Skip to content

Commercial Construction Loan: How Owners Size the Loan, Equity, Draws and SBA Options

Two-story steel-frame office building under construction with metal deck and stacked materials on site

A commercial construction loan funds a new building in monthly draws, then a permanent mortgage repays it. Federal guidelines cap bank construction loans at 80% of appraised value; SBA 504 can cut the owner’s share to 10%.

Key takeaways

  • Banks follow an 80% loan-to-value guideline for commercial construction loans, measured on appraised value, under 12 CFR Part 365, Appendix A; raw land is 65% and land development 75%.
  • For a building repaid from rents or a sale, a bank avoids a 150% risk weight only if the borrower puts in at least 15% of the as-completed value before the first advance (HVCRE definition, 12 CFR 324.2).
  • SBA 504 lets an owner-occupant contribute 10% of project cost, 15% for a business 2 years old or less or a special-purpose building, and 20% for both (13 CFR 120.910); the standard debenture cap is $5,000,000 (13 CFR 120.931).
  • SBA 7(a) loans top out at $5,000,000, with a variable rate capped at prime plus 3.0 points above $350,000: 10.00% at the 7.00% prime rate of October 29, 2026 (13 CFR 120.214; Federal Reserve H.15).
  • In our worked budget for a 20,000 sq ft Dallas office costing $5,689,000, a $5,500,000 appraisal caps a bank loan at $4,400,000, so the owner funds $1,289,000, or 22.7% of cost.

How does a commercial construction loan work?

A commercial construction loan is short-term debt to build or substantially renovate a commercial property. The lender commits a maximum at closing, the owner spends its equity first, and the lender then advances money against inspected work, charging interest only on the drawn balance. The SBA SOP 50 10 8.1 (effective October 1, 2026) writes the equity-first rule into every SBA construction loan.

Six stages of a commercial construction loan How a commercial construction loan moves from approval to takeout 1. Underwrite and appraise Plans, fixed-price contract, budget As-completed appraisal; state certified appraiser over $500,000 (12 CFR 323.3) 2. Close; owner cash first Loan capped near 80% of value (12 CFR 365 App. A); equity spent before the first draw (SBA SOP 50 10 8.1) 3. Monthly draws Pay application (AIA G702) Site inspection of work in place Lien waivers, title update Funds only actual outlays 4. Interest on drawn balance Interest-only, floating rate Prime 7.00% on Oct 29, 2026 Paid from interest reserve (Fed H.15) 5. Completion Final inspection against plans Final lien waivers Certificate of occupancy Retainage released 6. Takeout Permanent mortgage, or conversion to term loan, or 504 debenture repays the interim lender Sources: 12 CFR 365 App. A; 12 CFR 323.3; SBA SOP 50 10 8.1; Federal Reserve H.15 (Oct 30, 2026)
The six stages of a commercial construction loan, with the rule behind each step. Sources: 12 CFR 365 App. A; 12 CFR 323.3; SBA SOP 50 10 8.1; Federal Reserve H.15, October 30, 2026.
  1. Underwrite and appraise. The lender reviews plans, a fixed-price contract and the budget, and orders an as-completed appraisal; for an FDIC-supervised bank, a commercial real estate loan above $500,000 needs a state certified appraiser (12 CFR 323.3).
  2. Close, owner cash first. The loan is sized near 80% of value or less, and the owner’s cash and land go into the project before the first loan dollar (12 CFR Part 365; SBA SOP 50 10 8.1).
  3. Monthly draws. The contractor submits a pay application, an inspector confirms work in place, lien waivers come in, and the lender funds only actual outlays.
  4. Interest on the drawn balance. Payments are interest-only at a floating rate (prime was 7.00% on October 29, 2026) and are usually paid from an interest reserve inside the loan.
  5. Completion. Final inspection against the plans, final lien waivers, a certificate of occupancy, and retainage released to the contractor.
  6. Takeout. A permanent mortgage, a conversion to a term loan under the same note, or an SBA 504 debenture repays the interim lender.

The 9 numbers below recur through every step. Each comes from a regulation, an SBA rule or the Federal Reserve’s October 30, 2026 H.15 release, not a lender quote.

NumberWhat it governsSource
80%Maximum loan-to-value for commercial, multifamily and other nonresidential construction loans12 CFR 365, App. A
65% / 75%Raw land / land development loan-to-value limits12 CFR 365, App. A
15%Borrower capital, as a share of as-completed value, that keeps an income-producing project out of HVCRE12 CFR 324.2
150%Bank risk weight on an HVCRE loan12 CFR 324.32(j)
$500,000Commercial real estate loan size above which an FDIC-supervised bank needs a state certified appraiser12 CFR 323.3(d)(2)
$350,000SBA 7(a) construction component above which 100% performance and payment bonds are requiredSBA SOP 50 10 8.1
$5,000,000SBA 7(a) loan cap; standard SBA 504 debenture cap13 CFR 120.151, 120.931
$10,000,000Combined 7(a) plus 504 limit from July 4, 2026, when the 7(a) loan comes firstSBA, May 18, 2026
7.00% / 3.94%Bank prime rate / SOFR on October 29, 2026Fed H.15; New York Fed

How much can you borrow: loan-to-value or loan-to-cost?

Two ratios set the ceiling, and the lower one wins. Loan-to-value (LTV) divides the loan by the appraised value of the finished building; federal guidelines in 12 CFR Part 365 tell banks to keep commercial construction loans at or below 80% LTV. Loan-to-cost (LTC) divides the loan by the total budget. No regulation fixes LTC, so each lender sets its own limit.

The value in that test is the as-completed value, not the land value today. SBA SOP 50 10 8.1 requires the appraisal for new construction to estimate market value upon completion, and the lender must later get a statement that the building matches the plans the appraiser relied on. When the appraisal lands below cost, the 80% LTV test binds and the owner covers the gap.

Loan categorySupervisory LTV limitSource
Raw land65%12 CFR 365, App. A
Land development75%12 CFR 365, App. A
Construction: commercial, multifamily and other nonresidential80%12 CFR 365, App. A
Construction: 1 to 4 family residential85%12 CFR 365, App. A
Improved property (completed building)85%12 CFR 365, App. A
eCFR table of supervisory loan-to-value limits with the 80% commercial construction row boxed
12 CFR Part 365, Appendix A sets an 80% loan-to-value limit for commercial, multifamily and other nonresidential construction loans (row boxed). Source: eCFR, accessed November 1, 2026.

Three lines in the same appendix shape a construction loan. A loan that funds land development and then the building takes the limit of the final phase, 80%, and “loan disbursements should not exceed actual development or construction outlays”. Banks may exceed the limits case by case, but all such loans together should stay under 100% of total capital, and the commercial share under 30%.

The appendix also lists excluded transactions: a loan guaranteed by a U.S. government agency is outside the limit if the guaranty at least equals the slice above 80%. That is why an SBA 7(a) loan, with a guaranty of up to $3,750,000 on a $5,000,000 loan, can lend past 80% of value. For current hard-cost ranges by building type, our guide to commercial construction cost per square foot compiles the RLB and BLS figures.

How much equity do you need, and when does it go in?

Plan on equity at least equal to the gap between total cost and the loan, paid in before the lender’s first dollar. On a bank loan for an income-producing project, the HVCRE rule makes 15% of as-completed value the practical floor. SBA 504 sets 10%, 15% or 20% of project cost, and SBA 7(a) requires 10% only from start-ups operating 1 year or less.

PathMinimum owner moneyWhat countsSource
Bank loan, building repaid from rents or sale15% of as-completed appraised value, in before the bank advances funds and kept in until completion and stable cash flowCash, unencumbered readily marketable assets, paid development costs, contributed land at appraised value12 CFR 324.2 (HVCRE)
Bank loan, owner-occupied building repaid from business cash flowNo federal number; each bank’s policy must set minimum initial investment and hard equityBank policy12 CFR 365, App. A
SBA 504, existing business, general-purpose building10% of project costCash, or land that is part of the project13 CFR 120.910
SBA 504, business 2 years old or less, or limited or single-purpose building15% of project costSame13 CFR 120.910
SBA 504, both conditions20% of project costSame13 CFR 120.910
SBA 7(a), start-up operating 1 year or less10% of total project costCash and other sources listed in the SOPSBA SOP 50 10 8.1
SBA 7(a), established businessLender judgment; the credit memo must discuss equityLender policySBA SOP 50 10 8.1

Land you already own usually counts, but its value depends on when you bought it. For SBA 504, land bought less than 2 years before the application counts at cost; land held 2 years or more counts at appraised fair market value (SBA SOP 50 10 8.1). Under the HVCRE rule, contributed real property counts at its appraised value.

What does a commercial construction loan cost in November 2026?

No federal agency publishes an average commercial construction loan rate, so start from the index your lender quotes. On October 29, 2026 the bank prime rate was 7.00% and SOFR was 3.94%; lenders add a spread set deal by deal. SBA 7(a) caps that spread, and SBA 504 debenture rates follow the 10-year Treasury, which closed at 4.98%.

BenchmarkRateDateWhere it shows upSource
Bank prime loan rate7.00%Oct 29, 2026Floating bank construction loans; SBA 7(a) base rateFed H.15, Oct 30, 2026
SOFR (overnight)3.94%Oct 29, 2026Floating rate on larger bank loansNew York Fed
10-year Treasury4.98%Oct 29, 2026SBA 504 debenture rate is pegged to itFed H.15; SBA 504 page
Federal funds, effective3.88%Oct 29, 2026Policy rate behind primeFed H.15
7(a) cap, loans over $350,000Prime + 3.0 = 10.00%Oct 29, 2026 primeMaximum variable rate13 CFR 120.214(d)
7(a) cap, $250,001 to $350,000Prime + 4.5 = 11.50%Oct 29, 2026 primeMaximum variable rate13 CFR 120.214(d)
7(a) cap, $50,001 to $250,000Prime + 6.0 = 13.00%Oct 29, 2026 primeMaximum variable rate13 CFR 120.214(d)

Credit is available but not growing. Banks held $453.5 billion of construction and land development loans on June 30, 2026, and 0.99% were noncurrent (FDIC Quarterly Banking Profile, Q2 2026). In the July 2026 Senior Loan Officer Opinion Survey, standards for construction and land development loans “remained basically unchanged on net”, while a moderate net share of banks saw weaker demand. Our construction lending tracker follows these series every quarter.

Fees add to the rate. On a $5,000,000 SBA 7(a) loan with a 75% guaranty, the maximum upfront guaranty fee is $138,125, and it can be financed (SBA SOP 50 10 8.1). SBA puts total 504 fees at about 3% of the debenture, also financeable. Bank origination fees are not reported to regulators, so get them in writing on the term sheet.

Worked example: what does a $5.7 million owner-occupied office need?

Here is one owner-occupied project run through the three tests with every input shown. The building is a 20,000 sq ft office in Dallas; hard cost uses $200 per sq ft, inside the $165 to $240 range for Dallas secondary offices in the Rider Levett Bucknall (RLB) Q3 2026 cost report. Inputs marked as assumptions are ours; swap in your own.

Budget lineAmountBasis
Land, paid in cash by the owner$800,000Assumption
Hard cost, 20,000 sq ft at $200$4,000,000RLB Q3 2026: Dallas secondary office $165 to $240 per sq ft
Construction contingency, 7% of hard cost$280,000GSA P120 (PBS 1000.6B): 7% at award for new construction
Soft costs: design, permits, legal, title, appraisal, builder’s risk$400,000Assumption: 10% of hard cost
Lender fee, 1% of the loan$44,000Assumption
Interest reserve$165,000$4,400,000 x 50% average balance x 7.50% x 12 months
Total project cost$5,689,000Sum
Where the $5,689,000 goesBar chart of a $5,689,000 budget: hard cost $4,000 thousand, land $800 thousand, soft costs $400 thousand, contingency $280 thousand, reserve $165 thousand, fee $44 thousand$ thousandsHard cost4,000Land800Soft costs400Contingency (7%)280Interest reserve165Lender fee44.0
Hard cost is 70% of the $5,689,000 worked budget; the interest reserve adds $165,000. Source: CB&C arithmetic from RLB Q3 2026 and GSA P120, November 2026.
TestArithmeticResult
80% LTV guideline80% x $5,500,000 as-completed appraisal (assumption)Loan up to $4,400,000
Loan-to-cost$4,400,000 / $5,689,00077.3%
Owner money$5,689,000 minus $4,400,000$1,289,000, or 22.7% of cost
HVCRE floor (only if leased out or sold)15% x $5,500,000$825,000, met
Interest rate usedPrime 7.00% + 0.50 spread (assumption)7.50%

The appraisal moves the owner’s cash more than the rate does. In the runs below, a $500,000 lower appraisal adds $381,000 of owner money, while a 1-point higher rate adds $22,000 through the reserve.

Change from the base caseLoanTotal costOwner money
Base case$4,400,000$5,689,000$1,289,000
Appraisal $5,000,000$4,000,000$5,670,000$1,670,000
Appraisal $6,000,000$4,800,000$5,708,000$908,000 (HVCRE floor $900,000)
Build takes 18 months$4,400,000$5,771,500$1,371,500
Rate 8.50%$4,400,000$5,711,000$1,311,000
Rate 10.00% (7(a) cap level)$4,400,000$5,744,000$1,344,000

How do draws, inspections and the interest reserve work?

Draws pay the contractor for work in place, usually once a month. The lender funds a draw only after a pay application, an inspection that confirms the work, and lien waivers for the prior payment; 12 CFR Part 365 says disbursements should not exceed actual construction outlays. Interest accrues only on what has been drawn, and an interest reserve inside the loan pays it.

  1. Pay application. The contractor bills percent complete against the schedule of values on an AIA G702 and G703; our AIA G702 payment application guide shows the form line by line.
  2. Inspection. The lender’s inspector checks work in place. When a CDC provides interim financing on a 504 project, a qualified engineer, appraiser or other party must inspect before every progress payment (SBA SOP 50 10 8.1).
  3. Lien waivers and title. Waivers from the contractor, subcontractors and suppliers for amounts already paid; SBA lenders must collect them from all of these parties and document them in the loan file.
  4. Balance check. Undrawn loan plus remaining owner money must cover cost to complete. SBA lenders must see the borrower’s ability to pay overruns before approving a contract change, and neither the lender nor SBA must raise the loan.
  5. Funding. Money goes to the contractor or a title company, minus retainage under the contract.
  6. Interest. The month’s interest is charged on the drawn balance and paid from the interest reserve.

Tie the pay application to a clean schedule of values and collect conditional and unconditional lien waivers with each draw, because SBA SOP 50 10 8.1 makes SBA lenders collect waivers from every contractor, subcontractor and supplier; our pages on the schedule of values and lien waivers cover both forms.

The interest reserve is sized as loan x average share drawn x rate x months. With even draws the average balance is about half the loan, so a $4,400,000 loan at 7.50% for 12 months needs $165,000. 12 CFR Part 365 tells banks to set standards and limits on interest reserves, and lenders size them to the schedule, so a late finish can exhaust the reserve before the takeout.

RateReserve, 12-month buildReserve, 18-month build
6.50%$143,000$214,500
7.50%$165,000$247,500
8.50%$187,000$280,500
10.00% (7(a) cap over $350,000)$220,000$330,000
Interest reserve on a $4,400,000 loanBar chart: interest reserve rises from $143 thousand at 6.50% to $220 thousand at 10.00% for 12 months, and to $330 thousand for 18 months0100200300400$ thousands1432146.50%1652487.50%1872808.50%22033010.00% (7(a) cap)12-month build18-month build
A 6-month delay adds more to the interest reserve ($82,500 at 7.50%) than a 1-point rate rise ($22,000). Source: CB&C arithmetic, November 2026.

What will the lender require from you and your contractor?

Expect the lender to underwrite the contractor as closely as the owner. SBA rules spell this out: a fixed-price contract with a licensed contractor, final plans, and, when the 7(a) construction component tops $350,000, 100% performance and payment bonds plus builder’s risk and workers’ compensation insurance, unless the lender hires third-party construction monitoring with funds control.

RequirementWhen it appliesSource
Fixed-price construction contract with a licensed contractor; no material plan changes without lender (and surety) consentSBA 7(a) and 504 constructionSBA SOP 50 10 8.1
100% performance bond and labor and materials payment bond from a Treasury-approved surety; builder’s risk and workers’ comp7(a) construction component over $350,000, unless the lender uses third-party construction management with funds controlSBA SOP 50 10 8.1; 13 CFR 120.200
Evidence the building meets NEHRP seismic provisions (ASCE 7 or the International Building Code)New building or addition, SBA loansSBA SOP 50 10 8.1; 13 CFR 120.174
Environmental investigation, report dated within 1 year of the SBA loan numberAll commercial property taken as SBA collateralSBA SOP 50 10 8.1
Hazard insurance on collateralSBA loans over $500,00013 CFR 120.160(c)
As-completed appraisal by a state certified appraiserCommercial real estate loans over $500,000 at FDIC-supervised banks12 CFR 323.3
Projections showing debt service coverage of 1.15 or more within 2 years of the end of constructionSBA start-ups and loans based on projectionsSBA SOP 50 10 8.1

Bonds and builder’s risk insurance are priced into the contract, so ask bidders to carry them as separate lines; on SBA 7(a) jobs with more than $350,000 of construction, both are mandatory. Our pages on construction surety bonds, builder’s risk insurance and the Phase I environmental site assessment explain what each costs and covers.

Bank loan, SBA 504 or SBA 7(a): which fits your project?

A conventional bank loan fits investor buildings and owner projects with strong equity. SBA 504 fits owner-occupants who want a long fixed rate and the smallest contribution, if the business will occupy at least 60% of a new building. SBA 7(a) fits owner-occupants who want one lender and one loan up to $5,000,000, at a capped floating rate.

FeatureConventional bank loanSBA 504SBA 7(a)Source
MaximumBank policy within the 80% LTV guidelineDebenture $5,000,000 ($5,500,000 for small manufacturers and energy projects), plus a bank loan at least as large$5,000,000 loan12 CFR 365; 13 CFR 120.931, 120.920, 120.151
Owner moneyBank policy; 15% of value if HVCRE10%, 15% or 20% of project cost10% for start-ups; else lender judgment12 CFR 324.2; 13 CFR 120.910; SOP 50 10 8.1
RateSpread over prime or SOFRDebenture fixed, pegged to the 10-year Treasury; bank piece negotiatedVariable cap prime + 3.0 above $350,000SBA 504 page; 13 CFR 120.214
Term after completionSet by lender10, 20 or 25 yearsUp to 25 years plus the construction periodSBA 504 page; 13 CFR 120.212
Who funds the buildSame bankInterim lender; debenture sold after completion repays itThe 7(a) lenderSOP 50 10 8.1
OccupancyNone60% of a new building60% of a new building13 CFR 120.131

Run the same $5,689,000 budget through each path. The bank loan needs $1,289,000 of owner money. Under SBA 504, the bank lends 50% ($2,844,500), the CDC 40% ($2,275,600) and the owner 10% ($568,900), which the $800,000 of land already covers; the bank’s first lien is 51.7% of value, and 504 fees of about 3% add roughly $68,000 to the debenture. Under 7(a), a $5,000,000 loan leaves $855,625 of owner money after the $138,125 maximum guaranty fee and a larger reserve.

Owner money by financing pathBar chart: owner money is $1,289 thousand for a bank loan, $568.9 thousand minimum for SBA 504 and $855.6 thousand for SBA 7(a)05001,0001,500$ thousands1,289Bank loan at 80% LTV569SBA 504 (10% minimum)856SBA 7(a), $5,000,000 loan
On the same budget, the SBA 504 minimum contribution is $568,900, less than half the $1,289,000 a bank loan at 80% LTV leaves to the owner. Source: CB&C arithmetic, November 2026.

For how many contractors and owners use each program by state, see our report on SBA loans for construction companies.

Which path should you take? A decision table

Match the project to the first row that fits. Each threshold comes from a regulation or SBA rule, so it holds no matter which lender you call; pricing, fees and covenants still differ by lender, so compare 2 or 3 term sheets.

IfThenRule
You will lease the building to others or sell itUse a conventional construction loan; put 15% of as-completed value in cash or land before the first advance12 CFR 324.2; SBA 504 excludes rental real estate investment
Your business will occupy at least 60% of a new building and the project is about $12.5 million or lessPrice SBA 504 (a $5,000,000 debenture at 40% of cost)13 CFR 120.131, 120.931
Your business is 2 years old or lessBudget 15% for 504 (20% if the building is special purpose)13 CFR 120.910
Your business is 1 year old or less and you want 7(a)Budget at least 10% of total project costSBA SOP 50 10 8.1
The appraisal comes in below costOwner money equals cost minus 80% of value at a bank; a 7(a) guaranty can cover the slice above 80%12 CFR 365, App. A
The 7(a) construction component is over $350,000Require 100% performance and payment bonds from the contractor, or confirm the lender uses funds controlSBA SOP 50 10 8.1
SBA financing needed tops $10,000,000Use a conventional loan or add one alongside SBASBA, May 18, 2026
Decision flowchart: bank loan, SBA 504 or SBA 7(a) Which construction financing path fits the project? Will your operating business occupy at least 60% of the new building? (13 CFR 120.131) No: conventional construction loan 80% LTV guideline (12 CFR 365) If repaid by rents or sale: 15% of as-completed value in first (HVCRE) Yes. Does the SBA share fit the caps? 504 debenture up to $5,000,000; 7(a) loan up to $5,000,000; both up to $10M if 7(a) comes first No: bank loan, or 7(a) + 504 combined limit from July 4, 2026 (SBA news release 26-52) Yes. Want a long fixed rate and the lowest owner contribution? Yes: SBA 504 Owner 10%; 15% if 2 years old or less or special purpose; 20% if both (13 CFR 120.910) No: SBA 7(a) One lender; cap prime + 3.0 over $350,000; bonds if construction is over $350,000
Decision flowchart using the 60% occupancy rule, the $5,000,000 SBA caps and the 504 contribution tiers. Sources: 13 CFR 120.131, 120.910, 120.931; SBA, May 18, 2026.

CB&C is a matching service, not a lender. This page is general information, not financial, legal or lending advice; loan terms depend on the borrower, the project and the lender, and SBA rules change with each SOP version; this page reflects SOP 50 10 8.1, effective October 1, 2026.

What do several guides get wrong about commercial construction loans?

Four claims repeat across ranking guides and do not match the primary rules. The most common is a $5.5 million SBA 504 cap for every project; the $5,500,000 figure applies only to small manufacturers and energy projects under 13 CFR 120.931.

Claim in a top-ranking guide (2026)What the primary source saysSource
The SBA 504 loan goes up to $5.5 million$5,000,000 standard debenture limit; $5,500,000 only for small manufacturers and energy projects13 CFR 120.931; SOP 50 10 8.1
SBA 504 needs 10% down10% is the floor; 15% for a business 2 years old or less or a special-purpose building, 20% for both13 CFR 120.910
SBA 7(a) needs 10% to 20% downThe 10% minimum is for start-ups operating 1 year or less; for others the lender decidesSBA SOP 50 10 8.1
Lenders lend 80% to 85% of cost (no source given)No rule sets loan-to-cost; the federal guideline is 80% of appraised value, and draws should not exceed actual outlays12 CFR 365, App. A

What happens when construction ends?

Completion triggers the takeout. A bank loan either converts to a term loan under a conversion clause or is refinanced by a permanent mortgage; SBA 7(a) simply begins amortizing over up to 25 years. On a 504 project, the interim lender must be fully disbursed and the project complete before the debenture is sold to repay it (SBA SOP 50 10 8.1).

The lender will want proof of completion: a final inspection, final lien waivers, the certificate of occupancy and a statement that the building matches the appraised plans. For an income-producing project, a bank can move the loan out of HVCRE only after substantial completion and once cash flow covers debt service (12 CFR 324.2). Our substantial completion guide explains the certificate that starts these clocks.

Lenders review the contingency line closely, and our construction contingency guide shows the percentages public owners budget.

For the 504 rules themselves, including FY2027 fees, occupancy tests and a worked $4,000,000 example, see our guide to the SBA 504 loan.

How we compiled this

We read 4 ranking guides for the questions owners ask, then checked every rule against 11 primary documents accessed November 1, 2026: 12 CFR Parts 323, 324 and 365; 13 CFR Part 120; SBA SOP 50 10 8.1; two SBA program pages and SBA’s May 18, 2026 release; the Federal Reserve H.15 release of October 30, 2026; New York Fed SOFR; and RLB’s Q3 2026 cost report. Lender rate quotes were excluded because they are not dated primary data. The worked budget uses labelled assumptions and is arithmetic, not a loan offer.

Frequently asked questions

How much down payment do you need for a commercial construction loan?

At a bank, plan on cost minus 80% of the as-completed appraisal, since 12 CFR Part 365 caps commercial construction loans at 80% of value; for a rental or for-sale building, the HVCRE rule makes 15% of value the floor. SBA 504 requires 10% of project cost, 15% for a business 2 years old or less or a special-purpose building, and 20% for both.

What is the interest rate on a commercial construction loan today?

No agency publishes an average. Floating loans price as a spread over an index: on October 29, 2026 the bank prime rate was 7.00% and SOFR 3.94% (Federal Reserve H.15; New York Fed). SBA 7(a) loans over $350,000 are capped at prime plus 3.0, or 10.00%, and SBA 504 debentures track the 10-year Treasury, then 4.98%.

Can you use an SBA loan for ground-up construction?

Yes, if your business will occupy at least 60% of the new building and may lease up to 20% long term (13 CFR 120.131). SBA 504 covers buildings and land with a debenture up to $5,000,000, and 7(a) lends up to $5,000,000. Investment in rental real estate is not eligible for 504, so pure investor projects need a conventional loan.

Is a commercial construction loan interest-only?

During construction, usually yes: interest is charged only on the amount drawn, and many loans pay it from an interest reserve built into the budget. In our worked example, a $4,400,000 loan at 7.50% with even draws over 12 months needs a $165,000 reserve. Principal payments start at conversion or under the permanent loan.

Can land you already own count as equity?

Usually. Under SBA SOP 50 10 8.1, land bought less than 2 years before a 504 application counts at its cost, and land held 2 years or more counts at appraised fair market value. For bank loans on income-producing projects, the HVCRE rule in 12 CFR 324.2 counts contributed real property at its appraised value toward the 15% capital test.

Does the lender need a performance bond from my contractor?

For an SBA 7(a) loan whose construction component exceeds $350,000, yes: SBA SOP 50 10 8.1 requires 100% performance and payment bonds plus builder’s risk and workers’ compensation insurance, unless the lender uses third-party construction management with funds control. Below $350,000, or on conventional loans, the requirement is set by the lender’s own policy.

What happens to a construction loan when the building is finished?

It is repaid or converted. A bank loan may convert to a term loan or be refinanced by a permanent mortgage; SBA 7(a) amortizes over up to 25 years plus the construction period (13 CFR 120.212). On a 504 project, the debenture is sold after completion and its proceeds repay the interim lender (SBA SOP 50 10 8.1).

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.

← Back to all articles