Construction Management at Risk: How CMAR and the GMP Work
Commercial construction service

Construction Management at Risk: How CMAR and the GMP Work

Construction management at risk (CMAR) is a delivery method where you hire an architect and, separately, a construction manager who gives cost and schedule advice during design, then commits to a guaranteed maximum price (GMP) and builds the project. Costs above the GMP, apart from owner changes, fall on the construction manager.

Free Commercial Project Match

Tell us what you are building. We match you with licensed builders who fit it.

Step 1 of 3: Your project

Free for project ownersNo obligationAbout 60 seconds

  • Early builder inputEstimates and constructability reviews at each design stage.
  • A price ceilingThe GMP caps the cost of the work, fee and contingency.
  • Your own architectDesign stays under a separate contract with you.

What construction management at risk means

In construction management at risk the construction manager plays two roles in sequence. During design it works as your adviser, pricing the drawings as they develop, checking constructability and planning the schedule. Once design is far enough along it proposes a guaranteed maximum price, and when you accept it the manager becomes the builder, holding the trade subcontracts and carrying the risk of overruns within the agreed scope. The General Services Administration, which calls the method construction manager as constructor, describes it as engaging the contractor during design and setting a ceiling on the construction price before construction documents are prepared.

CM at risk vs CM agency: A CM agent advises the owner for a fee but holds no trade contracts and guarantees no price; the owner contracts with the trades or a general contractor. A CM at risk holds the contracts and commits to the GMP.

CMAR is one of the delivery options on our commercial construction services hub, alongside design-build and traditional design-bid-build.

Our guide to construction management companies compares agency, at-risk and general contractor firms and shows the fees public owners write into each contract.

The construction management at risk process, step by step

  1. Selection

    Owners usually select on qualifications, preconstruction approach, team, fee percentage and general conditions, not on a full construction price.

  2. Preconstruction services

    Estimates at schematic design, design development and construction documents; constructability reviews; schedule; value analysis.

  3. Early release packages

    Site work, foundations, steel or long-lead equipment can be bought before the full GMP when the schedule needs it.

  4. GMP proposal

    The manager prices the cost of the work, contingency, general conditions and fee, with written assumptions and clarifications.

  5. GMP amendment

    Accepting the proposal makes the manager contractually bound to build at or below the GMP.

  6. Subcontractor buyout

    Trade packages are bid to subcontractors; public owners often require open, documented procurement.

  7. Construction and reconciliation

    Monthly cost reporting, contingency tracking, and a final reconciliation of actual cost against the GMP.

Our commercial construction process guide shows how these steps line up with design phases and permits.

Cost estimate binders and drawing sets on a preconstruction review table
Illustrative photograph (generated image).

How a guaranteed maximum price is built

A GMP is not a lump sum. You pay the actual cost of the work plus the agreed fee, up to the ceiling. If the project comes in under, the savings go back to you or are shared as the contract says; the AIA form leaves room for specific savings-sharing terms. If it comes in over for reasons inside the manager's scope, the manager absorbs it. The GMP is only as good as the documents and assumptions it was based on, so read the qualifications list as carefully as the number.

What typically sits inside and outside a GMP
ComponentInside the GMP?What to check
Cost of the work (subcontracts, materials, self-performed labor)YesHow each trade package was bid and awarded
Construction manager's contingencyYesWhat it may be used for and whether unused amounts return to you
General conditions (site staff, trailer, temporary utilities)YesLump sum, capped or reimbursed at cost
FeeYesPercentage of cost or fixed amount; how it applies to change orders
Insurance and bondsUsuallyWhich policies and rates; Exhibit B requirements
AllowancesYesWhether each allowance is realistic for the unfinished design
Owner contingency and owner changesNoHeld by you for scope changes and unknowns
Design fees, permits and impact fees, furnitureUsually noWho pays and when

Typical arrangement under cost-plus-fee GMP agreements such as AIA A133-2019; contract terms decide.

Source: [1]

The same cost-plus-fee mechanics apply outside CMAR, and our guide to the cost-plus contract works through fixed, percentage and GMP fees side by side.

The owner's job during preconstruction

CMAR works best when the owner treats preconstruction as active work rather than a waiting period. At each design milestone you will receive an estimate from the manager and, often, a list of options to bring cost back to budget. Decisions made quickly keep the architect and manager aligned; decisions deferred tend to resurface as assumptions in the GMP. Set a budget with a clear owner contingency before design starts, and agree how estimate variances will be reconciled between the architect's cost consultant, if you have one, and the manager.

  • Decision logRecord every scope and quality decision with its cost effect and date.
  • Estimate reconciliationCompare the manager's estimate with any independent estimate line by line at each milestone.
  • Early package approvalsApprove early releases only when the design behind them is stable.
  • Subcontractor bid reviewAttend bid openings or review bid tabulations before the GMP is final.

Our guide to preconstruction services lists the estimates, reviews and fee terms to expect at each design stage.

The AIA A133 agreement and related documents

The most widely used private form is AIA Document A133-2019, the agreement between owner and construction manager as constructor where payment is the cost of the work plus a fee with a guaranteed maximum price. It splits services into a preconstruction phase and a construction phase, which may overlap on fast-tracked jobs. The GMP is set by an amendment, Exhibit A, and Exhibit B sets insurance and bond requirements. A133 is coordinated with the A201-2017 general conditions and the B133-2019 owner and architect agreement written for CMAR projects. Section 6.1.7 lets the parties add terms for the manager to share savings when the final cost is below the GMP.

Standard forms are routinely edited. Have a construction attorney review the agreement, particularly the definition of the cost of the work, contingency use and the treatment of savings. This is general information, not legal advice.

Because A133-2019 adopts the general conditions, its claim deadlines and insurance framework come from AIA A201-2017 and its 15 articles.

How A133-2019 pairs with A201-2017, B133-2019 and the GMP pay forms is shown in our AIA contract documents navigator.

Why the GMP matters when input costs outrun prices

A GMP moves price risk from you to the manager for the scope it covers, and that risk has been real. Federal producer price data shows what nonresidential contractors pay for materials, energy and services rising 8.9% in the year to August 2026, while the prices they charge for new nonresidential buildings rose 5.3%. Since January 2020 the gap is 52.8% against 46.3%. Managers price this risk into contingency and escalation allowances, which is one reason GMPs set very early carry larger contingencies.

What contractors pay vs what they charge

Producer prices and hourly earnings, January 2020 = 100

What contractors pay vs what they chargeLine chart rebased to January 2020 equals 100: by August 2026 inputs to new nonresidential construction reached 152.8, output prices for new nonresidential buildings 146.3, and hourly earnings in nonresidential building construction 132.3.80.0100120140160index, Jan 2020 = 100Jan 2020Jan 2021Jan 2022Jan 2023Jan 2024Jan 2025Aug 2026Inputs to new nonresidential constructionOutput: new nonresidential buildingsHourly earnings, nonres. building construction

Source: U.S. Bureau of Labor Statistics, Producer Price Indexes and Current Employment Statistics; CB&C rebasing

The squeeze differs by building type. Warehouses saw the smallest output price gain in the twelve months to August 2026, 4.3%, against the same 8.9% rise in inputs. Our commercial construction price index tracks the gap monthly, and the cost per square foot guide explains how to set an early budget before the manager's first estimate.

Output prices vs input costs by building type

12-month change to August 2026

Output prices vs input costs by building typeGrouped bar chart of twelve-month price changes to August 2026: output prices rose 5.8% for industrial buildings, 4.3% for warehouses, 5.2% for schools, 5.9% for offices and 5.0% for health care buildings, against an 8.9% rise in inputs to nonresidential construction.0246810.0%5.88.9Industrialbuildings4.38.9Warehouses5.28.9Schools5.98.9Office buildings58.9Health carebuildings5.38.9All newnonresidential…Output price (what contractors charge)Inputs to nonresidential construction

Source: U.S. Bureau of Labor Statistics, Producer Price Indexes (August 2026, preliminary)

CMAR on public projects: Florida's statute as an example

Public owners need statutory authority to use CMAR, and state laws set the rules. Florida's is section 255.103 of the Florida Statutes. Agencies select construction management entities through the qualifications-based process in section 287.055, the Consultants' Competitive Negotiation Act. The entity may be required to offer a guaranteed maximum price and a guaranteed completion date, or a lump-sum price, and when it does it must secure a surety bond under section 255.05 and hold the construction subcontracts. Agencies may also award continuing contracts for projects whose estimated construction cost does not exceed $7.5 million each; the statute directs the Department of Management Services to adjust that cap every July 1 starting in 2025, so confirm the current figure.

At the federal level, the General Services Administration adopted construction manager as constructor in a rule effective January 21, 2020, now codified at GSAR Subpart 536.71. Federal construction spending by state and buyer is in our federal construction contracts by state report.

School building addition under construction next to an existing campus
Illustrative photograph (generated image).

Construction management at risk vs design-build vs design-bid-build

Three delivery methods compared
QuestionCM at riskDesign-buildDesign-bid-build
Owner's contractsArchitect plus construction managerOne design-builderArchitect, then general contractor
Builder selected onMostly qualifications, fee and general conditionsQualifications, proposal, or bothLowest responsive bid, typically
Builder joinsDuring designAt the startAfter drawings are complete
Price setGMP amendmentProposal or Design-Build AmendmentBid award
Design controlOwner, through own architectDesign-builder, against owner criteriaOwner, through own architect
Main owner riskAssumptions behind an early GMPVague criteriaChange orders from design gaps
Typical AIA formA133-2019A141-2024A101 with A201

Typical arrangements. Public owners must follow their own procurement statutes.

Source: [1][2][3][4]

The biggest practical difference between CMAR and design-build is who the architect works for. In CMAR the architect is yours, which keeps an independent design check, while the manager's early estimates keep the design on budget. In design-build both sit in one contract. Compared with design-bid-build, CMAR gives up a single hard-bid price on finished drawings in exchange for builder input during design and an earlier start. Our design-build vs design-bid-build guide covers the other pairing.

When CMAR fits

  • Complex or phased projects: occupied renovations, hospitals and campuses where sequencing advice during design pays off.
  • Tight schedules: early packages let site work and structure start before interiors are designed.
  • Owners who want design control: the architect stays under your contract.
  • Larger budgets: preconstruction fees and the reporting load make more sense on bigger jobs.
  • Less suited: small, simple, fully designed buildings, where a hard bid is quicker and gives clean price competition.

Selecting a construction manager at risk

  • Estimate accuracyAsk how their design-stage estimates compared with final GMPs and final costs on recent jobs.
  • Preconstruction teamMeet the estimator, scheduler and project manager who will work during design.
  • Fee and general conditionsCompare the fee percentage and how general conditions are priced: lump sum, cap or cost.
  • Contingency rulesHow the manager's contingency is used, reported and returned if unspent.
  • Subcontractor procurementOpen bidding, owner participation in bid openings, and whether the manager may self-perform work.
  • Bonding and licensingBonding capacity for the GMP and the right license class for the state.

In South Florida, ask how the manager's preconstruction team handles High-Velocity Hurricane Zone product approvals and wind design reviews, since they affect long-lead envelope packages; our HVHZ construction primer explains why. Our guide to choosing a commercial contractor covers license and reference checks for any delivery method.

On hospital renovations, the CM's preconstruction work should include an ICRA class for every work area and a list of sprinkler and alarm outages, as explained in our healthcare construction guide.

Frequently asked questions

What is construction management at risk?

A delivery method in which the owner hires an architect and a construction manager separately. The manager advises during design, then commits to a guaranteed maximum price and builds the project, carrying the risk of overruns within its scope.

What is the difference between CM at risk and a general contractor?

A general contractor under design-bid-build usually joins after design and wins on bid price. A CM at risk joins during design, is chosen mainly on qualifications and fee, gives preconstruction advice, and then acts as the general contractor under a GMP.

What happens if the project costs more than the GMP?

For costs within the agreed scope, the construction manager pays the overrun. Owner-directed changes, and conditions the contract allocates to the owner, adjust the GMP through change orders.

What happens to savings under the GMP?

Unspent amounts generally stay with the owner unless the contract shares them. AIA A133-2019 includes a place to agree how the manager participates in savings when the final cost is below the GMP.

Is CMAR more expensive than design-bid-build?

Not necessarily. You pay preconstruction fees and the manager carries a contingency, but early cost advice can avoid redesign and the schedule can be shorter. Compare the full cost, including time, for your project.

Which contract is used for CM at risk?

In private work, AIA A133-2019 with A201-2017 general conditions and B133-2019 for the architect is common. Public agencies often use their own forms under their state statute. Have an attorney review whichever you use.

Can public agencies in Florida use CMAR?

Yes. Section 255.103 of the Florida Statutes authorizes construction management entities, selected through the section 287.055 process, and lets agencies require a guaranteed maximum price backed by a surety bond.

How early should the construction manager be hired?

Usually at or before schematic design, so its estimates and constructability reviews can still shape the design. Hiring late removes much of the benefit.