A concrete slump test measures how far fresh concrete sags after a 12 inch cone is lifted: most commercial mixes are specified at 3 to 5 inches, read to the nearest 1/4 inch under ASTM C143.
Key takeaways
- The slump cone is 12 in tall with an 8 in base and 4 in top, filled in 3 layers of 25 rod strokes each (U.S. Navy Builder training manual; WAQTC FOP for AASHTO T 119, 2025).
- The whole test, from first scoop to lifting the mold, must finish within 2 1/2 minutes, and the lift itself takes 5 ± 2 seconds (AASHTO T 119 FOP, WSDOT Materials Manual, January 2026).
- Unless the project specification says otherwise, ACI 301 calls for a 4 in slump at the point of delivery, and ACI 117 allows ±1 in, so 3 to 5 in passes (ACI 301-20, ACI 117-10).
- Federal jobs under UFGS 03 30 00 (Change 10, August 2025) test slump at the start of placement and every time cylinders are made: at least once a day, per 150 yd3 and per 5,000 ft2 of slab or wall.
- About 1 gallon of water per cubic yard raises slump about 1 in, and water can only be added before more than about 1/4 yd3 leaves the drum (NRMCA CIP 26, 2023).
How is the concrete slump test done?
The concrete slump test is run on a sample taken under ASTM C172, started within 5 minutes of sampling, and finished within 2 1/2 minutes. A technician fills a dampened steel cone in three layers, rods each layer 25 times, lifts the cone straight up in about 5 seconds and measures the drop. The procedure below follows the WAQTC field operating procedure for AASHTO T 119-23, the highway twin of ASTM C143.
- Sample the load from the middle of discharge (ASTM C172). If the mix has aggregate over 1 1/2 in (37.5 mm), wet-sieve it first. Start testing within 5 minutes.
- Dampen the inside of the mold and set it on a flat, rigid, nonabsorbent, dampened base. Stand on both foot pieces.
- Fill to 1/3 of the volume, about 2 5/8 in (67 mm) deep. Rod 25 times through the full depth, starting near the perimeter with the rod slightly tilted, then spiraling to the center.
- Fill to 2/3 of the volume, about 6 1/8 in (155 mm) deep. Rod 25 times, entering about 1 in (25 mm) into the first layer.
- Overfill the mold. Rod 25 times, about 1 in into the second layer, topping up so concrete always stays above the rim.
- Strike off the top with a screeding and rolling motion of the rod and clean concrete from around the base.
- Lift the mold 12 in (300 mm) straight up in 5 ± 2 seconds with no twist. From the start of filling to this point, no more than 2 1/2 minutes.
- Set the empty mold upside down next to the concrete, lay the rod across it and measure to the displaced original center of the top surface, to the nearest 1/4 in (5 mm).
| Item | Dimension or limit | Source |
|---|---|---|
| Cone height | 12 in (300 mm) | U.S. Navy Builder manual; ASTM C143 |
| Cone base diameter | 8 in (200 mm) | U.S. Navy Builder manual; ASTM C143 |
| Cone top diameter | 4 in (100 mm) | U.S. Navy Builder manual; ASTM C143 |
| Tamping rod | 5/8 in (16 mm) diameter, 16 to 24 in long, hemispherical tip | AASHTO T 119 FOP (2025) |
| Layers and strokes | 3 layers, 25 strokes each | AASHTO T 119 FOP (2025) |
| Layer 1 and 2 depth | About 2 5/8 in (67 mm) and 6 1/8 in (155 mm) | AASHTO T 119 FOP (2025) |
| Start after sampling | Within 5 minutes | AASHTO T 119 FOP (2025) |
| Mold lift | 12 in in 5 ± 2 seconds | AASHTO T 119 FOP (2025) |
| Fill to lift, total | 2 1/2 minutes | AASHTO T 119 FOP (2025) |
| Read to | Nearest 1/4 in (5 mm) | AASHTO T 119 FOP (2025) |
| Maximum aggregate | 1 1/2 in (37.5 mm), larger is sieved out | ASTM C143/C143M section 4.2 |
The current edition is ASTM C143/C143M-26b, listed as active on the ASTM store page (updated August 2026). Ask the testing agency which edition its technicians follow. TxDOT Item 421 section 4.8.1 requires testers to hold ACI certification or a recognized equivalent, and the WAQTC exam checklist is derived in part from ACI CP-1.
How do you read a true, shear or collapse slump?
Only a true slump, where the concrete settles evenly and keeps a rough cone shape, is a valid result. If one side shears off or falls away, AASHTO T 119 says to discard the test and run a new one on another portion of the sample. Two shears in a row mean the mix lacks the cohesion the test needs, per the T 119 FOP Note 1.
| Result shape | What it means | What to do | Source |
|---|---|---|---|
| True slump | Mass subsides evenly | Record to the nearest 1/4 in | AASHTO T 119 FOP |
| Zero or near-zero slump (under 1/2 in) | May not be plastic enough for the test to be meaningful | Use the consistency test the spec names for stiff mixes | ASTM C143 Note 2 |
| Shear slump | One side slides off | Discard; retest on another portion. Two in a row: mix lacks cohesion | AASHTO T 119 FOP Note 1 |
| Collapse (over about 9 in) | Too fluid to hold shape | Use slump flow, ASTM C1611, for self-consolidating concrete | ASTM C143 Note 2; UFGS 03 30 00 3.14.3.2 |
ASTM C143 warns that slumps under 1/2 in (15 mm) may not be adequately plastic and slumps over about 9 in (230 mm) may not be cohesive enough for the number to mean much (ASTM C143/C143M Significance and Use). The same section says slump tracks water content in the lab, but the link to strength is not clearly shown in the field, so slump never replaces cylinders.
What slump should concrete have for each element?
Most commercial concrete is ordered at 3 to 5 inches of slump, per NRMCA CIP 31 (2023). Slip-form paving needs 2 inches or less, while walls, pumped mixes and congested rebar may need 7 to 9 inches. The project specification, written by the engineer, is the number that governs; the table shows typical published ranges.
| Element or use | Slump range, in | Source |
|---|---|---|
| Default when the spec is silent | 4 (3 to 5 with tolerance) | ACI 301-20 4.2.2.2; ACI 117-10 |
| Most applications | 3 to 5 | NRMCA CIP 31 (2023) |
| Slip-form construction | 2 maximum | NRMCA CIP 31 (2023) |
| Walls, pumped concrete, congested reinforcement | 7 to 9 | NRMCA CIP 31 (2023) |
| Walls over 9 in thick, caps, columns, piers | 3 to 7 | TxDOT 2024 Item 421 Table 9 |
| Bridge slabs, approach slabs, overlays | 3 to 6 | TxDOT 2024 Item 421 Table 9 |
| Inlets, manholes, walls under 9 in, barrier, formed pavement | 4 to 6 | TxDOT 2024 Item 421 Table 9 |
| Precast concrete | 4 to 9 | TxDOT 2024 Item 421 Table 9 |
| Underwater placements | 6 to 8 1/2 | TxDOT 2024 Item 421 Table 9 |
| Footings and toppings (federal guide spec option) | 6 maximum | UFGS 03 30 00 2.5.1 table |
| Any target slump on federal work | 9 maximum | UFGS 03 30 00 2.5.1 d |
Older mix-design tables in ACI 211.1, now published as ACI PRC-211.1-22, list maximum and minimum slumps by construction type and note that air entrainment usually permits lower slumps for the same placing job. Higher slump through a water reducer is a different matter: TxDOT Item 421 section 4.2.5 lets a mix exceed Table 9 with admixtures only if the w/cm stays the same or lower and the concrete does not segregate. To pick the strength class that goes with these slumps, see our guide to concrete psi by element.
What slump tolerance do ACI 117 and ASTM C94 allow?
A target slump of 4 inches or less carries a ±1 inch tolerance under ACI 117, and anything over 4 inches carries ±1 1/2 inches. ASTM C94, the ready-mix purchase standard, splits the target band more finely and adds a separate rule for slumps written as a maximum. Ask the engineer which standard and edition the spec names before the first pour.
| How slump is specified | Specified slump | Tolerance | Source |
|---|---|---|---|
| Target (ACI 117) | 4 in or less | ±1 in | ACI 117-10 |
| Target (ACI 117) | Over 4 in | ±1 1/2 in | ACI 117-10 |
| Target (ASTM C94) | 2 in or less | ±1/2 in | ASTM C94/C94M |
| Target (ASTM C94) | Over 2 in through 4 in | ±1 in | ASTM C94/C94M |
| Target (ASTM C94) | Over 4 in | ±1 1/2 in | ASTM C94/C94M |
| Maximum or “not to exceed” (ASTM C94) | 3 in or less | +0, minus 1 1/2 in | ASTM C94/C94M |
| Maximum or “not to exceed” (ASTM C94) | Over 3 in | +0, minus 2 1/2 in | ASTM C94/C94M |
Worked example: a spec reads “4 in slump, tolerances per ACI 117.” The acceptance window is 3 to 5 in, so a 5 1/4 in reading fails and a 3 in reading passes. If the same spec read “4 in maximum” under ASTM C94/C94M, the window becomes 1 1/2 to 4 in. The ready-mix producer is responsible for the specified slump for 30 minutes after the requested time or the truck’s arrival, whichever is later (NRMCA CIP 31).
How often should slump be tested on a commercial job?
Commercial specifications tie slump testing to strength sampling: at least once a day per mix, once per 150 cubic yards and once per 5,000 square feet of slab or wall, plus at the start of placement. That is the federal rule in UFGS 03 30 00 and the strength-test frequency in ACI 318-19 section 26.12.2.1 and ACI 301.
| Trigger | Slump test required | Source |
|---|---|---|
| Start of placement | Yes, first load | UFGS 03 30 00 3.14.3.1 |
| Each time strength cylinders are made | Yes | UFGS 03 30 00 3.14.3.1 |
| Strength samples, per mix | At least 1 per day, 1 per 150 yd3, 1 per 5,000 ft2 of slab or wall; 5 sets minimum per project | UFGS 03 30 00 3.14.3.4 |
| Optional volume interval | Every [X] yd3, filled in by the designer | UFGS 03 30 00 3.14.3.1 |
| Pumped concrete | Sample at pump inlet and hose discharge; slump loss in the line 2 in maximum | UFGS 03 30 00 3.7.2 |
| Air content (air-entrained mixes) | Same frequency as slump | UFGS 03 30 00 3.14.3.5 |
| Hot or cold weather (below 50 °F or above 80 °F) | Temperature every batch or every 20 yd3, and whenever slump is tested | UFGS 03 30 00 3.14.3.3 |
Worked example: a 400 yd3 suspended deck of 18,000 ft2 placed in one day needs at least 4 strength samples by area (18,000 / 5,000 = 3.6, rounded up) and 3 by volume (400 / 150 = 2.7, rounded up), so the higher count, 4, governs, each with a slump test, plus the first-truck test. Put the frequency in the testing agency’s scope during submittal review, so nobody argues about it on pour day.
What should you do when a truck fails the slump test?
A load that tests high gets one check test on a fresh sample; if that also fails, the federal spec rejects it. A load that tests low may be brought up with withheld water or an admixture, mixed 30 drum revolutions and retested, and a second failure is a rejection. TxDOT lets a contractor keep over-slump concrete at its own risk with extra cylinders.
| If | Then | Source |
|---|---|---|
| Slump above spec plus tolerance | Run a check test on a new sample; if it fails, the load fails | UFGS 03 30 00 3.14.3.1 |
| Over-slump on a TxDOT job | May be used at contractor’s option; the Engineer makes and tests strength specimens | TxDOT Item 421 4.8.3 |
| Slump below spec, under about 1/4 yd3 discharged, trim water on ticket | Add measured water, 30 revolutions at mixing speed, retest | NRMCA CIP 26; ASTM C94 |
| Slump below spec, w/cm already at maximum | No water; water-reducing admixture only if approved | NRMCA CIP 26; TxDOT Item 421 4.2.5 |
| Still low after all withheld water | Rejected unless the Engineer allows | TxDOT Item 421 4.8.3 |
| Discharge not started in time | Reject: TxDOT 45, 60 or 90 min at 90 °F and above, 75 to 89 °F, under 75 °F (75, 90, 120 min with Type B or D admixture); UFGS 90 min | TxDOT Item 421 Table 14; UFGS 03 30 00 3.6.2 |
| Segregation or excess bleeding seen | Reject regardless of slump | TxDOT Item 421 4.8.3 |
Write the rejection on the delivery ticket with the time, slump reading and technician name, and record it in the daily report. If the rejected load leads to a dispute over cost or schedule, the paper trail feeds a change order or back-charge, and an unclear spec clause belongs in an RFI before the next pour.
How does water added at the site change slump and strength?
Adding about 1 gallon of water per cubic yard raises slump about 1 inch, per NRMCA CIP 26 (2023). Water beyond the design amount delays set, cuts strength and raises cracking risk, and if the buyer asks for it, the buyer owns the result. ASTM C94 permits jobsite water only within the specified slump and w/cm, followed by 30 drum revolutions at mixing speed.
| Step | Input | Result |
|---|---|---|
| Specified slump | 4 in target, ACI 117 ±1 in | Acceptable 3 to 5 in |
| Measured on a preliminary sample after the first 1/4 yd3 | 2 1/2 in | 1/2 in below the window |
| Aim for | 4 in | Increase needed: 1 1/2 in |
| Rule of thumb | 1 gal per yd3 per 1 in | 1.5 gal per yd3 |
| Load size | 10 yd3 | 15 gal total |
| Trim water held back on ticket | 20 gal (example) | 15 gal is within the limit; w/cm not exceeded |
| Mix and retest | 30 revolutions at mixing speed | Acceptance test on a C172 sample |
CIP 26 adds four controls: measure every gallon and record it on the ticket, have the owner’s representative initial the addition, stop once more than about 1/4 yd3 has been discharged, and agree at a pre-placement meeting who may authorize water. When the spec bans jobsite water, the producer can batch all design water at the plant and use admixtures on site. Trucks with automated slump monitoring may add water in transit; TxDOT Item 421 4.6.2 requires their reports daily and an automated reading within 1 in of a manual slump.
Extra water also lengthens the time before forms can be loaded, which is covered in our concrete curing time guide. On slab work, ordering a mid-range water reducer at the plant is usually cheaper than rejected loads; compare it against our concrete slab cost per square foot figures.
When is the slump test the wrong test?
The slump test does not apply to non-plastic or non-cohesive concrete, mixes with aggregate over 1 1/2 inches unless sieved, or self-consolidating concrete, per ASTM C143 sections 4.2 and 4.3. Self-consolidating concrete is checked by slump flow under ASTM C1611, with a Visual Stability Index, at the frequency UFGS 03 30 00 section 3.14.3.2 sets for the first two batches and each cylinder set.
- Slump flow (ASTM C1611): spread diameter from the same cone; TxDOT Item 421 lists 22 to 27 in for precast self-consolidating concrete.
- Stiff mixes under 1/2 in slump: the C143 result has little meaning; the spec should name another consistency test.
- Strength: slump is never a substitute for cylinders under ASTM C31 and C39.
Slump checks sit inside the wider testing plan required by IBC Chapter 17 and explained in our special inspections guide, and a floor that will be ground and sealed has its own pricing in our polished concrete cost guide.
How we compiled this
We read the WAQTC field operating procedure for AASHTO T 119 in the WSDOT Materials Manual (January 2026), ASTM’s C143 and C94 abstracts, UFGS 03 30 00 Change 10, TxDOT’s 2024 Item 421, NRMCA CIP 26 and CIP 31, a U.S. Navy Builder training manual and ACI’s catalog and FAQ pages, 12 primary documents in all, accessed November 2026. ACI 117 and ASTM C94 tolerance values are as published in those standards; confirm the edition your contract names. We did not run tests ourselves.
Frequently asked questions
What is a good slump for concrete?
For most commercial work a good slump is 3 to 5 inches, the range NRMCA CIP 31 (2023) gives for most applications and the window ACI 301-20 produces with its 4 inch default and ACI 117 tolerance of plus or minus 1 inch. Slip-form paving needs 2 inches or less, and pumped walls or congested reinforcement may need 7 to 9 inches.
How long does a slump test take?
The test must start within 5 minutes of taking the sample and run from the first scoop to lifting the cone within 2 1/2 minutes, per the AASHTO T 119 field procedure in the WSDOT Materials Manual (January 2026). The cone lift itself takes 5 seconds, plus or minus 2. Measuring adds under a minute, so a technician finishes in about 4 minutes.
Is a 6 inch slump too wet?
A 6 inch slump is too wet only if the specification says so. It is above the ACI 301 default window of 3 to 5 inches, but TxDOT Item 421 Table 9 allows up to 6 inches for bridge slabs and up to 7 inches for columns and thick walls. With a water reducer, ACI 301 permits up to 8 inches when the w/cm limit is met.
Does a higher slump mean weaker concrete?
Higher slump from added water usually means weaker concrete: NRMCA CIP 26 (2023) says water beyond the design amount reduces strength, delays setting and raises cracking risk. Higher slump from a water-reducing admixture usually does not, provided the w/cm stays the same. ASTM C143 notes the slump to strength link is not clearly shown under field conditions, so cylinders decide strength.
Who performs the slump test on a commercial job?
The owner’s testing agency or special inspector usually performs it, using a technician holding ACI Field Testing Technician Grade I or an equivalent. TxDOT Item 421 section 4.8.1 requires ACI certification or a recognized equivalent. The contract should say who pays for retests of failed loads, which is often the contractor or ready-mix supplier, not the owner.
What is the difference between slump and slump flow?
Slump measures how far concrete drops from the 12 inch cone, under ASTM C143. Slump flow, under ASTM C1611, measures how wide self-consolidating concrete spreads after the same cone is lifted, often 22 to 27 inches for precast in TxDOT Item 421. Use slump flow when a mix would collapse in the slump test, above about 9 inches.
Sources
- WSDOT Materials Manual M 46-01.48, WAQTC FOP for AASHTO T 119, Slump of Hydraulic Cement Concrete, January 2026. Accessed November 9, 2026.
- ASTM C143/C143M-26b, Standard Test Method for Slump of Concrete, ASTM International. Accessed November 9, 2026.
- ASTM C143/C143M-20, scope and significance and use, ASTM International. Accessed November 9, 2026.
- ASTM C94/C94M, Standard Specification for Ready-Mixed Concrete, ASTM International (active edition C94/C94M-26d). Accessed November 9, 2026.
- ACI 117-10 (reapproved 2015), Specification for Tolerances for Concrete Construction and Materials, American Concrete Institute. Accessed November 9, 2026.
- ACI 301-20, Specifications for Concrete Construction, American Concrete Institute. Accessed November 9, 2026.
- ACI 318-19(22), Building Code Requirements for Structural Concrete, American Concrete Institute. Accessed November 9, 2026.
- ACI FAQ: recommended slump range by construction type (ACI PRC-211.1-22), American Concrete Institute. Accessed November 9, 2026.
- UFGS 03 30 00 Cast-in-Place Concrete, Change 10, August 2025, USACE, NAVFAC, AFCEC via WBDG. Accessed November 9, 2026.
- TxDOT 2024 Standard Specifications, Item 421 Hydraulic Cement Concrete, Texas Department of Transportation. Accessed November 9, 2026.
- NRMCA CIP 26, Jobsite Addition of Water, 1995, 2014, 2023. Accessed November 9, 2026.
- NRMCA CIP 31, Ordering Ready Mixed Concrete, 2000, 2016, 2023. Accessed November 9, 2026.
- U.S. Navy Builder training manual, Slump Testing, hosted by Integrated Publishing. Accessed November 9, 2026.