Shop Drawings: Who Prepares, Seals and Reviews Them, Trade by Trade

Steel frame of a commercial building under construction with a tower crane and stacked beams

Shop drawings are the drawings a contractor, subcontractor, fabricator or supplier prepares to show exactly how one part of the work will be made and installed; under AIA A201-2017 the architect reviews them only against the design concept.

Key takeaways

  • AIA A201-2017 §3.12.1 defines shop drawings as “drawings, diagrams, schedules, and other data specially prepared for the Work” by the contractor or anyone below it, and §3.12.4 says they “are not Contract Documents” (A201-2017, University of Maine System copy).
  • The architect’s review covers conformance with the design concept only; dimensions, quantities and installation stay with the contractor, and approving an item does not approve the assembly it sits in (A201 §4.2.7).
  • A shop drawing needs a professional engineer’s seal when the contract delegates design to the contractor (A201 §3.12.10.1), for example steel connections designed under AISC 303 Option 3 in UFGS 05 12 00.
  • Public review clocks run 15 to 30 days per round: 30 calendar days in UFGS 01 33 00 (August 2026) and up to 30 calendar days for a Type 3 working drawing in the WSDOT 2027 Standard Specifications §1-05.3.
  • Some shop drawings also go to the building department as deferred submittals; Seattle lists curtain wall, precast piles and large skylights and aims to finish the first review “within two weeks” (Seattle SDCI).

What are shop drawings?

Shop drawings are project-specific drawings made by the builder side to show how a component will be fabricated, assembled and installed. AIA A201-2017 §3.12 separates them from product data, which is a maker’s published catalog information, and from samples, which are physical pieces that set the standard the work is judged by. All three are submittals, and none of them is part of the contract.

ItemWhat it isWho makes itShop drawing example vs otherSource
Shop drawingsDrawings, diagrams and schedules prepared for this projectContractor, subcontractor, sub-subcontractor, manufacturer, supplier or distributorSteel connection details with bolt and weld sizesA201-2017 §3.12.1; UFGS 01 33 00 SD-02
Product dataPublished illustrations, schedules, performance charts and brochuresManufacturer, furnished by the contractorSprinkler head cut sheet showing model and listingA201 §3.12.2; UFGS SD-03
SamplesPhysical examples that set the standard for judging the workSupplier or installerLaminate chip or a full-size cabinet mock-upA201 §3.12.3; UFGS SD-04
Design dataCalculations behind a contractor-designed elementContractor’s licensed engineerSealed connection calculations, sprinkler hydraulic calculationsA201 §3.12.10.1; UFGS SD-05

The federal definition is broader. UFGS 01 33 00 (August 2026) counts three things as SD-02 shop drawings: drawings prepared for a portion of the work, a maker’s or fabricator’s instructions for producing and integrating the product, and coordination drawings that show how several systems fit together. A shop drawing is useful only if it carries information the design set leaves to the builder: UFGS 05 12 00 says steel fabrication drawings “must not be reproductions of contract drawings.”

Who prepares, reviews and stamps shop drawings?

A detailer working for the subcontractor or fabricator draws the shop drawings, the general contractor checks and stamps them, and the architect or engineer of record reviews them for design intent. Under AIA A201-2017 the contractor must review, approve and submit them (§3.12.5), and a licensed engineer seals them only when the contract hands design to the contractor (§3.12.10.1).

PartyRole on the shop drawingMark it addsClause
Detailer or fabricatorDraws members, sizes, connections, field dimensions and installation detailsTitle block with drawing number, date and revisionA201 §3.12.1; UFGS 01 33 00 §1.6.4.2.1
Contractor’s delegated design engineerDesigns the part the contract delegates, such as steel connections or sprinkler hydraulicsSignature and seal on drawings and calculationsA201 §3.12.10.1; UFGS 05 12 00 §1.5.3
General contractorChecks field measurements, coordinates trades, approves and submitsContractor’s review stamp; unstamped packages come back “not reviewed”A201 §3.12.5, §3.12.6; UFGS §1.12.1.d
Architect and engineer of recordReviews for conformance with information given and the design conceptAction stamp: approved, approved as noted, revise and resubmit, not reviewedA201 §4.2.7
Building official (deferred submittal items only)Approves the item before it is installedPermit approval of the deferred submittalMinnesota Rules 1300.0130 subp. 9; Seattle Building Code §104.10.3

The review runs in a fixed order. Each step has its own clause, and a package that skips one comes back without action.

  1. The detailer or fabricator prepares the drawings from the contract documents and verified field dimensions (A201 §3.12.6).
  2. Where the contract delegates design, the contractor’s engineer seals the drawings and calculations (A201 §3.12.10.1).
  3. The general contractor reviews, approves, stamps and submits on the submittal schedule (A201 §3.12.5).
  4. The architect and engineer of record review for design concept only and return an action stamp (A201 §4.2.7).
  5. For a deferred submittal item, the design professional in responsible charge forwards it to the building official, and the item is not installed until the building official approves it (Minnesota Rules 1300.0130 subp. 9).
  6. Fabrication starts only after approval (A201 §3.12.7); a revise and resubmit stamp sends the package back to step 1.
Shop drawing review path under AIA A201-20171. Detailer or fabricator preparesfrom contract documents and field dimensions2. Delegated engineer sealsonly if design is delegated (A201 §3.12.10.1)3. General contractor reviews and stampsA201 §3.12.5 and §3.12.64. Architect and engineer of recorddesign concept only (A201 §4.2.7)Action stampapproved, approved as noted,revise and resubmit, not reviewed5. Deferred submittal item?building official approvesbefore installationApprovedRevise and resubmitflag every change (A201 §3.12.9)same review period againResubmit6. Fabricate after approvalno work before approval (A201 §3.12.7)back to step 1Steps 2 and 5 apply only when the contract delegates design or the permit lists a deferred submittal.Sources: AIA A201-2017; Minnesota Rules 1300.0130 subp. 9 (IBC §107.3.4.1 wording).
Shop drawing review path: contractor stamp (A201 §3.12.5), architect review for design concept only (§4.2.7), no fabrication before approval (§3.12.7), deferred items to the building official first (Minnesota Rules 1300.0130 subp. 9). Accessed November 2026.

What does the review stamp on a shop drawing mean?

A review stamp records an action on one submittal, not a transfer of responsibility. AIA A201-2017 §4.2.7 says the review “is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities,” and §3.12.8 keeps the contractor liable for errors in approved shop drawings. Each stamp wording below tells the field whether it may fabricate.

Stamp wordingCode (UFGS)Can you fabricate?What it does not meanSource
Approved / acceptedAYesThat dimensions, quantities, means and methods or safety precautions were checkedUFGS 01 33 00 §1.12.1.a; A201 §4.2.7
Approved as notedANYes, if you take no exception to the correctionsThat a correction changing price or time is free; give notice under the changes clauseUFGS §1.12.1.b, §1.13
Revise and resubmit / disapprovedRRNoThat the next review is faster; it gets the same review period againUFGS §1.12.1.c, §1.11.a
Not reviewedNRNoA design objection; it was unstamped, incomplete, already approved or not requiredUFGS §1.12.1.d
Receipt acknowledgedRAInformation-only items onlyApproval of anythingUFGS §1.12.1.e
Contractor’s review stampNoneNot by itselfDesign approval; it certifies the contractor checked and coordinated the packageA201 §3.12.5, §3.12.6
Engineer’s sealNoneNot by itselfApproval by the architect; it shows who is responsible for the delegated designA201 §3.12.10.1
What each mark on a reviewed shop drawing meansOne shop drawing sheet, three different marksContractor’s review stampchecked and coordinatedfield measurementsA201 §3.12.5, §3.12.6Engineer’s sealdelegated design onlysignature on drawingsand calculationsA201 §3.12.10.1Architect’s action stampA, AN, RR, NR or RAdesign concept onlyA201 §4.2.7Not covered by any of the three marksdimensions, quantities, means and methods or safety precautions (A201 §4.2.7)Still on the contractor after approvalerrors and omissions, and any deviation not flagged at submittal (A201 §3.12.8)
Three marks, three meanings: the contractor stamp (A201 §3.12.5), the engineer’s seal for delegated design (§3.12.10.1) and the architect’s action stamp (§4.2.7); none covers dimensions, quantities or means and methods. Source: AIA A201-2017.

The limits matter most when a shop drawing quietly changes the design. In the July 17, 1981 Kansas City Hyatt Regency walkway collapse, the original design hung both walkways from one set of rods, the fabricator’s shop drawings used two sets, and the National Bureau of Standards found that “these shop drawings were reviewed by the contractor, structural engineer and architect” (NBSIR 82-2465, 1982). A201 §3.12.8 now relieves a contractor of a deviation only if it flagged the deviation at submittal and got written approval as a minor change, Change Order or Construction Change Directive.

Common beliefWhat the primary source saysSource
An approved shop drawing becomes part of the contractShop drawings “are not Contract Documents”A201-2017 §3.12.4
Approval moves liability for errors to the architectThe contractor is not relieved of responsibility for errors or omissions in shop drawings by the architect’s approvalA201 §3.12.8
A deviation drawn on an approved sheet is acceptedOnly if specifically flagged at submittal and approved in writing as a minor change, Change Order or CCDA201 §3.12.8
Changes on a resubmittal are covered by the new approvalApproval does not apply to revisions the contractor did not point out in writingA201 §3.12.9
Agency review shifts accuracy to the agencyReview “shall neither confer upon the Contracting Agency nor relieve the Contractor of responsibility for the accuracy of the drawings”WSDOT M 41-10 §1-05.3 (2027)

This page describes standard contract language and public specifications, not legal advice; your signed contract, its supplementary conditions and your state’s engineering board rules control.

When do shop drawings need an engineer’s seal?

A shop drawing needs a licensed engineer’s seal when it contains design the contract assigns to the contractor, not when it only details a completed design. AIA A201-2017 §3.12.10.1 requires the signature and seal on “all drawings, calculations, specifications, certifications, Shop Drawings, and other submittals” prepared by that professional, and the owner and architect must first state the performance and design criteria.

SituationSeal required?Who sealsSource
Fabricator details a fully designed element from the contract drawingsNo seal by default; contractor’s stamp onlyNoneA201 §3.12.10, §3.12.5
Contract delegates steel connection designYes, on connection calculations, and on fabrication drawings where the spec says soContractor’s registered professional engineerUFGS 05 12 00 §1.5.2, §1.5.3 (AISC 303 Option 3)
Steel shoring and temporary bracingYes, where the bracketed spec option is keptRegistered professional engineerUFGS 05 12 00 §1.5.2
Federal fire sprinkler working plansYesQualified Fire Protection Engineer (P.E. who passed the NCEES fire protection exam)UFGS 21 13 13 §1.2.3
WSDOT Type 2E or 3E working drawingYes, seal, date and registration number on the cover pageLicensed professional under WAC 196 and WAC 308WSDOT M 41-10 §1-05.3
Deferred submittal item on a permit (trusses, joists, curtain wall, precast planks)Design documents by the item’s designer; reviewed by the design professional in responsible charge before the building officialItem designer, then responsible-charge reviewerMinnesota Rules 1300.0130 subp. 9; Seattle Building Code §104.10.3

The building department route is separate from the architect’s review. IBC §107.3.4.1, carried with nearly the same wording in Minnesota Rules 1300.0130 subp. 9, defines deferred submittals as portions of the design “not submitted at the time of the application,” lets them proceed only with the building official’s prior approval, and bars installing the item until its design and submittal documents are approved. The 2021 Seattle Building Code §104.10.3 names 9 items the structural engineer in responsible charge reviews this way, including wood trusses, steel joists, prefabricated stair systems and curtain wall systems.

A fabricator’s shop can also replace some special inspection. 2024 IBC §1704.2.5 requires special inspection of structural items fabricated off site unless the fabricator is approved under §1704.2.5.1, in which case it submits a certificate of compliance at the end of fabrication. Who hires those inspectors is covered in our guide to special inspections under IBC Chapter 17.

Does this shop drawing need an engineer’s seal?Q1. Does the contract delegate designto the contractor?Engineer seals drawingsand calculations (A201 §3.12.10.1)YesQ2. Is the item a deferred submittalon the permit?NoResponsible-charge review,then building official approvalbefore installationYesContractor stamp and architect review;no sealNoSources: AIA A201-2017; UFGS 05 12 00; Minnesota Rules 1300.0130 subp. 9; Seattle Building Code §104.10.3.
Seal decision: delegated design needs an engineer’s seal (A201 §3.12.10.1); deferred submittal items need responsible-charge review and building official approval (Minnesota Rules 1300.0130); otherwise contractor stamp and architect review only.

Which trades produce shop drawings, and which standard governs each?

Any trade that fabricates off site or must fit around other trades produces shop drawings, and each specification section names the standard they must follow. The federal guide specifications below are free to read and name the governing standard and the required content, which makes them a usable checklist for private jobs too, where the project manual’s own Division 05 to 23 sections may say less.

TradeWhat the shop drawing must showGoverning standard namedSeal or certificationSource
Structural steelBolt location, type and size; welds; member sizes and lengths; connection details; blocks, copes and cuts; deviations highlighted with reasonsANSI/AISC 303 (2022), AISC 326, AISC 325; AWS A2.4 weld symbolsP.E. seal on delegated connection calculations; erection drawings sealed where specifiedUFGS 05 12 00 §1.5.1 to §1.5.3
Reinforcing steelPlacing drawings with fabrication dimensions, bar and support locations, splice locations, lap lengths, mechanical and welded splice detailsACI 301 (2020), ACI 117 tolerances, CRSI Manual of Standard Practice (2024)None by defaultUFGS 03 30 00 (February 2019)
Curtain wallElevations, full-size sections, framing, jointing, metal types and thicknesses, flashing, field connections, weep and drainage, glazing and glass sizes, erection detailsAAMA 501 series and ASTM E330/E330M, E331 performance testsP.E.-signed calculations where UFC 4-010-01 antiterrorism criteria apply (§1.9.1.1)UFGS 08 44 00 (May 2019)
Fire sprinklerWorking plans: floor plans at 1/8 in = 1 ft minimum, sprinkler spacing dimensions, building sections, riser details at 1/2 in = 1 ft, hangers and bracing; with hydraulic calculationsNFPA 13 (2025) working plan requirementsDesigner NICET Level III or IV in Water-Based Systems Layout; QFPE stampUFGS 21 13 13 §1.4.1.1, §1.4.2.1
HVAC ductworkDuct layout with supports and hangers, gauge, reinforcement spacing, rigidity class, static pressure and seal classes; equipment layout and clearancesANSI/SMACNA 006 (2020) HVAC Duct Construction StandardsNone by defaultUFGS 23 30 00 §1.4.4 (February 2025)
Architectural millwork and caseworkPlans, elevations, sections, attachment details, furring and blocking, cutouts for installed itemsAWI Architectural Woodwork Standards, custom or premium gradeAWI Quality Certification Program label where specifiedUFGS 06 41 16.00 10 §1.4.4 (August 2025)

Two trades carry extra timing rules. UFGS 21 13 13 wants sprinkler shop drawings no later than 28 days before system installation and rejects partial packages: shop drawings, product data and calculations go in together or come back “disapproved without review.” UFGS 06 41 16.00 10 asks for a full-size casework mock-up before final shop drawing approval. Bar sizes and grades that appear on placing drawings are listed in our rebar sizes chart, and the performance tests a curtain wall shop drawing must reflect are set out in our curtain wall guide.

How long does shop drawing review take?

Plan on 15 to 30 days per review round, counted from receipt. AIA A201-2017 sets no number, so the review period is whatever the specification states: 30 calendar days in UFGS 01 33 00, 15 business days at the VA, up to 20 or 30 calendar days for WSDOT Type 2 or Type 3 working drawings, and a two-week target for Seattle’s permit review.

DocumentReviewerReview period per roundResubmittalSource
AIA A201-2017 §4.2.7ArchitectPer approved submittal schedule, or “reasonable promptness”SameAIA via University of Maine System
UFGS 01 33 00 §1.11 (August 2026)Federal Contracting Officer30 calendar days; 14 more for variations (§1.10.4)Same as initialWBDG
WSDOT M 41-10 §1-05.3, Type 3 (2027)State DOT EngineerUp to 30 calendar days; written approval before workExtension of time considered if exceededWSDOT
WSDOT M 41-10 §1-05.3, Type 2 (2027)State DOT EngineerUp to 20 calendar days; review and commentSame ruleWSDOT; steel shop plans are Type 2 under §6-03.3(7)
VA 01 33 23 §1.10 (November 2023)U.S. Department of Veterans Affairs15 business daysSame as initialWBDG
DASNY 013300 §1.4.BNew York State public authority15 days; 21 days for sequential review15 daysDASNY
Seattle SDCI permit shop drawingsCity building department“Within two weeks” (14 days) target for initial reviewNot statedSeattle SDCI
Shop drawing review period per round in public specificationsReview days per round: 30 UFGS and WSDOT Type 3, 21 DASNY sequential, 20 WSDOT Type 2, 15 VA and DASNY, 14 SeattledaysUFGS 01 33 00, Contracting Officer (calend30.0WSDOT Type 3 working drawing (calendar)30.0DASNY 013300, sequential review (days)21.0WSDOT Type 2 working drawing (calendar)20.0VA 01 33 23 (business)15.0DASNY 013300, initial review (days)15.0Seattle SDCI permit review target (two wee14.0
Review periods per round run from 14 to 30 days in the public documents read for this page; every one that addresses resubmittals restarts the same clock. Sources: UFGS 01 33 00, WSDOT M 41-10, DASNY 013300, VA 01 33 23, Seattle SDCI, accessed November 2026.

The resubmittal is where schedules slip, because every public specification here restarts the full clock. The worked example below adds review time only, for a package returned once and approved on the second round; the contractor’s own correction time and the fabricator’s lead time come on top.

SpecificationFirst reviewSecond reviewVariation allowanceReview days before fabrication
UFGS 01 33 00, package with a flagged variation30301430 + 30 + 14 = 74 calendar days
UFGS 01 33 00, no variation3030030 + 30 = 60 calendar days
WSDOT Type 3 working drawing3030030 + 30 = 60 calendar days
WSDOT Type 2 (steel shop plans)2020020 + 20 = 40 calendar days
VA 01 33 231515015 + 15 = 30 business days, about 6 weeks
DASNY 0133001515015 + 15 = 30 days
WSDOT Standard Specifications section 1-05.3 with the 20 and 30 calendar day review periods boxed
WSDOT Standard Specifications M 41-10 (2027), §1-05.3 Working Drawings, page 1-43: up to 20 calendar days for Type 2 and up to 30 calendar days for Type 3 working drawings. WSDOT, accessed November 15, 2026.

Federal and state owners also refuse to pay for slow resubmittals. UFGS 01 33 00 §1.11 says “no delay damages or time extensions will be allowed for time lost in late submittals,” and WSDOT §1-05.3 puts “all risk and all costs of any Work delays caused by rejection or nonapproval” on the contractor. Back-scheduling submit dates from the on-site need date, with a copyable log, is laid out in our guide to submittals in construction.

How do shop drawings differ from submittals, construction documents and as-builts?

Construction documents say what to build, shop drawings say how one piece will be made, and as-built drawings record what was actually built. Shop drawings are one kind of submittal, alongside product data and samples. The drawings and specifications are Contract Documents under AIA A201-2017 §1.1.1; shop drawings never are (§3.12.4), and as-builts are a closeout deliverable.

AttributeConstruction documentsShop drawingsSubmittals (all)As-built drawingsSource
Prepared byArchitect and engineersContractor, subcontractor, fabricator, supplierContractor and its suppliersContractor, from field marksA201 §3.12.1; UFGS SD-11
TimingDesign phase, before biddingAfter award, before fabricationPreconstruction to closeoutDuring work, delivered at closeoutUFGS 01 33 00
Contract document?YesNoNoNo; a recordA201 §1.1.1, §3.12.4
Sealed?Yes, by the design professionals for permitOnly delegated designOnly delegated design or certificationsNot by defaultA201 §3.12.10.1
Who reviewsBuilding official at permitContractor, then architect; building official for deferred itemsArchitect or Contracting OfficerOwner at closeoutA201 §4.2.7; Minnesota Rules 1300.0130
Level of detailDesign intent, sizes, performance criteriaExact fabrication dimensions, connections, piece marksVaries by typeFinal locations and field changesUFGS 05 12 00 §1.5.2

The sequence links all four. The design team issues the set described in our guide to construction documents, the shop drawings translate it for the shop, questions about gaps in the design go out as an RFI rather than as a note on a shop drawing, and the last approved shop drawing revision feeds the record set described in our guide to as-built drawings. WSDOT §6-03.3(7), for example, asks for as-built shop plans on sheets no smaller than 11 by 17 inches before physical completion.

What should a shop drawing package include before it goes to the architect?

A package that misses a basic item comes back unreviewed and restarts the clock. Check these 8 items before it leaves the general contractor’s office. The format rules come from UFGS 01 33 00 §1.6.4.2, and the content rules from AIA A201-2017 §3.12; private specifications usually repeat both in their Section 01 33 00.

  1. Sheet size between 8 1/2 by 11 inches and 30 by 42 inches, drawn to scale with the scale shown, dark lines on white (UFGS 01 33 00 §1.6.4.2).
  2. Title, drawing number, date, and revision numbers and dates on every sheet, with the submittal number next to the title block (UFGS §1.6.4.2.1).
  3. Same unit of measure as the contract drawings, and dimensions on everything except diagrams (UFGS §1.6.4.2.b).
  4. Field measurements verified or marked “to be verified,” because the contractor represents it has checked them (A201 §3.12.6).
  5. Every deviation from the contract documents clouded and explained in writing on the transmittal (A201 §3.12.8; UFGS 05 12 00 §1.5.2).
  6. On a resubmittal, every change beyond the reviewer’s comments called out (A201 §3.12.9).
  7. Seal and signature of the delegated engineer on drawings and calculations where the contract delegates design (A201 §3.12.10.1).
  8. Contractor’s review stamp, signed and dated, plus related product data and calculations in the same package (A201 §3.12.5; UFGS 21 13 13).

Which shop drawing path applies to your package?

The path depends on 3 questions: does the package contain contractor design, is the item a deferred submittal on the permit, and what does the contract’s review clock say. The decision table carries the same logic as the seal flowchart above, with the clause and the review time that apply on the public jobs listed on this page.

IfThenClauseClock
The fabricator only details a complete designContractor stamp, architect review; no sealA201 §3.12.5, §4.2.7Spec review period, 15 to 30 days
The contract delegates design (steel connections, curtain wall anchorage, sprinklers)Engineer seals drawings and calculations; architect checks design concept onlyA201 §3.12.10.1; UFGS 05 12 00 §1.5.3Same period; WSDOT Type 3E up to 30 calendar days
The item is listed as a deferred submittal on the permit setDesign professional in responsible charge reviews, then the building official approves before installationMinnesota Rules 1300.0130 subp. 9; Seattle Building Code §104.10.3Seattle target: 2 weeks for initial review
Your shop drawing differs from the contract documentsFlag the deviation in writing at submittal; it binds only once approved as a minor change, Change Order or CCDA201 §3.12.814 extra calendar days for variations (UFGS §1.10.4)
The drawings leave a gap or conflict you cannot resolveSend an RFI before detailing that areaA201 §3.2.2, §4.2.14Separate RFI clock
The stamp reads revise and resubmit or not reviewedDo not order or fabricate; fix, flag all changes and resubmitA201 §3.12.7, §3.12.9; UFGS §1.12.1Full review period again (UFGS §1.11.a)
The stamp reads approved as noted and a note changes cost or timeProceed only if you take no exception; otherwise give notice under the changes clauseUFGS §1.12.1.b, §1.13; A201 §15.1.3Claim notice within 21 days (A201 §15.1.3.1)

The general conditions that carry §3.12 and §4.2.7 are mapped article by article in our AIA A201 guide, and sprinkler working plans tie into the system budgets in our fire sprinkler system cost guide.

Shop drawings travel with other submittals, and questions they raise go back as an RFI.

How we compiled this

We read AIA A201-2017 §3.12 and §4.2.7 in the University of Maine System copy, 8 federal guide specifications from WBDG (UFGS 01 33 00, 03 30 00, 05 12 00, 06 41 16.00 10, 08 44 00, 21 13 13, 23 30 00 and VA 01 33 23), the WSDOT 2027 Standard Specifications, DASNY 013300, Minnesota Rules 1300.0130, the 2021 Seattle Building Code Chapter 1, Seattle SDCI’s shop drawing page, 2024 IBC Chapter 17 and NBSIR 82-2465: 17 documents, accessed November 2026. Standards named in the trade table (AISC 303, NFPA 13, SMACNA 006, AWI AWS) are cited as the specifications reference them; we did not quote their paywalled text, and we did not survey designers or contractors.

Frequently asked questions

Who prepares shop drawings?

The contractor’s side prepares them: a subcontractor, fabricator, manufacturer or supplier, usually through a detailer. AIA A201-2017 §3.12.1 lists the contractor, subcontractor, sub-subcontractor, manufacturer, supplier or distributor. The architect does not draw them; the general contractor must review, approve and stamp them before they go to the architect (§3.12.5).

Are shop drawings part of the contract documents?

No. AIA A201-2017 §3.12.4 states that shop drawings, product data and samples “are not Contract Documents.” They show how the contractor proposes to meet the drawings and specifications. A deviation shown on an approved shop drawing binds only if the contractor flagged it at submittal and received written approval as a minor change, Change Order or Construction Change Directive (§3.12.8).

Do shop drawings need to be stamped by an engineer?

Only when they contain design the contract delegates to the contractor. AIA A201-2017 §3.12.10.1 then requires the licensed professional’s signature and seal on the drawings and calculations. UFGS 05 12 00 requires sealed calculations for steel connections designed under AISC 303 Option 3, and UFGS 21 13 13 requires a fire protection engineer’s stamp on sprinkler working plans.

How long does an architect have to review shop drawings?

AIA A201-2017 sets no fixed number: the architect acts on the approved submittal schedule or with “reasonable promptness” (§4.2.7). Public specifications fill the gap with 15 to 30 days per round, such as 30 calendar days in UFGS 01 33 00 and 15 business days in VA 01 33 23, and each resubmittal gets the same period again.

Can fabrication start before shop drawings are approved?

Not under standard terms. AIA A201-2017 §3.12.7 bars any work that requires a submittal until the architect approves it, and UFGS 01 33 00 §1.12.1 lets work proceed only on approved or approved-as-noted stamps. WSDOT §6-03.3(7) also says no steel may be fabricated until the working drawing review is complete and the material source is accepted.

What is the difference between shop drawings and as-built drawings?

Shop drawings come before fabrication and show how a piece will be made; as-built drawings come at closeout and record what was installed, including field changes. The last approved shop drawing revision usually feeds the record set: WSDOT §6-03.3(7) asks for as-built shop plans on sheets at least 11 by 17 inches before physical completion.