Design-Build Contract: The Forms, Clauses and Pricing Compared

Commercial building under construction with exposed steel frame and a tower crane

A design-build contract is one agreement under which a single firm designs and builds your project, usually on AIA A141-2024, DBIA 525 or 530, or ConsensusDocs 410 or 415, priced as lump sum, cost plus fee or GMP.

Key takeaways

  • AIA’s current owner form is A141-2024, which replaced A141-2014; in the 2024 edition the Design-Build Amendment that fixes the price is Exhibit B, and Exhibit A is Insurance and Bonds (AIA A141-2024 summary).
  • AIA’s 2014 A142 design-builder and contractor agreement is not in the 2024 family; its store address now opens the A441 design-builder and subcontractor page (AIA store, checked November 21, 2026).
  • DBIA’s owner forms are 525 (lump sum) and 530 (cost plus fee with an optional GMP), both paired with the 535 general conditions, Third Edition, released in 2022 (DBIA, September 15, 2022); DBIA’s current 530 sample is dated 2024.
  • All three families leave copyright in the drawings with the design-builder by default and give the owner a license; only the timing and the trigger for losing it differ (A141-2024 §13.3, DBIA 530 §4.2, ConsensusDocs 410 §3.1.8).
  • A141-2024 sets three clocks owners miss: 21 days to give notice of a claim (§15.1.3.1), a one-year correction period (§12.2.2.1) and a 10-year outside limit on claims after Substantial Completion (§15.1.2) (A141-2024 public copy).

What is a design-build contract?

A design-build contract is a single prime agreement in which the owner hires one entity, the design-builder, to deliver both design services and construction. The design-builder then hires its own architect, engineers and trades. Under AIA A141-2024 §3.1.5, the design-builder answers to the owner for the acts and omissions of its Architect, Consultants and Subcontractors, which is the single point of responsibility owners buy (AIA A141-2024).

The contract is different from a design-bid-build construction contract in three ways. It starts before the design exists, so it carries the owner’s requirements instead of finished drawings. It usually prices the job in two steps: a fee for early design, then a Contract Sum once a proposal is accepted (A141-2024 §2.1 and §2.3). And it puts a design standard of care (§3.1.11) and a construction warranty (§3.1.12) in the same document. The broader delivery-method question, including how to judge firms, sits on our guide to how design-build contractors work and when the method fits.

Key numberWhat it controlsSource
17 articles, 3 exhibitsStructure of AIA A141-2024 (A Insurance and Bonds, B Design-Build Amendment, C Sustainable Projects)A141-2024 §17.1
10 itemsOwner’s Criteria blanks, §1.1.1 to §1.1.10, fixed as of the agreement dateA141-2024 §1.1
14 daysControl Estimate due after signing when the price is cost plus fee without a GMPA141-2024 §9.2.1
21 daysNotice of a claim before final paymentA141-2024 §15.1.3.1
1 yearCorrection period after Substantial Completion (AIA and DBIA)A141 §12.2.2.1, DBIA 535 §2.10
10 yearsOutside limit to start a claim after Substantial CompletionA141-2024 §15.1.2
$179.99AIA one-time license price for A141-2024, November 2026AIA store
5 offerorsFederal only: normal cap on the phase-two shortlist in two-phase design-buildFAR 36.303-1(a)(4)

Which standard forms are used: AIA A141 and A142, DBIA 500 series, ConsensusDocs 410 and 415?

Three US publishers sell standard design-build forms: AIA Contract Documents, the Design-Build Institute of America (DBIA) and ConsensusDocs, a coalition of industry associations. Each family has an owner agreement, a designer agreement and subcontract forms that pass the prime terms down. AIA rebuilt its design-build family in 2024 and DBIA in 2022; the newest public ConsensusDocs 410 guidance is the April 2017 guidebook, which says the form was updated in March 2017.

Family and editionOwner and design-builderDesign-builder and designerDesign-builder and tradesEarly or consultant formsSource
AIA, 2024 familyA141-2024 (traditional); A141PDB-2024 (progressive)B141-2024 (replaced B143-2014)A441-2024; A142-2014 was the 2014 builder formC141-2024 owner’s consultantAIA summary, AIA 2024 update
DBIA, 2022 editions525 lump sum; 530 cost plus fee, GMP option; 535 general conditions; 544 progressive540550/555 general contractor; 560/565 design-build sub; 570 sub520 preliminary agreementDBIA 2022 release
ConsensusDocs, 410 rev. 2017410 cost plus fee with GMP; 415 lump sum (requires 400 first); 411 progressive420450 sub; 460 design-build sub400 preliminary agreementConsensusDocs catalog, April 2026
Who signs what on a design-build project, by form familyWho signs what on a design-build project, by form familyOwner signs one prime agreement. Sources: AIA, DBIA and ConsensusDocs publications, accessed Nov 2026Ownerone prime agreementDesign-builderA141-2024 or DBIA 525/530 + 535or ConsensusDocs 410/415Architect / engineerAIA B141-2024DBIA 540, CD 420Trade subcontractorsAIA A441-2024DBIA 570, CD 450Builder, if separateAIA A142-2014 (2014 set)DBIA 550 or 555Before the prime agreement (optional)AIA C141-2024: owner hires its own consultant to write the Owner’s Criteria or bridging documents.DBIA 520 and ConsensusDocs 400: preliminary agreements that pay the design-builder for early designbefore a price is fixed. ConsensusDocs 415 (lump sum) requires the 400 first.The owner’s consultant has no contract with the design-builder; it advises the owner only.
The owner signs one prime agreement; the design-builder signs the designer and trade forms. Form numbers from AIA, DBIA and ConsensusDocs publications, accessed November 2026.

On A142 specifically: AIA’s A142-2014 summary describes it as the agreement between a design-builder and a separate construction contractor, with four exhibits (Terms and Conditions, Insurance and Bonds, Preconstruction Services, Cost of the Work). The 2024 family list does not include an A142, and the A441-2024 subcontract now incorporates A141-2024 by reference. If a design-builder offers you A142-2014 paperwork for its builder, ask why it is using a 2014 form under a 2024 prime agreement.

How do the forms compare clause by clause?

The forms cover the same 12 clause topics with different defaults, and the section numbers below let you find each one in your copy. AIA numbers come from a public copy of A141-2024; DBIA numbers from public copies of the 2022 Third Edition 525/530 and 535 (DBIA’s current sample is dated 2024); ConsensusDocs numbers from the publisher’s 2017 comparison chart and 2017 guidebook, so confirm them against the revision you buy.

ClauseAIA A141-2024DBIA 525/530 + 535 (2022)ConsensusDocs 410 (2017 rev.)
Owner’s requirementsOwner’s Criteria §1.1; reliance and Modification §1.5Owner’s Project Criteria and Basis of Design Documents, 535 §1.2; reliance on design specs 530 §3.4Owner’s Program, Exhibit B (guidebook §2.4.2)
When price is fixedProposal §4.4, then Design-Build Amendment §4.5 (Exhibit B)525: at signing; 530: GMP at signing or later, §6.6GMP Proposal when documents allow, §3.2
Pricing optionsStipulated sum, cost plus fee, cost plus fee with GMP (Exhibit B)Lump sum (525); cost plus fee with GMP option (530)Cost plus fee with GMP (410); lump sum (415)
Design standard of care§3.1.11: skill and care of design-builders in the same locality535 §2.3: care and skill of the profession at the same time and localityNo defined standard; Art. 3 ‘reasonable skill and judgment’
Construction warranty§3.1.12: Construction Work new, good quality, free from defects535 §2.9: may be limited to a time frame set in the Agreement§3.8: materials and equipment; manufacturer warranties pass through
Correction period1 year after Substantial Completion, §12.2.2.11 year, 535 §2.101 year correction clause
Insurance and bondsArt. 11 and Exhibit A; §3.1.16535 Art. 5; §5.1.2 delete design-build exclusionsArt. 10 insurance; §11.7 bonds; bonds 471 to 473
Ownership of documentsArt. 13; license on signing, §13.3530 Art. 4; license on payment in full, §4.2§3.1.8 check-the-box copyright; owner gets tangible documents on payment
ChangesChange Order §6.2; Change Directive §6.3Change Order 535 §9.1; Work Change Directive §9.2; minor changes §9.3Art. 9; concealed conditions §9.4
Consequential damagesMutual waiver §15.1.7Mutual waiver with carve-outs, 535 §10.5Limited waiver; parties list exceptions, §6.5
Termination for convenience§14.1.5 (7 days’ notice, before Amendment) and §14.2.4; fees §14.1.7535 §11.6 (10 days’ notice); amount in 530 Art. 8Art. 12, §12.3
DisputesMediation §15.3; arbitration or litigation box §1.3.2535 Art. 10; arbitration §10.3Art. 13: optional dispute mitigation, else mediation

What older summaries get wrong

Much of what ranks for this topic was written against the 2014 AIA and 2010 DBIA editions. Four claims in circulation no longer match the forms an owner buys in November 2026.

Claim in circulationWhat the current form saysPrimary source
A141’s Exhibit A is the Design-Build Amendment (AIA’s own 2024 update page still says so)In A141-2024 Exhibit A is Insurance and Bonds; Exhibit B is the Design-Build Amendment (§17.1)A141-2024, AIA summary
A142 is AIA’s current design-builder and contractor formThe 2024 family lists A441-2024 for trades; the A142-2014 store link redirects to A441AIA 2024 update, AIA store
A141 makes the design-builder warrant its design is defect-free (2017 chart, written on A141-2014)A141-2024 adds a design standard of care (§3.1.11) and warrants the Construction Work (§3.1.12)A141-2024 vs 2017 chart
The owner owns the drawings because it paid for themAIA, DBIA and ConsensusDocs keep copyright with the design-builder unless the parties transfer itA141 §13.1, DBIA 530 §4.1, CD 410 §3.1.8

How are the owner’s criteria and basis of design attached?

The owner’s requirements are written into the agreement itself or attached as an exhibit, and that choice decides what the price is measured against. A141-2024 §1.1 has 10 blanks: program, design requirements, physical characteristics, sustainability, BIM, budget, milestones, required consultants, other criteria and fast-track needs. The criteria are fixed at signing, and §1.5 requires a Modification adjusting schedule, services and compensation if they change materially.

AIA A141-2024: from Owner’s Criteria to the one-year correction periodAIA A141-2024: from Owner’s Criteria to the one-year correction periodSection numbers from a public copy of AIA Document A141-2024, accessed November 21, 2026§1.1Owner’s Criteria fixed at signingprogram, design requirements, budget, milestones (1.1.1 to 1.1.10)§4.2Design-builder evaluates the criteriaflags conflicts; changes need a Modification (§1.5)§4.3Preliminary Designowner gives written consent to proceed (§4.3.2)§4.4Design-Builder’s Proposaldrawings list, assumptions, Contract Sum, schedule, acceptance date§4.5Design-Build Amendment (Exhibit B)fixes Contract Sum and Contract Time; no Contract Sum costs before it§5.1 to 5.2Construction Documents and Construction Workchanges by Change Order (§6.2) or Change Directive (§6.3)§9.8Substantial Completionstarts the correction period and the claims clock§12.2.2One-year correction period10-year outside limit on claims (§15.1.2)
The A141-2024 sequence: criteria fixed at signing (§1.1), price fixed only at the Design-Build Amendment (§4.5). Source: public copy of AIA A141-2024, accessed November 21, 2026.

DBIA uses two layers. The Owner’s Project Criteria state what the owner needs; the Basis of Design Documents are the design-builder’s documents the price rests on, defined in DBIA 535 §1.2 and listed in the GMP exhibit or proposal under 530. Under 530 §3.4, if your criteria include prescriptive design specifications, the design-builder may rely on them and can claim time and money when they are wrong, yet it still owes the performance requirements (DBIA 530, 2022).

  1. Write performance requirements (loads, energy targets, occupancy, finishes by room type) rather than design details, so the design-builder owns the design.
  2. List each document in A141-2024 §1.1 or the DBIA Owner’s Project Criteria by title and date; an undated reference invites a later version fight.
  3. Attach the geotechnical report and survey as information, not criteria; under A141-2024 §7.2.5 the design-builder may rely on the accuracy of surveys and reports the owner furnishes, so mislabelled criteria shift risk back to you.
  4. At the Design-Build Amendment (A141 §4.5) or GMP proposal (DBIA 530 §6.6), check the list of drawings, assumptions and clarifications line by line: anything listed as an assumption is a future change order.

Lump sum, GMP or cost plus fee: which pricing fits?

Pick lump sum when the design is far enough along to price the whole job, GMP when you want a ceiling but the design is still moving, and cost plus fee without a GMP only when speed matters more than price certainty. All three AIA options sit in A141-2024 Exhibit B; DBIA splits them across 525 and 530; ConsensusDocs across 415 and 410. The general mechanics of each type are on our page about the main types of construction contracts.

OptionAIADBIAConsensusDocsWho carries overrun riskPayment paperwork
Lump sum / stipulated sumExhibit B525415 (after 400)Design-builder, within scopeSchedule of values, A141 §9.2
Cost plus fee with GMPExhibit B530410Design-builder above the GMPSchedule of values; G742GMP-2024
Cost plus fee, no GMPExhibit B; Control Estimate §9.2.1530 without GMPNot offered as a base formOwnerControl Estimate; G742CW-2024

Source for the payment forms: AIA 2024 design-build update. Under a GMP the open-book rules are the heart of the deal, so read our guide to cost-plus contracts and audit rights before agreeing the fee.

Which design-build pricing option fits?Which design-build pricing option fits?Decision logic for A141-2024 Exhibit B, DBIA 525/530 and ConsensusDocs 410/415. Editorial guide, not adviceIs the design developed enough (bridging orschematic documents) to price the whole job now?YesNoFix the price at signingStipulated sum / lump sumA141 Exhibit B, DBIA 525,ConsensusDocs 415 (after CD 400)Do you want a price ceiling beforeconstruction starts?YesNoGMPCost of the Work + fee + GMPA141 Exhibit B, DBIA 530,ConsensusDocs 410Cost plusCost + fee,no GMP:A141 ControlEstimate §9.2.1What each choice shiftsLump sum: the design-builder keeps savings and absorbs overruns inside the agreed scope.GMP: the owner pays actual cost plus fee up to the cap; savings split is a negotiated term.Cost plus without GMP: the owner carries overrun risk; insist on open-book audit rights.
Price certainty follows design maturity: lump sum when scope is priceable, GMP for a ceiling, cost plus only for speed. Forms: A141-2024 Exhibit B, DBIA 525/530, ConsensusDocs 410/415.

Worked example: what a GMP savings split pays

The inputs below are illustrative, not market data; they show the arithmetic an Exhibit B or DBIA 530 GMP creates. Fee percentage, contingency and savings split are all negotiated blanks in the forms.

LineInput or formulaAmount
Estimated Cost of the WorkDesign-builder’s proposal$8,000,000
Design-builder’s contingencyInside the GMP, 3% of cost$240,000
Fee4% of cost plus contingency$329,600
GMPSum of the three lines$8,569,600
Actual cost at completionExample result$8,100,000
Fee on actual cost4% x $8,100,000$324,000
Savings under the GMP$8,569,600 minus ($8,100,000 + $324,000)$145,600
Owner share at a 75/25 split0.75 x $145,600$109,200
Design-builder share0.25 x $145,600$36,400

Two terms move this result most: whether the fee is fixed or a percentage of actual cost (a fixed $329,600 fee would cut the savings by $5,600), and whether unspent contingency returns to the owner or counts as savings to split. Write both into the amendment; how to size the contingency line is covered in our guide to construction contingency.

Who carries design liability and professional insurance?

The design-builder carries design liability to the owner, and its architect answers only to the design-builder. A141-2024 §3.1.7 says the architect’s and consultants’ services are for the design-builder’s exclusive benefit, so an owner with a design defect claims against the design-builder, which then pursues its designer. The standard for design is professional negligence (A141 §3.1.11, DBIA 535 §2.3); the standard for construction is a warranty of defect-free work.

Who answers for a design error under a design-build contractWho answers for a design error under a design-build contractStandard-of-care sections: A141-2024 §3.1.11, DBIA 535 §2.3, ConsensusDocs 410 Art. 3 (2017 chart)1. Ownerowner claims againstthe design-builder only2. Design-builderanswers for its architect(A141 §3.1.5); carriesPL per insurance exhibit3. Architectowner has no directcontract; design servicesbenefit the D-B (§3.1.7)Two standards in one contractDesign services: the professional standard of care (skill and care ordinarily used in the same locality).Construction Work: warranted new, of good quality and free from defects (A141 §3.1.12, DBIA 535 §2.9).Performance guarantees or fitness-for-purpose language raise the bar above the standard of care andmay fall outside professional liability cover: check with the insurer before signing.Insurance hooks in the formsDBIA 535 §5.1.2: the design-builder’s policies must delete design-build exclusions.A141-2024 §3.1.16 and Exhibit A: coverage types and limits are filled in per project.Owner’s own consultants (criteria architect) must carry professional liability (A141 §7.1.3).
The owner claims against the design-builder, which answers for its architect (A141-2024 §3.1.5, §3.1.7). Standards: A141 §3.1.11, DBIA 535 §2.3; insurance: DBIA 535 §5.1.2.

Insurance follows that split. A141-2024 puts coverage types and limits in Exhibit A (§3.1.16), and DBIA 535 §5.1.2 requires the design-builder’s insurance to delete any design-build or similar exclusion that could compromise coverage (DBIA 535, 2022). The ConsensusDocs 410 guidebook warns owners not to add a design standard higher than the customary one, because it may void the designer’s errors and omissions cover. Before signing, ask the design-builder’s broker three questions: is professional liability written on the design-builder or only on its architect; what are the per-claim limit and the extended reporting period; and does the general liability policy carry a design-build exclusion?

Bonds need the same check. ConsensusDocs publishes a performance bond (471) where the surety is not liable for design costs and two payment bonds (472 liable, 473 not liable) per its April 2026 catalog. Ask which bond form secures design as well as construction; our guide to how a performance bond works covers the claim process.

Who owns the drawings and other documents?

The design-builder owns them by default under all three families, and the owner gets a license. Under A141-2024 Article 13, the design-builder and its consultants keep copyright (§13.1) and grant the owner a nonexclusive license (§13.3) to construct, use, maintain, alter and add to the project; the license ends only if the design-builder terminates for the owner’s default or the owner terminates for convenience without paying the §14.1.7 fees.

DBIA 530 §4.1 keeps ownership with the design-builder too, but §4.2 grants the owner’s license only on payment in full, and the owner indemnifies the design-builder for later alteration (§4.5). ConsensusDocs 410 §3.1.8 has a check box for transferring copyright, with an optional negotiated fee; if nobody ticks it, copyright stays with the design-builder (CD 410 guidebook, 2017).

  • If you may finish the project with another firm, negotiate a license that survives termination for cause and covers native CAD and BIM files, not only PDFs.
  • If you will build a prototype on 10 more sites, ask for reuse rights in writing; every standard license is limited to this Project.
  • If you are an owner under 530, ask for an interim license during construction, since §4.2 starts only at payment in full.

How do changes, claims deadlines and warranties work?

Changes run through a signed Change Order when price and time are agreed, or an owner-signed directive when they are not: A141-2024 §6.2 and §6.3, DBIA 535 §9.1 and §9.2, with DBIA 535 §9.3 allowing minor changes at no cost. A material change to the owner’s criteria after signing triggers a Modification under A141 §1.5, which is the clause most owner program changes land in. The forms that document a change on site are covered in our guide to construction change orders.

A141-2024 clocks owners should diaryA141-2024 clocks owners should diaryDay counts from a public copy of AIA A141-2024 and DBIA 535 (2022), accessed November 21, 202610 daysnotice before changing either party’s representative (A141 §1.2.5)14 daysControl Estimate due after signing, cost plus without GMP (§9.2.1)21 daysnotice of a Claim after the event or after first recognising it (§15.1.3.1)7 daysowner’s notice to terminate for convenience before the Amendment (§14.1.5)10 daysowner’s notice to terminate for convenience under DBIA 535 §11.6.130 dayswork stopped: design-builder may terminate after 7 days’ notice (§14.2.1.1)1 yearcorrection period after Substantial Completion (A141 §12.2.2.1, DBIA 535)10 yearsoutside limit for claims after Substantial Completion (A141 §15.1.2)
Notice periods and limits in AIA A141-2024 and DBIA 535 (2022), from 7 days to 10 years. Sources: public copies of both forms, accessed November 21, 2026.
ClockA141-2024DBIA 535 (2022)What the owner should do
Claim notice21 days after the event or first recognition, §15.1.3.1Notice under Art. 10, §10.1Diary every directive date; answer claims in writing
Correction period1 year after Substantial Completion, §12.2.2.11 year, §2.10Walk the building at month 10 and send one defect list
Warranty of Construction Work§3.1.12, no fixed term in the clause§2.9, term may be limited in the AgreementStrike or extend any warranty term written into the Agreement
Outside limit on claims10 years after Substantial Completion, §15.1.2Set by state law unless agreedCheck your state’s statute of repose before agreeing a shorter limit
Convenience termination notice7 days before the Amendment, §14.1.510 days, §11.6.1Fill in the §14.1.7 fee as a fixed sum, not a percentage

Substantial Completion starts both the one-year correction period and the 10-year claims limit in A141-2024, so the certificate date matters; AIA’s design-build certificate is G744-2024. Our page on substantial completion explains what the certificate should list.

Which clauses should owners negotiate first?

Start with the blanks that the forms leave open, because a blank defaults to the design-builder’s proposal. The table ranks them by money at stake on a typical commercial job, our editorial judgment from reading the forms, not survey data. For each, the third column names the section to edit in A141-2024 or DBIA 2022.

ClauseForm defaultWhat owners commonly ask forWhere
Owner’s Criteria detailWhatever you write in 10 blanksPerformance specs plus a dated document listA141 §1.1; DBIA 535 §1.2
Pre-amendment fee and capBlankFixed fee with a cap and a deliverables listA141 §2.1.1
Contingency and savingsNegotiated in the Amendment or GMPUnspent contingency returns to owner; split statedA141 Exhibit B; DBIA 530 §6.6
Liquidated damagesBlankDaily rate tied to real carrying costA141 §2.3.2; DBIA 530 §5.4
Document licenseLicense for this Project onlyLicense surviving termination, native filesA141 §13.3; DBIA 530 §4.2
Professional liabilityLimits in insurance exhibitNamed limits, 3+ year tail, no design-build exclusionA141 Exhibit A; DBIA 535 §5.1
Convenience termination feeBlankFixed sum that falls as design progressesA141 §14.1.7; DBIA 530 Art. 8
Retainage on design feesSet in payment termsNo retainage on completed design phases, or a lower rateA141 §9.6; DBIA 530 §7.2

The 3-year tail in that table is a common owner request, not a form default; ask your broker what your state’s statute of repose suggests. Payment applications against a stipulated sum or GMP follow a schedule of values, set out in our guide to building a schedule of values.

Which design-build contract should you use?

Use the family your lender, public-procurement rules or design-builder’s insurer already accepts, then pick the pricing variant. Public owners often must use their own form: federal agencies follow two-phase selection under FAR 36.303 (federal only), where phase one may not score price and the shortlist is normally capped at five offerors (eCFR, FAR 36.303-1). For a private owner the decision table below applies.

If your situation isUseWhy
Bridging documents or a design competition already fix the scopeDBIA 525 or A141 with stipulated sumPrice fixed at signing; 2017 chart notes 525 needs bridging or a competition
Program only, and you want a price ceiling before constructionA141 (GMP in Exhibit B), DBIA 530 or ConsensusDocs 410GMP set after preliminary design
Program only, schematic design included in the owner’s program, lump sum wantedConsensusDocs 400 then 415415 assumes schematic design is done
You want to select the team first and price laterA141PDB-2024, DBIA 544 or ConsensusDocs 411Progressive forms price in phases
Your project team already uses AIA A201 and G-series formsA141-2024 familySame definitions and G741/G742 change and payment forms
You need an independent criteria architectAIA C141-2024 or DBIA 520 consultant scopeOwner’s own adviser outside the design-builder’s contract

Whichever family you choose, buy the current edition: A141-2024 costs $179.99 for one-time use from the AIA store as of November 2026, and the wider AIA catalog is mapped in our guide to AIA contract documents. This page is general information about published standard forms, not legal or insurance advice; have a construction attorney in your state review the edited agreement and your broker review the insurance exhibit before signing.

Owners comparing delivery methods can read progressive design-build and design assist versus design-build.

How we compiled this

We read 7 primary documents in November 2026: a public copy of AIA A141-2024, AIA’s A141-2024, A142-2014 and 2024 family summaries, public 2022 copies of DBIA 530 and 535, and ConsensusDocs’ 2017 comparison chart, 410 guidebook and April 2026 catalog, plus FAR 36.303-1. Section numbers were taken from those documents; the public copies were posted by public owners and may include owner edits, so we cited only standard headings. We excluded law-firm and vendor commentary as sources.

Frequently asked questions

What is the difference between AIA A141 and A142?

A141 is the agreement between the owner and the design-builder. A142-2014 was the 2014 agreement between a design-builder and a separate construction contractor, with four exhibits. The 2024 AIA design-build family has no A142: trades sign A441-2024, which incorporates A141-2024 by reference, and the A142-2014 store link now opens the A441 page (checked November 2026).

Is a design-build contract lump sum or GMP?

Either. AIA A141-2024 lets the parties choose a stipulated sum, cost of the work plus a fee, or cost plus fee with a guaranteed maximum price in the Exhibit B Design-Build Amendment. DBIA splits the choice between 525 (lump sum) and 530 (cost plus fee with an optional GMP), and ConsensusDocs between 415 (lump sum) and 410 (GMP).

Who owns the design in a design-build contract?

By default the design-builder and its designers keep the copyright and the owner receives a license to use the documents for this project. A141-2024 grants the license at signing (§13.3); DBIA 530 grants it on payment in full (§4.2); ConsensusDocs 410 has a check box to transfer copyright (§3.1.8). Reuse on other sites needs a written transfer or license.

Does the design-builder need professional liability insurance?

The standard forms leave the coverage and limits to the insurance exhibit, so the owner must name them: A141-2024 Exhibit A and DBIA 535 Article 5. DBIA 535 §5.1.2 also requires the design-builder to delete design-build exclusions from its policies. Ask whether professional liability sits with the design-builder or only its architect, and what the per-claim limit and tail period are.

What is the Design-Build Amendment in AIA A141?

It is the document the owner and design-builder sign once they agree on the design-builder’s proposal. Under A141-2024 §4.5 it sets the Contract Sum, the information and assumptions it rests on, and the Contract Time. In the 2024 edition it is Exhibit B; in A141-2014 it was Exhibit A. No Contract Sum costs may be incurred before it without written approval.

Can an owner terminate a design-build contract for convenience?

Yes, under all three families. A141-2024 allows it on seven days’ notice before the Design-Build Amendment (§14.1.5) and at any time after it (§14.2.4), with termination and licensing fees set in §14.1.7. DBIA 535 §11.6.1 requires 10 days’ written notice and payment for work done, termination costs and the amount in 530 Article 8.

Sources

Last reviewed November 2026 by the CB&C Editorial Team. See our editorial standards.