AIA A101: How to Fill In the 2017 Stipulated Sum Agreement

Site office table with a hard hat and rolled drawings beside a window onto a steel-framed building under construction

AIA A101 is the American Institute of Architects’ fixed-price owner-contractor agreement: the 2017 edition adopts the A201-2017 general conditions, puts insurance and bonds in Exhibit A, and sells for $179.99 per use (AIA, November 2026).

Key takeaways

  • A101-2017 has 9 articles plus Exhibit A, and the owner’s real decisions sit in Articles 3 to 7: dates, Contract Sum, payment dates, retainage, liquidated damages, the dispute box and the termination fee (AIA A101 instructions).
  • Six blanks have a printed fallback: commencement on the Agreement date (§3.1), monthly applications (§5.1.2), final payment 30 days after the final Certificate (§5.2.2), the local legal interest rate (§5.3), the Architect as Initial Decision Maker (§6.1) and litigation (§6.2) (A101-2017, Oakton Community College copy).
  • AIA’s rule for §5.1.3: the last day of work in an Application for Payment should be at least 14 days before the payment date, because A201-2017 §9.4.1 gives the Architect 7 days to certify (AIA instructions).
  • A101 prints no retainage rate. Public owners filled in 10% (Oakton, 2019) and 5% (Southcentral Foundation draft), and 30 of 46 jurisdictions with a percentage limit cap public retainage at 5%.
  • Exhibit A makes the Owner buy builder’s risk on an all-risks completed value form of at least the initial Contract Sum unless a box shifts it; Anderson County, Texas set $1,000,000 per occurrence, $2,000,000 aggregate and 100% bonds in 2026 (Exhibit A copy).
  • A101’s copyright line lists 16 editions since 1915 and the 2017 edition is current; AIA said in 2022 that A201 “will be updated again in 2027” (AIA, April 2022).
Key numberWhat it meansSource
$179.99One-time use license for A101, and the same again for A201-2017AIA store, Nov 2026
9 + 1Articles in A101-2017, plus Exhibit A, Insurance and BondsA101-2017 copy
14 daysMinimum gap AIA suggests between the last day of billed work and the payment dateAIA instructions §5.1.3
7 daysTime the Architect has to certify an Application for PaymentA201-2017 §9.4.1
30 daysFinal payment after the final Certificate for Payment, if §5.2.2 is left as printedA101 §5.2.2
10 daysNotice needed to change the Owner’s or Contractor’s representativeA101 §8.4
5%Public retainage cap in 30 of 46 jurisdictions with a percentage limitCB&C tracker, Oct 2026

What is AIA A101 and when do you use it?

AIA A101-2017 is the Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum. AIA says to use it on large design-bid-build projects where the full scope is defined at signing and the price is fixed by bid or negotiation (AIA store page). It is not a full contract alone: A201-2017 and Exhibit A complete it.

The split between the three documents is practical. A101 holds the deal: parties, dates, the Contract Sum, payment dates, retainage, the dispute box and the termination fee. A201-2017 holds the procedures in 15 articles, and the printed A101 cover says not to use it with other general conditions unless the form is modified (A101-2017 cover note). Those 15 articles, with their claim and payment deadlines, are covered in our guide to the AIA A201 general conditions.

A101 is one of the seven AIA owner-builder agreements compared below, each sold at $179.99, and AIA’s store pairs it with A201, A401, G702, G703 and the G901 to G904 lien waiver forms. How those forms fit into the A to G series, and which go together for each delivery method, is mapped in our guide to AIA contract documents.

AIA A101-2017: nine articles, Exhibit A and the A201 general conditions it adopts AIA A101-2017 agreement: what the owner fills in, article by article Source: AIA Document A101-2017 (Oakton Community College copy) and AIA instructions, accessed November 2026 Art. 1 The Contract Documents No blanks: lists what forms the Contract Art. 2 The Work of This Contract No blanks: Work as shown in the Contract Documents Art. 3 Commencement and Substantial Completion Commencement box; completion date or calendar days Art. 4 Contract Sum Contract Sum; alternates; allowances; unit prices; liquidated damages Art. 5 Payments Payment dates; retainage percent; final payment; interest rate Art. 6 Dispute Resolution Initial Decision Maker; arbitration or litigation box Art. 7 Termination or Suspension Termination for convenience fee Art. 8 Miscellaneous Provisions Representatives; insurance and bonds (Exhibit A); electronic notice Art. 9 Enumeration of Contract Documents Drawings, specifications, addenda, other exhibits A201-2017 General Conditions adopted by reference 15 articles: changes, payment, claims, insurance framework Exhibit A Insurance and Bonds Owner’s property insurance Contractor’s coverage limits Bond penal sums
A101-2017 has 9 articles; the owner’s blanks sit in Articles 3 to 8, with insurance and bonds in Exhibit A and procedures in A201-2017. Source: AIA Document A101-2017 (Oakton Community College copy) and AIA instructions, accessed November 1, 2026.

What does each article of A101-2017 cover?

A101-2017 has nine articles and one exhibit. Articles 1, 2 and 9 define the Contract Documents and the Work; Articles 3 to 8 hold the fill-in points that set time, money and risk; Exhibit A sets insurance and bonds. The table lists each article, what the owner fills in and the section numbers, taken from a public bid copy of the form (A101-2017, Oakton Community College).

ArticleTitleWhat the owner fills inSections
1The Contract DocumentsNo blanks: lists what forms the ContractAgreement, conditions, drawings, specifications, addenda, Modifications
2The Work of This ContractNo blanks: Work as shown in the Contract DocumentsWork by others goes in the Supplementary Conditions
3Date of Commencement and Substantial CompletionCommencement box; completion date or calendar days§3.1, §3.3.1, phased dates §3.3.2
4Contract SumContract Sum; alternates; allowances; unit prices; liquidated damages§4.1 to §4.5; bonus or incentive §4.6
5PaymentsPayment dates; retainage percent; final payment; interest rate§5.1.2, §5.1.3, §5.1.7, §5.2.2, §5.3
6Dispute ResolutionInitial Decision Maker; arbitration or litigation box§6.1, §6.2
7Termination or SuspensionTermination for convenience fee§7.1.1, tied to A201 §14.4.3
8Miscellaneous ProvisionsRepresentatives; insurance and bonds (Exhibit A); electronic notice§8.2, §8.3, §8.5, §8.6, other provisions
9Enumeration of Contract DocumentsDrawings, specifications, addenda, other exhibits§9.1.1 to §9.1.9; E203-2013 and E204-2017 by date
Exhibit AInsurance and BondsOwner’s property insurance; Contractor’s coverage limits; Bond penal sumsArticles A.1 to A.4

The 2017 edition moved most of the owner’s choices into fill points. AIA lists the changes from A101-2007 as a three-box commencement date (§3.1), a completion date or day count (§3.3.1), new fill points for liquidated damages (§4.5) and bonuses (§4.6), a three-part retainage section (§5.1.7) and a termination fee (§7.1.1), with insurance moved to Exhibit A (AIA A101-2017 summary).

What happens if you leave an A101 blank empty?

Six A101 blanks have a printed fallback, so leaving them empty is itself a choice: the Agreement date starts the clock, applications run monthly, final payment falls 30 days after the final Certificate, late payments earn the local legal rate, the Architect decides claims first and disputes go to court. Retainage, liquidated damages and the termination fee have no fallback number.

BlankIf left emptyWhat it means for the ownerSection
CommencementDate of the AgreementContract Time starts at signing, even if permits are not issuedA101 §3.1
Application periodOne calendar month ending on the last day of the monthMonthly billing on G702 and G703A101 §5.1.2
Final payment30 days after the Architect’s final Certificate for PaymentOwner’s last deadline to release the balanceA101 §5.2.2
Interest on late paymentLegal rate prevailing where the Project is locatedA state prompt payment statute may also apply; Oakton cited 50 ILCS 505A101 §5.3
Initial Decision MakerThe ArchitectThe owner’s design professional rules first on every ClaimA101 §6.1
Binding dispute methodLitigation in a court of competent jurisdictionNo arbitration unless a box is checked or both agree in writingA101 §6.2
Liquidated damagesNone: §4.5 reads “if any”Lost rent and lost use are waived under A201 §15.1.7A101 §4.5
RetainageNo printed percentageAgree a rate within any statutory capA101 §5.1.7.1
Termination feeNone statedOwner pays Work executed and termination costs onlyA201 §14.4.3

The liquidated damages row is the costly one. A201-2017 §15.1.7 is a mutual waiver of consequential damages that includes the Owner’s rental expenses and losses of use, income and profit, and it states that it does not preclude liquidated damages (A201-2017 text, City of Rochester, NH copy). With §4.5 blank, a late opening can leave the owner with no agreed daily recovery.

What does a filled-in A101 look like?

The table is a worked example of the key A101 blanks for an assumed $2.4 million single-building job, written the way AIA’s instructions ask. Payment, retainage, insurance and bond entries copy values public owners used; the dates, sum, allowance, damages figure and fee are assumptions to replace. This is not legal advice: have counsel review the wording before signing.

SectionBlankExample entry you can adaptBasis
CoverAgreement datethe Second day of November in the year Two Thousand Twenty-SixForm asks for the date in words
CoverOwner[Exact legal name], a [state] limited liability company, [address]AIA: legal name and entity type
§3.1Commencement[X] A date set forth in a notice to proceed issued by the OwnerOne of 3 printed boxes
§3.3.1Substantial Completion[X] Not later than three hundred (300) calendar days from the date of commencement of the WorkAssumed; A201 §8.1.4 days are calendar days
§4.1Contract SumTwo Million Four Hundred Thousand Dollars and Zero Cents ($2,400,000.00)Assumed
§4.3AllowancesExterior signage: $25,000.00Assumed
§4.5Liquidated damages$1,250.00 per calendar day for each day Substantial Completion is late, subject to adjustments of the Contract TimeWorksheet below
§5.1.3Payment datesReceived not later than the last day of a month; paid not later than the last day of the following month; late applications paid within thirty (30) daysSouthcentral Foundation draft
§5.1.7.1RetainageFive percent (5%)Southcentral Foundation draft
§5.1.7.1.1Items not retainedGeneral conditions; insurance premiumsThe form’s own examples: general conditions, insurance
§5.1.7.2ReductionNo retainage on Applications after the Work is 50% complete, if the Architect finds progress satisfactory and the surety consents on AIA G707AAIA instructions
§6.1Initial Decision MakerLeave blank (Architect), or name an independent person not a partyA101 §6.1
§6.2Binding dispute[X] Litigation in a court of competent jurisdictionBox Southcentral Foundation checked
§7.1.1Termination fee$24,000.00 if terminated before the Work is 50% complete; $12,000.00 afterAssumed amounts; declining shape per AIA instructions
Ex. A §A.3.2.2.1General liability$1,000,000 each occurrence; $2,000,000 general aggregateAnderson County, TX, 2026
Ex. A §A.3.2.3Auto liability$1,000,000 per accidentAnderson County, TX, 2026
Ex. A §A.3.4BondsPayment Bond 100%; Performance Bond 100%, on AIA A312Anderson County, TX, 2026

How do owners show edits to the printed form?

Owners who change printed text, not just blanks, show it. AIA software prints a vertical line in the margin where the author added or deleted text and produces an Additions and Deletions Report (Anderson County Exhibit A). The University of Wisconsin System’s 2025 A101 deleted §4.2 alternates and §5.1.3 and wrote “None” in §4.5 (UW System A101, March 2025).

Bidders should ask for that report before pricing, because a deleted payment clause moves the timing into the general conditions. Where those edits belong in a bid review is set out in how to compare construction bids line by line.

How do the A101 payment dates and retainage work?

Section 5.1.3 sets three numbers: the day of the month the Architect must receive an Application for Payment, the day the Owner pays, and a period for late applications. AIA’s instructions say the last day of billed work should be at least 14 days before the payment date, because A201-2017 §9.4.1 gives the Architect 7 days to certify.

AIA instructions page with the section 5.1.3 guidance on a 14-day gap before the payment date boxed
AIA’s own instruction for §5.1.3: the last day of work in an application should be no less than 14 days before the payment date, allowing 7 days for the Architect. Source: AIA Contract Documents, Instructions: A101-2017, Article 5, accessed November 1, 2026.

The calendar below runs one cycle on the Southcentral Foundation fill-ins, with October 2026 work and the A201-2017 clocks. Section 8.1.4 of A201-2017 makes every day a calendar day, so weekends count (A201-2017 text).

DayDateEventRule
Day 0Sat Oct 31, 2026Application for Payment received by the ArchitectA101 5.1.3 fill-in: not later than the last day of the month
Day 7Sat Nov 7, 2026Architect certifies, certifies in part or withholdsA201-2017 9.4.1: within 7 days of receipt
Day 30Mon Nov 30, 2026Owner payment dueA101 5.1.3 fill-in: not later than the last day of the next month
Day 33Thu Dec 3, 2026Due date for an application received late, on Nov 3A101 5.1.3 fill-in: 30 days after the Architect receives it
Day 37Mon Dec 7, 2026Subs paid if owner paid Nov 30; if unpaid, 7 days lateA201-2017 9.6.2 and 9.7
Day 44Mon Dec 14, 2026Earliest work stoppage after 7 days’ written noticeA201-2017 9.7
Worked A101 payment calendar for October 2026 work One A101 payment cycle for October 2026 work (calendar days) Fill-ins as in the Southcentral Foundation A101 draft; clocks from A201-2017. Example dates. Day 0 Sat Oct 31, 2026 Application for Payment received by the Architect A101 5.1.3 fill-in: not later than the last day of the month Day 7 Sat Nov 7, 2026 Architect certifies, certifies in part or withholds A201-2017 9.4.1: within 7 days of receipt Day 30 Mon Nov 30, 2026 Owner payment due A101 5.1.3 fill-in: not later than the last day of the next month Day 33 Thu Dec 3, 2026 Due date for an application received late, on Nov 3 A101 5.1.3 fill-in: 30 days after the Architect receives it Day 37 Mon Dec 7, 2026 Subs paid if owner paid Nov 30; if unpaid, 7 days late A201-2017 9.6.2 and 9.7 Day 44 Mon Dec 14, 2026 Earliest work stoppage after 7 days’ written notice A201-2017 9.7
With Southcentral Foundation’s §5.1.3 fill-ins, October 2026 work is paid by Nov 30, and an unpaid contractor can stop work no earlier than Dec 14 under A201-2017 §9.7. Example dates; sources: Southcentral Foundation A101 draft and A201-2017, accessed November 1, 2026.

Each application is priced against the schedule of values, which §5.1.4 says must allocate the entire Contract Sum. How to build those lines is covered in our schedule of values guide, and the AIA pay form that carries them is walked through in our AIA G702 guide.

How much retainage should A101 say?

A101-2017 prints no retainage rate: §5.1.7.1 is a blank with the note that retainage “may be limited by governing law”. Public copies show 10% at Oakton Community College in 2019 and 5% in the Southcentral Foundation draft. On public work, 30 of the 46 jurisdictions with a percentage limit cap retainage at 5%, including California under Public Contract Code 7201.

The arithmetic shows what the rate does to cash. On the assumed $2.4 million job billed in 8 equal $300,000 applications, 5% retainage holds $120,000 at Substantial Completion, 10% holds $240,000, and 10% cut to 5% after the halfway point holds $180,000. Statutory caps and 50% reduction rules by state are in our prompt payment and retainage tracker.

ApplicationWork certifiedHeld at 5% (cumulative)Held at 10% (cumulative)10%, then 5% after 50% (cumulative)
Month 1$300,000$15,000$30,000$30,000
Month 2$300,000$30,000$60,000$60,000
Month 3$300,000$45,000$90,000$90,000
Month 4$300,000$60,000$120,000$120,000
Month 5$300,000$75,000$150,000$135,000
Month 6$300,000$90,000$180,000$150,000
Month 7$300,000$105,000$210,000$165,000
Month 8$300,000$120,000$240,000$180,000
Retainage held on an assumed $2.4 million A101 jobLine chart: retainage held reaches $240,000 at 10%, $180,000 at 10% cut to 5% halfway, and $120,000 at 5%050,000100,000150,000200,000250,000$Month 1Month 2Month 3Month 4Month 5Month 6Month 7Month 810% throughout10%, then 5% after 50%5% throughout
On an assumed $2.4 million job, 10% retainage holds $240,000 by Substantial Completion, twice the $120,000 held at 5%. Source: CB&C arithmetic on A101-2017 §5.1.7, November 2026.

Release happens at Substantial Completion under §5.1.7.3, when the Contractor may bill the retainage withheld, less any conditions the owner wrote in. AIA’s instructions say surety consent is needed before reducing or releasing retainage on a bonded job, using AIA G707A (AIA instructions §5.1.7.2 and §5.1.7.3).

How do you set liquidated damages in Section 4.5?

Section 4.5 asks for the terms of liquidated damages: a daily amount the Contractor owes for each day Substantial Completion is late. AIA’s instructions say the amount must be a reasonable estimate of the Owner’s actual loss, not a penalty, and that Owner’s counsel should draft it. Build it from your own daily costs, as in this worksheet with assumed inputs.

Daily lossAssumed inputArithmeticPer day
Lost net rent on the new space12,000 sq ft at $30.00 per sq ft per year12,000 x $30.00 / 365$986.30
Extended contract administration by the Architect$250.00 per dayFee quote$250.00
Total estimated loss$986.30 + $250.00$1,236.30
Amount written into §4.5Rounded$1,250.00
30 days late30 x $1,250.00$37,500.00

Keep the file that supports each input, since the estimate is what separates liquidated damages from a penalty. Public owners handle §4.5 differently: the Southcentral Foundation draft left the rate as “$TBD per day” set per project and allowed time extensions for delayed materials, while the UW System 2025 form wrote “None” (Southcentral Foundation draft).

A201-2017 §15.1.1 also says the Owner does not have to file a Claim to impose liquidated damages under the Contract Documents. Pair a §4.5 rate with a realistic §3.3.1 date, because a 300-day schedule with no float turns every weather day into a dispute.

What goes in Exhibit A, Insurance and Bonds?

Exhibit A sets who insures what and for how much. The Owner buys builder’s risk property insurance on an all-risks completed value form of at least the initial Contract Sum unless a checked box moves it to the Contractor; the Contractor’s liability limits and the bond penal sums are blanks. The table follows the 2026 Anderson County, Texas copy (A101-2017 Exhibit A).

SectionWhat it setsFill-inAnderson County, TX entry (2026)
§A.2.3.1Owner’s builder’s risk, replacement cost, at least the initial Contract Sum plus ModificationsPrinted; no amount blankKept as printed
§A.2.3.1.1Causes of loss: fire, explosion, theft, vandalism, malicious mischief, collapse, earthquake, flood, windstormSub-limitsSub-limit line deleted
§A.2.3.3Existing structure cover during remodeling or additionsPrintedDeleted
§A.2.4.1 to §A.2.4.7Optional owner cover: loss of use, ordinance or law, expediting, extra expense, civil authority, ingress or egress, soft costsCheck boxes and limitsDeleted
§A.3.1.3Additional insured on ISO forms CG 20 10 07 04 and CG 20 37 07 04PrintedKept
§A.3.2.2.1Commercial general liability, occurrence formEach occurrence; general aggregate; products-completed operations aggregate$1,000,000; $2,000,000; products line deleted
§A.3.2.3Automobile liabilityPer accident$1,000,000
§A.3.2.5Workers’ compensationStatutory limitsStatutory
§A.3.2.6Employers’ liabilityEach accident; each employee; policy limitDeleted
§A.3.2.8Professional liability, if the Contractor provides professional servicesPer claim; aggregate$1,000,000; $1,000,000
§A.3.3.2.2Railroad protective liability, Work within 50 feet of railroad propertyBox and limitsDeleted
§A.3.4Payment and performance bondsPenal sum of each100% each, on AIA A312

AIA’s exhibit FAQ says the same exhibit serves A101, A102 and A103, while A133 uses it as Exhibit B (AIA Insurance and Bonds Exhibit FAQ). Who should carry builder’s risk, and when the §A.3.3.2.1 box makes sense, is covered in our builder’s risk insurance guide. How sureties price the 100% bonds in §A.3.4 is in our construction surety bond data.

This page describes a standard form and is not insurance or legal advice. AIA recommends reviewing Exhibit A together with A201-2017 Article 11 with an insurance broker and counsel; ask the broker to confirm each limit is available at a stated premium before bid day.

A101 vs A102, A103, A133 and A141: which agreement fits?

Pick A101 when the price is fixed before work starts and the drawings define the full scope. Use A102 or A103 when the owner pays actual cost plus a fee, A133 when a construction manager prices the job during design, A141-2024 for design-build, and A104 or A105 for smaller work. All seven sell for $179.99 for one-time use (AIA store, November 2026).

AgreementBasis of paymentGeneral conditionsBest fit, per AIASource
A101-2017Stipulated sum (fixed price)A201-2017Large design-bid-build job, scope defined at signingAIA A101 page
A102-2017Cost of the Work plus a fee, with a guaranteed maximum price (GMP)A201-2017Price develops with design; owner wants a capAIA A102 page
A103-2017Cost of the Work plus a fee, no GMPA201-2017Cost not fully known when work startsAIA A103 page
A104-2017Stipulated sum or cost plus, abbreviated formBuilt into the formWork of limited scopeAIA A104 page
A105-2017Stipulated sum, short formBuilt into the formResidential or small commercial workAIA A105 page
A133-2019Cost plus a fee with a GMP set by amendmentA201-2017; insurance in Exhibit BConstruction manager as constructor joins during designAIA A133 page
A141-2024Contract Sum set by the Exhibit B Design-Build AmendmentIts own design-build termsOne firm designs and builds; replaced A141-2014AIA A141-2024 summary
IfUseThreshold or reasonSource
Drawings are complete and the price is fixed by bidA101-2017 + A201-2017 + Exhibit AFull scope defined at signingAIA A101 page
Job is of limited scopeA104-2017AIA’s abbreviated formAIA A101 summary
Job is small commercial or residentialA105-2017AIA’s short formAIA A101 summary
Price develops with design and you want a capA102-2017Cost plus fee, GMPAIA A102 page
Cost is unknown and you accept no capA103-2017Cost plus fee, no GMPAIA A103 page
A construction manager prices during designA133-2019GMP binds when the amendment is signedAIA A133 page
One firm designs and buildsA141-2024Contract Sum set in Exhibit BAIA A141-2024 summary
Your subcontract must flow down A101 termsA401-2017Must be modified if used with A104 or A105AIA A401 page
Which AIA owner-contractor agreement fits: A101, A102, A103, A104, A105, A133 or A141 Which AIA owner-contractor agreement fits your project? Source: AIA Contract Documents store pages and help summaries, accessed November 2026 Is the full scope defined and the price fixed when you sign? Is the job small or of limited scope? Yes A104-2017 or A105-2017 short forms Yes A101-2017 + A201-2017 + Exhibit A No Will one firm design and build? No A141-2024 Contract Sum set in Exhibit B Yes Does a construction manager join during design? No A133-2019 GMP amendment Yes Want a guaranteed maximum price (GMP)? No A102-2017 cost plus fee, GMP Yes A103-2017 cost plus fee, no GMP No
A fixed price on a fully defined scope points to A101-2017; cost-plus, CM at risk and design-build point to A102, A103, A133-2019 or A141-2024. Source: AIA Contract Documents store pages and summaries, accessed November 1, 2026.

The trade-off between fixed price and the other methods is laid out in design-build vs design-bid-build. When a construction manager will carry the price from design to a GMP, the A133-2019 route is explained in our guide to construction management at risk.

How much does AIA A101 cost, and which edition is current?

As of November 1, 2026, AIA Contract Documents sells A101 for $179.99 as a one-time use license, and A201-2017 for another $179.99. A101-2017 is the current edition, and its copyright line lists 16 editions since 1915. AIA has published no 2027 A101, though it wrote in April 2022 that A201 “will be updated again in 2027” (AIA Contract Documents).

The A101 store page says Exhibit A “is required to establish insurance and bond provisions” but does not say whether it is billed separately, so confirm with AIA before budgeting. The same page offers an unlimited subscription covering 300+ documents with no published price (AIA A101 store page).

Public bid copies are not free templates. The Anderson County copy states it is licensed for one-time use only, and AIA’s list still lists A201-2007 beside A201-2017 (AIA list of current documents). A101-2017 adopts A201-2017 by name, so check that both documents in your set carry the 2017 year.

The retainage percentage you write into the agreement is explained month by month in our guide to retainage in construction.

Exhibit A §A.3.1.3 asks for ISO CG 20 10 07 04 and CG 20 37 07 04; what those forms do and do not cover is set out in our additional insured guide.

How we compiled this

In November 2026 we read 4 public-owner copies of A101-2017 and its Exhibit A (Oakton Community College, the University of Wisconsin System, Southcentral Foundation and Anderson County, Texas), the A201-2017 text posted by the City of Rochester, NH, 4 AIA help articles, 2 AIA articles and 8 AIA store pages. Prices are list prices shown to a logged-out visitor on November 1, 2026. Worked-example dates, sums and damages inputs are assumptions and are labelled as such; we did not buy documents or reproduce AIA text beyond short quotes.

Frequently asked questions

Is AIA A101 free?

No. AIA Contract Documents sells A101-2017 for $179.99 as a one-time use license, and A201-2017 costs another $179.99 (AIA store, November 2026). Copies posted with public bids, such as Anderson County, Texas’s 2026 Exhibit A, are licensed for one-time use by that owner and are not reusable templates for your project.

What is the difference between AIA A101 and A201?

A101-2017 is the agreement: parties, dates, Contract Sum, payment dates, retainage, the dispute box and the termination fee. A201-2017 is the general conditions in 15 articles that A101 adopts by reference, covering changes, payment procedure, claims, insurance framework and termination. You sign A101; A201 rides along with it.

What is the difference between AIA A101 and A102?

A101-2017 pays a stipulated sum, a fixed price agreed before work starts. A102-2017 pays the Cost of the Work plus a fee, capped by a guaranteed maximum price. Both use A201-2017 and the same Exhibit A for insurance and bonds, and both sell for $179.99 per use (AIA store, November 2026).

What happens if no dispute resolution box is checked in A101?

Claims go to litigation. Section 6.2 of A101-2017 says that if the Owner and Contractor do not select a binding dispute method, or later agree in writing to another one, Claims are resolved in a court of competent jurisdiction. Mediation under A201-2017 Article 15 still comes first.

Does AIA A101 require retainage?

No rate is printed. Section 5.1.7.1 of A101-2017 is a blank for a percentage or amount, with a note that governing law may limit it. Public owners have written 10% and 5%, and 30 of 46 jurisdictions with a percentage limit cap public retainage at 5% (CB&C tracker, October 2026).

Is A101-2017 the latest version?

Yes. As of November 2026, AIA’s current list shows A101-2017, and its copyright line lists 16 editions since 1915. AIA wrote in April 2022 that A201 will be updated again in 2027 but has published no new A101. Check that your A101 and A201 both carry the 2017 year.

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.