Skip to content

AIA A201-2017 General Conditions: Articles, Deadlines and What Owners Change

Construction site trailer interior with marked-up drawings on a plan table and a concrete frame visible through the window

AIA A201 is the American Institute of Architects’ General Conditions of the Contract for Construction: a 15-article rulebook, current edition 2017, that A101, A102, A103 and A133 agreements adopt for changes, payment, claims, insurance and termination.

Key takeaways

  • A201-2017 has 15 articles and is the keystone of AIA’s Conventional family: A101, A102 and A103 adopt it by reference (AIA Contract Documents summary).
  • Two deadlines cost the most when missed: a claim must be started within 21 days (§15.1.3.1), sent by certified or registered mail or courier with proof of delivery (§1.6.2), and concealed site conditions must be reported within 14 days (§3.7.4), down from 21 days in A201-2007 (A201-2017 standard form).
  • Payment runs on 7-day clocks: the architect acts on a pay application within 7 days (§9.4.1), the contractor pays subcontractors within 7 days of being paid (§9.6.2), and a contractor still unpaid 7 days after the due date may stop work on 7 more days’ notice (§9.7).
  • Coverage types and limits left A201 Article 11 in 2017: they now sit in Exhibit A to A101, A102 and A103, and Exhibit B to A133 (AIA exhibit FAQ).
  • Read the owner’s version, not the blank form: in our section-by-section comparison, the University of Wisconsin System’s 2018 version changed 115 of 341 standard sections and deleted the §15.1.7 waiver of consequential damages, while Anderson County, Texas (2026) changed 6 (UW System copy, Anderson County copy).
  • A201 sells for $179.99 for one-time use (AIA store, October 2026); AIA said in 2022 that the next update is due in 2027 (AIA).

What is AIA A201 and which agreements use it?

AIA A201-2017 is the general conditions document of the AIA Conventional, or design-bid-build, family. It is never signed on its own; how it fits with the rest of the A to G series is mapped in our guide to AIA contract documents. The owner-contractor agreement (A101-2017, A102-2017 or A103-2017) adopts it by reference, and the A401-2017 subcontract and B101-2017 owner-architect agreement incorporate it, according to the AIA summary of A201-2017.

The split is practical. The agreement holds the deal: parties, Contract Sum, dates, retainage percentage, the Initial Decision Maker and the choice of arbitration or litigation. A201 holds the procedures that run the job. The AIA store page lists A101, A102, A133 and A401 as the documents A201 “works best with”, and AIA’s Insurance and Bonds Exhibit FAQ confirms A133-2019 uses the same insurance exhibit structure (as Exhibit B). Our guide to construction management at risk and the A133 agreement covers the GMP side.

Documents that adopt or work with AIA A201-2017 Owner-contractor agreements adopt A201-2017; subcontract and architect agreements incorporate it; exhibits and G-series forms attach to specific articles. The A201 family around the general conditions Adopt A201 by reference A101-2017 stipulated sum A102-2017 cost plus fee, GMP A103-2017 cost plus fee, no GMP A133-2019 CM at risk, GMP A201-2017 General Conditions, 15 articles Incorporate or amend A201 A401-2017 subcontract B101-2017 owner-architect A503 guide: supplementary terms Exhibits Insurance and Bonds: Exhibit A (A101, A102, A103) Insurance and Bonds: Exhibit B (A133) Sustainability: E204-2017 (A133 uses E234-2019) G-series forms by article G701-2017 Change Order: §7.2 G714-2017 Construction Change Directive: §7.3 G702-1992 payment: §9.3; G704-2017: §9.8.4
A101, A102, A103 and A133 adopt A201-2017; A401 and B101 incorporate it; insurance sits in Exhibit A or B. Sources: AIA A201 summary and Insurance and Bonds Exhibit FAQ, accessed October 2026.

Four G-series forms carry out specific A201 sections: G701-2017 Change Order (§7.2), G714-2017 Construction Change Directive (§7.3), G702-1992 Application and Certificate for Payment (§9.3) and G704-2017 Certificate of Substantial Completion (§9.8.4). For sustainability terms, AIA lists E204-2017, Sustainable Projects Exhibit, for this family and E234-2019 for A133 projects. Where the contract fits in the project timeline is set out in the seven phases of the commercial construction process.

What do the 15 articles of A201-2017 cover?

The 15 articles of A201-2017 run from General Provisions (Article 1) to Claims and Disputes (Article 15), with 341 numbered sections in the standard form we parsed. Articles 7, 9 and 15 drive most day-to-day administration: changes, payment and claims. The table summarizes each article in our own words; the clause text is AIA copyright and is available from AIA Contract Documents.

ArticleTitleSectionsWhat it governs
1General Provisions§1.1 to §1.8What the Contract Documents are, how they are read together, ownership of drawings, notice rules (§1.6), digital data and BIM protocols
2Owner§2.1 to §2.5Owner’s information and services, evidence of financing (§2.2), the right to stop the Work (§2.4) and to carry it out after a default (§2.5)
3Contractor§3.1 to §3.18Review of documents and site, supervision, warranty (§3.5), permits and concealed conditions (§3.7), schedules, submittals, indemnification (§3.18)
4Architect§4.1 to §4.2The Architect’s role in administering the contract until the final Certificate for Payment (§4.2.1), site visits, submittal review
5Subcontractors§5.1 to §5.4Naming and objecting to subcontractors (§5.2), flow-down of terms (§5.3), contingent assignment to the Owner (§5.4)
6Construction by Owner or by Separate Contractors§6.1 to §6.3Owner’s own forces and separate prime contracts, coordination and mutual responsibility
7Changes in the Work§7.1 to §7.4Change Orders (§7.2), Construction Change Directives (§7.3), minor changes by the Architect (§7.4)
8Time§8.1 to §8.3Contract Time, calendar-day definition (§8.1.4), progress, delays and extensions (§8.3)
9Payments and Completion§9.1 to §9.10Schedule of values, applications and certificates, withholding, failure of payment (§9.7), Substantial Completion (§9.8), final payment
10Protection of Persons and Property§10.1 to §10.4Safety programs, hazardous materials (§10.3), emergencies (§10.4)
11Insurance and Bonds§11.1 to §11.5Framework only: who buys what (detail in the agreement’s exhibit), waivers of subrogation (§11.3), insured-loss settlement (§11.5)
12Uncovering and Correction of Work§12.1 to §12.3Uncovering work, the one-year correction period (§12.2.2), accepting nonconforming work
13Miscellaneous Provisions§13.1 to §13.5Governing law (§13.1), assignment, tests and inspections, interest on late payments (§13.5)
14Termination or Suspension of the Contract§14.1 to §14.4Termination by the Contractor, by the Owner for cause, suspension and termination for convenience (§14.4)
15Claims and Disputes§15.1 to §15.4Claim notice and time limits, consequential damages waiver (§15.1.7), Initial Decision Maker, mediation, arbitration

Article 4 matters even though the Architect does not sign the owner-contractor contract: under §4.2.1 the Architect administers it and represents the Owner until the final Certificate for Payment, and under A101 §6.1 the Architect is the default Initial Decision Maker, the person who rules first on a claim before mediation.

What deadlines does AIA A201 set?

AIA A201 sets at least 15 hard deadlines, and §8.1.4 defines every “day” as a calendar day unless a clause says otherwise. The short clocks are the payment cycle (7 days), concealed conditions and subcontractor objections (14 days) and claim notice (21 days). The long ones are the one-year correction period and the 10-year outer limit on claims.

RuleSectionDeadlineSource
Architect acts on an Application for Payment§9.4.17 days after receiptA201-2017 form
Contractor pays each subcontractor§9.6.27 days after receiving paymentA201-2017 form
Stop work for non-certification or non-payment§9.77 days late, then 7 more days’ noticeA201-2017 form
Owner shows evidence of financing after start (on request)§2.2.214 daysA201-2017 form
Notice of concealed or unknown conditions§3.7.4Before disturbing, no later than 14 daysA201-2017 form
Architect objects to a proposed subcontractor§5.2.114 days after receiving the namesA201-2017 form
Contractor objects to an insured-loss settlement§11.5.214 days after noticeA201-2017 form
Notice that required insurance is cancelled or expiring§11.1.4, §11.2.33 business daysA201-2017 form
Initiate a Claim§15.1.3.121 days after the event or first recognition, whichever is laterA201-2017 form
Initial Decision Maker’s first action§15.2.210 days after receiptA201-2017 form
Claimant may skip a silent IDM§15.2.130 days after referralA201-2017 form
Demand that the other party file for mediation§15.2.6.130 days after receiving the decisionA201-2017 form
Contractor may terminate after a stoppage§14.1.1, §14.1.330 consecutive days, then 7 days’ noticeA201-2017 form
Correction of Work after Substantial Completion§12.2.2.11 yearA201-2017 form
Outer limit for any Claim§15.1.210 years after Substantial CompletionA201-2017 form
A201-2017 deadlines in calendar daysBar chart of 15 A201-2017 deadlines from 7 days for payment certification to 60 days for an arbitration staycalendar days§9.4.1 Architect acts on pay application7§9.6.2 Contractor pays subcontractors7§15.2.2 IDM first action on a claim10.0§15.2.4 Party answers IDM request10.0§9.7 Late 7 days plus 7 days' notice14.0§3.7.4 Concealed conditions notice14.0§2.2.2 Owner shows financing14.0§5.2.1 Architect objects to subcontractor14.0§11.5.2 Object to insured-loss settlement14.0§15.1.3.1 Initiate a claim21.0§15.2.1 Silent IDM before mediation30.0§15.2.6.1 Demand mediation30.0§14.1.1 Stoppage before termination30.0§15.3.2 Arbitration stay for mediation60.0§14.1.4 Stoppage for repeated failures60.0
A201-2017 runs from 7-day payment steps to 60-day dispute stays; the claim notice is 21 days. Source: AIA Document A201-2017, accessed October 2026.

Worked example: when can a contractor stop work for late payment?

Under §9.7, a contractor may stop work only after payment is 7 days late and a further 7 days’ written notice has run. With an application received on Thursday 1 October 2026 and a payment date of 2 November 2026 written into A101 §5.1.3, the earliest stop date is Monday 16 November 2026, 14 days after the due date.

StepSectionDateArithmetic
Architect receives the Application for Payment§9.3Thu 1 Oct 2026Assumed start date
Architect must certify, part-certify or withhold§9.4.1Thu 8 Oct 20261 Oct + 7 days
Owner payment due under the agreementA101 §5.1.3Mon 2 Nov 2026Date the parties filled in (assumed)
Payment now late enough to trigger §9.7§9.7Mon 9 Nov 20262 Nov + 7 days
Earliest stop if the 7-day notice goes out that day§9.7Mon 16 Nov 20269 Nov + 7 days
Contractor pays subcontractors once paid (say 20 Nov)§9.6.2Fri 27 Nov 202620 Nov + 7 days

The stop also extends the Contract Time and adds the contractor’s shutdown, delay and start-up costs plus interest (§9.7, with the rate from §13.5). State prompt-payment statutes can shorten these clocks on public work; the prompt payment and retainage rules by state list the statutory periods.

How does a claim move through Article 15?

A claim under A201-2017 Article 15 starts with written notice within 21 days (§15.1.3.1), goes to the Initial Decision Maker, then to mediation, then to arbitration or litigation. Mediation must happen before arbitration or litigation (§15.3.1). Work and payments continue while the claim is open (§15.1.4.1), apart from the §9.7 stop and Article 14 terminations.

  1. Notice: within 21 days after the event or after the claimant first recognizes the condition, whichever is later, to the other party and the Initial Decision Maker (§15.1.3.1). Delivery by certified or registered mail, or courier with proof of delivery (§1.6.2).
  2. Cost and time claims: give notice before doing the disputed work (§15.1.5); time claims include an estimate of cost and delay, and weather claims need data showing the weather was abnormal (§15.1.6.2).
  3. Initial Decision Maker: within 10 days of receipt, request data, reject, approve, suggest a compromise or say it cannot decide (§15.2.2); a party asked for data answers within 10 days (§15.2.4).
  4. Decision: in writing with reasons (§15.2.5). With no decision 30 days after referral, the claimant may go to mediation (§15.2.1).
  5. Mediation: either party may demand that the other file within 30 days of receiving the decision, and the other side then has 30 days to file (§15.2.6.1). The American Arbitration Association administers it unless agreed otherwise; fees are split equally (§15.3.2, §15.3.4).
  6. Binding resolution: arbitration under §15.4 or litigation, whichever box was checked in A101 §6.2. A demand to file comes 30 days after mediation ends or 60 days after it was demanded, and the recipient has 60 days (§15.3.3).
How a claim moves through AIA A201-2017 Article 15 Six steps from the event to binding dispute resolution, with the day counts and section numbers from A201-2017. A201-2017 claim path (claims found before the one-year correction period ends) 1. Event or condition Clock starts at the event, or when the claimant first recognizes it, whichever is later 2. Notice within 21 days §15.1.3.1: to the other party and the Initial Decision Maker §1.6.2: certified mail or courier 3. IDM acts in 10 days §15.2.2: ask for data, reject, approve, suggest a compromise or decline to decide 4. Initial decision §15.2.5: written, with reasons §15.2.1: no decision in 30 days lets the claimant move on 5. Mediation §15.2.6.1: demand within 30 days of receiving the decision §15.3.2: AAA unless agreed 6. Binding resolution Arbitration (§15.4) or litigation, as checked in A101 §6.2 No box checked: litigation While the claim is open §15.1.4.1: contractor keeps working and owner keeps paying §15.1.2: no claim more than 10 years after Substantial Completion Found after the correction period §15.1.3.2: notice to the other party only no 21-day clock, no IDM decision §12.2.2.1: correction period is one year after Substantial Completion
A claim found before the one-year correction period ends needs notice in 21 days, then IDM review, mediation and binding resolution. Source: AIA Document A201-2017 Article 15, accessed October 2026.

Weather is the most data-dependent claim. Section 15.1.6.2 asks for proof the conditions were abnormal for the period, and the weather workday index for 56 US metros shows the normal-year baseline from NOAA 1991 to 2020 records. If a claim involves a lien, §15.2.8 lets the claimant meet statutory lien deadlines regardless of Article 15; the mechanics lien deadlines by state give those dates.

What does the mutual waiver of consequential damages cover?

Section 15.1.7 is a mutual waiver: the Owner gives up claims for rental expenses, lost use, income, profit, financing, business and reputation, and lost management or employee productivity; the Contractor gives up principal-office expenses, lost financing, business and reputation, and lost profit other than profit on the Work itself. It applies to Article 14 terminations and does not block liquidated damages.

Owners and contractors negotiate this clause. David A. Senter of Maynard Nexsen (August 2020) lists three common edits: waiving only what insurance does not cover, carving out third-party claims, and capping consequential damages at a share of contract value, which he puts at typically 5% to 15% (Maynard Nexsen). Our comparison below found one of two public owners deleted §15.1.7 outright.

Arbitration or litigation?

A201 does not choose the forum by itself. A101-2017 §6.2 offers three boxes: arbitration under A201 §15.4, litigation, or other. If no box is checked, claims go to litigation in a court of competent jurisdiction, as the printed A101 text states (A101-2017 copy, Oakton Community College). If arbitration is chosen, §13.1 says the Federal Arbitration Act governs §15.4.

Where did the insurance terms go in A201-2017?

In A201-2017, Article 11 keeps only the insurance framework: licensed carriers, additional insureds, notice of lapses, waivers of subrogation and the Owner’s role as fiduciary for insured losses. Coverage types and dollar limits moved to the Insurance and Bonds exhibit of the owner-contractor agreement, according to the AIA summary and the AIA exhibit FAQ.

ItemWhere it sits in 2017DetailSource
Coverage types and limitsAgreement exhibit, not A201Exhibit A to A101, A102, A103, A132 and A134; Exhibit B to A133AIA Insurance and Bonds Exhibit FAQ
Licensed insurers and suretiesA201 §11.1.1, §11.1.2Companies lawfully authorized in the project’s jurisdictionA201-2017 form
Additional insuredsA201 §11.1.1Owner, Architect and the Architect’s consultants on the contractor’s CGL policyA201-2017 form
Lapse in coverageA201 §11.1.4, §11.2.3Notice within 3 business days; the other party may stop the WorkA201-2017 form
Owner skips property insuranceA201 §11.2.2Owner must tell the contractor in writing before work startsA201-2017 form
Waivers of subrogationA201 §11.3Mutual, to the extent losses are covered by property insuranceA201-2017 form
Insured-loss settlementA201 §11.5Owner adjusts as fiduciary; contractor has 14 days to objectA201-2017 form

Section 11.4 also has the Owner waive claims against the Contractor and Architect for loss of use of the Owner’s property due to fire or other hazards, however caused, whether or not the Owner buys loss-of-use insurance. Bond types and penal sums come from the Contract Documents under §11.1.2; the construction surety bond data covers how performance and payment bonds are priced and required. This page explains a standard form and is not legal or insurance advice; AIA itself recommends reviewing Article 11 and the exhibit with an insurance broker and counsel.

What do owners change in A201?

Owners change A201 through supplementary conditions or AIA’s Additions and Deletions process, and AIA publishes A503 as its guide for writing them. We compared two public-owner versions against the standard text, section by section: the University of Wisconsin System changed about a third of the sections, while Anderson County, Texas changed only forum, venue and governing law. Of the 33 standard sections the two owners deleted, 20 sit in Article 15.

ProvisionStandard A201-2017UW System (12/26/2018)Anderson County, TX (2026)
§15.1.3.1 claim notice21 days21 days kept; adds a condition-precedent and waiver sentence21 days, unchanged
§1.6.2 how claim notice is deliveredCertified or registered mail, or courier with proof of deliveryAlso allows electronic delivery with proof it was readUnchanged
§3.7.4 concealed conditions14 days14 days, unchanged14 days, unchanged
§15.1.7 mutual waiver of consequential damagesIncludedDeletedUnchanged
§2.2 evidence of the Owner’s financingIncludedDeletedUnchanged
§15.4 arbitrationApplies if chosen in A101 §6.2Deleted with §15.3.3Replaced: litigation in Anderson County
§13.1 governing lawLaw of the project’s location; FAA governs arbitrationState of Wisconsin lawAnderson County, Texas named; FAA sentence dropped
Article 11 insuranceFramework plus agreement exhibitRewritten: insurer A.M. Best rating of at least B; owner builder’s risk at least the initial Contract Sum, replacement costUnchanged
§9.6.2 paying subcontractors7 days after payment7 calendar days, extended to every person who furnished goods or servicesUnchanged

The counts come from parsing each document into numbered sections and comparing the text of every section that appears in the standard form. The arithmetic is below; percentages are of the 341 standard sections.

MeasureUW System 2018Anderson County 2026Arithmetic
Numbered sections in the standard form341341Parsed from the AIA sample
Standard sections changed (text match below 97%)115 (33.7%)6 (1.8%)115 / 341; 6 / 341
Standard sections deleted25 (7.3%)8 (2.3%)25 / 341; 8 / 341
New sections the owner added1560Section numbers absent from the standard form
Sections in the owner’s final version472333341 minus deleted plus added

Two of Anderson County’s 6 changes (§1.7 and §1.8) drop a reference to E203-2013, which AIA later replaced, so they may reflect AIA’s own updated text rather than an owner edit. For bidders, the lesson is to read the owner’s version, not the form: a 21-day notice clause can carry new waiver language, as UW’s §15.1.3.1 does. That check belongs in comparing construction bids line by line and in the five checks for choosing a commercial contractor.

What changed from A201-2007, and is a 2027 edition coming?

The 2017 edition replaced A201-2007 with shorter notice for concealed conditions (21 to 14 days), formal delivery rules for claim notices, an insurance exhibit outside the general conditions and clearer dispute clocks. AIA still lists A201-2007 for sale, so check which edition a contract names; the AIA document list carries both.

SectionA201-2007A201-2017Source
§3.7.4 concealed conditions notice21 days14 daysAIA summary
§1.6 noticeNotice rules sat in Article 13Moved to Article 1; claims notice by certified or registered mail or courierAIA summary
Article 11 insuranceDetailed coverages in A201Moved to the agreement’s Insurance and Bonds exhibitAIA summary
§14.4.3 termination for convenienceNo fee fill pointTermination fee set in the agreement (A101 §7.1.1)AIA A101 summary
§15.1.2 time limits on claimsIn Article 13Moved to Article 15; 10-year outer limitAIA summary
§15.2.6.1 mediation demandClock ran from the decision date (30 and 60 days)Clock runs from receipt; 30 days each stepAIA summary
§15.3.3 demand to file binding resolutionNo equivalentNew: 30 or 60 days, then 60 days to fileAIA summary
AIA help page excerpt with the section 3.7.4 change from 21 to 14 days boxed
AIA’s own summary, Article 3, §3.7.4: the concealed-conditions reporting period fell from 21 days (A201-2007) to 14 days. Source: AIA Contract Documents, Summary: A201-2017, accessed 19 October 2026.

Is there a 2027 edition of A201?

Not yet. AIA wrote in April 2022 that A201 “will be updated again in 2027” and that the update takes at least three years (AIA Contract Documents). As of October 2026, AIA’s current list shows A201-2017 as the latest edition, with no 2027 draft or release date published. The general conditions date back to 1911 (AIA history), and AIA says the ten-year cycle has run “on the sevens” since 1987.

AIA A201 general conditions editions, 1911 to 2017, and the 2027 revision AIA has scheduled Sixteen editions listed in the A201-2017 copyright line, evenly spaced, with 2027 shown as the next scheduled revision. 16 editions of the A201 general conditions (markers evenly spaced, not to scale) 1911 1915 1918 1925 1937 1951 1958 1961 1963 1966 1970 1976 1987 1997 2007 2017 2027 Ten-year cycle “on the sevens” since 1987; 2017 is current 2027: next revision scheduled (AIA, 2022) 1911: first AIA standardized general conditions
The A201-2017 copyright line lists 16 editions since 1911; AIA said in 2022 the next update is due in 2027. Sources: AIA Document A201-2017; AIA Contract Documents, accessed October 2026.

Which form fits your project: A201 or something else?

A201-2017 fits design-bid-build and CM-at-risk projects that use A101, A102, A103 or A133. It does not fit construction manager as advisor projects, which use A232-2019, or small jobs where AIA points to A104-2017 or A105-2017. Use the table to match the situation to the form and the clause to check first.

IfThenSource
You sign a stipulated-sum agreement (A101-2017)A201-2017 is your general conditions; fill in Exhibit AAIA A101 summary
You pay cost of the work plus a fee with a GMP (A102-2017)A201-2017 applies; the GMP terms sit in A102AIA A201 summary
You hire a construction manager at risk (A133-2019)A201-2017 applies; insurance goes in Exhibit B; sustainability in E234-2019AIA exhibit FAQ
You use a construction manager as advisorUse A232-2019, the CMa general conditions, not A201AIA document list
The project is small or of limited scopeAIA suggests A104-2017 or A105-2017, its abbreviated and short formsAIA A201 summary
You want to change A201 termsWrite supplementary conditions; AIA’s guide is A503AIA document list
You leave A101 §6.2 blankClaims go to litigation, not arbitrationA101-2017 text (Oakton copy)
A concealed condition turns upNotice before disturbing it, and within 14 days (§3.7.4)A201-2017 form

Design-build, where one entity holds design and construction, uses AIA’s separate A141 family rather than A201; the trade-offs are laid out in design-build vs design-bid-build compared.

The agreement side of the pair, including the §5.1.3 payment dates and the §6.2 dispute box, is set out in our guide to the AIA A101 agreement.

How we compiled this

We read the AIA A201-2017 standard form as reproduced in a City of Rochester, NH bid package (sample PDF), 7 AIA Contract Documents pages and 3 public-owner contract copies, all accessed in October 2026. We parsed the standard form and the UW System and Anderson County versions into numbered sections and compared them with a text-similarity script, then read every flagged key section by hand. On October 26, 2026 we re-read §3.7.4, §9.3.1 to §9.7, §15.1.2 and §15.1.3.1 in the posted form and re-checked the store price. We excluded one 2018 draft whose extracted text mixed deleted and inserted words, and we did not use law-firm commentary for any section fact. This is not legal advice.

Frequently asked questions

What is the difference between AIA A101 and A201?

A101-2017 is the signed agreement: parties, Contract Sum, dates, retainage, the Initial Decision Maker, the arbitration or litigation choice and any termination fee. A201-2017 is the general conditions: the procedures for changes, payment, claims, insurance and termination. A101 adopts A201 by specific reference, so a stipulated-sum contract normally needs both documents plus Exhibit A for insurance and bonds.

Is AIA A201 free to download?

No. AIA Contract Documents sells A201 at $179.99 per document for one-time use, as listed on its store page on October 26, 2026. Copies on public bid sites are licensed project copies, often with owner edits, so they show one owner’s version rather than the standard form. AIA’s free help-center summary explains the 2017 changes section by section.

What is the 21-day rule in A201?

Section 15.1.3.1 of A201-2017 requires a claim to be started within 21 calendar days after the event, or after the claimant first recognizes the condition, whichever is later. The rule covers claims found before the one-year correction period ends. Notice goes to the other party and the Initial Decision Maker by certified or registered mail, or courier with proof of delivery.

Can a claim notice under A201 be sent by email?

Not under the standard 2017 text. Section 1.6.2 says notice of a claim counts as served only by certified or registered mail, or by courier providing proof of delivery. Email works for other notices only if the agreement sets an electronic method (§1.6.1). Owners can change this: the University of Wisconsin System’s 2018 version also accepts electronic notice with proof it was read.

Does A201 apply to construction manager projects?

Only for one of the two AIA construction manager models. For a construction manager as constructor, or CM at risk, A133-2019 adopts A201-2017, with insurance in Exhibit B and sustainability terms in E234-2019. For a construction manager as advisor, AIA publishes separate general conditions, A232-2019, so A201 is not the right document.

Is there an AIA A201-2027?

Not as of October 2026. AIA said in April 2022 that A201 would be updated again in 2027 and that the process takes at least three years, but its current document list still shows A201-2017 as the latest edition. Contracts signed now use A201-2017 or, less often, A201-2007, which AIA still sells.

Sources

Last reviewed October 2026 by the CB&C Editorial Team. See our editorial standards.

← Back to all articles