A commercial build-out is the interior construction that turns leased shell space into a usable office, store, restaurant or clinic. Across 984 Texas registrations in 2025 and 2026, median estimates ran $70 to $133 per sq ft.
Key takeaways
- Median estimated build-out cost in Texas was $90 per sq ft for office, $70 for retail, $129 for restaurants and $133 for medical and dental space, across 984 privately funded projects registered from January 2025 to November 2026 (TDLR TABS).
- The federal leasing standard prices the step from shell to basic finished office at a general allowance of $49.13 per usable sq ft, indexed to local costs (GSA Pricing Desk Guide, 5th ed., 2020, section 2.5.4).
- In Austin, finish-out building permits took a median 71 days from application to issue and 204 days from issue to final inspection, against 42 and 102 days for remodels of existing space (City of Austin permit data, 2025 to 2026).
- Texas requires registration and accessibility plan review for any build-out with an estimated cost of $50,000 or more (16 TAC 68.50).
- The 2026 U.S. average office fit-out cost was $162 per sq ft, with San Francisco at $228 (Cushman & Wakefield, March 2026).
| Key number | Value | Source and date |
|---|---|---|
| Texas build-out median, office / retail / restaurant / medical | $90 / $70 / $129 / $133 per sq ft | TDLR TABS, registered Jan 2025 to Nov 2026 |
| GSA general TI allowance, shell to vanilla office | $49.13 per usable sq ft (index city) | GSA PDG 5th ed., Aug 2020 |
| U.S. average office fit-out | $162 per sq ft | Cushman & Wakefield, Mar 2026 |
| Austin finish-out: permit review / construction | 71 / 204 days (medians) | City of Austin, issued Jan 2025 to Nov 2026 |
| Texas accessibility registration threshold | $50,000 estimated cost | 16 TAC 68.50 |
What does full build-out mean in commercial real estate?
A full build-out means the space is finished for one tenant’s use and ready for a certificate of occupancy: layout walls, doors, ceilings, lighting, power and data, HVAC distribution, restrooms and finishes are all in place. When the landlord builds it to an agreed plan, it is a turnkey build-out. The GSA Pricing Desk Guide calls this work tenant improvements: finishes and fixtures that take space from shell to finished, code-compliant use (section 2.5.1).
Listings describe five starting conditions. Each one shifts work, and cost, between landlord and tenant. The labels are market shorthand, not code terms, so the lease exhibit (often called the work letter) is the only reliable description of what you will receive. The only itemized public standard is GSA Table 2-4, compared below.
| Item | Cold shell | Warm shell | Vanilla shell / white box | Second-generation | Full build-out (turnkey) |
|---|---|---|---|---|---|
| Structure, roof, exterior walls | Yes | Yes | Yes | Yes | Yes |
| Concrete slab | Often unfinished | Yes | Finished, ready for flooring | Prior flooring | New flooring |
| Utility stubs (water, sewer, power) | To the space | Yes | Yes | Connected | Connected |
| Electrical panel | Often no | Yes | Yes | Prior tenant’s | Sized to tenant |
| HVAC equipment | No | Rooftop unit or core supply | Yes | Prior tenant’s | Sized to tenant |
| HVAC ductwork and diffusers | No | Usually no | Open-plan layout | Prior layout | Tenant layout |
| Fire sprinklers | Mains only, if any | Mains | Heads for open plan | Prior layout | Tenant layout |
| Restrooms | No | Code minimum or core | Yes | Yes | Yes |
| Perimeter drywall | No | Sometimes | Taped and primed | Yes | Painted |
| Ceiling grid and lights | No | No | Yes | Prior layout | Tenant layout |
| Interior walls, doors, finishes | No | No | No | Prior tenant’s | Yes |
| Use-specific systems (hood, med gas) | No | No | No | Only if same use | Yes |
The table reflects common lease drafting. A white box registered in Dallas County in October 2025 shows how one landlord defined it: taped and bedded walls with no final paint, tiled restroom walls and floor, HVAC, basic lighting, doors and windows, at an estimated $2.5 million for 29,358 sq ft, or $85 per sq ft (TABS2026002318).
What does a cold shell, warm shell or vanilla shell actually include?
A cold shell (also dark or gray shell) is structure, roof, walls and a slab with utilities stubbed in. A warm shell adds the base systems: an electrical panel, HVAC equipment, sprinkler mains and code-minimum restrooms. A vanilla shell or white box adds primed walls, a lit ceiling grid, open-plan ductwork and a finished slab: $85 per sq ft in one 2025 Dallas County record.
The one published, itemized shell standard in U.S. leasing is warmer than most broker usage. GSA Table 2-4 (Pricing Desk Guide, 5th edition, effective August 1, 2020) puts all of the items in the table below into the landlord’s shell rent for federal office leases. A tenant comparing a federal-style lease with a strip-center listing that says shell is comparing two different starting points.
| Item | What a typical broker cold shell includes | What GSA Table 2-4 shell includes | Source |
|---|---|---|---|
| Floor | Slab, sometimes left out at plumbing trenches | Broom-clean slab, flat and level to ASTM E1155 FF35 / FL25 | GSA PDG Table 2-4 |
| Walls | Bare structure | Gypsum board on perimeter and demising walls, spackled and prime painted | GSA PDG Table 2-4 |
| Ceiling and lights | None | Suspended acoustical ceiling, one light fixture per 80 usable sq ft, lighting controls | GSA PDG Table 2-4 |
| HVAC | None or a stub | Operational system with VAV boxes, ducts and diffusers for open office at 0.75 cfm per sq ft | GSA PDG Table 2-4 |
| Power | Service stub | Panels at 120/208 V, 3-phase, with 4 watts per usable sq ft excluding lighting and HVAC | GSA PDG Table 2-4 |
| Sprinklers | Mains, if the building is sprinklered | Mains and heads in an open-plan layout | GSA PDG Table 2-4 |
| Restrooms | None | Building common restrooms complete and operational | GSA PDG Table 2-4 |
Second-generation space was built out for a previous tenant. It can save most of the HVAC, ceiling and restroom cost when the prior use matches yours, but a change of use can trigger the change-of-occupancy rules in Chapter 10 of the International Existing Building Code. Our guide to commercial occupancy classifications explains which use groups count as a change.
Who pays for a commercial build-out?
The landlord usually pays for the shell and base building through the rent, and the tenant pays for improvements inside the premises, offset by any tenant improvement (TI) allowance in the lease. In a turnkey deal, the landlord builds an agreed plan and the tenant pays only for changes beyond it. GSA amortizes the TI allowance it spends into the rent over the firm lease term (PDG section 2.5.8).
| Cost bucket | Usually paid by | Examples | Source |
|---|---|---|---|
| Base building and shell | Landlord, in shell rent | Structure, envelope, lobbies, elevators, core restrooms, main utility service | GSA PDG 2.4.1 and Table 2-4 |
| Warm-shell systems | Landlord in many new retail centers; lease decides | Electrical panel, rooftop HVAC unit, sprinkler mains | Lease exhibit |
| Tenant improvements | Tenant, net of the TI allowance | Partitions, doors, ceilings, lighting, outlets, ductwork extensions, plumbing fixtures in the suite, finishes | GSA PDG 2.5.2 |
| Use-specific systems | Tenant | Kitchen hood and grease duct, medical gas, x-ray shielding, raised floor | GSA PDG 2.5.5 customization examples |
| Upgrades above building standard | Tenant | Upgraded ceilings, specialty lighting, millwork | GSA PDG 2.5.2 |
The GSA general TI component, $49.13 per usable sq ft in the August 2020 edition, is set to take space from shell to vanilla office and is indexed to local construction costs each year (section 2.5.4). Agencies with heavier needs get customization tiers of 10% to 60% on top. Lease terms and allowance math are covered in our guide to the tenant improvement allowance. This page is general information, not legal or financial advice: have a real estate attorney review the work letter before you sign.
How much does a commercial build-out cost per square foot?
Texas publishes the owner’s estimated construction cost and floor area for every project registered with the Texas Department of Licensing and Regulation (TDLR) in its TABS project database. Across 984 privately funded build-outs and tenant finish-outs registered from January 2025 to November 2026, median estimates were $90 per sq ft for office, $70 for retail, $129 for restaurants and $133 for medical and dental space.
| Space type | Projects | 25th percentile | Median | 75th percentile | Median size | Median project cost | Median planned construction | Source |
|---|---|---|---|---|---|---|---|---|
| Office | 132 | $50 | $90 | $152 | 4,240 sq ft | $378,750 | 4.0 months | TDLR TABS |
| Retail and personal service | 196 | $46 | $70 | $125 | 2,510 sq ft | $200,000 | 3.0 months | TDLR TABS |
| Restaurant | 489 | $76 | $129 | $204 | 2,325 sq ft | $300,000 | 3.5 months | TDLR TABS |
| Medical and dental | 167 | $86 | $133 | $206 | 2,949 sq ft | $398,000 | 4.1 months | TDLR TABS |
These are owner estimates at registration, in Texas, for projects of $50,000 or more, so they exclude small cosmetic jobs and do not include furniture, equipment or design fees unless the owner counted them. National office benchmarks run higher: the Cushman & Wakefield 2026 Americas Office Fit Out Cost Guide puts the U.S. average at $162 per sq ft and gateway markets at $196. Our commercial construction cost per square foot page covers ground-up buildings instead.
Does a shell build-out cost more than second-generation space?
For uses with heavy plumbing and mechanical work, yes. Medical and dental build-outs in shell or first-generation space ran a median $172 per sq ft against $127 in existing space, and restaurants $133 against $113. Retail showed no gap, at $60 for both, because most retail scopes are light on plumbing.
| Space type | Shell or first-generation: projects, median | Existing or second-generation: projects, median | Gap per sq ft | Source |
|---|---|---|---|---|
| Office | 82, $146 | 539, $90 | $56 | TDLR TABS via our office renovation cost analysis |
| Restaurant | 109, $133 | 153, $113 | $20 | TDLR TABS |
| Medical and dental | 37, $172 | 52, $127 | $45 | TDLR TABS |
| Retail and personal service | 41, $60 | 58, $60 | $0 | TDLR TABS |
Projects whose registration did not say shell or existing space are left out of this split. Office figures come from a larger office-only pull of 621 registrations from January 2025 to October 2026.
Real registrations near the median
| Scope as registered | County | Area | Estimated cost | Per sq ft | TDLR record |
|---|---|---|---|---|---|
| Office finish-out in existing shell | Webb | 3,505 sq ft | $300,000 | $86 | TABS2025010662 |
| Existing office modified for a new tenant, 2 new accessible restrooms, conference room | Rockwall | 3,659 sq ft | $350,000 | $96 | TABS2025013448 |
| Finish-out of existing shell for a paint store | Tarrant | 4,275 sq ft | $300,000 | $70 | TABS2026025877 |
| Tenant finish of an existing tenant space for a cafe | Fort Bend | 1,876 sq ft | $245,000 | $131 | TABS2026010936 |
| Medical finish-out of a cold shell in new construction | Collin | 2,500 sq ft | $340,000 | $136 | TABS2026010947 |
| Existing retail space converted to a dental office | Dallas | 2,948 sq ft | $409,083 | $139 | TABS2026018182 |
Worked example: what will a 3,000 sq ft build-out cost?
Multiply the floor area by the Texas percentile for your space type, then subtract the allowance and add a contingency. For a 3,000 sq ft dental office, the middle half of Texas registrations points to $258,000 to $618,000, with $399,000 at the median. The allowance below is hypothetical; use the number in your lease.
| Line | Low (25th pct.) | Median | High (75th pct.) | Basis |
|---|---|---|---|---|
| Rate, medical and dental | $86 per sq ft | $133 per sq ft | $206 per sq ft | TDLR TABS medians above |
| Construction estimate, 3,000 sq ft | $258,000 | $399,000 | $618,000 | 3,000 x rate |
| Less TI allowance at $50 per sq ft (hypothetical) | minus $150,000 | minus $150,000 | minus $150,000 | Lease term, illustration |
| Tenant share before contingency | $108,000 | $249,000 | $468,000 | CB&C arithmetic |
| Plus 10% contingency on construction | $25,800 | $39,900 | $61,800 | Illustration rate |
| Tenant cash needed | $133,800 | $288,900 | $529,800 | CB&C arithmetic |
The same 3,000 sq ft at the retail median of $70 is $210,000 and at the restaurant median of $129 is $387,000. How to size the reserve line is set out in our guide to construction contingency.
What permits and inspections does a build-out need?
Almost every build-out needs a building permit, because International Building Code (IBC) Section 105.1 requires one to construct, alter or change the occupancy of a building. Section 105.2 exempts finish work such as painting, carpet, tile and cabinets, so a cosmetic refresh may need no building permit where the local code keeps that exemption. Trade permits for electrical, mechanical and plumbing work follow the building permit.
- Before you sign: get the work letter listing every system the landlord will deliver, and walk the space with a builder. Our tenant improvement contractors page covers that walk-through.
- Design: a test fit, then construction documents; IBC Section 107.1 requires them to be prepared by a registered design professional where state law says so.
- Landlord approval: most leases require written approval of the plans before they go to the city.
- Permit application: building permit, plus a health department plan review for food service under FDA Food Code section 8-201.11. In Texas, register any project of $50,000 or more with TDLR for accessibility review (16 TAC 68.50).
- Plan review: Austin finish-out permits took a median 71 days from application to issue in 2025 and 2026.
- Construction and inspections: IBC Section 110.3 lists the required inspections, including framing, gypsum board, fire- and smoke-resistant penetrations, energy efficiency and final.
- Certificate of occupancy: IBC Section 111.1 bars occupying the space or changing its use until the building official issues one. Texas-registered projects also need an inspection by a Registered Accessibility Specialist (TDLR FAQ).
Our certificate of occupancy guide covers IBC Section 111. City permit rules are in our commercial building permits overview.
How long does a commercial build-out take?
Plan on about 9 months from permit application to final inspection for a first-time finish-out, and closer to 5 months for a remodel of existing space. In City of Austin permit records for permits issued from January 2025 to November 2026, finish-outs took a median 71 days in review and 204 days in construction, and restaurants were slowest at 92 and 282 days.
| Permit group | Permits (review / final) | Review, median days | Review, middle half | Construction, median days | Construction, middle half | Source |
|---|---|---|---|---|---|---|
| All commercial finish-outs | 348 / 288 | 71 | 45 to 123 | 204 | 119 to 282 | City of Austin |
| Office finish-out | 108 / 67 | 52 | 32 to 76 | 143 | 122 to 216 | City of Austin |
| Retail finish-out (small sample) | 13 / 10 | 88 | 59 to 124 | 216 | 118 to 265 | City of Austin |
| Restaurant finish-out | 40 / 31 | 92 | 72 to 142 | 282 | 221 to 412 | City of Austin |
| Medical and dental finish-out | 33 / 18 | 102 | 81 to 129 | 166 | 133 to 238 | City of Austin |
| Remodel of existing commercial space | 4,951 / 3,020 | 42 | 14 to 83 | 102 | 50 to 175 | City of Austin |
Owners planned shorter jobs than the permits recorded: the median planned construction period in the Texas registrations was 3.0 to 4.1 months by space type. Design, landlord approval and equipment lead times come before the permit application and are not in these counts.
Which space condition should you lease?
Match the condition to the systems your use needs and to your opening date. A use that can reuse a prior tenant’s plumbing and ductwork saves the most; a use that needs new plumbing at every room gains little from second-generation space unless the prior tenant had the same use. In Texas, medical shell space ran $45 per sq ft more than existing space.
| If | Then | Basis |
|---|---|---|
| You need to open in under 6 months | Favor second-generation space of the same use; Austin remodels took a median 42 + 102 days against 71 + 204 for finish-outs | City of Austin |
| You run a restaurant and a second-generation restaurant with a hood is available | Have the hood, grease duct and interceptor inspected before signing; existing space ran $113 against $133 per sq ft for shell | TDLR TABS |
| You run a medical or dental practice | Budget $172 per sq ft at the median for shell space and confirm plumbing access under the slab | TDLR TABS |
| The listing says shell and the allowance is below about $49 per sq ft | Ask the landlord to deliver a vanilla shell instead; that is the GSA cost of the shell-to-vanilla step in 2020 dollars | GSA PDG 2.5.4 |
| The work is paint, carpet and cabinets only | Ask the building department whether the IBC 105.2 finish-work exemption applies locally | IBC 105.2 |
| Your Texas project is $50,000 or more | Register with TDLR and book the accessibility review and inspection | 16 TAC 68.50 |
Restaurant-specific systems are covered in our restaurant build-out contractors guide, and clinic requirements in our medical office construction guide.
Restaurant spaces cost more to finish, as our restaurant construction cost guide shows, and the allowance is booked as in TI allowance accounting.
How we compiled this
We pulled 3,426 TDLR TABS project records registered from January 2025 to November 2026 by keyword, kept 984 privately funded interior build-outs with a stated cost and floor area between 400 and 100,000 sq ft, and sorted them by space type from the project name and scope. Timeline figures come from 5,740 City of Austin building permits in classes C-1000 (remodel) and C-1001 (finish-out) issued in the same period; 274 finish-out permits with review intervals over 365 days, which share application dates with a master building permit, were excluded from review medians. Definitions follow the GSA Pricing Desk Guide; code sections come from the 2024 IBC. We did no site visits or surveys.
Frequently asked questions
What does build-out mean in a commercial lease?
Build-out means the interior construction that makes leased space usable for the tenant: walls, ceilings, lighting, HVAC ducts, plumbing fixtures and finishes. The lease work letter states who builds it, to what standard and with how much landlord money. GSA calls the same work tenant improvements, the finishes and fixtures that take space from shell to a finished, code-compliant condition.
What is the difference between a vanilla shell and a white box?
Most brokers use the two terms for the same condition: taped and primed perimeter walls, a ceiling grid with lights, HVAC ductwork for an open plan, a working restroom and a finished slab. A Dallas County white box registered in 2025 added restroom tile, doors and windows at $85 per sq ft. Some landlords use white box for a slightly more finished space, so read the lease exhibit.
Is a build-out the same as tenant improvements?
In practice, yes. Tenant improvements, leasehold improvements, fit-out and finish-out all describe construction inside a leased space. Build-out is more often used for first-time work in shell space, and remodel for changing second-generation space. Texas TABS registrations use finish-out for both, and Austin permits separate Commercial Finish Out (class C-1001) from Commercial Remodel (class C-1000).
How much does an office build-out cost per square foot?
Texas office build-outs registered from January 2025 to November 2026 had a median estimate of $90 per sq ft, with the middle half between $50 and $152, across 132 projects. Shell office build-outs ran higher, at a median $146 in a larger office sample. The Cushman and Wakefield 2026 national average is $162 per sq ft, and San Francisco is $228.
How long does a tenant build-out take?
Austin commercial finish-out permits issued in 2025 and 2026 took a median 71 days of plan review and 204 days from permit issue to final inspection. Office finish-outs were quicker at 52 and 143 days, and restaurants slower at 92 and 282 days. Remodels of existing space took a median 42 and 102 days. Add design and landlord approval time before the permit application.
Do I need a permit for a commercial build-out?
Usually yes. IBC Section 105.1 requires a building permit to construct, alter or change the occupancy of a building, and trade permits cover the electrical, mechanical and plumbing work. Painting, carpet, tile and cabinets are exempt under Section 105.2 where the local code keeps that exemption. In Texas, projects of $50,000 or more also need TDLR accessibility registration.
Sources
- Texas Department of Licensing and Regulation: Texas Architectural Barriers Online Search (TABS), project registrations Jan 2025 to Nov 2026, accessed November 21, 2026.
- City of Austin Development Services: Issued Construction Permits (dataset 3syk-w9eu), accessed November 21, 2026.
- U.S. General Services Administration, Public Buildings Service: Pricing Desk Guide, 5th Edition (effective Aug 1, 2020), Table 2-4 and sections 2.5.1 to 2.5.8, accessed November 21, 2026.
- International Code Council: 2024 International Building Code, Chapter 1, Sections 105, 107, 110, 111, accessed November 21, 2026.
- International Code Council: 2024 International Existing Building Code, Chapter 10 Change of Occupancy, accessed November 21, 2026.
- Texas Department of Licensing and Regulation: 16 Texas Administrative Code 68.50, Submission of Construction Documents, accessed November 21, 2026.
- Texas Department of Licensing and Regulation: Architectural Barriers FAQ, accessed November 21, 2026.
- U.S. Food and Drug Administration: FDA Food Code, section 8-201.11, accessed November 21, 2026.
- Cushman & Wakefield: Office fit-out costs across the Americas rise (2026 Americas Office Fit Out Cost Guide), accessed November 21, 2026.