Preconstruction services are the estimating, constructability review, scheduling, long-lead buying and site logistics work a builder does during design. Public records put the fee at about 0.4% to 1% of construction cost (2015 to 2026).
Key takeaways
- The Texas State University System CM-at-Risk contract requires cost estimates at 5 design checkpoints: schematic design, design development and 50%, 75% and 100% construction documents (TXST contract §5.4.2).
- AIA A133-2019 §5.1.1 offers 3 ways to pay for the preconstruction phase: a stipulated sum, a multiple of direct personnel expense, or actual cost with an optional maximum (AIA Contract Documents).
- Public agencies in Arizona only: owners may not consider fees, price or man-hours at any point when selecting a construction manager at risk, then may sign a separate preconstruction contract (ARS 34-603(C)(1)).
- Des Moines, Iowa capped preconstruction services at $71,120 in April 2024 on a city office renovation whose final GMP was $17,889,445.75 in January 2025, about 0.40% (Des Moines Council Communication 25-006).
- Friendswood ISD in Texas approved a $12,000 pre-construction fee on an estimated $3 million budget in February 2026, or 0.4% (Community Impact, Feb. 24, 2026).
| Key number | What it governs | Source |
|---|---|---|
| 5 estimate checkpoints | SD, DD, 50% CD, 75% CD, 100% CD | TXST §5.4.2 |
| 5% of construction cost | Targeted savings from the constructability program | TXST Exhibit G |
| 10/20/20/10/20/20% | Share of the preconstruction fee paid per stage | TXST §12.1.1 |
| 0.4% to 1% | Preconstruction fee as a share of construction cost in 3 public records, 2015 to 2026 | Des Moines; Friendswood ISD; Mt. SAC §2.1.1 |
| 90% complete | Washington public GC/CM projects negotiate the maximum allowable construction cost once documents reach this point | RCW 39.10.370(1) |
| $7.5 million | Per-project cap on Florida public continuing CM contracts, CPI-adjusted each July 1 from 2025 | Fla. Stat. 255.103(4) |
What do preconstruction services include?
Preconstruction services cover eight jobs: cost estimating at each design milestone, constructability review, scheduling, value engineering input, long-lead procurement, site logistics, permitting support and a bid package plan. The Texas State University System CM-at-Risk contract lists all eight in Article 5, and on federal projects the General Services Administration names scheduling, cost estimating, constructability reviews, cost reconciliation and market analysis in GSAM 536.7105-1(b).
| Service | What the builder produces | Clause that names it | Source |
|---|---|---|---|
| Cost estimating | Estimated Construction Cost report at each checkpoint, reconciled with the owner’s estimator | TXST §5.4.2 to §5.4.3 | TXST |
| Constructability review | Constructability Report updated at least monthly | TXST §5.2.2, Exhibit G | TXST |
| Scheduling | Critical Path Method schedule covering design, construction and owner-managed work | TXST §5.3.2; GSAM 536.7105-1(b) | GSAM |
| Value engineering input | Cost alternatives; engineering-practice items referred to the licensed designer | TXST §5.2.1; RCW 39.10.360(6) | RCW |
| Long-lead procurement | List of items with extended delivery times and advice on buying them early | TXST §5.6.1 | TXST |
| Site logistics | Recommendations on site use, temporary facilities, deliveries, traffic, parking and storage | TXST §5.1.6 | TXST |
| Permitting support | Help obtaining code and regulatory approvals | TXST §5.6.5 | TXST |
| Bid package strategy | Trade package plan, with self-performed packages identified | TXST §5.6.4; Tex. Gov’t Code 2269.255 | Texas statute |
What is a constructability review?
A constructability review is the builder reading the drawings for work that will be hard, slow or costly to build, then proposing alternatives before the design is final. In the TXST contract the Constructability Report is updated at least monthly, and Exhibit G targets savings of 5% of construction costs using 17 Construction Industry Institute (CII) constructability concepts.
Exhibit G schedules reviews at schematic design, design development and at 30%, 50% and 95% construction documents. The report must also flag drawing discrepancies likely to cause change orders or claims once construction starts (TXST §5.2.2).
Is value engineering part of preconstruction?
Usually yes, but the term changes meaning by contract. Washington’s GC/CM statute, RCW 39.10.360(6), lists value engineering among design-phase services, while on federal GSA work the GSA final rule (84 FR 69648) says value engineering as defined in FAR Part 48 does not apply to construction manager as constructor (CMc) contracts. TXST §5.2.1 sends any suggestion that involves professional engineering to the licensed designer.
How are long-lead items and site logistics handled?
The builder lists equipment and materials with long delivery times, advises on buying them early and plans how the site will take deliveries, storage, parking and traffic (TXST §5.1.6 and §5.6.1). Under ConsensusDocs 500, the construction manager can issue subcontracts for fully designed portions before the whole design is done, which is how an early long-lead package gets ordered.
Metals are the current pressure point. Since April 6, 2026, Section 232 duties of 50% apply to steel, aluminum and most copper articles on their full customs value under Proclamation 11021, and the BLS producer price index for steel mill products rose 45.7% from January 2025 to August 2026. Our construction material tariffs tracker follows each action.
What permitting support is included?
Builders support permits during design; they rarely own the design submittal. TXST §5.6.5 has the construction manager help obtain code and regulatory reviews from the Texas Higher Education Coordinating Board, the Texas Department of Licensing and Regulation, the State Fire Marshal and the local fire department, while §8.8 makes pulling building permits a construction-phase duty.
What should you receive at SD, DD and CD?
Expect an estimate at the end of each design phase that gets more detailed as drawings develop, plus a constructability review, an updated schedule and, by design development, a long-lead list. TXST §5.4.2 requires the design development and construction document estimates to come from quantity takeoffs priced by unit, in Construction Specifications Institute (CSI) division format, with escalation shown, and lump sum estimates are rejected where quantities can be measured.
| Stage | Builder deliverables | Estimate | Fee share paid (TXST §12.1.1) |
|---|---|---|---|
| Program verification | Check program, schedule and cost limit against each other (§5.1.2); site visit (§5.1.4) | Check against the Construction Cost Limitation | 10% |
| Schematic design (SD) | Estimate at end of SD; constructability comments; CPM schedule | Estimated Construction Cost report | 20% |
| Design development (DD) | Estimate from quantities, CSI format; long-lead list; constructability review | Detailed, unit-priced | 20% |
| GMP development | GMP proposal with assumptions and exclusions | Guaranteed maximum price | 10% |
| Construction documents (CD) | Estimates at 50%, 75% and 100% CD; bid package strategy; code compliance review (§5.5.5) | Detailed, unit-priced | 20% |
| Subcontractor bids | Advertise and take trade bids; buyout pricing | Bid-based | 20% |
When the GMP lands varies by owner. The TXST payment schedule places GMP development before construction documents; the University of Central Florida UCF-613 notice sets the GMP at 100% construction documents with possible early release packages; Washington negotiates its maximum allowable construction cost at 90% or more. Our commercial construction process guide shows where these stages sit against permits and closeout.
Which contracts cover preconstruction?
Most private projects use AIA A133-2019 or ConsensusDocs 500, both of which split the work into a preconstruction phase and a construction phase priced later by GMP. Owners who want to keep the option of changing builders after design sign a standalone preconstruction agreement, such as the Vanderbilt University GMP Preconstruction Form Agreement of August 2, 2024. Federal GSA projects use their own rule, GSAM 536.71.
| Document | How it handles preconstruction | Price basis | Source |
|---|---|---|---|
| AIA A133-2019 | Construction manager acts as owner’s adviser in the preconstruction phase; phases may overlap; GMP Amendment (Exhibit A) usually signed before precon ends | §5.1.1: stipulated sum, multiple of direct personnel expense, or actual cost with optional maximum | AIA |
| AIA A201-2017 | General conditions paired with A133; Article 9 payment and Article 11 insurance apply | None for precon | AIA |
| ConsensusDocs 500 | GMP with Preconstruction Services Option: scheduling, budget and design input; early subcontracts for fully designed portions; GMP set by the 500.1 amendment | Cost of the work plus fee, capped by GMP | ConsensusDocs |
| ConsensusDocs 510 | Construction manager at risk with an option to buy preconstruction services; no GMP is determined | Cost of the work plus fee | ConsensusDocs |
| Owner-written precon agreement (Vanderbilt, 2024) | Separate Preconstruction Fee; precon costs not includable in the Cost of the Work; termination pays in proportion to services done | Fixed fee, progress payments | Vanderbilt |
| GSA CMc (GSAM 536.71), federal only | Design phase services, then construction as a GMP option | Firm fixed price for design phase services | Acquisition.gov |
A133 also carries terms owners tend to skip: §1.1.13 for the staffing plan during preconstruction, §12.1.2 sending preconstruction claims straight to mediation without an Initial Decision Maker, and §14.3.1 for insurance limits during the preconstruction phase. The construction management at risk guide covers what happens once the GMP is signed. This is general information, not legal advice.
In design-build, preconstruction sits inside one contract, AIA A141-2024 being the current AIA form, so the owner buys design and price development from the same firm. Our design-build contractors guide compares the lump-sum and progressive versions.
How do public owners buy preconstruction services?
Private owners can choose and pay a builder any way they like, so this section matters only to public agencies. Public owners need a statute, and the statutes differ on when price can enter selection. Arizona bans any fee or cost information in selection (ARS 34-603), Texas allows fees in a one-step process or in step two of a two-step process (Gov’t Code 2269.253), Washington takes sealed percent-fee bids from finalists (RCW 39.10.360(4)), and the GSA evaluates a firm fixed price for design phase services alongside the GMP options.
| Jurisdiction | Statute | Preconstruction rule | Price in selection | Source |
|---|---|---|---|---|
| Federal (GSA) | GSAM 536.71, effective Jan. 21, 2020 | Design phase services at a firm fixed price; GMP option not exercised until the final estimated cost of work is set | Yes: total evaluated price includes both | GSAM |
| Florida | Fla. Stat. 255.103(2) | Construction management entity handles scheduling and coordination in preconstruction and construction; may be required to offer a GMP or lump sum with a guaranteed completion date | Qualifications under s. 287.055, then negotiation | Florida Senate |
| Texas | Gov’t Code 2269.251 to 2269.258 | Construction manager-at-risk consults during design; owner’s architect may not serve as CMAR (2269.252(b)) | One-step: fees and general conditions allowed; two-step: none in step one, then up to 5 offerors | Texas Legislature |
| Arizona | ARS 34-101(23), 34-603 | Preconstruction services are services during the design phase; separate precon contract allowed | No: fees, price and man-hours barred at every step | Arizona Legislature |
| Washington | RCW 39.10.360, 39.10.370 | Solicitation must state the form of any preconstruction contract; MACC negotiated at 90% or more | Finalists submit sealed bids for percent fee on MACC | Washington Legislature |

Two procedural details change budgets. Under Tex. Gov’t Code 2269.258, if no GMP exists at award, the performance and payment bonds must each equal the construction budget, and they are due within 10 days of signing unless a bid bond covers the gap. Our construction surety bonds report explains how those bonds are priced.

How are preconstruction services priced?
Public contracts use five structures: a lump sum (TXST Article 6.1, Vanderbilt), a multiple of personnel cost or actual cost with a cap (AIA A133 §5.1.1), a hybrid of fixed fee plus capped hourly staff and capped expenses (Kent State Article 2), a firm-fixed-price federal line item, and Washington’s percent fee bid. Where public records state the dollar amount, the fee runs about 0.4% to 1% of construction cost, as the table below shows.
| Model | How it works | Where it appears | Owner check | Source |
|---|---|---|---|---|
| Lump sum (stipulated sum) | One fixed fee for all precon, no increase unless scope changes materially (TXST §6.2, §6.4) | AIA A133 §5.1.1; TXST Art. 6; Vanderbilt form | Count the estimates and meetings the fee covers | TXST |
| Multiple of direct personnel expense | Staff cost times an agreed multiple, plus reimbursables | AIA A133 §5.1.1 | Ask for the staffing plan (§1.1.13) and the rate adjustment month (§5.1.3) | AIA |
| Actual cost with a maximum | Actual costs; a maximum cost may be set | AIA A133 §5.1.1 | Write the cap in dollars | AIA |
| Hybrid | Fixed fee for overhead and profit allocated by stage, hourly personnel costs to a cap, reimbursables to a cap with no mark-up | Kent State CMR Art. 2, §9.1.4.1 | Track 3 caps separately | Kent State |
| Firm fixed price line item | Separate line item on SF 1442, evaluated with the GMP options | GSAM 536.7103, 536.7104 | Price is fixed at award | GSAM |
| Percent fee bid | Finalists bid a percent fee on the MACC; fee renegotiated if the MACC moves more than 15% | RCW 39.10.360(4), 39.10.370(6) | Precon contract form disclosed in the solicitation | RCW |
Is the preconstruction fee credited against the construction fee? Not in the 4 public owner documents we read. Vanderbilt’s 2024 form states that preconstruction costs are not includable in the Cost of the Work, and TXST and Kent State pay a separate preconstruction fee before any GMP. A credit is a negotiated term: write the amount and its trigger, such as signing the GMP Amendment, into the agreement.
Real fee figures are scarce, and no private owner publishes one. The 3 public records we could verify are below, each with its date and what the base includes; treat them as negotiating benchmarks, not market rates.
| Owner and project | Date | Preconstruction fee | Project size stated | Fee as share | Source |
|---|---|---|---|---|---|
| City of Des Moines, Iowa: city administration building renovation (CM at risk) | Approved April 15, 2024 | Not to exceed $71,120 | Final GMP $17,889,445.75 (January 13, 2025) | 0.40% of GMP | Council Communication 25-006 |
| Friendswood ISD, Texas: foundation projects at a high school and administration building (CM at risk) | Approved February 23, 2026 | $12,000 | Estimated construction budget $3,000,000, including all construction management fees | 0.4% of budget | Community Impact, Feb. 24, 2026 (news report) |
| Mt. San Antonio Community College District, California: master agreement (agency CM) | September 10, 2015 | 1% of anticipated construction cost up to $1,000,000; 0.75% above | Set per project | 0.75% to 1% | Mt. SAC agreement §2.1.1 |
The worked example applies that range to a private job: an $8,000,000 building, priced at the 0.40% Des Moines ratio and at Mt. SAC’s 0.75%, with the fee released on the TXST §12.1.1 schedule. It is CB&C arithmetic, not a quote.
| Line | Share | At 0.40% ($32,000) | At 0.75% ($60,000) | Basis |
|---|---|---|---|---|
| Program verification | 10% | $3,200 | $6,000 | TXST §12.1.1 |
| Schematic design | 20% | $6,400 | $12,000 | TXST §12.1.1 |
| Design development | 20% | $6,400 | $12,000 | TXST §12.1.1 |
| GMP development | 10% | $3,200 | $6,000 | TXST §12.1.1 |
| Construction documents | 20% | $6,400 | $12,000 | TXST §12.1.1 |
| Subcontractor bids | 20% | $6,400 | $12,000 | TXST §12.1.1 |
| Total | 100% | $32,000 | $60,000 | $8,000,000 x 0.40% or 0.75% |
Scope drives the number more than the budget does. The UCF-613 notice, for a 58,000 gross square foot building with a construction cost of about $46,000,000, states that cost estimating at major drawing milestones is included in the preconstruction fee. Our cost per square foot guide helps set the budget the first estimate is tested against.
Should you pay for preconstruction services?
Pay for them when you need a price, a schedule or long-lead orders before the drawings are finished, or when the job is hard to build in place. Skip or limit them when drawings are complete and the scope is simple, because a hard bid gives clean price competition. Public agencies, not private owners, must also follow their statute’s rules on when fees can be considered, such as ARS 34-603 or Tex. Gov’t Code 2269.253.
| If | Then | Why |
|---|---|---|
| Drawings are complete and the scope is simple | Hard bid; precon optional (design-bid-build) | Price competition on finished documents |
| You need a price or long-lead orders before construction documents are finished | Pay for full precon with a CM or GC (A133, ConsensusDocs 500) | ConsensusDocs 500 allows subcontracts for fully designed portions before the whole design is done |
| Build risk is high: occupied renovation, phased site or tight site logistics | Scoped precon agreement: reviews at SD, DD and CD | TXST Exhibit G schedules constructability reviews at SD, DD, 30%, 50% and 95% CD |
| None of the above applies | Limited precon: one estimate at SD and a constructability review at DD | Keeps an early cost check for a fraction of a full fee; full precon ran 0.4% to 1% of cost in the records above |
| Steel, aluminum or copper items are on the critical path | Ask for the long-lead list at DD at the latest | 50% Section 232 duties since April 6, 2026 |
| Public owners only: you are an Arizona public agent | Select on qualifications only, then negotiate the precon fee | ARS 34-603(C)(1)(a) |
| Public owners only: you are a Florida local agency with a continuing CM contract | Order precon under it if each project is at or below $7.5 million, CPI-adjusted | Fla. Stat. 255.103(4) |
| You may want to change builders after design | Sign a standalone precon agreement with termination paid in proportion | Vanderbilt form; ARS 34-603(C)(1)(c)(i) |
The design-bid-build branch trades early builder input for a single bid on 100% construction documents. Our design-build vs design-bid-build comparison sets out what each delivery method gives up.
What should a preconstruction agreement say?
A preconstruction agreement should fix the deliverables by milestone, the fee structure and caps, the payment schedule, the named staff, what happens if you do not proceed to a GMP, and whether any fee is credited later. The eight items below come from clauses in A133-2019, the TXST, Kent State and Vanderbilt documents, so each has a model to copy.
- Deliverables by milestone: number and timing of estimates, for example SD, DD and 50%, 75% and 100% CD, each reconciled with your estimator (TXST §5.4.2 to §5.4.3).
- Fee structure: which A133 §5.1.1 method applies, with dollar caps on hourly staff and reimbursables (Kent State §2.3 to §2.4).
- Payment schedule: fee share per stage, such as 10%, 20%, 20%, 10%, 20% and 20% (TXST §12.1.1).
- Staffing plan: named estimator, scheduler and preconstruction manager (A133 §1.1.13).
- Exit terms: right to stop after design with the fee paid in proportion to services completed (Vanderbilt termination clause); the owner may accept, reject or negotiate the GMP proposal under A133.
- Early packages: written approval and a dollar limit for each long-lead or early release purchase.
- Credit: whether any precon fee is credited against the construction fee, and when.
- Insurance and disputes: precon-phase policy limits (A133 §14.3.1) and the claims path (A133 §12.1.2).
Bring these 8 items to the interview with each firm and compare answers line by line, the same way our guide to comparing construction bids lines up general conditions and fees. Have a construction attorney review the final form.
The architect’s side of the same checkpoints, from AIA B101 deliverables to permit and bid sets, is set out in our guide to construction documents by design phase.
Each milestone estimate maps to an AACE class with its own accuracy range, set out in our guide to estimating construction costs by design stage.
Match the builder’s estimate checkpoints to the drawings the MEP engineer delivers at each design phase.
How we compiled this
In October 2026 we read 20 primary documents: the AIA A133-2019 instructions, 3 ConsensusDocs pages, the GSA final rule and GSAM Subpart 536.71, 6 statute sections from Florida, Texas, Arizona and Washington, 4 public owner contract documents (Texas State University System, Kent State, Vanderbilt, University of Central Florida), 2 public fee records (City of Des Moines council papers, the Mt. San Antonio Community College District agreement), and BLS and Federal Register tariff data from our own research. One fee figure comes from a news report and is labeled as such. We excluded school board fee figures we could only see in search snippets, and we give the fee only as the 0.4% to 1% range found in those dated public records, because no private-sector source publishes one. On October 26, 2026 we re-read the TXST contract, the Friendswood report and the Des Moines papers at source.
Frequently asked questions
What is the difference between preconstruction and construction management?
Preconstruction is a phase; construction management is a role. Under AIA A133-2019 the construction manager acts as the owner’s adviser during the preconstruction phase, then becomes the builder once a guaranteed maximum price is accepted. A general contractor on a negotiated job, or a design-builder, can provide the same preconstruction services without the construction manager title.
Is the preconstruction fee credited against the construction fee?
Only if the contract says so. In the Texas State University System, Kent State and Vanderbilt documents we read, the preconstruction fee is separate, and Vanderbilt keeps preconstruction costs out of the Cost of the Work. The fee itself is modest: about 0.4% of cost in Des Moines (2024) and Friendswood ISD (2026). If you want a credit, write the dollar amount and the trigger, such as signing the GMP Amendment, into the agreement.
What happens if the owner and builder cannot agree on a GMP?
Under AIA A133-2019, the usual private form, the owner may accept, reject or negotiate the GMP proposal. If talks fail, the exit runs through the termination terms, so check before signing what they pay for preconstruction work done; Vanderbilt’s 2024 form pays the fee in proportion to services completed. Public statutes add a fallback: Texas Government Code 2269.254 has owners end talks in writing and move to the next ranked offeror.
Can the architect provide preconstruction services instead of the builder?
The architect can produce cost estimates, but on Texas public construction manager-at-risk projects the owner’s architect or engineer, or a related entity, may not serve as the construction manager-at-risk under Government Code 2269.252(b). The value of builder preconstruction comes from subcontractor pricing, sequencing and logistics knowledge that a designer’s estimate usually lacks.
How long do preconstruction services last?
Preconstruction runs from the builder’s selection through the GMP and trade buyout, so its length follows the design schedule. AIA A133-2019 lets the preconstruction and construction phases overlap on fast-tracked jobs. For Arizona multi-location projects, ARS 34-603 requires the agent to intend to start construction at each location within 30 months of signing the first preconstruction or other construction services contract.
Do preconstruction estimates guarantee the price?
No. Estimates become a price only when a GMP or lump sum is signed. Texas Government Code 2269.258 reflects this: when no GMP exists at award, the performance and payment bonds must each equal the construction budget. TXST section 5.4.4 requires the builder to warn the owner as soon as an estimate is likely to exceed the cost limit.
Sources
- Instructions: A133-2019, Owner and Construction Manager as Constructor, Cost of the Work Plus a Fee with a GMP, AIA Contract Documents. Accessed October 19, 2026.
- Owner and Construction Manager Agreement (GMP with Preconstruction Services Option), 500, ConsensusDocs. Accessed October 19, 2026.
- Owner and Construction Manager Agreement (Cost of Work with Preconstruction Services Option), 510, ConsensusDocs. Accessed October 19, 2026.
- CM At-Risk: How to Make the Most of This Project Delivery Method Contractually (Sept. 11, 2025), ConsensusDocs. Accessed October 19, 2026.
- GSAR: Construction Manager as Constructor final rule, 84 FR 69648, General Services Administration, Federal Register. Accessed October 19, 2026.
- GSAM Subpart 536.71, Construction Manager as Constructor, Acquisition.gov. Accessed October 19, 2026.
- Florida Statutes 255.103, Construction management or program management entities, The Florida Senate. Accessed October 19, 2026.
- Texas Government Code Chapter 2269, Subchapter F, Construction Manager-at-Risk, Texas Legislature. Accessed October 19, 2026.
- Arizona Revised Statutes 34-101, Definitions, Arizona State Legislature. Accessed October 19, 2026.
- Arizona Revised Statutes 34-603, Procurement of construction-manager-at-risk services, Arizona State Legislature. Accessed October 19, 2026.
- RCW 39.10.360, GC/CM contract award process, Washington State Legislature. Accessed October 19, 2026.
- RCW 39.10.370, GC/CM subcontract bidding and MACC, Washington State Legislature. Accessed October 19, 2026.
- Contract Between Owner and CM-at-Risk (draft dated 05/27/15), Texas State University System. Accessed October 19, 2026.
- University Construction Manager at Risk Agreement Form, Kent State University, Office of the University Architect. Accessed October 19, 2026.
- GMP Preconstruction Form Agreement (2024-08-02), Vanderbilt University. Accessed October 19, 2026.
- Notice to Construction Managers, UCF-613 Discovery and Innovation Hub, University of Central Florida Facilities Planning. Accessed October 19, 2026.
- Council Communication 25-006, GMP Amendment No. 2, City Facility Expansion Phase 1 (January 13, 2025), City of Des Moines. Accessed October 26, 2026.
- Master Agreement for Construction Management Services (September 10, 2015), Mt. San Antonio Community College District. Accessed October 26, 2026.
- Friendswood ISD moves forward with foundation projects at Friendswood HS, administration building (Feb. 24, 2026), Community Impact. Accessed October 19, 2026.
- Producer Price Index commodity data (WPU1017 steel mill products), U.S. Bureau of Labor Statistics. Accessed October 19, 2026.
- Proclamation 11021, Strengthening Actions Taken To Adjust Imports of Aluminum, Steel, and Copper, Federal Register. Accessed October 19, 2026.