Progressive Design Build: How the Two Phases and the Off-Ramp Work

Graded commercial jobsite with survey stakes, a soil boring rig and a site trailer in morning light

Progressive design build is design-build in two phases: the owner hires one firm on qualifications, pays it to design and price the work in Phase 1, then accepts its Phase 2 price or exits.

Key takeaways

  • DBIA Document 544 (2024, Second Edition) splits the job into Phase 1 (preliminary design and an open-book Phase 2 price) and Phase 2 (final design, construction, commissioning and warranty), priced as a lump sum or cost of the work plus a fee with an optional guaranteed maximum price (GMP).
  • If the owner does not accept the Phase 2 proposal, DBIA 544 §1.3.2.3 gives it three options: change the proposal, continue on cost reimbursement with no contract price, or terminate for convenience.
  • Washington RCW 39.10.300(1) lets public bodies use design-build “including progressive design-build” on projects over $2,000,000 that meet one of three tests; parking garages and pre-engineered metal buildings qualify at any cost.
  • Missouri RSMo 67.5060.15, in effect from August 28, 2026, requires a two-stage selection with a shortlist of 2 to 3 firms, bars construction pricing in proposals and expires August 28, 2036.
  • Wilsonville, Oregon signed a $4,804,723 Phase 1 agreement in June 2022; its third GMP came in at $36,836,661.92, 41.2% above the $26,082,917 budget, and staff weighed the off-ramp before recommending approval (Wilsonville URA Resolution 338 packet).

How does progressive design build work, phase by phase?

Progressive design build runs as a qualifications-based selection, then a paid Phase 1 in which the design-builder develops the design and an open-book price, then a Phase 2 that finishes design and builds. The owner commits to construction only when it accepts the Phase 2 proposal. DBIA Document 544 defines Phase 1 as completing preliminary design, setting the construction plan and establishing Phase 2 costs.

The selection step is what separates it from fixed-price design-build. Missouri’s statute bars price or fees from the qualifications stage and allows only preconstruction pricing, “in the form of proposed rates, fees, or other acceptable forms”, at the proposal stage (RSMo 67.5060.15(5) and (8)(d)). Washington likewise says cost or price factors “are not permitted” in the request for qualifications (RCW 39.10.330(1)(d)).

Progressive design build process: selection, Phase 1, proposal decision, Phase 2 or off-ramp How progressive design build runs: selection, Phase 1, proposal, Phase 2 SELECTION (qualifications first) 1. RFQ: qualifications only, no price or fees RSMo 67.5060.15(5); RCW 39.10.330(1)(d) 2. Shortlist and proposals: approach plus preconstruction fee or rates only Missouri: 2 to 3 firms, no construction pricing (15(8)(b), (d)); Washington: up to 5 finalists 3. Negotiate the Phase 1 agreement with the top-ranked firm If talks fail, move to the next-ranked firm (RSMo 67.5060.15(8)(f)) PHASE 1 (design and preconstruction, paid separately) 4. Validate the owner’s project criteria Design-builder writes an evaluation and recommendations (DBIA 544 §1.1.2) 5. Design to the Exhibit B level and estimate open-book Level set as a percent of design or defined deliverables (DBIA 544 §1.2.1) 6. Proposal for Phase 2 (DBIA 544 §1.3.1) Lump sum, or cost of the work plus fee with optional GMP, plus basis of design documents, assumptions, schedule, allowances 7. Owner accepts the proposal? No Yes Off-ramp options (§1.3.2.3) i. Suggest changes the firm accepts ii. Continue cost-reimbursable, with no contract price iii. Terminate for convenience; reusing the design costs an extra fee (§4.3.2) Phase 2 (DBIA 544 §1.2.2) Contract Price Amendment and notice to proceed (§1.3.2.2) Finish design, procure, build, start up, commission, warranty Bonds due before construction (RCW 39.10.330(7))
Selection on qualifications, a paid Phase 1, a Phase 2 proposal and the owner’s accept-or-off-ramp choice. Sources: DBIA 544 (2024) §§1.1.2 to 1.3.2.3; RSMo 67.5060.15; RCW 39.10.330, accessed November 2026.
  1. Request for qualifications. Firms submit experience, key staff and their primary design consultants and trade partners; no price or fee (RSMo 67.5060.15(4) and (5)).
  2. Shortlist and proposals. Missouri narrows to no more than 3 and no fewer than 2 firms; Washington allows up to 5 finalists and requires an honorarium for unsuccessful finalists (RCW 39.10.330(2) and (9)). Proposals describe design, preconstruction and construction approach with no construction price (RSMo 67.5060.15(8)(b)).
  3. Negotiate the Phase 1 agreement. The owner negotiates a preconstruction services agreement with the top-ranked firm and may move to the next-ranked firm if talks fail (RSMo 67.5060.15(8)(f)).
  4. Validate the criteria. The design-builder reviews the owner’s project criteria in writing and recommends changes before design proceeds (DBIA 544 §1.1.2).
  5. Design and estimate open-book. Design advances to the level defined in Exhibit B, either a percent of design completion or a list of deliverables (DBIA 544 §1.2.1).
  6. Phase 2 proposal. The firm prices the rest of the job as a lump sum or as cost of the work plus fee with an optional GMP, with the basis of design documents attached (DBIA 544 §1.3.1).
  7. Owner decision. Acceptance becomes a Contract Price Amendment and a notice to proceed (§1.3.2.2); rejection triggers the off-ramp options (§1.3.2.3).
  8. Phase 2. The firm completes design, procures, builds, starts up, commissions and warrants the work (§1.2.2). In Washington, the performance and payment bond is due before construction starts, not for design or preconstruction (RCW 39.10.330(7)).

What goes into the Phase 2 proposal?

DBIA 544 §1.3.1 lists 12 items the Phase 2 proposal includes unless the parties agree otherwise. The owner reviews them, sends written comments, and the design-builder adjusts the proposal before acceptance (§1.3.2.1). Owners who want a single document to compare against their budget should insist on items 1 to 4 at minimum, because they fix price, scope and time.

#Proposal item (DBIA 544 §1.3.1)Why the owner checks it
1Contract price: lump sum, or fee plus estimated cost of the work with optional GMP, including the design-builder’s contingencySets the payment basis for Phase 2
2Basis of design documents, including the owner’s project criteriaDefines what the price buys
3Assumptions and clarificationsExclusions that later become change orders
4Scheduled substantial completion date and project scheduleTies the price to a duration
5 to 7Allowance items and values; alternate prices; unit pricesShows which costs are still estimates
8Additional services not includedFuture price increases already named
9 to 10Savings provision; performance incentivesWho keeps money left under a GMP
11Time limit for acceptanceStarts the off-ramp clock if missed
12Owner’s permit listPermits and approvals the owner must obtain

What is the off-ramp, and who keeps the design?

The off-ramp is the owner’s right to stop after Phase 1 if it cannot agree a Phase 2 price. Under DBIA 544 §1.3.2.3, a rejected or unanswered proposal is “deemed withdrawn”, and the owner picks one of three options. If the owner then finishes the project with another firm using the design-builder’s work product, DBIA 544 §4.3.2 requires an additional payment that the parties should set before signing.

Who actsOptionWhat followsClause
Owneri. Suggest modifications to the proposalIf the design-builder accepts in writing, the proposal is accepted§1.3.2.3 i
Ownerii. Continue the work on cost reimbursementNo contract price applies; paid under §6.1.2§1.3.2.3 ii
Owneriii. Terminate for convenienceNo §8.2 payment for uncompleted work; work-product use fee under §4.3.2 if the design is reused§1.3.2.3 iii; §4.3
Design-builder, if the owner picks none(a) continue and be paid as under option ii; (b) suspend; (c) give notice that the agreement is completedIf the owner does not act within 10 days of that notice, the agreement is deemed completed§1.3.2.3

DBIA’s instruction sheet says the owner “should not use the Termination for Convenience Clause to obtain Design-Builder’s valuable design concepts, and then seek lower bids” (DBIA 544 instructions, §4.3). Statutes are thinner here: Missouri’s PDB subsection says the parties “may amend the contract to authorize construction” once price is accepted (RSMo 67.5060.15(8)(g)) but does not say who owns the drawings if they never agree. Put the §4.3.2 work-product fee and the deliverables list in the Phase 1 agreement before signing; this page is not legal advice, and your attorney should confirm how a public-records or state licensing rule affects design ownership.

Progressive design build vs design build: what changes?

The difference is when the price is fixed and how the firm is chosen. In fixed-price (lump-sum) design-build, competing teams submit a conceptual design and a firm price, and price carries real weight in the award. In progressive design build, the owner selects on qualifications and a preconstruction fee, then negotiates the construction price with one firm after Phase 1. Missouri’s statute sets both processes side by side.

FeatureFixed-price design-buildProgressive design buildSource
Selection stagesThree: qualifications, technical proposal with conceptual design, cost proposalTwo: qualifications, then approach proposalRSMo 67.5060.8(2), .15(2)
Price in the awardFirm, fixed cost of design and construction, with bid security; at least 40% of pointsPreconstruction rates or fees only; no construction pricingRSMo 67.5060.13(1)-(2), .15(8)(b), (d)
Design in the proposalDesign to the level the request for proposal sets; at least 40% of pointsApproach to design development, estimating and value engineeringRSMo 67.5060.12(2), (6); .15(8)(c)
Stipend to losing shortlisted firmsYes, for Phase II design workNot defined for PDB in Missouri; Washington honorarium applies to all design-build finalistsRSMo 67.5060.1(12); RCW 39.10.330(9)
When the price is setAt awardAfter Phase 1, at the level set in Exhibit BDBIA 544 §1.2.1
Phase 2 price formLump sumLump sum, or cost plus fee with or without a GMPDBIA 544 §1.3
Exit before constructionNot built in; termination clauses onlyOff-ramp after the Phase 2 proposalDBIA 544 §1.3.2.3
Owner staffingReview design against criteriaAlso audit open-book estimates and each GMP packageWilsonville Res. 338 staff report

DBIA’s own guidance on which Phase 2 price form to choose is specific: cost-plus with a GMP “is desirable” when project criteria remain uncertain after Phase 1, while a lump sum “may be suitable” when criteria and design are settled (DBIA 544 instructions). For the wider comparison of design-build with the traditional route, see our guide to design-build vs design-bid-build.

Is progressive design build the same as CMAR?

No. Construction manager at risk keeps two contracts, one with the architect and one with the builder, while progressive design build puts design and construction under one contract with one firm. Both negotiate a GMP during design. Arizona’s transportation statute defines CMAR as a construction contract “separate from the contract for design services” (ARS 28-7361), which is the structural line between the two. Our construction management at risk guide covers the two-contract version.

Which states authorize progressive design-build for public owners?

Public owners need statutory authority to skip low-bid award, and only some statutes name progressive design-build. In the statutes we read as of November 2026, Washington and Missouri authorize it by name for public bodies, Mississippi for its transportation commission, and DBIA reports Illinois and South Carolina authority; other states may allow it under general design-build language. Private owners need no statute.

RCW 39.10.300 text with subsection (1), design-build including progressive design-build over $2,000,000, boxed
Washington RCW 39.10.300(1) authorizes design-build “including progressive design-build” for public works over $2,000,000. Source: Washington State Legislature, RCW 39.10.300, accessed 2026-11-21.
StateStatuteWho may use PDBKey limitsChecked against
WashingtonRCW 39.10.300, .270, .280, .330Public bodies that are certified (3 years, needs 1 design-build project in the prior 5) or get project approval; WSDOT is exempt from certificationOver $2,000,000 and specialized, innovative or time-saving; garages and pre-engineered metal buildings at any cost; RFQ without price; up to 5 finalistsStatute text, RCW 39.10.270 and RCW 39.10.280
MissouriRSMo 67.5060.15 and .16 (2026 H.B. 2474)All political subdivisions; water and wastewater projects named in .16Two-stage; 2 to 3 firms; no construction price in proposals; PDB subsection expires August 28, 2036Statute text (revisor.mo.gov)
MississippiMiss. Code 65-1-85(11), amended by 2024 S.B. 2645Mississippi Transportation Commission onlyDefines PDB as progressing “toward a final design, scope, schedule and contract price”Bill text as sent to the Governor
IllinoisProgressive Design-Build Pilot Program ActState construction agency pilot2026 S.B. 3645 moves the PDB sunset from January 1, 2027 to January 1, 2028DBIA 2026 legislative update; statute site did not load
South CarolinaS. 831, Act No. 177, signed May 18, 2026SCDOT, as “phased design-build”Paired with public-private partnership authorityDBIA 2026 legislative update

Washington’s text shows how authority is usually written: progressive design-build is a sub-type of the design-build procedure, so it inherits the design-build thresholds and award rules in RCW 39.10.330. An uncertified Washington body must show the project review committee that low-bid lump sum “is not practical” or that the alternative gives “a substantial fiscal benefit”, plus staff with construction experience and a written management plan (RCW 39.10.280(2)). Check your own state’s public contracting code before issuing an RFQ; a bill passing is not the same as authority for your agency type.

What does a real progressive design-build price look like?

Public agenda packets show the numbers that guides leave out. In Wilsonville, Oregon, a road, sewer and bridge program, the Phase 1 agreement was $4,804,723, or 16.7% of the $28,831,288 fiscal 2022-23 budget. The third GMP package arrived at $36,836,661.92 against a $26,082,917 budget, a $10,753,744.92 gap, and staff documented the off-ramp alternative for the board’s December 4, 2023 meeting.

LineAmountSource
Phase 1 agreement, not to exceed (design, permitting, right-of-way support), June 6, 2022$4,804,723.00URA Res. 324 staff report
Fiscal 2022-23 budget, five capital projects$28,831,288URA Res. 324 staff report
Phase 1 as share of that budget16.7%CB&C calculation
GMP 3 (sewer, street, roundabout, bridge, water relocation), December 4, 2023$36,836,661.92URA Res. 338 staff report
Fiscal 2023-24 amended budget for the same items$26,082,917URA Res. 338 staff report
GMP 3 over budget$10,753,744.92 (41.2%)CB&C calculation
Phase 1 fee as share of GMP 313.0%CB&C calculation
Wilsonville GMP 3 vs budget by projectBar chart: bridge GMP $23.46M vs $17.27M budget; street $6.53M vs $5.17M; roundabout $3.14M vs $2.63M; sewer $2.70M vs $1.01M010,000,00020,000,00030,000,000$17,272,69023,459,662Boeckman Dip Bridge5,166,3366,531,000Street improvements2,630,6963,142,000Roundabout1,013,1952,704,000Sanitary sewer01,000,000Water relocationFY 2023-24 amended budgetGMP 3 amount
Wilsonville’s GMP 3 totalled $36,836,661.92 against a $26,082,917 budget; the bridge line alone rose $6,186,972 (35.8%). Source: Wilsonville URA Resolution 338 staff report, December 4, 2023.

Wilsonville also shows how one Phase 1 agreement can feed several GMP packages, each approved by the board as a contract amendment before that work starts:

  • August 2, 2021: Resolution 2916 authorizes progressive design-build for the corridor.
  • March 30, 2022: 4 proposals received; the 2 highest-scoring teams interviewed.
  • June 6, 2022: Phase 1 agreement, not to exceed $4,804,723.
  • February 23, 2023: GMP 1, a traffic signal needed for later detours.
  • July 17, 2023: GMP 2, the Meridian Creek culvert replacement.
  • December 4, 2023: GMP 3, $36,836,661.92 for the bridge, road, roundabout and sewer, on the board’s agenda with substantial completion planned for summer 2025.
Wilsonville Boeckman Road progressive design-build timeline, 2021 to 2025 Wilsonville, Oregon: one Phase 1 agreement, three GMP packages Aug 2, 2021 PDB method authorized (Res. 2916) Mar 30, 2022 4 proposals received; 2 interviewed Jun 6, 2022 Phase 1 agreement $4,804,723 Feb 23, 2023 GMP 1: traffic signal for detours Jul 17, 2023 GMP 2: Meridian Creek culverts Dec 4, 2023 GMP 3: $36,836,661.92 bridge, road, sewer Summer 2025 GMP 3 work substantially complete (plan) Sources: Wilsonville URA Resolution 324 (June 6, 2022) and Resolution 338 (December 4, 2023) staff reports
Wilsonville priced its corridor in three GMP amendments after one $4,804,723 Phase 1 agreement. Source: Wilsonville URA Resolutions 324 (June 6, 2022) and 338 (December 4, 2023).

The staff report names the causes as added scope from soil conditions and regional inflation, citing a 20% rise in the ENR Seattle construction cost index since 2021. To test the price, the city used independent cost estimators on every pay item, got a second estimate on the GMP 3 schedule of values, and required competitive low-bid pricing for 41 trade and supplier categories (Res. 338 packet).

The off-ramp analysis listed three risks of cancelling and bidding GMP 3: no guarantee of a lower price, the city taking on the risk that the design documents were complete, and a construction delay of at least six months that would push the bridge past the opening of a new school. Staff recommended approving GMP 3. That is the off-ramp working as designed: a real choice priced in time and risk, not a free exit.

How can Phase 1 change before any price is set?

Phase 1 can absorb scope changes that would void a fixed-price award. Fresno, California awarded Phase One design of a 234-stall parking structure for $1,612,769 on June 12, 2025, under a modified DBIA progressive design-build agreement. When state grant money arrived, the council approved an amendment on August 28, 2025 adding $341,890 so the structure could grow to 600 or more stalls (Fresno legislation ID 25-1120).

Fresno parking structureOriginal Phase OneAfter Amendment 1
Stalls234600 or more
Phase One contract$1,612,769$1,954,659 (+21.2%)
Contingency$160,000 (derived: $195,000 minus $35,000)$195,000
Phase One cost per stall (CB&C calculation)$6,892$3,258 at 600 stalls

Both projects show the same pattern: the Phase 1 fee is a real cost, equal to 13.0% of GMP 3 and 16.7% of the fiscal 2022-23 budget in Wilsonville’s civil program, and the owner’s bargaining power at the GMP stage comes from independent estimates and its contingency plan, not from competing bids.

When should an owner choose progressive design build?

Choose progressive design build when the scope cannot yet be written tightly enough for competitors to price, when site or existing-building conditions are unknown, or when funding arrives in stages. Choose fixed-price design-build when a design criteria package can carry a firm price. In Washington, also confirm the project clears the $2,000,000 floor or is a garage or pre-engineered metal building.

IfThenBasis
Washington public project at or under $2,000,000 that is not a parking garage or pre-engineered metal buildingPDB is not available under RCW 39.10.300; use another methodRCW 39.10.300(1)-(2)
You can issue a design criteria package that firms can price as a firm, fixed costFixed-price design-build; price counts for at least 40% of points in Missouri’s modelRSMo 67.5060.13
You need a construction price before spending on designFixed-price design-build or design-bid-buildDBIA 544 §1.3 sets price only after Phase 1
Soils, utilities or an existing structure are unknownPDB, with the GMP set after investigationWilsonville GMP 3 soil-driven scope
Funding or program size may change during designPDB; amend Phase 1 rather than rebidFresno Amendment 1, 234 to 600+ stalls
No staff or owner’s representative can audit open-book estimatesHire that capacity before choosing PDBRCW 39.10.280(2)(c)
Criteria still uncertain after Phase 1Phase 2 as cost plus fee with a GMPDBIA 544 instructions
Criteria and design settled after Phase 1Phase 2 as a lump sumDBIA 544 instructions
Decision flowchart: progressive design build or fixed-price design-build Progressive design build or fixed-price design-build? 1. Washington public body, project at or under $2,000,000, not a garage or PEMB? PDB not authorized by RCW 39.10.300: use another method Yes No 2. Can you write a design criteria package firms can price as a firm, fixed cost? Fixed-price design-build (Missouri Phase III model) Yes No 3. Must you see a construction price before paying for any design? Fixed-price design-build or design-bid-build Yes No 4. Can your staff or an owner’s rep audit open-book estimates and GMP packages? Hire that capacity first (RCW 39.10.280(2)(c)) No Yes Progressive design build fits Unknown site or building conditions, scope still moving, or funding arriving in stages: select on qualifications, set the price at the Phase 1 proposal, keep the off-ramp
Four checks before choosing progressive design build, using RCW 39.10.300, RCW 39.10.280(2)(c), RSMo 67.5060.13 and DBIA 544 §1.3, accessed November 2026.

Owners comparing the Phase 2 payment forms can read our explainers on the cost-plus contract and the other types of construction contracts. If you are still deciding whether design-build fits at all, our page on hiring design-build contractors covers the broader choice.

What does DBIA publish on progressive design-build?

The Design-Build Institute of America (DBIA) publishes a standard-form agreement, a water-sector variant and best-practice guides for progressive design-build. Its March 3, 2026 primer, Progressive Design-Build Done Right, is free and covers procurement, contracting and execution. DBIA says PDB is roughly one-third of design-build procurements, citing FMI’s 2024 Design-Build Utilization Study (DBIA, March 2026).

DocumentEdition or dateWhat it coversAccess
DBIA 544, Standard Form of Progressive Design-Build Agreement2024, Second EditionTwo-phase agreement; Phase 2 price as lump sum or cost plus fee with optional GMP; off-ramp §1.3.2.3Paid, one-year license; free sample with instructions
DBIA 545, PDB Agreement for Water and Wastewater ProjectsCurrent store listingWater and wastewater variantPaid
Progressive Design-Build Done Right primerMarch 3, 2026Owner readiness, qualifications-focused procurement, phased contracting, transparent cost validationFree download
Deeper Dive: Progressive Design-BuildStore listingThe PDB process and its key phasesDBIA bookstore
PDB: Recommendations for Owners and PDB TeamsStore listingACEC Research Institute, Charles Pankow Foundation and DBIA study of practice and outcomesDBIA bookstore

DBIA 544 also offers an alternate in which the design-builder guarantees only its general conditions line inside the GMP (§6.1). If you are drafting the Phase 1 scope, our preconstruction services guide lists deliverables that fit Exhibit B, and our performance bond guide explains the Phase 2 bond.

For the contract forms behind each phase, see our design-build contract guide and how CMAR compares with design-build.

How we compiled this

We read 10 primary documents in November 2026: Washington RCW 39.10.270, .280, .300 and .330; Missouri RSMo 67.5060 as effective August 28, 2026; Mississippi 2024 S.B. 2645; Arizona ARS 28-7361; the DBIA 544 (2024) sample and instructions; and Wilsonville and Fresno council records. Illinois and South Carolina come from DBIA’s 2026 summary because the Illinois statute site did not load. We left out California, whose code site blocked access, and Arizona’s 2023 PDB bill, which is not in current ARS 28-7361. CB&C calculations are labelled.

Frequently asked questions

What is the difference between design-build and progressive design build?

In fixed-price design-build, competing teams submit a conceptual design and a firm price, and price weighs in the award; Missouri’s model gives cost at least 40% of points (RSMo 67.5060.13). In progressive design build, the owner selects on qualifications and a preconstruction fee, pays for Phase 1 design, and negotiates the construction price with that one firm afterward.

What is an off-ramp in progressive design build?

It is the owner’s right to stop after Phase 1 if it will not accept the Phase 2 price. Under DBIA 544 §1.3.2.3 the owner can suggest changes, continue on cost reimbursement, or terminate for convenience. If it reuses the design with another firm, §4.3.2 requires an extra work-product payment that the parties should fix before signing.

How is the design-builder paid in Phase 1?

Phase 1 is a separate paid scope, usually a negotiated fee or rates for design and preconstruction services. Wilsonville, Oregon set a $4,804,723 not-to-exceed amount in 2022, and Fresno, California awarded $1,612,769 for a parking structure in 2025. Missouri lets owners consider only preconstruction pricing at selection (RSMo 67.5060.15(8)(d)).

At what percent of design is the GMP set in progressive design build?

No statute or standard form fixes a single percent. DBIA 544 §1.2.1 leaves it to Exhibit B, expressed as a percent of design completion or a list of deliverables, and DBIA’s instructions warn that setting the GMP too early leaves too little scope definition while setting it too late delays the owner’s price decision.

Can private owners use progressive design build?

Yes. Private owners need no statute; they adopt the two-phase structure by contract, commonly DBIA 544 (2024) with its Exhibit B Phase 1 scope. Statutes such as Washington RCW 39.10.300 and Missouri RSMo 67.5060.15 matter only to public bodies that would otherwise have to award construction to the lowest responsive bidder.

Is progressive design build faster than design-bid-build?

It can start construction earlier because design and pricing overlap and early GMP packages can buy long-lead materials; Wilsonville’s first of three GMPs, approved February 23, 2023, built a traffic signal needed for detours before the bridge package was priced. No statute guarantees a time saving, and Washington requires owners to justify one under RCW 39.10.300(1)(c) or another listed reason.

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.