Construction Warranty: What Is Covered, for How Long and How to Claim

New commercial office building at dusk with construction fencing still along the sidewalk

A construction warranty on commercial work is the contractor’s promise that the work meets the contract and is free from defects (AIA A201-2017 §3.5); it does not end after one year, only the duty to come back and correct does.

Key takeaways

  • The contractor’s general warranty in AIA A201-2017 §3.5.1 covers materials that are new and of good quality and work that conforms to the Contract Documents and is free from defects. The section states no expiry date.
  • The one-year period in A201 §12.2.2.1 is a duty to return and correct work found nonconforming within 1 year of substantial completion; §12.2.5 says it sets no limit on how long the contractor stays liable for other obligations.
  • Warranties start on the substantial completion date unless the certificate says otherwise (A201 §9.8.4), and A201 §15.1.2 bars claims filed more than 10 years after that date.
  • State statutes of repose cap defect claims at 5 years in Virginia (Va. Code 8.01-250), 7 years in Florida (Fla. Stat. 95.11(3)(b)), 8 years in Arizona (A.R.S. 12-552) and 10 years in Texas (CPRC 16.009) and for latent defects in California (CCP 337.15).
  • Manufacturer terms are separate and can start before your building opens: one rooftop unit maker’s standard warranty runs 12 months from installation or 18 months from factory shipment, whichever comes first (AAON, accessed November 2026).
  • On federal jobs, FAR 52.246-21 runs the warranty 1 year from final acceptance, and repaired work gets a fresh 1-year warranty from the repair date.

How long does a construction warranty last?

A commercial construction warranty has three clocks. The contractor’s duty to return and fix defects runs 1 year from substantial completion under AIA A201-2017 §12.2.2.1. The contractor’s underlying warranty under §3.5 has no stated end; it lasts until the state statute of limitations or repose, or the form’s 10-year cap in §15.1.2, cuts off a claim. Manufacturer warranties run on their own terms, from 1 to 30 years.

The table below sets out each clock and what controls it. Numbers are from the primary documents named in the Source column, as of November 2026. A contract can change any contractual clock; it cannot extend a statute of repose past the state’s limit.

ClockLengthStartsSource
Correction period (callback duty)1 yearSubstantial completionA201-2017 §12.2.2.1
Contractor’s general warrantyNo stated end in the formSubstantial completionA201-2017 §3.5.1, §9.8.4
Outer limit on all claims10 yearsSubstantial completionA201-2017 §15.1.2
Federal construction warranty1 year; 1 year again for repaired workFinal acceptance or possessionFAR 52.246-21(b), (d)
Rooftop unit standard parts warranty12 months (or 18 from shipment)Installation or shipment, earlier end winsAAON warranty page, 2026
TPO roof membrane warranty options15, 20 or 25 years; 5 to 30 yearsPer the issued certificateDuro-Last TPO60 sheet (2024); JM TPO 80 mil sheet (2016)
State statute of repose5 to 10 years in the six states belowUsually substantial completionState statutes, linked below
Warranty and claim clocks measured from substantial completionBars from year 0 at substantial completion: 1-year correction period, 2 to 30-year warranties and 5 to 10-year state repose limits.Clocks that start at substantial completion (years)Correction duty and contract cap in rust, warranties in teal, state statutes in ink012345678910Years after substantial completion (11-month walk-through falls just before year 1)11-month walk-throughA201 correction period (§12.2.2.1)1 yrCurtain wall installer warranty (UH spec)2 yrsRooftop unit compressor (AAON)5 yrsVirginia repose (8.01-250)5 yrsWashington accrual limit (4.16.310)6 yrsArizona repose (12-552)8 yrs, up to 9Texas repose (16.009)10 yrsCalifornia latent defects (337.15)10 yrsA201 outer claim limit (§15.1.2)10 yrsTPO roof maker warranty options15 to 30 yrs
Measured from substantial completion: the A201-2017 correction period ends at 1 year, while repose runs 5 years in Virginia to 10 years in Texas and California. Florida’s 7 years runs from the certificate of occupancy. Sources: A201-2017, state codes, AAON, University of Houston spec; accessed November 2026.

What is the difference between the A201 warranty and the one-year correction period?

The A201 §3.5 warranty is a promise about quality; the §12.2.2 correction period is a promise to show up and repair. Under §12.2.2.1 the contractor must correct nonconforming work found within 1 year of substantial completion after the owner’s notice. After that year, the owner can still claim money for breach of the §3.5 warranty, because §12.2.5 says the 1-year period “relates only to the specific obligation of the Contractor to correct the Work.”

The year has two rules many guides skip. Section 12.2.2.2 extends it for work first performed after substantial completion, by the gap between substantial completion and when that work was done. Section 12.2.2.3 says corrective work does not restart the year, so a roof drain fixed in month 11 is not covered by a new 12 months unless the contract adds it.

The owner also has a duty. Under §12.2.2.1, an owner who fails to notify the contractor during the year and give it a chance to correct waives both the right to require correction and the claim for breach of warranty on that item. Written notice, sent when the defect is found, protects both rights.

FeatureGeneral warranty (§3.5)Correction period (§12.2.2)Source
What it promisesNew, good-quality materials; work conforms and is free from defectsContractor returns and corrects nonconforming workA201-2017 §3.5.1, §12.2.2.1
LengthNo stated end; limited by statute and the 10-year cap1 year from substantial completion§12.2.5, §15.1.2
Owner remedyDamages for breachRepair by the contractor; owner may correct after a 10-day notice§2.5, §12.2.2.1
Owner’s dutyBring the claim in timeNotify promptly or waive correction and the warranty claim§12.2.2.1, §15.1.3
ExcludedAbuse, alterations by others, poor maintenance, improper operation, normal wearSame exclusions apply through §3.5§3.5.1
Federal contrastWarranty of 1 year from final acceptanceRepaired work warranted 1 year from repairFAR 52.246-21(b), (d)

Our guide to the A201 general conditions, article by article shows where these sections sit in the full form.

What do manufacturer warranties cover on roofing, HVAC and curtain wall?

Manufacturer warranties, which A201 calls special warranties, cover a product or system and are issued by the maker or installer, not the general contractor. Section 3.5.2 requires them to be issued in the owner’s name or transferable to the owner, and §9.10.2 makes their delivery a condition of final payment. Their length comes from the maker’s sheet or the owner’s specification, from 12 months for rooftop unit parts to 30 years for some roof membranes.

SystemWarranty published or specifiedLengthSource
TPO roof membrane, 60 and 80 milMaker warranty options15, 20 or 25 yearsDuro-Last Duro-TECH TPO60 data sheet, Oct 2024
TPO roof membrane, 80 milPeak Advantage guarantee options5, 10, 15, 20, 25 or 30 yearsJohns Manville JM TPO 80 mil sheet RS-8634, 2016
Packaged rooftop unit, standardParts, defects in materials or workmanship12 months from install or 18 from shipment, whichever firstAAON warranty page, accessed Nov 2026
Rooftop unit compressorComponent warranty5 yearsAAON, same page
Rooftop gas heat exchangerAluminized steel; stainless steel15 years; 25 yearsAAON, same page
Glazed aluminum curtain wallInstaller special assembly warranty2 years from substantial completionUniversity of Houston spec 08 44 13, rev. 2018
Curtain wall factory finishManufacturer finish warranty20 years from substantial completionUniversity of Houston spec 08 44 13
Curtain wall, state owner specMaterials and workmanship; finish10 years; 20 yearsIllinois CDB spec 08 44 13, Aug 2021
Longest published or specified warranty term by systemBar chart: rooftop parts 1 year, installer 2, compressor 5, curtain wall 10, heat exchangers 15 and 25, finish 20, TPO 25 and 30yearsRooftop unit parts, standard (AAON)1Curtain wall installer (Univ. of Houston s2Rooftop unit compressor (AAON)5Curtain wall materials and workmanship (Il10.0Aluminized heat exchanger (AAON)15.0Curtain wall finish (Houston and Illinois 20.0Stainless heat exchanger (AAON)25.0TPO 60 and 80 mil membrane (Duro-Last)25.0TPO 80 mil membrane (Johns Manville)30.0
Published and specified warranty terms run from 1 year for standard rooftop unit parts to 30 years for one maker’s 80 mil TPO guarantee. Sources: AAON, Duro-Last, Johns Manville, University of Houston and Illinois CDB specs; accessed November 2026.

Three details change what these warranties are worth. A maker term that runs from shipment can lapse before the owner moves in: a unit shipped in October and installed in December reaches its 12-month install limit before an 18-month shipment limit. Many roof warranties need the maker’s own inspection before the certificate issues; our TPO roofing cost guide lists the membrane options by thickness. And curtain wall specs split the installer’s assembly term (2 years at the University of Houston) from the finish term (20 years), so a leaking joint and a chalking finish go to different parties; our curtain wall guide covers the testing behind those terms.

For equipment, ask the mechanical contractor for a start-up letter from the maker that moves the warranty start to the substantial completion date, which A201 §3.5.2 and §9.8.4 assume. Our commercial HVAC system guide covers rooftop unit types and their efficiency rules.

Do implied warranties apply to commercial construction?

Implied warranties are duties the law adds whether or not the contract states them, most often a duty to build in a good and workmanlike way. On a commercial job the written warranty usually does the work: A201-2017 §3.5.1 already promises conforming, defect-free work, and §13.3.1 says contract remedies add to, and do not limit, the rights the law otherwise gives.

State law decides how long implied warranties last and whether a contract can disclaim them. Arizona’s statute, A.R.S. 12-552(F), expressly puts implied warranties of habitability, fitness and workmanship inside its 8-year repose period, and 12-552(G) says the statute does not shorten an express written warranty. The warranty of habitability is mainly a residential doctrine; on a commercial job, the written §3.5 warranty and the specifications usually set the standard.

Bonds are a separate layer. A performance bond may back the contractor’s correction duty, depending on the bond form, and some public owners require a separate bond for the warranty period. Our guide to performance bonds explains what the surety promises.

When does the warranty clock start?

Under AIA A201-2017 §9.8.4, warranties required by the Contract Documents start on the date of substantial completion of the Work, or of a designated portion, unless the Certificate of Substantial Completion states another date. If the owner occupies part of the building early, §9.9.1 requires a written agreement on when the correction period and warranties start for that part.

The date on the certificate matters more than the date the contractor leaves. Our guide to substantial completion and the G704 certificate explains how the architect sets it. State statutes can use a different trigger: Florida’s repose runs from the certificate of occupancy, temporary certificate or certificate of completion, whichever is earliest, and Arizona treats first use, availability for use or final inspection as substantial completion (A.R.S. 12-552(H)).

Worked example: one building, six end dates

A hypothetical Arizona office building reaches substantial completion on March 2, 2026. Its rooftop units shipped on October 15, 2025 and were installed on December 1, 2025. The table applies each rule to those dates.

ClockRuleArithmeticEnds
Rooftop unit standard parts12 months from install or 18 from shipment, earlier wins (AAON)Dec 1, 2025 + 12 months = Dec 1, 2026; Oct 15, 2025 + 18 months = Apr 15, 2027Dec 1, 2026 (9 months after substantial completion)
11-month walk-throughBook about 30 days before the correction period endsMar 2, 2027 minus 1 monthEarly February 2027
Correction period1 year from substantial completion (§12.2.2.1)Mar 2, 2026 + 1 yearMar 2, 2027
Curtain wall installer warranty, if the spec matches Houston’s2 years from substantial completionMar 2, 2026 + 2 yearsMar 2, 2028
Arizona repose8 years; 9 if the defect is found in year 8 (12-552(A), (E))Mar 2, 2026 + 8 years (+ 1)Mar 2, 2034 (Mar 2, 2035 at most)
A201 outer claim limit10 years from substantial completion (§15.1.2)Mar 2, 2026 + 10 yearsMar 2, 2036, but the Arizona statute ends claims first

The rooftop unit row is the trap: its standard term ends 3 months before the contractor’s correction period. A start-up letter that moves the maker’s start to March 2, 2026, or a purchased 2-year parts extension that the same maker lists, closes that gap.

What are the statute of limitations and statute of repose by state?

A statute of limitations runs from when a claim accrues or a defect is discovered; a statute of repose is a hard outer limit measured from completion, even for defects nobody has found. In the six states below, construction repose runs 5 to 10 years. When the contract says nothing shorter, these statutes decide how long the A201 §3.5 warranty can be enforced in court.

StateLimitation or discovery ruleRepose (outer limit)Clock startsStatute
ArizonaContract actions inside the repose period; implied warranties included8 years; up to 9 if injury or latent defect arises in year 8First use, availability for use or final inspectionA.R.S. 12-552
CaliforniaPatent (visible) defects: 4 yearsLatent defects: 10 yearsSubstantial completion, no later than final inspection, recorded notice of completion, occupation, or 1 year after work stopsCCP 337.1; CCP 337.15
Florida4 years; latent defects from discovery7 yearsEarliest of temporary CO, CO or certificate of completionFla. Stat. 95.11(3)(b)
TexasResidual period: 4 years from accrual (§16.051)10 years; 8 years when a governmental entity suesSubstantial completionCPRC 16.009
VirginiaInjury claims under §8.01-243 and §8.01-2465 years; does not cover makers or suppliers of installed equipmentPerformance of the services and constructionVa. Code 8.01-250
WashingtonOrdinary limitation period runs once the claim accruesClaim must accrue within 6 yearsSubstantial completion or end of services, whichever is laterRCW 4.16.310
Construction statute of repose in six statesBar chart: Virginia 5, Washington 6, Florida 7, Arizona 8, Texas 10, California 10 yearsyearsVirginia (8.01-250)5Washington, accrual limit (4.16.310)6Florida (95.11(3)(b))7Arizona (12-552)8Texas (CPRC 16.009)10.0California, latent defects (CCP 337.15)10.0
Construction repose runs from 5 years in Virginia to 10 years in Texas and, for latent defects, California; Arizona allows up to 9 years for a defect found in year 8. Sources: official state code sites, accessed November 15, 2026.

Two statutes change the warranty math. Florida’s 95.11(3)(b) says warranty repairs on permitted work do not extend the period, and treats each building on a multi-building project as its own improvement. Virginia’s 5-year limit in 8.01-250 does not protect makers or suppliers of equipment and machinery, so a failed boiler can still be pursued against its maker after the contractor is out of reach. This page is general information, not legal advice; ask a construction lawyer licensed in the project’s state which period applies and whether your contract shortened it.

How do you make a construction warranty claim?

A warranty claim under AIA A201-2017 starts with written notice and runs on two deadlines the form sets: a claim found inside the correction period needs notice within 21 days of recognizing the condition (§15.1.3.1), and the owner may correct work itself if the contractor does not start within 10 days of notice (§2.5). The eight steps below follow the form’s order.

  1. Identify the warranty. Check the closeout binder: the §3.5 general warranty, any special warranty listed in the specifications, and the maker certificate with its own start date. Our guide to as-built drawings and closeout records lists what that binder should hold.
  2. Document the defect. Record the date found, location, photos, the specification section and any leak or failure history.
  3. Send written notice. Notify the contractor and the architect promptly (§12.2.2.1); inside year 1, within 21 days of recognizing the condition (§15.1.3.1).
  4. Notify the maker. For equipment and systems, give model, serial number and install date within the notice window printed on the certificate.
  5. Give access. Let the contractor inspect and correct within a reasonable time (§12.2.2.1).
  6. Send a 10-day cure notice. If the contractor does not start correcting within 10 days, the owner may correct and charge the cost, subject to the architect’s approval (§2.5).
  7. Log the repair. Corrective work does not restart the 1-year period (§12.2.2.3), unlike federal work under FAR 52.246-21(d).
  8. Escalate. File a claim under Article 15 inside the state statute and the 10-year cap in §15.1.2; final payment does not waive claims for nonconforming work or special warranties (§9.10.4).
Eight steps to make a construction warranty claim under AIA A201-2017Identify the warranty, document, give written notice, notify the maker, give access, send a ten-day cure notice, log the repair, escalate under Article 15.How to make a construction warranty claim (AIA A201-2017)1. Identify the warrantyContract §3.5, specialwarranty or maker term2. Document the defectPhotos, date found,location, spec section3. Written noticePromptly; claims insideyear 1: within 21 days4. Notify the makerModel, serial, installdate, its notice window5. Give accessContractor inspectsand corrects (§12.2.2.1)6. Ten-day cure noticeIf no start in 10 days,owner may correct (§2.5)7. Log the repairCorrective work does notrestart year 1 (§12.2.2.3)8. EscalateArticle 15 claim, insiderepose and §15.1.2 capRust boxes carry the two notice deadlines in the form: 21 days (§15.1.3.1) and 10 days (§2.5).
A warranty claim under AIA A201-2017 runs on two notice deadlines: 21 days for a claim found inside year 1 (§15.1.3.1) and a 10-day cure notice before the owner corrects (§2.5). Source: A201-2017, accessed November 2026.

What should the 11-month walk-through cover?

The 11-month walk-through is an inspection held about 30 days before the 1-year correction period ends, so every defect found can still be sent under A201 §12.2.2.1. HUD’s MAP Guide 4430.G §12.6.3 (rev. March 2021) sets the federal model where HUD requires it: a first inspection within 9 months of final completion and a last one no later than the 10th day of the 12th month, attended by the architect, owner and general contractor.

AreaWhat to checkWarranty it falls under
RoofPonding water after rain, open seams, flashing at curbs and drains§12.2.2.1 and the membrane maker certificate
Rooftop and mechanical unitsHeating season and cooling season performance, compressor faults, condensate leaksMaker parts, compressor and heat exchanger terms
Envelope and curtain wallWater at sills and stack joints, failed sealant, fogged insulating glassInstaller assembly warranty (2 years in the Houston spec)
Slabs and finishesCracks beyond the specified tolerance, floor finish failures, door alignment§3.5.1, minus normal wear and shrinkage the spec permits
SitePaving settlement, drainage at entries, landscaping that did not establish§12.2.2.1
Open punch itemsItems finished after substantial completionExtended year under §12.2.2.2

Bring the building engineer’s work orders from year 1, since HUD form HUD-95379 asks the architect to list improper maintenance separately and §3.5.1 excludes it. Items still open from the construction punch list belong in the same report. Buildings that went through building commissioning can use the commissioning agent’s seasonal test results as the baseline for the 11-month report.

Which warranty covers this defect?

The table gives the first move for the six situations owners meet most often, with the A201-2017 or statute section behind each. It assumes an unmodified A201-2017; supplementary conditions often change the 1-year period, the 10-year cap or the notice rules, so read the project’s own Division 01 warranty section first.

If the defect isThenRule
Found before substantial completionPut it on the punch list; the contractor corrects at its cost§12.2.1
Found within 1 year of substantial completionSend written notice now; the contractor must return and correct§12.2.2.1
In equipment or a roof with a maker certificateClaim under the certificate, issued in the owner’s name§3.5.2; maker terms
Found after year 1 but inside the state periodClaim damages for breach of the §3.5 warranty§12.2.5; state statute
Caused by abuse, poor maintenance or normal wearNot covered by the contractor’s warranty§3.5.1
On a federal contractNotify the contractor in writing; 1 year from final acceptance, renewed for repaired workFAR 52.246-21(b), (d), (e)
Which warranty covers this defectDecision flow: before substantial completion goes to the punch list; within one year the contractor corrects; maker items go to the maker; later defects are warranty claims inside the state repose period.Which warranty covers this defect?Found before substantial completion?If no, go downYes: punch list, contractor correctsat its cost (§12.2.1)YesFound within 1 year of substantial completion?If no, go downYes: written notice, contractor mustcome back and correct (§12.2.2.1)YesEquipment or material with a maker warranty?If no, go downYes: claim under the maker’s terms,issued to the owner (§3.5.2)YesInside the state repose and limitation period?If no, go downYes: breach of warranty claim under§3.5 and Article 15YesNo: usually time barred. Abuse, poor maintenance and normal wear are excluded at any age (§3.5.1).
Timing decides the route: before substantial completion it is a punch list item (§12.2.1), within 1 year a correction request (§12.2.2.1), later a §3.5 warranty claim inside the state period. Source: A201-2017, accessed November 2026.

Warranty rights survive closeout: under A201-2017 §9.10.4, final payment does not waive the owner’s claims for nonconforming work or for special warranties. Our guide to retainage in construction covers what can still be withheld at closeout.

Bonded jobs may add a maintenance bond for the warranty term, which starts at substantial completion under most forms.

How we compiled this

We read the warranty, correction, closeout and claims sections of AIA A201-2017, FAR 52.246-21, six state limitation and repose statutes on their official legislature sites, one HUD handbook section, three maker warranty documents and two owner curtain wall specifications: 15 primary documents, opened or re-read in November 2026. We left out state statutes whose official pages did not load and maker terms we saw only in search summaries.

Frequently asked questions

Is a construction warranty only one year?

Not under AIA A201-2017. The 1-year period in §12.2.2.1 is the contractor’s duty to return and correct work. Section 12.2.5 says that year sets no limit on other obligations, so the §3.5 warranty can be enforced until the state statute of repose or the form’s 10-year cap in §15.1.2 ends it, unless the contract was edited to shorten it.

What does a contractor's warranty not cover?

A201-2017 §3.5.1 excludes damage or defects caused by abuse, alterations not made by the contractor, improper or insufficient maintenance, improper operation, and normal wear and tear and usage. Equipment and roofing are usually covered by separate maker certificates instead, which A201 §3.5.2 requires to be issued in the owner’s name or transferable to the owner.

Does a warranty repair restart the warranty period?

Under A201-2017, no: §12.2.2.3 says corrective work does not extend the 1-year correction period. Federal contracts differ, because FAR 52.246-21(d) warrants repaired or replaced work for 1 year from the repair date. Florida’s 95.11(3)(b) also says warranty repairs on permitted work do not extend the 7-year repose period.

When does a construction warranty start?

On the substantial completion date in the Certificate of Substantial Completion, unless the certificate states another date (A201-2017 §9.8.4). For early occupancy of part of a building, §9.9.1 requires a written agreement on when that part’s warranties start. Federal warranties start at final acceptance under FAR 52.246-21(b).

What is the 11-month warranty walk-through?

It is an inspection about 30 days before the 1-year correction period ends, so defects can still be sent to the contractor under A201 §12.2.2.1. HUD’s MAP Guide §12.6.3 sets a similar schedule where HUD requires it: a first inspection within 9 months of final completion and a last one by the 10th day of the 12th month.

How long do I have to sue a contractor for construction defects?

It depends on the state statute of repose: 5 years in Virginia, 6 years for a claim to accrue in Washington, 7 years in Florida, 8 years in Arizona and 10 years in Texas and, for latent defects, California. A201-2017 §15.1.2 adds a 10-year contractual cap. This is general information, not legal advice.