AIA A101 is the American Institute of Architects’ fixed-price owner-contractor agreement: the 2017 edition adopts the A201-2017 general conditions, puts insurance and bonds in Exhibit A, and sells for $179.99 per use (AIA, November 2026).
Key takeaways
- A101-2017 has 9 articles plus Exhibit A, and the owner’s real decisions sit in Articles 3 to 7: dates, Contract Sum, payment dates, retainage, liquidated damages, the dispute box and the termination fee (AIA A101 instructions).
- Six blanks have a printed fallback: commencement on the Agreement date (§3.1), monthly applications (§5.1.2), final payment 30 days after the final Certificate (§5.2.2), the local legal interest rate (§5.3), the Architect as Initial Decision Maker (§6.1) and litigation (§6.2) (A101-2017, Oakton Community College copy).
- AIA’s rule for §5.1.3: the last day of work in an Application for Payment should be at least 14 days before the payment date, because A201-2017 §9.4.1 gives the Architect 7 days to certify (AIA instructions).
- A101 prints no retainage rate. Public owners filled in 10% (Oakton, 2019) and 5% (Southcentral Foundation draft), and 30 of 46 jurisdictions with a percentage limit cap public retainage at 5%.
- Exhibit A makes the Owner buy builder’s risk on an all-risks completed value form of at least the initial Contract Sum unless a box shifts it; Anderson County, Texas set $1,000,000 per occurrence, $2,000,000 aggregate and 100% bonds in 2026 (Exhibit A copy).
- A101’s copyright line lists 16 editions since 1915 and the 2017 edition is current; AIA said in 2022 that A201 “will be updated again in 2027” (AIA, April 2022).
| Key number | What it means | Source |
|---|---|---|
| $179.99 | One-time use license for A101, and the same again for A201-2017 | AIA store, Nov 2026 |
| 9 + 1 | Articles in A101-2017, plus Exhibit A, Insurance and Bonds | A101-2017 copy |
| 14 days | Minimum gap AIA suggests between the last day of billed work and the payment date | AIA instructions §5.1.3 |
| 7 days | Time the Architect has to certify an Application for Payment | A201-2017 §9.4.1 |
| 30 days | Final payment after the final Certificate for Payment, if §5.2.2 is left as printed | A101 §5.2.2 |
| 10 days | Notice needed to change the Owner’s or Contractor’s representative | A101 §8.4 |
| 5% | Public retainage cap in 30 of 46 jurisdictions with a percentage limit | CB&C tracker, Oct 2026 |
What is AIA A101 and when do you use it?
AIA A101-2017 is the Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum. AIA says to use it on large design-bid-build projects where the full scope is defined at signing and the price is fixed by bid or negotiation (AIA store page). It is not a full contract alone: A201-2017 and Exhibit A complete it.
The split between the three documents is practical. A101 holds the deal: parties, dates, the Contract Sum, payment dates, retainage, the dispute box and the termination fee. A201-2017 holds the procedures in 15 articles, and the printed A101 cover says not to use it with other general conditions unless the form is modified (A101-2017 cover note). Those 15 articles, with their claim and payment deadlines, are covered in our guide to the AIA A201 general conditions.
A101 is one of the seven AIA owner-builder agreements compared below, each sold at $179.99, and AIA’s store pairs it with A201, A401, G702, G703 and the G901 to G904 lien waiver forms. How those forms fit into the A to G series, and which go together for each delivery method, is mapped in our guide to AIA contract documents.
What does each article of A101-2017 cover?
A101-2017 has nine articles and one exhibit. Articles 1, 2 and 9 define the Contract Documents and the Work; Articles 3 to 8 hold the fill-in points that set time, money and risk; Exhibit A sets insurance and bonds. The table lists each article, what the owner fills in and the section numbers, taken from a public bid copy of the form (A101-2017, Oakton Community College).
| Article | Title | What the owner fills in | Sections |
|---|---|---|---|
| 1 | The Contract Documents | No blanks: lists what forms the Contract | Agreement, conditions, drawings, specifications, addenda, Modifications |
| 2 | The Work of This Contract | No blanks: Work as shown in the Contract Documents | Work by others goes in the Supplementary Conditions |
| 3 | Date of Commencement and Substantial Completion | Commencement box; completion date or calendar days | §3.1, §3.3.1, phased dates §3.3.2 |
| 4 | Contract Sum | Contract Sum; alternates; allowances; unit prices; liquidated damages | §4.1 to §4.5; bonus or incentive §4.6 |
| 5 | Payments | Payment dates; retainage percent; final payment; interest rate | §5.1.2, §5.1.3, §5.1.7, §5.2.2, §5.3 |
| 6 | Dispute Resolution | Initial Decision Maker; arbitration or litigation box | §6.1, §6.2 |
| 7 | Termination or Suspension | Termination for convenience fee | §7.1.1, tied to A201 §14.4.3 |
| 8 | Miscellaneous Provisions | Representatives; insurance and bonds (Exhibit A); electronic notice | §8.2, §8.3, §8.5, §8.6, other provisions |
| 9 | Enumeration of Contract Documents | Drawings, specifications, addenda, other exhibits | §9.1.1 to §9.1.9; E203-2013 and E204-2017 by date |
| Exhibit A | Insurance and Bonds | Owner’s property insurance; Contractor’s coverage limits; Bond penal sums | Articles A.1 to A.4 |
The 2017 edition moved most of the owner’s choices into fill points. AIA lists the changes from A101-2007 as a three-box commencement date (§3.1), a completion date or day count (§3.3.1), new fill points for liquidated damages (§4.5) and bonuses (§4.6), a three-part retainage section (§5.1.7) and a termination fee (§7.1.1), with insurance moved to Exhibit A (AIA A101-2017 summary).
What happens if you leave an A101 blank empty?
Six A101 blanks have a printed fallback, so leaving them empty is itself a choice: the Agreement date starts the clock, applications run monthly, final payment falls 30 days after the final Certificate, late payments earn the local legal rate, the Architect decides claims first and disputes go to court. Retainage, liquidated damages and the termination fee have no fallback number.
| Blank | If left empty | What it means for the owner | Section |
|---|---|---|---|
| Commencement | Date of the Agreement | Contract Time starts at signing, even if permits are not issued | A101 §3.1 |
| Application period | One calendar month ending on the last day of the month | Monthly billing on G702 and G703 | A101 §5.1.2 |
| Final payment | 30 days after the Architect’s final Certificate for Payment | Owner’s last deadline to release the balance | A101 §5.2.2 |
| Interest on late payment | Legal rate prevailing where the Project is located | A state prompt payment statute may also apply; Oakton cited 50 ILCS 505 | A101 §5.3 |
| Initial Decision Maker | The Architect | The owner’s design professional rules first on every Claim | A101 §6.1 |
| Binding dispute method | Litigation in a court of competent jurisdiction | No arbitration unless a box is checked or both agree in writing | A101 §6.2 |
| Liquidated damages | None: §4.5 reads “if any” | Lost rent and lost use are waived under A201 §15.1.7 | A101 §4.5 |
| Retainage | No printed percentage | Agree a rate within any statutory cap | A101 §5.1.7.1 |
| Termination fee | None stated | Owner pays Work executed and termination costs only | A201 §14.4.3 |
The liquidated damages row is the costly one. A201-2017 §15.1.7 is a mutual waiver of consequential damages that includes the Owner’s rental expenses and losses of use, income and profit, and it states that it does not preclude liquidated damages (A201-2017 text, City of Rochester, NH copy). With §4.5 blank, a late opening can leave the owner with no agreed daily recovery.
What does a filled-in A101 look like?
The table is a worked example of the key A101 blanks for an assumed $2.4 million single-building job, written the way AIA’s instructions ask. Payment, retainage, insurance and bond entries copy values public owners used; the dates, sum, allowance, damages figure and fee are assumptions to replace. This is not legal advice: have counsel review the wording before signing.
| Section | Blank | Example entry you can adapt | Basis |
|---|---|---|---|
| Cover | Agreement date | the Second day of November in the year Two Thousand Twenty-Six | Form asks for the date in words |
| Cover | Owner | [Exact legal name], a [state] limited liability company, [address] | AIA: legal name and entity type |
| §3.1 | Commencement | [X] A date set forth in a notice to proceed issued by the Owner | One of 3 printed boxes |
| §3.3.1 | Substantial Completion | [X] Not later than three hundred (300) calendar days from the date of commencement of the Work | Assumed; A201 §8.1.4 days are calendar days |
| §4.1 | Contract Sum | Two Million Four Hundred Thousand Dollars and Zero Cents ($2,400,000.00) | Assumed |
| §4.3 | Allowances | Exterior signage: $25,000.00 | Assumed |
| §4.5 | Liquidated damages | $1,250.00 per calendar day for each day Substantial Completion is late, subject to adjustments of the Contract Time | Worksheet below |
| §5.1.3 | Payment dates | Received not later than the last day of a month; paid not later than the last day of the following month; late applications paid within thirty (30) days | Southcentral Foundation draft |
| §5.1.7.1 | Retainage | Five percent (5%) | Southcentral Foundation draft |
| §5.1.7.1.1 | Items not retained | General conditions; insurance premiums | The form’s own examples: general conditions, insurance |
| §5.1.7.2 | Reduction | No retainage on Applications after the Work is 50% complete, if the Architect finds progress satisfactory and the surety consents on AIA G707A | AIA instructions |
| §6.1 | Initial Decision Maker | Leave blank (Architect), or name an independent person not a party | A101 §6.1 |
| §6.2 | Binding dispute | [X] Litigation in a court of competent jurisdiction | Box Southcentral Foundation checked |
| §7.1.1 | Termination fee | $24,000.00 if terminated before the Work is 50% complete; $12,000.00 after | Assumed amounts; declining shape per AIA instructions |
| Ex. A §A.3.2.2.1 | General liability | $1,000,000 each occurrence; $2,000,000 general aggregate | Anderson County, TX, 2026 |
| Ex. A §A.3.2.3 | Auto liability | $1,000,000 per accident | Anderson County, TX, 2026 |
| Ex. A §A.3.4 | Bonds | Payment Bond 100%; Performance Bond 100%, on AIA A312 | Anderson County, TX, 2026 |
How do owners show edits to the printed form?
Owners who change printed text, not just blanks, show it. AIA software prints a vertical line in the margin where the author added or deleted text and produces an Additions and Deletions Report (Anderson County Exhibit A). The University of Wisconsin System’s 2025 A101 deleted §4.2 alternates and §5.1.3 and wrote “None” in §4.5 (UW System A101, March 2025).
Bidders should ask for that report before pricing, because a deleted payment clause moves the timing into the general conditions. Where those edits belong in a bid review is set out in how to compare construction bids line by line.
How do the A101 payment dates and retainage work?
Section 5.1.3 sets three numbers: the day of the month the Architect must receive an Application for Payment, the day the Owner pays, and a period for late applications. AIA’s instructions say the last day of billed work should be at least 14 days before the payment date, because A201-2017 §9.4.1 gives the Architect 7 days to certify.

The calendar below runs one cycle on the Southcentral Foundation fill-ins, with October 2026 work and the A201-2017 clocks. Section 8.1.4 of A201-2017 makes every day a calendar day, so weekends count (A201-2017 text).
| Day | Date | Event | Rule |
|---|---|---|---|
| Day 0 | Sat Oct 31, 2026 | Application for Payment received by the Architect | A101 5.1.3 fill-in: not later than the last day of the month |
| Day 7 | Sat Nov 7, 2026 | Architect certifies, certifies in part or withholds | A201-2017 9.4.1: within 7 days of receipt |
| Day 30 | Mon Nov 30, 2026 | Owner payment due | A101 5.1.3 fill-in: not later than the last day of the next month |
| Day 33 | Thu Dec 3, 2026 | Due date for an application received late, on Nov 3 | A101 5.1.3 fill-in: 30 days after the Architect receives it |
| Day 37 | Mon Dec 7, 2026 | Subs paid if owner paid Nov 30; if unpaid, 7 days late | A201-2017 9.6.2 and 9.7 |
| Day 44 | Mon Dec 14, 2026 | Earliest work stoppage after 7 days’ written notice | A201-2017 9.7 |
Each application is priced against the schedule of values, which §5.1.4 says must allocate the entire Contract Sum. How to build those lines is covered in our schedule of values guide, and the AIA pay form that carries them is walked through in our AIA G702 guide.
How much retainage should A101 say?
A101-2017 prints no retainage rate: §5.1.7.1 is a blank with the note that retainage “may be limited by governing law”. Public copies show 10% at Oakton Community College in 2019 and 5% in the Southcentral Foundation draft. On public work, 30 of the 46 jurisdictions with a percentage limit cap retainage at 5%, including California under Public Contract Code 7201.
The arithmetic shows what the rate does to cash. On the assumed $2.4 million job billed in 8 equal $300,000 applications, 5% retainage holds $120,000 at Substantial Completion, 10% holds $240,000, and 10% cut to 5% after the halfway point holds $180,000. Statutory caps and 50% reduction rules by state are in our prompt payment and retainage tracker.
| Application | Work certified | Held at 5% (cumulative) | Held at 10% (cumulative) | 10%, then 5% after 50% (cumulative) |
|---|---|---|---|---|
| Month 1 | $300,000 | $15,000 | $30,000 | $30,000 |
| Month 2 | $300,000 | $30,000 | $60,000 | $60,000 |
| Month 3 | $300,000 | $45,000 | $90,000 | $90,000 |
| Month 4 | $300,000 | $60,000 | $120,000 | $120,000 |
| Month 5 | $300,000 | $75,000 | $150,000 | $135,000 |
| Month 6 | $300,000 | $90,000 | $180,000 | $150,000 |
| Month 7 | $300,000 | $105,000 | $210,000 | $165,000 |
| Month 8 | $300,000 | $120,000 | $240,000 | $180,000 |
Release happens at Substantial Completion under §5.1.7.3, when the Contractor may bill the retainage withheld, less any conditions the owner wrote in. AIA’s instructions say surety consent is needed before reducing or releasing retainage on a bonded job, using AIA G707A (AIA instructions §5.1.7.2 and §5.1.7.3).
How do you set liquidated damages in Section 4.5?
Section 4.5 asks for the terms of liquidated damages: a daily amount the Contractor owes for each day Substantial Completion is late. AIA’s instructions say the amount must be a reasonable estimate of the Owner’s actual loss, not a penalty, and that Owner’s counsel should draft it. Build it from your own daily costs, as in this worksheet with assumed inputs.
| Daily loss | Assumed input | Arithmetic | Per day |
|---|---|---|---|
| Lost net rent on the new space | 12,000 sq ft at $30.00 per sq ft per year | 12,000 x $30.00 / 365 | $986.30 |
| Extended contract administration by the Architect | $250.00 per day | Fee quote | $250.00 |
| Total estimated loss | $986.30 + $250.00 | $1,236.30 | |
| Amount written into §4.5 | Rounded | $1,250.00 | |
| 30 days late | 30 x $1,250.00 | $37,500.00 |
Keep the file that supports each input, since the estimate is what separates liquidated damages from a penalty. Public owners handle §4.5 differently: the Southcentral Foundation draft left the rate as “$TBD per day” set per project and allowed time extensions for delayed materials, while the UW System 2025 form wrote “None” (Southcentral Foundation draft).
A201-2017 §15.1.1 also says the Owner does not have to file a Claim to impose liquidated damages under the Contract Documents. Pair a §4.5 rate with a realistic §3.3.1 date, because a 300-day schedule with no float turns every weather day into a dispute.
What goes in Exhibit A, Insurance and Bonds?
Exhibit A sets who insures what and for how much. The Owner buys builder’s risk property insurance on an all-risks completed value form of at least the initial Contract Sum unless a checked box moves it to the Contractor; the Contractor’s liability limits and the bond penal sums are blanks. The table follows the 2026 Anderson County, Texas copy (A101-2017 Exhibit A).
| Section | What it sets | Fill-in | Anderson County, TX entry (2026) |
|---|---|---|---|
| §A.2.3.1 | Owner’s builder’s risk, replacement cost, at least the initial Contract Sum plus Modifications | Printed; no amount blank | Kept as printed |
| §A.2.3.1.1 | Causes of loss: fire, explosion, theft, vandalism, malicious mischief, collapse, earthquake, flood, windstorm | Sub-limits | Sub-limit line deleted |
| §A.2.3.3 | Existing structure cover during remodeling or additions | Printed | Deleted |
| §A.2.4.1 to §A.2.4.7 | Optional owner cover: loss of use, ordinance or law, expediting, extra expense, civil authority, ingress or egress, soft costs | Check boxes and limits | Deleted |
| §A.3.1.3 | Additional insured on ISO forms CG 20 10 07 04 and CG 20 37 07 04 | Printed | Kept |
| §A.3.2.2.1 | Commercial general liability, occurrence form | Each occurrence; general aggregate; products-completed operations aggregate | $1,000,000; $2,000,000; products line deleted |
| §A.3.2.3 | Automobile liability | Per accident | $1,000,000 |
| §A.3.2.5 | Workers’ compensation | Statutory limits | Statutory |
| §A.3.2.6 | Employers’ liability | Each accident; each employee; policy limit | Deleted |
| §A.3.2.8 | Professional liability, if the Contractor provides professional services | Per claim; aggregate | $1,000,000; $1,000,000 |
| §A.3.3.2.2 | Railroad protective liability, Work within 50 feet of railroad property | Box and limits | Deleted |
| §A.3.4 | Payment and performance bonds | Penal sum of each | 100% each, on AIA A312 |
AIA’s exhibit FAQ says the same exhibit serves A101, A102 and A103, while A133 uses it as Exhibit B (AIA Insurance and Bonds Exhibit FAQ). Who should carry builder’s risk, and when the §A.3.3.2.1 box makes sense, is covered in our builder’s risk insurance guide. How sureties price the 100% bonds in §A.3.4 is in our construction surety bond data.
This page describes a standard form and is not insurance or legal advice. AIA recommends reviewing Exhibit A together with A201-2017 Article 11 with an insurance broker and counsel; ask the broker to confirm each limit is available at a stated premium before bid day.
A101 vs A102, A103, A133 and A141: which agreement fits?
Pick A101 when the price is fixed before work starts and the drawings define the full scope. Use A102 or A103 when the owner pays actual cost plus a fee, A133 when a construction manager prices the job during design, A141-2024 for design-build, and A104 or A105 for smaller work. All seven sell for $179.99 for one-time use (AIA store, November 2026).
| Agreement | Basis of payment | General conditions | Best fit, per AIA | Source |
|---|---|---|---|---|
| A101-2017 | Stipulated sum (fixed price) | A201-2017 | Large design-bid-build job, scope defined at signing | AIA A101 page |
| A102-2017 | Cost of the Work plus a fee, with a guaranteed maximum price (GMP) | A201-2017 | Price develops with design; owner wants a cap | AIA A102 page |
| A103-2017 | Cost of the Work plus a fee, no GMP | A201-2017 | Cost not fully known when work starts | AIA A103 page |
| A104-2017 | Stipulated sum or cost plus, abbreviated form | Built into the form | Work of limited scope | AIA A104 page |
| A105-2017 | Stipulated sum, short form | Built into the form | Residential or small commercial work | AIA A105 page |
| A133-2019 | Cost plus a fee with a GMP set by amendment | A201-2017; insurance in Exhibit B | Construction manager as constructor joins during design | AIA A133 page |
| A141-2024 | Contract Sum set by the Exhibit B Design-Build Amendment | Its own design-build terms | One firm designs and builds; replaced A141-2014 | AIA A141-2024 summary |
| If | Use | Threshold or reason | Source |
|---|---|---|---|
| Drawings are complete and the price is fixed by bid | A101-2017 + A201-2017 + Exhibit A | Full scope defined at signing | AIA A101 page |
| Job is of limited scope | A104-2017 | AIA’s abbreviated form | AIA A101 summary |
| Job is small commercial or residential | A105-2017 | AIA’s short form | AIA A101 summary |
| Price develops with design and you want a cap | A102-2017 | Cost plus fee, GMP | AIA A102 page |
| Cost is unknown and you accept no cap | A103-2017 | Cost plus fee, no GMP | AIA A103 page |
| A construction manager prices during design | A133-2019 | GMP binds when the amendment is signed | AIA A133 page |
| One firm designs and builds | A141-2024 | Contract Sum set in Exhibit B | AIA A141-2024 summary |
| Your subcontract must flow down A101 terms | A401-2017 | Must be modified if used with A104 or A105 | AIA A401 page |
The trade-off between fixed price and the other methods is laid out in design-build vs design-bid-build. When a construction manager will carry the price from design to a GMP, the A133-2019 route is explained in our guide to construction management at risk.
How much does AIA A101 cost, and which edition is current?
As of November 1, 2026, AIA Contract Documents sells A101 for $179.99 as a one-time use license, and A201-2017 for another $179.99. A101-2017 is the current edition, and its copyright line lists 16 editions since 1915. AIA has published no 2027 A101, though it wrote in April 2022 that A201 “will be updated again in 2027” (AIA Contract Documents).
The A101 store page says Exhibit A “is required to establish insurance and bond provisions” but does not say whether it is billed separately, so confirm with AIA before budgeting. The same page offers an unlimited subscription covering 300+ documents with no published price (AIA A101 store page).
Public bid copies are not free templates. The Anderson County copy states it is licensed for one-time use only, and AIA’s list still lists A201-2007 beside A201-2017 (AIA list of current documents). A101-2017 adopts A201-2017 by name, so check that both documents in your set carry the 2017 year.
The retainage percentage you write into the agreement is explained month by month in our guide to retainage in construction.
Exhibit A §A.3.1.3 asks for ISO CG 20 10 07 04 and CG 20 37 07 04; what those forms do and do not cover is set out in our additional insured guide.
How we compiled this
In November 2026 we read 4 public-owner copies of A101-2017 and its Exhibit A (Oakton Community College, the University of Wisconsin System, Southcentral Foundation and Anderson County, Texas), the A201-2017 text posted by the City of Rochester, NH, 4 AIA help articles, 2 AIA articles and 8 AIA store pages. Prices are list prices shown to a logged-out visitor on November 1, 2026. Worked-example dates, sums and damages inputs are assumptions and are labelled as such; we did not buy documents or reproduce AIA text beyond short quotes.
Frequently asked questions
Is AIA A101 free?
No. AIA Contract Documents sells A101-2017 for $179.99 as a one-time use license, and A201-2017 costs another $179.99 (AIA store, November 2026). Copies posted with public bids, such as Anderson County, Texas’s 2026 Exhibit A, are licensed for one-time use by that owner and are not reusable templates for your project.
What is the difference between AIA A101 and A201?
A101-2017 is the agreement: parties, dates, Contract Sum, payment dates, retainage, the dispute box and the termination fee. A201-2017 is the general conditions in 15 articles that A101 adopts by reference, covering changes, payment procedure, claims, insurance framework and termination. You sign A101; A201 rides along with it.
What is the difference between AIA A101 and A102?
A101-2017 pays a stipulated sum, a fixed price agreed before work starts. A102-2017 pays the Cost of the Work plus a fee, capped by a guaranteed maximum price. Both use A201-2017 and the same Exhibit A for insurance and bonds, and both sell for $179.99 per use (AIA store, November 2026).
What happens if no dispute resolution box is checked in A101?
Claims go to litigation. Section 6.2 of A101-2017 says that if the Owner and Contractor do not select a binding dispute method, or later agree in writing to another one, Claims are resolved in a court of competent jurisdiction. Mediation under A201-2017 Article 15 still comes first.
Does AIA A101 require retainage?
No rate is printed. Section 5.1.7.1 of A101-2017 is a blank for a percentage or amount, with a note that governing law may limit it. Public owners have written 10% and 5%, and 30 of 46 jurisdictions with a percentage limit cap public retainage at 5% (CB&C tracker, October 2026).
Is A101-2017 the latest version?
Yes. As of November 2026, AIA’s current list shows A101-2017, and its copyright line lists 16 editions since 1915. AIA wrote in April 2022 that A201 will be updated again in 2027 but has published no new A101. Check that your A101 and A201 both carry the 2017 year.
Sources
- A101: Owner and Contractor Agreement, Stipulated Sum (store page, price, when to use), AIA Contract Documents, accessed November 1, 2026.
- Instructions: A101-2017, AIA Contract Documents help centre, accessed November 1, 2026.
- Summary: A101-2017, AIA Contract Documents help centre, accessed November 1, 2026.
- FAQs: Insurance and Bonds Exhibit, AIA Contract Documents help centre, accessed November 1, 2026.
- Summary: A141-2024, AIA Contract Documents help centre, accessed November 1, 2026.
- List of all current AIA Contract Documents, AIA Contract Documents, accessed November 1, 2026.
- Five Things You Didn’t Know About AIA Contract Documents (April 19, 2022), AIA Contract Documents, accessed November 1, 2026.
- A102, A103, A104, A105, A133-2019, A141-2024, A201-2017 and A401 store pages, AIA Contract Documents, accessed November 1, 2026.
- AIA Document A101-2017 (bid copy, produced April 12, 2019), Oakton Community College, accessed November 1, 2026.
- AIA Document A101-2017 with Exhibit A (draft produced February 4, 2022, posted December 2024), Southcentral Foundation, accessed November 1, 2026.
- AIA Document A101-2017 as modified (produced March 20, 2025), University of Wisconsin System, accessed November 1, 2026.
- AIA Document A101-2017 Exhibit A, Insurance and Bonds, AgriLife Facility (dated March 20, 2026), Anderson County, Texas, accessed November 1, 2026.
- AIA Document A201-2017 sample (Sections 8.1.4, 9.4.1, 9.6.2, 9.7, 14.4.3, 15.1.1, 15.1.7), City of Rochester, NH, accessed November 1, 2026.
- California Public Contract Code Section 7201 (retention proceeds), California Legislative Information, accessed October 8, 2026 (CB&C retainage tracker check).