumption, not a sourced rate
5. Total before land and equipment$622,265$508,745Steps 1 + 3 + 4
Range at the middle half of step 1$403,200 to $698,400$218,400 to $612,000$168 to $291 and $91 to $255 per sq ft

The $113,601 of kitchen systems in step 2 is close to the $103,200 gap between the two construction estimates. That is the case for a second-generation space in one line: the savings come almost entirely from reusable kitchen systems, so a space whose hood is too short or whose interceptor is undersized saves little.

Stacked bar chart: worked example cost of a 2,800 sq ft restaurant in a shell versus a second-generation spaceWorked example: 2,400 sq ft fast casual restaurant, before land and equipmentRest of finish-out: $450,399Kitchen systems: $113,601Contingency 10%: $56,400Total $622,265First-generation shellRe-fit construction: $460,800Contingency 10%: $46,080Total $508,745Second-generation re-fitPlan review fee $1,865 in each bar. Sources: TDLR TABS medians, USAspending, City of Tampa, LA County.
In the worked example, $113,601 of public-price kitchen systems explains most of the $113,520 gap between a shell ($622,265) and a second-generation re-fit ($508,745). Sources: TDLR TABS fast casual medians; USAspending awards; City of Tampa; LA County, accessed November 21, 2026.

Landlords often pay part of this. A tenant improvement allowance is negotiated per square foot in the lease, and how it is paid out and accounted for is set out in our guide to the tenant improvement allowance. For a fixed-scope buffer, see our page on construction contingency.

How do common restaurant cost figures compare with filed records?

The figures repeated on most cost pages are older survey averages or unsourced ranges. Filed Texas records put ground-up quick service restaurants at a median $423 per sq ft, several times the $63 per sq ft fast food average still quoted from an undated industry survey, and they put re-fits of existing restaurants at $125, not $85 (TDLR TABS).

What several guides sayWhat the records showSource of the record figure
Fast food averages $63 per sq ft; full service $198 (undated survey, widely re-quoted)QSR ground-up median $423; QSR re-fit $148; full service ground-up $229 (12 records)TDLR TABS
New restaurant $242 per sq ft; renovation of an existing restaurant $85 (same survey)Ground-up median $371; existing-restaurant re-fit $125TDLR TABS
2019 national model, 5,000 sq ft restaurant: $199 to $220 per sq ft including feesGround-up 4,000 to 5,999 sq ft: median $243, middle half $174 to $448 (2024 to 2026)TDLR TABS
Restaurant renovation $150 to $600 per sq ft (2026 guide, no source)Existing-restaurant re-fit middle half $66 to $200 per sq ftTDLR TABS
Hood installation $20,000 to $60,000 or more (2026 guide, no source)One hood plus grease duct installed: $27,279.76 (2025)USAspending FA302025C0002

Prices in the records are also rising for new buildings: ground-up registrations had a median of $345 per sq ft in 2024, $358 in 2025 and $504 in the 74 records filed so far in 2026, while shell finish-outs moved only from $139 to $152 (TDLR TABS). The 2026 jump partly reflects a smaller, more drive-thru-heavy mix, so read it as direction, not a rate. For all building types, our commercial construction cost per square foot page tracks national cost data.

Which starting space should you choose for your restaurant?

Choose by what the concept needs that a lease space cannot give. A drive-thru or brand prototype needs a pad and a ground-up budget near $421 per sq ft; a sit-down or counter concept that fits an existing restaurant with a usable hood and interceptor can budget near $125; anything else starts from a shell near $146 (TDLR TABS). The table and chart below hold the same logic.

If your projectThenBudget anchor (median, Texas records 2024 to 2026)
Needs a drive-thru lane, pad site or chain prototypeBuild ground-up$421 per sq ft with drive-thru; 6.0 planned months
Fits a former restaurant whose hood covers your line, suppression is UL 300 listed and interceptor meets the utility tableTake the second-generation space$125 per sq ft; 3.0 planned months
Fits a former restaurant but the hood is short or suppression is not UL 300 listedSecond-generation space plus replacements$125 per sq ft plus $27,279.76 hood and duct and $9,249 to $62,834 suppression
Is a vanilla shell, or an office or retail space being convertedPlan a first-generation finish-out$146 per sq ft; 3.8 planned months
Adds dining or kitchen area to a restaurant you already runPlan an addition$175 per sq ft
Needs more cooking load than a 200 A single-phase service carriesAsk the utility for a three-phase quote before signing$6,400 connection up to 800 A at one utility (2026)
Decision flowchart: which restaurant starting space and which median cost per square foot appliesWhich starting space fits your restaurant budget?Need a drive-thru, a pad siteor a brand prototype building?YesNoGround-up buildingMedian $421 per sq ftMiddle half $273 to $615 (drive-thru)Land and equipment extraWas the space a restaurant with aType I hood, grease interceptorand gas service still in place?YesNoHood covers your cooking line,suppression is UL 300 listed,utility accepts the interceptor?First-generation shellMedian $146 per sq ftMiddle half $87 to $216or a conversionYesNoSecond-generation re-fitMedian $125 per sq ftMiddle half $66 to $200Second-generation plus replacementsHood and duct $27,280; one suppressionsystem $9,249 to $62,834; interceptor $4,000 to $8,500
Drive-thru and prototype concepts lead to ground-up construction ($421 per sq ft median with a drive-thru); a former restaurant with usable kitchen systems leads to a $125 re-fit. Source: TDLR TABS 2024 to 2026 and USAspending awards, accessed November 21, 2026.

The kitchen is the costliest part, so see commercial kitchen cost and the inspections needed before opening.

How we compiled this

On November 21, 2026 we searched the TDLR TABS public registry for 35 restaurant terms and chain names registered from January 1, 2024, opened 2,623 project records, and kept 1,788 restaurant projects after dropping non-restaurant scopes, records under 300 sq ft or outside $15 to $2,000 per sq ft, 29 records whose stated size conflicted with the scope text, and 238 repeats of an identical cost and size. One national burger chain filed 100 new-store registrations at an identical $750,000 estimate; 23 survive the repeat filter, and without them the ground-up median is $389 per sq ft. Line-item prices come from 7 federal award records, 4 municipal or utility documents and the Defense Department pricing guide. We did not survey contractors or price any project ourselves.

Frequently asked questions

How much does it cost to build a restaurant per square foot?

Texas registrations from 2024 to 2026 put a new freestanding restaurant at a median $371 per sq ft, with the middle half between $207 and $580. Quick service chains ran higher, at a median $423, and small buildings under 2,500 sq ft ran $423. These are construction estimates without land; equipment may or may not be included, depending on the filer (TDLR TABS).

How much does a restaurant build-out or fit-out cost?

Finishing a first-generation shell or converting a non-restaurant space ran a median $146 per sq ft, or $300,000 for a median 2,390 sq ft, across 547 Texas records registered 2024 to 2026. Fast casual chains ran higher, at a median $235 per sq ft, and independent restaurants lower, at $118 (TDLR TABS).

Is it cheaper to take over an existing restaurant space?

Usually, by a modest margin. Re-fits of existing restaurants had a median of $125 per sq ft against $146 for shell finish-outs in Texas records. The saving depends on reusing the hood, suppression, grease interceptor and walk-in; replacing one hood and duct alone cost $27,279.76 on a 2025 federal award (USAspending).

How much does a fast food restaurant cost to build?

Ground-up quick service restaurants registered in Texas from 2024 to 2026 had a median estimated cost of $1,200,000, or $423 per sq ft, for a median 2,739 sq ft building across 191 records. Records that mention a drive-thru ran a median $421 per sq ft. Land and the equipment package are usually outside that figure (TDLR TABS).

How long does restaurant construction take?

Planned schedules in Texas registrations ran a median 6.0 months for a ground-up restaurant, 3.8 months for a shell finish-out and 3.0 months for a re-fit of an existing restaurant, measured from the start and completion dates in each record. Permits, health plan review and utility upgrades come before that clock starts (TDLR TABS).

What costs are not included in restaurant construction estimates?

Land, the cooking and refrigeration equipment package, furniture, design fees and opening costs usually sit outside a construction estimate, along with fees such as health plan review, which Los Angeles County prices at $1,044 to $2,723 by size. Ask your builder to list each exclusion in writing before comparing bids (LA County form).

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.

← Back to all articles